TOMORROW WORLD PHASE-2 is a plotted development in Raigiri, Bhongir mandal, Yadadri Bhuvanagiri district, developed by registered promoter INCREDIBLE INDIA PROJECTS PVT LTD. The registered site extent is 289350.2 sqmts, and the layout approval records 460 plots over Ac.71.50 cents; plot-size configurations are not stated. The project is registered with TG-RERA under P02000002670, and the promoter’s completion undertaking gives 01-12-2023.
More from Incredible India Projects Pvt Ltd · 4 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
13 items to check before you pay, 6 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered project name | TOMORROW WORLD PHASE-2 RERA record |
| Project type / phase | Plotted development; registered portion is Phase-2. RERA record |
| TG-RERA registration | P02000002670; granted under section 5. RERA record |
| Registration validity | Certificate states validity from 06/03/2021 to 01/12/2023; it records a two-year validity period. No extension is recorded in the supplied certificate. Registration validity is distinct from the project’s completion undertaking and from occupancy/completion certification. |
| Registered promoter | INCREDIBLE INDIA PROJECTS PVT LTD. RERA record |
| Status in supplied record | New Project. Current TG-RERA registration status beyond the certificate’s stated validity is not established by the supplied records. RERA record |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality / revenue village | Raigiri; the layout approval identifies Raigiri Revenue Village. RERA record |
| Mandal | Bhongir in the RERA certificate; the layout approval states Bhuvanagiri Mandal. |
| District / PIN | Yadadri Bhuvanagiri, 508116. RERA record |
| Project survey numbers | 799/P, 800/P, 801/P, 775/P and 766/P. RERA record |
| Registered site extent | The supplied TG-RERA project fields state total area 289350.2 sqmts, area affected in road widening/FTL of tanks/nala widening 145403.52 sqmts, and net area 143946.68 sqmts. RERA filing |
| Layout approval extent | The layout approval describes Ac.71.50 cents. |
| Boundaries | East, west, north and south: NEIGHBOURS LAND. No neighbouring landowners are identified in the supplied fields. RERA filing |
Development identity
| Item | Project record |
|---|---|
| Sanctioning authority | Director of Town and Country Planning; the filed layout approval refers to YTDA and delegated authority to Bhongir Municipality. Approvals record |
| Principal approval | Draft TLP No.10/2020/YTDA; proceedings Lr.Roc.No.2335/2018/YTDA; approval date is recorded as 07-2.020 in the extraction. Approvals record |
| Approved development | 460 plots across the approval’s stated Ac.71.50 cents. |
| Approved site allocations stated in the layout approval | Open space: Ac.5.36 cents (7.50); social infrastructure: Ac.1.791 cents (2.50%); roads: Ac.20.52, cents (28.70); utilities: Ac.0.91 cents (1.27%). These are approval-document figures. |
| Approved built-up area | 143946.68 sqmts is listed in the RERA filing’s built-up area fields; a separate built-up-area schedule is not supplied. RERA filing |
| Towers, floors and building configuration | Not disclosed in the supplied record; this is a plotted layout, and no tower or floor schedule is provided. |
| RERA-declared unit count | The supplied project filing does not state a separate plot inventory count; the layout approval records 460 plots. |
Offering and status
| Item | Project record |
|---|---|
| Offering | Plots in a plotted layout; the approval records 460 plots. Plot-size bands and plot-by-plot inventory are not supplied. |
| Booked / available counts | Not disclosed in the supplied materials. RERA record Document index |
| Construction / development stage | The RERA header reports 70% completeness. This is a recorded progress figure; no independent site verification is supplied. RERA record |
| Completion date | The Form B declaration gives a promoter undertaking to complete by 01-12-2023. |
| Occupancy / completion certificate | No occupancy or completion certificate is included in the supplied project documents; the status is not established here. Document index |
2. The project story
TOMORROW WORLD PHASE-2 is a plotted development registered with TG-RERA under P02000002670, on land identified in the project filing as survey numbers 799/P, 800/P, 801/P, 775/P and 766/P in Raigiri, Bhongir mandal, Yadadri Bhuvanagiri district. The layout approval describes 460 plots over Ac.71.50 cents and sets out areas for plots, roads, open space, social infrastructure and utilities. RERA record
The RERA header records 70% completeness, while the promoter’s Form B gives a completion undertaking of 01-12-2023. Those are record disclosures, not independently verified present-day site progress. The supplied documents do not establish which individual plots are booked or available, whether all layout works have been completed, or whether a completion/occupancy certificate has been issued. RERA record Document index
3. Master plan, architecture & building design
The supplied approval is for a plotted layout, not a tower or apartment-building scheme. It records 460 plots, and allocates areas for roads, open space, social infrastructure and utilities. The project filing separately lists approved built-up area as 143946.68 sqmts; no drawing-based building schedule, plot arrangement sheet, plot-size schedule, building footprint, floor configuration or tower count is available in the supplied evidence. RERA filing
The layout approval identifies Plot Nos.156 to 232, stated as 26055.00 sq yds and 15.13%, as mortgaged to YTDA under Mortgage Deed No. 5107/2020, dated 12-06-2020. The approval says those plots and the mortgaged area are not permitted to be sold while under mortgage.
