Green Acres
VAZEER · Mancherial · RERA P01200008273
GREEN ACRES is a residential plotted development at Hajipur, Pantancheruvu, Mancherial District. The registered promoter is Vazeer Sultan. The project covers 9,981.43 sq m and comprises 32 plots on Survey Nos. 42/A, 42/B and 42/C; plot configurations are not disclosed. It is registered under TG-RERA number P01200008273, with proposed completion by 02/12/2024.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
11 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Project record |
|---|---|
| Registered project name | GREEN ACRES RERA record |
| Project type | Plotted development / residential layout RERA record |
| Phase or registered portion | No phase identifier disclosed; the registration covers the plotted project on Survey Nos. 42/A, 42/B and 42/C |
| TG-RERA registration | P01200008273 Approvals record |
| Registration validity | 24/05/2024 to 02/12/2024, unless extended by the Authority Approvals record |
| Registered promoter | Vazeer Sultan; the project records also use “VAZEER” Corporate record |
| Legal entity type | Not disclosed in the supplied records Corporate record |
| RERA status | Registered; the supplied certificate states the above validity period. No extension record is supplied here. Registration validity is distinct from the project completion undertaking. Approvals record |
Land and geographic identity
| Field | Project record |
|---|---|
| Locality / street | Hajipur / HAZIPUR RERA record RERA filing |
| Revenue village | Hajipur RERA record RERA filing |
| Mandal | Pantancheruvu in the project header and filing fields; approval documents identify Hajipur mandal RERA record RERA filing |
| District | Mancherial RERA record RERA filing |
| PIN | 504207 RERA record RERA filing |
| Project survey numbers and subdivisions | 42/A, 42/B and 42/C RERA record Land records |
| RERA-filed site area | 9,981.43 sq m total and net area RERA filing |
| Layout area stated in approval documents | 11,938.09 sq yd |
| Boundaries as filed | East: 12M W ROAD; West: land of Survey No. 41; North: PSathyanarayana Rao and Sabbepalli Shivar; South: land of Survey No. 43 RERA filing |
Development identity
| Field | Project record |
|---|---|
| Sanctioning authority | District Town and Country Planning Officer, Mancherial District (DTCP) Approvals record |
| Principal layout approval | Final Technical Layout Pattern TLP. No.4/2021/DTCPO/MNCL, dated 11/06/2024 Approvals record |
| Earlier draft layout record | Draft Technical Layout Pattern Draft-TLP.No.04/2021/DTCPO/MNCL, dated 02-12-2021 |
| Approved built-up area | 5,891.41 sq m, as reported in the RERA filing RERA filing |
| Layout plots | Final approval records 32 plots |
| Buildings / floor configuration | Not applicable to the filed plotted layout; no building count or floor configuration is disclosed |
| Parking | No sanctioned parking-space count or plot-wise parking allocation is supplied RERA filing |
Offering and status
| Field | Project record |
|---|---|
| Unit type | Plots RERA record |
| Plot count | 32 in the final layout approval |
| Plot size range | Not disclosed in the supplied RERA unit records or extracted layout data RERA unit table Layout record |
| Booked / available counts | Not supplied RERA unit table |
| RERA-filed saleable-area range | Not available in the supplied unit-type records RERA unit table |
| Construction / development stage | A RERA-filed project completeness figure of 80% is supplied; it is not independent site verification. RERA record |
| Completion date | Promoter’s Form B undertaking: 02/12/2024 |
| Occupancy / completion certificate status | Not applicable as a building OC status for the plotted-layout offering; no separate project completion certificate is supplied in the reviewed records. The final layout approval is not an OC. |
2. The project story
GREEN ACRES is registered as a residential plotted development at Hajipur, Mancherial, covering Survey Nos. 42/A, 42/B and 42/C. The final layout approval describes 32 residential plots and assigns land to plots, roads and open space. It also records plots 14–19 as the layout’s mortgage plots and describes their release by a registered deed.