4. Homes, configurations & floor plans
This is a plotted project; the supplied evidence does not contain a plot-by-plot schedule, plot-size bands, booked/available counts or saleable-area figures.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Plots | 460 plots stated in layout approval | Not disclosed | Not disclosed | Not disclosed | Not applicable / not supplied | Not supplied |
The supplied floor-plan record contains three drawings, all awaiting scan processing; none has a software-measured carpet area. Apartment carpet-area or loading comparisons are therefore not applicable on the evidence provided. Floor plans
5. Parking & vehicle circulation
The supplied project record does not establish a sanctioned parking-space count, visitor or accessible parking, parking allocation to individual plots, or a parking layout. The developer-submitted amenity list includes Open Parking, but provides no quantity or allocation details. RERA amenities Promoter website
The layout approval requires road formation with black top and provides for roads to be handed over to the Local Body by registered gift deed before release of the final layout. It does not provide road widths, access points, internal-driveway dimensions or pedestrian–vehicle separation in the supplied extraction.
6. Amenities, recreation & open spaces
| Facility | Open space / recreational open space |
|---|---|
| Description / size | Approval states Ac.5.36 cents (7.50). |
| Evidence source | RERA amenities |
| Declared progress / verified status | Listed as available “YES” in the RERA amenity record, with progress shown as 0; completion is not independently verified. RERA amenities |
| Facility | Park / green strip |
|---|---|
| Description / size | Park development and avenue plantation are included among layout works; no park size or count is supplied. |
| Evidence source | Promoter website |
| Declared progress / verified status | Developer-submitted amenity listing; completion not independently verified. RERA amenities |
| Facility | Tot lot |
|---|---|
| Description / size | “Green Strip/TOT LOT/Park” appears in the RERA amenity list; no separate size or equipment details are supplied. |
| Evidence source | RERA amenities |
| Declared progress / verified status | Listed as available “YES”, progress 0; completion is not independently verified. |
| Facility | Social infrastructure area |
|---|---|
| Description / size | Approval states Ac.1.791 cents (2.50%). No facility type or building specification is identified. |
| Declared progress / verified status | Area allocation appears in the approval extraction; delivery status is not established. |
| Facility | Community buildings |
|---|---|
| Description / size | Listed in RERA amenities; no building description or size is supplied. |
| Evidence source | RERA amenities |
| Declared progress / verified status | No “available” status or completion evidence supplied; progress 0. |
The approval also identifies road and utilities allocations, which are covered under circulation and services rather than counted as recreational amenities.
7. Utilities, building services & safety
The layout approval specifies infrastructure works comprising storm-water drains; underground drainage lines and a common septic tank/STP; internal water-supply pipelines, an overhead tank and an assured water-supply source; electrical supply lines, street lights and a transformer; and rainwater-harvesting pits. It also requires park development and avenue plantation. These are approval conditions / specified works, not evidence that the facilities are complete or operational.
| Evidence in supplied record | Internal water-supply pipelines, overhead tank and assured water-supply source are specified in the layout approval. |
|---|---|
| Status / limitation | Source capacity, storage capacity and completion status are not supplied. |
| Evidence in supplied record | Underground drainage lines and common septic tank / STP are specified; storm-water drains are also specified. |
|---|---|
| Status / limitation | Treatment capacity, reuse arrangements and completion status are not supplied. |
| Evidence in supplied record | Electrical supply lines, street lights and transformer are specified; the amenity list also names an electrical meter room/sub-station/receiving station. |
|---|---|
| Status / limitation | Capacity, backup provision and completion status are not supplied. RERA amenities |
| Evidence in supplied record | Rainwater-harvesting pits are specified in the approval; the amenity list also names water conservation/rainwater harvesting. |
|---|---|
| Status / limitation | Quantity, capacity and installed status are not supplied. RERA amenities |
| Evidence in supplied record | Solid-waste management and disposal appears in the RERA amenity list. |
|---|---|
| Status / limitation | Design, capacity and implementation status are not supplied. RERA amenities |
| Evidence in supplied record | Fire protection and fire-safety requirements appears in the RERA amenity list. |
|---|---|
| Status / limitation | No system specifications, clearance or completion evidence is supplied. RERA amenities |
| Evidence in supplied record | No specific accessibility, CCTV or access-control details are supplied. |
|---|---|
| Status / limitation | Not established by the available record. |
8. Location, access & connectivity
The registered project location is Raigiri, Bhongir mandal, Yadadri Bhuvanagiri district, Telangana, PIN 508116. The supplied geocode identifies SubCentre, Raigiri, NH163, Rayagiri, Bhongiri mandal, Yadadri Bhuvanagiri. RERA record Location record
The location data lists the nearest sampled Outer Ring Road interchange at approximately 29.0 km. The promoter’s website describes proximity to Bhongir Railway Station, the Hyderabad–Yadgirigutta Expressway and named local destinations; these are promoter-provided connectivity claims, not distance- or travel-time measurements verified in the supplied record. Location record Promoter website
9. Developer & development status
The registered legal promoter is INCREDIBLE INDIA PROJECTS PVT LTD, a private limited company. The supplied RERA filing identifies it as the promoter and names VARRI TULSIRAM VIJAY KUMAR as authorized signatory. The RERA certificate lists the promoter office as “Village: Mandal: District: Hyderabad, Pin: 500052.” Corporate record Parties record
The promoter’s website is incredibleindiaproject.in. The supplied record does not provide a company registration number or a complete registered-office address. Promoter website Corporate record
No subsequent extension, tower/plot-wise construction schedule, independently verified progress report or completion/occupancy certificate is supplied here. Document index
10. Approvals, official records & documents
| Supplied evidence | Form C, P02000002670, issued 06/03/2021. |
|---|---|
| What it establishes | Registration certificate for TOMORROW WORLD PHASE-2; stated validity ends 01/12/2023. |
| Supplied evidence | Director of Town and Country Planning communication, Draft TLP No. 10/2020/YTDA; proceedings Lr.Roc.No.2335/2018/YTDA. |
|---|---|
| What it establishes | Draft layout approval for 460 plots across the identified survey numbers, subject to stated development and handover conditions. |
| Supplied evidence | Promoter declaration, verified at Hyderabad on 14th Dec, 2020. |
|---|---|
| What it establishes | Promoter’s declarations on title, encumbrances, project funds, approvals and completion undertaking. |
| Supplied evidence | Title-related documents 145775–145779 and advocate’s title search report 145115. Document index |
|---|---|
| What it establishes | Documents are listed in the supplied RERA filing; this overview does not determine title. |
| Supplied evidence | Document 145117, described as an IGRS statement for 01-01-1987 to 29-06-2016. |
|---|---|
| What it establishes | Filed search material for the stated period. |
| Supplied evidence | Layout approval document 145198; the separate layout-plan item 145118 is not extracted. Document index |
|---|---|
| What it establishes | Approval details are available in the extracted approval communication; a separately extracted stamped layout drawing is not supplied. |
| Supplied evidence | Not present in the supplied documents. Document index |
|---|---|
| What it establishes | Certificate status is not established by this evidence set. |
1. Project at a glance
Project identity
Registered project name: TOMORROW WORLD PHASE-2
Project type / phase: Plotted development; registered portion is Phase-2.