The RERA filing reports 80% completeness, while the promoter’s Form B undertaking specified completion by 02/12/2024. The supplied information does not identify which individual layout works were complete at the stated percentage, and it does not independently verify the site’s present condition. No building construction progress or occupancy-certified building portion is reported. RERA record
3. Master plan, architecture & building design
This is a plotted layout, not a multi-storey building project in the supplied approval material. The final layout approval records 32 plots across a stated layout area of 11,938.09 sq yd. Its stated allocation is 7,046.31 sq yd (59.04%) for plotted area, 3,694.63 sq yd (30.94%) for roads, and 1,197.15 sq yd (10.02%) for open space.
The approval refers to internal roads, drains and nala channelization, avenue planting, rainwater-harvesting pits, street lighting, electricity facilities, sewerage disposal and protected water supply. The approval conditions also require roads and open spaces to be handed over to the local body by registered deed. These are approval-record descriptions and conditions; they do not, by themselves, establish the present delivery or operational status of the works.
The RERA-filed site-area figure and the approval-document layout-area figure are stated separately above; no area conversion or reconciliation is made in this overview. No individual plot dimensions, plot-size bands, building footprints, floor plans or building configuration are supplied. RERA filing
4. Homes, configurations & floor plans
The offering is plots, rather than apartments. The final layout approval records 32 plots, but the supplied data does not provide plot-by-plot areas, a plot-size range, booking status, availability or a RERA-filed saleable-area schedule. RERA unit table Layout record
The floor-plan dataset contains two drawings, with both scans pending and no software-measured carpet areas. Apartment carpet-area or loading comparisons therefore cannot be reported for this plotted project. Floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Residential plots | 32 approved | Not supplied | Not supplied | Not supplied | Not applicable | Not supplied |
5. Parking & vehicle circulation
No parking-space count, visitor or accessible parking provision, parking allocation by plot, or dedicated parking arrangement is disclosed in the supplied project records. The layout approval describes internal roads and road widths, including 33-foot roads; a road-width entry does not establish a parking allocation or an exclusive parking right.
6. Amenities, recreation & open spaces
The approval documents describe layout-level open space and infrastructure. The RERA amenity data reports some items at 75% and others at 0%; these are reported progress fields, not independent confirmation of completion. RERA amenities
| Description / size | 1,197.15 sq yd; 10.02% of the layout in the final approval |
|---|---|
| Evidence source | Final layout approval |
| Declared progress / verified status | Approval-record allocation; no independent completion verification supplied |
| Description / size | Internal roads; approval also describes roads with sub-surface, curbstones, metalling and side drains |
|---|---|
| Evidence source | Final layout approval RERA amenities |
| Declared progress / verified status | RERA amenity progress field: 75%; not independently verified |
| Description / size | Layout open space; the RERA amenity record labels “Green Strip/TOT LOT/Park” |
|---|---|
| Evidence source | RERA amenities Promoter website |
| Declared progress / verified status | RERA amenity progress field: 75%; no independent verification |
| Description / size | Avenue plantation and greenery are described in layout approval conditions |
|---|---|
| Evidence source | Final layout approval |
| Declared progress / verified status | Approval-record description; present delivery not verified |
| Description / size | No size or facility details supplied |
|---|---|
| Evidence source | RERA amenities Promoter website |
| Declared progress / verified status | RERA amenity progress field: 0% |
| Description / size | Listed in vendor data only |
|---|---|
| Evidence source | Promoter website |
| Declared progress / verified status | No RERA progress or approval evidence supplied |
7. Utilities, building services & safety
The final layout approval describes protected water supply, water supply, sewerage and drainage disposal systems, nala channelization, rainwater-harvesting structures, street lighting and electricity facilities. It also places responsibility for effective maintenance of services on the local body after handover. The records supplied do not establish current operational status or provide capacities, engineering schedules, or independent completion verification.