TG-RERA registration: P02000002670; granted under section 5.
Registration validity: Certificate states validity from 06/03/2021 to 01/12/2023; it records a two-year validity period. No extension is recorded in the supplied certificate. Registration validity is distinct from the project’s completion undertaking and from occupancy/completion certification.
Registered promoter: INCREDIBLE INDIA PROJECTS PVT LTD.
Status in supplied record: New Project. Current TG-RERA registration status beyond the certificate’s stated validity is not established by the supplied records.
Land and geographic identity
Locality / revenue village: Raigiri; the layout approval identifies Raigiri Revenue Village.
Mandal: Bhongir in the RERA certificate; the layout approval states Bhuvanagiri Mandal.
District / PIN: Yadadri Bhuvanagiri, 508116.
Project survey numbers: 799/P, 800/P, 801/P, 775/P and 766/P.
Registered site extent: The supplied TG-RERA project fields state total area 289350.2 sqmts, area affected in road widening/FTL of tanks/nala widening 145403.52 sqmts, and net area 143946.68 sqmts.
Layout approval extent: The layout approval describes Ac.71.50 cents.
Boundaries: East, west, north and south: NEIGHBOURS LAND. No neighbouring landowners are identified in the supplied fields.
Development identity
Sanctioning authority: Director of Town and Country Planning; the filed layout approval refers to YTDA and delegated authority to Bhongir Municipality.
Principal approval: Draft TLP No.10/2020/YTDA; proceedings Lr.Roc.No.2335/2018/YTDA; approval date is recorded as 07-2.020 in the extraction.
Approved development: 460 plots across the approval’s stated Ac.71.50 cents.
Approved site allocations stated in the layout approval: Open space: Ac.5.36 cents (7.50); social infrastructure: Ac.1.791 cents (2.50%); roads: Ac.20.52, cents (28.70); utilities: Ac.0.91 cents (1.27%). These are approval-document figures.
Approved built-up area: 143946.68 sqmts is listed in the RERA filing’s built-up area fields; a separate built-up-area schedule is not supplied.
Towers, floors and building configuration: Not disclosed in the supplied record; this is a plotted layout, and no tower or floor schedule is provided.
RERA-declared unit count: The supplied project filing does not state a separate plot inventory count; the layout approval records 460 plots.
Offering and status
Offering: Plots in a plotted layout; the approval records 460 plots. Plot-size bands and plot-by-plot inventory are not supplied.
Booked / available counts: Not disclosed in the supplied materials.
Construction / development stage: The RERA header reports 70% completeness. This is a recorded progress figure; no independent site verification is supplied.
Completion date: The Form B declaration gives a promoter undertaking to complete by 01-12-2023.
Occupancy / completion certificate: No occupancy or completion certificate is included in the supplied project documents; the status is not established here.
2. The project story
TOMORROW WORLD PHASE-2 is a plotted development registered with TG-RERA under P02000002670, on land identified in the project filing as survey numbers 799/P, 800/P, 801/P, 775/P and 766/P in Raigiri, Bhongir mandal, Yadadri Bhuvanagiri district. The layout approval describes 460 plots over Ac.71.50 cents and sets out areas for plots, roads, open space, social infrastructure and utilities.
The RERA header records 70% completeness, while the promoter’s Form B gives a completion undertaking of 01-12-2023. Those are record disclosures, not independently verified present-day site progress. The supplied documents do not establish which individual plots are booked or available, whether all layout works have been completed, or whether a completion/occupancy certificate has been issued.
3. Master plan, architecture & building design
The supplied approval is for a plotted layout, not a tower or apartment-building scheme. It records 460 plots, and allocates areas for roads, open space, social infrastructure and utilities. The project filing separately lists approved built-up area as 143946.68 sqmts; no drawing-based building schedule, plot arrangement sheet, plot-size schedule, building footprint, floor configuration or tower count is available in the supplied evidence.
The layout approval identifies Plot Nos.156 to 232, stated as 26055.00 sq yds and 15.13%, as mortgaged to YTDA under Mortgage Deed No. 5107/2020, dated 12-06-2020. The approval says those plots and the mortgaged area are not permitted to be sold while under mortgage.
4. Homes, configurations & floor plans
This is a plotted project; the supplied evidence does not contain a plot-by-plot schedule, plot-size bands, booked/available counts or saleable-area figures.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Plots | 460 plots stated in layout approval | Not disclosed | Not disclosed | Not disclosed | Not applicable / not supplied | Not supplied |
The supplied floor-plan record contains three drawings, all awaiting scan processing; none has a software-measured carpet area. Apartment carpet-area or loading comparisons are therefore not applicable on the evidence provided.
5. Parking & vehicle circulation
The supplied project record does not establish a sanctioned parking-space count, visitor or accessible parking, parking allocation to individual plots, or a parking layout. The developer-submitted amenity list includes Open Parking, but provides no quantity or allocation details.
The layout approval requires road formation with black top and provides for roads to be handed over to the Local Body by registered gift deed before release of the final layout. It does not provide road widths, access points, internal-driveway dimensions or pedestrian–vehicle separation in the supplied extraction.
6. Amenities, recreation & open spaces
| Facility | Open space / recreational open space |
|---|---|
| Description / size | Approval states Ac.5.36 cents (7.50). |
| Declared progress / verified status | Listed as available “YES” in the RERA amenity record, with progress shown as 0; completion is not independently verified. |
| Facility | Park / green strip |
|---|---|
| Description / size | Park development and avenue plantation are included among layout works; no park size or count is supplied. |
| Declared progress / verified status | Developer-submitted amenity listing; completion not independently verified. |
| Facility | Tot lot |
|---|---|
| Description / size | “Green Strip/TOT LOT/Park” appears in the RERA amenity list; no separate size or equipment details are supplied. |
| Declared progress / verified status | Listed as available “YES”, progress 0; completion is not independently verified. |
| Facility | Social infrastructure area |
|---|---|
| Description / size | Approval states Ac.1.791 cents (2.50%). No facility type or building specification is identified. |
| Declared progress / verified status | Area allocation appears in the approval extraction; delivery status is not established. |
| Facility | Community buildings |
|---|---|
| Description / size | Listed in RERA amenities; no building description or size is supplied. |
| Declared progress / verified status | No “available” status or completion evidence supplied; progress 0. |
The approval also identifies road and utilities allocations, which are covered under circulation and services rather than counted as recreational amenities.
7. Utilities, building services & safety
The layout approval specifies infrastructure works comprising storm-water drains; underground drainage lines and a common septic tank/STP; internal water-supply pipelines, an overhead tank and an assured water-supply source; electrical supply lines, street lights and a transformer; and rainwater-harvesting pits. It also requires park development and avenue plantation. These are approval conditions / specified works, not evidence that the facilities are complete or operational.