| Evidence in the supplied record | Protected water supply and water-supply system described in the final layout approval |
|---|---|
| Status / limitation | No source, storage or capacity details supplied; current operation not independently verified |
| Evidence in the supplied record | Sewerage disposal, drainage systems, side drains and nala channelization described in the approval |
|---|---|
| Status / limitation | No treatment capacity or operating evidence supplied |
| Evidence in the supplied record | Rainwater-harvesting structures and pits described in the approval |
|---|---|
| Status / limitation | No capacity or completion verification supplied |
| Evidence in the supplied record | Electricity facilities and street lighting described in the approval |
|---|---|
| Status / limitation | No supply, substation capacity or backup details supplied |
| Evidence in the supplied record | No project-specific fire-system details supplied |
|---|---|
| Status / limitation | Not established by the supplied records |
| Evidence in the supplied record | No project-specific details supplied |
|---|---|
| Status / limitation | Not established by the supplied records |
8. Location, access & connectivity
The registered project location is Hajipur, Mancherial District, Telangana, PIN 504207, in revenue village Hajipur, on Survey Nos. 42/A, 42/B and 42/C. The filed east boundary is described as “12M W ROAD”; the final layout approval also records internal roads, including a 33-foot road entry. RERA record RERA filing RERA filing
The supplied location data lists the nearest sampled Outer Ring Road interchange at approximately 186.1 km. It does not provide other measured distances or travel times. Location record
9. Developer & development status
The TG-RERA certificate names Vazeer Sultan as promoter. The supplied material does not establish the promoter’s legal entity type, corporate registration identifiers, registered office for a corporate entity, or official project contact details. The certificate lists the promoter’s address as House No. 42-51/2, Mandamarry, Mandamarry Mandal, Mancherial, PIN 504231. Corporate record
The RERA header reports 80% completeness, and Form B contains a promoter undertaking to complete the project by 02/12/2024. These are filed/project-declared records, not an independent site progress assessment. The project is a plotted layout; no tower- or building-wise construction stages are supplied. RERA record
10. Approvals, official records & documents
| Record | Supplied evidence |
|---|---|
| TG-RERA registration | Form C certificate for GREEN ACRES, registration P01200008273, covering Survey Nos. 42/A, 42/B and 42/C; validity stated as 24/05/2024–02/12/2024 |
| Principal layout approval | Final Technical Layout Pattern TLP. No.4/2021/DTCPO/MNCL, dated 11/06/2024, issued by the District Town and Country Planning Officer, Mancherial District |
| Draft layout approval | Draft Technical Layout Pattern Draft-TLP.No.04/2021/DTCPO/MNCL, dated 02-12-2021 |
| Layout and infrastructure record | Final layout approval describes plot, road and open-space allocations and layout-level utility provisions |
| Promoter declaration | Form B affidavit/declaration, dated 02/05,2024, including the promoter’s completion undertaking and project-account declarations |
| Completion / occupancy record | No separate project completion certificate or building occupancy certificate supplied in the reviewed materials Document index |
| Plan and connectivity records | HMDA Master Plan 2031 zoning sheet is image-only and no survey-specific zone determination is supplied; the public HMDA DPMS layout lookup was unavailable in the supplied evidence HMDA |
1. Project at a glance
Project identity
Registered project name: GREEN ACRES
Project type: Plotted development / residential layout
Phase or registered portion: No phase identifier disclosed; the registration covers the plotted project on Survey Nos. 42/A, 42/B and 42/C
TG-RERA registration: P01200008273
Registration validity: 24/05/2024 to 02/12/2024, unless extended by the Authority
Registered promoter: Vazeer Sultan; the project records also use “VAZEER”
Legal entity type: Not disclosed in the supplied records
RERA status: Registered; the supplied certificate states the above validity period. No extension record is supplied here. Registration validity is distinct from the project completion undertaking.
Land and geographic identity
Locality / street: Hajipur / HAZIPUR
Revenue village: Hajipur
Mandal: Pantancheruvu in the project header and filing fields; approval documents identify Hajipur mandal
District: Mancherial
PIN: 504207
Project survey numbers and subdivisions: 42/A, 42/B and 42/C
RERA-filed site area: 9,981.43 sq m total and net area
Layout area stated in approval documents: 11,938.09 sq yd
Boundaries as filed: East: 12M W ROAD; West: land of Survey No. 41; North: PSathyanarayana Rao and Sabbepalli Shivar; South: land of Survey No. 43
Development identity
Sanctioning authority: District Town and Country Planning Officer, Mancherial District (DTCP)
Principal layout approval: Final Technical Layout Pattern TLP. No.4/2021/DTCPO/MNCL, dated 11/06/2024
Earlier draft layout record: Draft Technical Layout Pattern Draft-TLP.No.04/2021/DTCPO/MNCL, dated 02-12-2021
Approved built-up area: 5,891.41 sq m, as reported in the RERA filing
Layout plots: Final approval records 32 plots
Buildings / floor configuration: Not applicable to the filed plotted layout; no building count or floor configuration is disclosed
Parking: No sanctioned parking-space count or plot-wise parking allocation is supplied
Offering and status
Unit type: Plots
Plot count: 32 in the final layout approval
Plot size range: Not disclosed in the supplied RERA unit records or extracted layout data
Booked / available counts: Not supplied
RERA-filed saleable-area range: Not available in the supplied unit-type records
Construction / development stage: A RERA-filed project completeness figure of 80% is supplied; it is not independent site verification.
Completion date: Promoter’s Form B undertaking: 02/12/2024
Occupancy / completion certificate status: Not applicable as a building OC status for the plotted-layout offering; no separate project completion certificate is supplied in the reviewed records. The final layout approval is not an OC.
2. The project story
GREEN ACRES is registered as a residential plotted development at Hajipur, Mancherial, covering Survey Nos. 42/A, 42/B and 42/C. The final layout approval describes 32 residential plots and assigns land to plots, roads and open space. It also records plots 14–19 as the layout’s mortgage plots and describes their release by a registered deed.
The RERA filing reports 80% completeness, while the promoter’s Form B undertaking specified completion by 02/12/2024. The supplied information does not identify which individual layout works were complete at the stated percentage, and it does not independently verify the site’s present condition. No building construction progress or occupancy-certified building portion is reported.
3. Master plan, architecture & building design
This is a plotted layout, not a multi-storey building project in the supplied approval material. The final layout approval records 32 plots across a stated layout area of 11,938.09 sq yd. Its stated allocation is 7,046.31 sq yd (59.04%) for plotted area, 3,694.63 sq yd (30.94%) for roads, and 1,197.15 sq yd (10.02%) for open space.
The approval refers to internal roads, drains and nala channelization, avenue planting, rainwater-harvesting pits, street lighting, electricity facilities, sewerage disposal and protected water supply. The approval conditions also require roads and open spaces to be handed over to the local body by registered deed. These are approval-record descriptions and conditions; they do not, by themselves, establish the present delivery or operational status of the works.
The RERA-filed site-area figure and the approval-document layout-area figure are stated separately above; no area conversion or reconciliation is made in this overview. No individual plot dimensions, plot-size bands, building footprints, floor plans or building configuration are supplied.
4. Homes, configurations & floor plans
The offering is plots, rather than apartments. The final layout approval records 32 plots, but the supplied data does not provide plot-by-plot areas, a plot-size range, booking status, availability or a RERA-filed saleable-area schedule.
The floor-plan dataset contains two drawings, with both scans pending and no software-measured carpet areas. Apartment carpet-area or loading comparisons therefore cannot be reported for this plotted project.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Residential plots | 32 approved | Not supplied | Not supplied | Not supplied | Not applicable | Not supplied |
5. Parking & vehicle circulation
No parking-space count, visitor or accessible parking provision, parking allocation by plot, or dedicated parking arrangement is disclosed in the supplied project records. The layout approval describes internal roads and road widths, including 33-foot roads; a road-width entry does not establish a parking allocation or an exclusive parking right.
6. Amenities, recreation & open spaces
The approval documents describe layout-level open space and infrastructure. The RERA amenity data reports some items at 75% and others at 0%; these are reported progress fields, not independent confirmation of completion.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Open space | 1,197.15 sq yd; 10.02% of the layout in the final approval | Final layout approval | Approval-record allocation; no independent completion verification supplied |
| Internal roads and footpaths | Internal roads; approval also describes roads with sub-surface, curbstones, metalling and side drains | Final layout approval | RERA amenity progress field: 75%; not independently verified |
| Green strip / park | Layout open space; the RERA amenity record labels “Green Strip/TOT LOT/Park” | RERA amenity progress field: 75%; no independent verification | |
| Avenue plantation / greenery | Avenue plantation and greenery are described in layout approval conditions | Final layout approval | Approval-record description; present delivery not verified |
| Community buildings | No size or facility details supplied | RERA amenity progress field: 0% | |
| Theme park | Listed in vendor data only | No RERA progress or approval evidence supplied |
7. Utilities, building services & safety
The final layout approval describes protected water supply, water supply, sewerage and drainage disposal systems, nala channelization, rainwater-harvesting structures, street lighting and electricity facilities. It also places responsibility for effective maintenance of services on the local body after handover. The records supplied do not establish current operational status or provide capacities, engineering schedules, or independent completion verification.