| Evidence in supplied record | Internal water-supply pipelines, overhead tank and assured water-supply source are specified in the layout approval. |
|---|---|
| Status / limitation | Source capacity, storage capacity and completion status are not supplied. |
| Evidence in supplied record | Underground drainage lines and common septic tank / STP are specified; storm-water drains are also specified. |
|---|---|
| Status / limitation | Treatment capacity, reuse arrangements and completion status are not supplied. |
| Evidence in supplied record | Electrical supply lines, street lights and transformer are specified; the amenity list also names an electrical meter room/sub-station/receiving station. |
|---|---|
| Status / limitation | Capacity, backup provision and completion status are not supplied. |
| Evidence in supplied record | Rainwater-harvesting pits are specified in the approval; the amenity list also names water conservation/rainwater harvesting. |
|---|---|
| Status / limitation | Quantity, capacity and installed status are not supplied. |
| Evidence in supplied record | Solid-waste management and disposal appears in the RERA amenity list. |
|---|---|
| Status / limitation | Design, capacity and implementation status are not supplied. |
| Evidence in supplied record | Fire protection and fire-safety requirements appears in the RERA amenity list. |
|---|---|
| Status / limitation | No system specifications, clearance or completion evidence is supplied. |
| Evidence in supplied record | No specific accessibility, CCTV or access-control details are supplied. |
|---|---|
| Status / limitation | Not established by the available record. |
8. Location, access & connectivity
The registered project location is Raigiri, Bhongir mandal, Yadadri Bhuvanagiri district, Telangana, PIN 508116. The supplied geocode identifies SubCentre, Raigiri, NH163, Rayagiri, Bhongiri mandal, Yadadri Bhuvanagiri.
The location data lists the nearest sampled Outer Ring Road interchange at approximately 29.0 km. The promoter’s website describes proximity to Bhongir Railway Station, the Hyderabad–Yadgirigutta Expressway and named local destinations; these are promoter-provided connectivity claims, not distance- or travel-time measurements verified in the supplied record.
9. Developer & development status
The registered legal promoter is INCREDIBLE INDIA PROJECTS PVT LTD, a private limited company. The supplied RERA filing identifies it as the promoter and names VARRI TULSIRAM VIJAY KUMAR as authorized signatory. The RERA certificate lists the promoter office as “Village: Mandal: District: Hyderabad, Pin: 500052.”
The promoter’s website is incredibleindiaproject.in. The supplied record does not provide a company registration number or a complete registered-office address.
No subsequent extension, tower/plot-wise construction schedule, independently verified progress report or completion/occupancy certificate is supplied here.
10. Approvals, official records & documents
| Supplied evidence | Form C, P02000002670, issued 06/03/2021. |
|---|---|
| What it establishes | Registration certificate for TOMORROW WORLD PHASE-2; stated validity ends 01/12/2023. |
| Supplied evidence | Director of Town and Country Planning communication, Draft TLP No. 10/2020/YTDA; proceedings Lr.Roc.No.2335/2018/YTDA. |
|---|---|
| What it establishes | Draft layout approval for 460 plots across the identified survey numbers, subject to stated development and handover conditions. |
| Supplied evidence | Promoter declaration, verified at Hyderabad on 14th Dec, 2020. |
|---|---|
| What it establishes | Promoter’s declarations on title, encumbrances, project funds, approvals and completion undertaking. |
| Supplied evidence | Title-related documents 145775–145779 and advocate’s title search report 145115. |
|---|---|
| What it establishes | Documents are listed in the supplied RERA filing; this overview does not determine title. |
| Supplied evidence | Document 145117, described as an IGRS statement for 01-01-1987 to 29-06-2016. |
|---|---|
| What it establishes | Filed search material for the stated period. |
| Supplied evidence | Layout approval document 145198; the separate layout-plan item 145118 is not extracted. |
|---|---|
| What it establishes | Approval details are available in the extracted approval communication; a separately extracted stamped layout drawing is not supplied. |
| Supplied evidence | Not present in the supplied documents. |
|---|---|
| What it establishes | Certificate status is not established by this evidence set. |
Frequently asked questions
Is TOMORROW WORLD PHASE-2 registered with Telangana RERA?
Yes. TOMORROW WORLD PHASE-2 is registered with the Telangana Real Estate Regulatory Authority as P02000002670; the registration status is New Project.
Who is the developer of TOMORROW WORLD PHASE-2?
The promoter named in the RERA registration is INCREDIBLE INDIA PROJECTS PVT LTD.
Where is TOMORROW WORLD PHASE-2 located?
TOMORROW WORLD PHASE-2 is in RAIGIRI, Bhongir, Yadadri Bhuvanagiri, Telangana (508116).
When will TOMORROW WORLD PHASE-2 be completed?
The promoter's proposed date of completion filed with RERA is 01/12/2023. This is the promoter's declaration, not a guarantee.