| Evidence in the supplied record | Protected water supply and water-supply system described in the final layout approval |
|---|---|
| Status / limitation | No source, storage or capacity details supplied; current operation not independently verified |
| Evidence in the supplied record | Sewerage disposal, drainage systems, side drains and nala channelization described in the approval |
|---|---|
| Status / limitation | No treatment capacity or operating evidence supplied |
| Evidence in the supplied record | Rainwater-harvesting structures and pits described in the approval |
|---|---|
| Status / limitation | No capacity or completion verification supplied |
| Evidence in the supplied record | Electricity facilities and street lighting described in the approval |
|---|---|
| Status / limitation | No supply, substation capacity or backup details supplied |
| Evidence in the supplied record | No project-specific fire-system details supplied |
|---|---|
| Status / limitation | Not established by the supplied records |
| Evidence in the supplied record | No project-specific details supplied |
|---|---|
| Status / limitation | Not established by the supplied records |
8. Location, access & connectivity
The registered project location is Hajipur, Mancherial District, Telangana, PIN 504207, in revenue village Hajipur, on Survey Nos. 42/A, 42/B and 42/C. The filed east boundary is described as “12M W ROAD”; the final layout approval also records internal roads, including a 33-foot road entry.
The supplied location data lists the nearest sampled Outer Ring Road interchange at approximately 186.1 km. It does not provide other measured distances or travel times.
9. Developer & development status
The TG-RERA certificate names Vazeer Sultan as promoter. The supplied material does not establish the promoter’s legal entity type, corporate registration identifiers, registered office for a corporate entity, or official project contact details. The certificate lists the promoter’s address as House No. 42-51/2, Mandamarry, Mandamarry Mandal, Mancherial, PIN 504231.
The RERA header reports 80% completeness, and Form B contains a promoter undertaking to complete the project by 02/12/2024. These are filed/project-declared records, not an independent site progress assessment. The project is a plotted layout; no tower- or building-wise construction stages are supplied.
10. Approvals, official records & documents
TG-RERA registration: Form C certificate for GREEN ACRES, registration P01200008273, covering Survey Nos. 42/A, 42/B and 42/C; validity stated as 24/05/2024–02/12/2024
Principal layout approval: Final Technical Layout Pattern TLP. No.4/2021/DTCPO/MNCL, dated 11/06/2024, issued by the District Town and Country Planning Officer, Mancherial District
Draft layout approval: Draft Technical Layout Pattern Draft-TLP.No.04/2021/DTCPO/MNCL, dated 02-12-2021
Layout and infrastructure record: Final layout approval describes plot, road and open-space allocations and layout-level utility provisions
Promoter declaration: Form B affidavit/declaration, dated 02/05,2024, including the promoter’s completion undertaking and project-account declarations
Completion / occupancy record: No separate project completion certificate or building occupancy certificate supplied in the reviewed materials
Plan and connectivity records: HMDA Master Plan 2031 zoning sheet is image-only and no survey-specific zone determination is supplied; the public HMDA DPMS layout lookup was unavailable in the supplied evidence
Frequently asked questions
Is GREEN ACRES registered with Telangana RERA?
Yes. GREEN ACRES is registered with the Telangana Real Estate Regulatory Authority as P01200008273; the registration status is New Project.
Who is the developer of GREEN ACRES?
The promoter named in the RERA registration is VAZEER.
Where is GREEN ACRES located?
GREEN ACRES is in HAZIPUR, Hajipur, Pantancheruvu, Mancherial, Telangana (504207).
When will GREEN ACRES be completed?
The promoter's proposed date of completion filed with RERA is 02/12/2024. This is the promoter's declaration, not a guarantee.
More projects in Pantancheruvu