Sign in

GREENMETROs TULASI PRIDE

GREENMETRO INFRATECH & PROJECTS PRIVATE LIMITED · Sangareddy · RERA P01100006584

GREENMETROs TULASI PRIDE is a plotted development at Budhera Gram Panchayat, Budhera village, Munipally mandal, Sangareddy district. The registered promoter is GREENMETRO INFRATECH & PROJECTS PRIVATE LIMITED. The registered land area is 101171.41 sq.m, and the draft layout approval describes 342 plots; towers, blocks, floors and plot configurations are not disclosed. Its TG-RERA registration is P01100006584, and its proposed completion date is 30/11/2026.

More from Greenmetro Infratech & Projects Pvt Ltd · 12 projects →

01What we found

Period endedTG-RERA registration ran to 1 Apr 2026 - check its extension on TG-RERA
20documents on file - each fact links to its page
27court cases on this project's land (survey 148, 150, 151, 152, 153, Budhera)
7items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

7 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldRecord
Registered project nameGREENMETROs TULASI PRIDE RERA record
Project typePlotted development; the filed layout approval describes a draft layout of plots. RERA record RERA filing
Phase / registered portionNo separate phase name is disclosed. The RERA certificate identifies the registered project against the listed survey numbers.
TG-RERA registrationP01100006584, issued 07/07/2023; certificate states validity through 01/04/2026. Registration validity is distinct from the completion date. RERA record
Registered promoterGREENMETRO INFRATECH & PROJECTS PRIVATE LIMITED RERA record
RERA status in supplied recordRegistration certificate supplied; no extension is recorded in that certificate. Current status after its stated expiry is not established by the certificate.

Land and geographic identity

FieldRecord
LocalityBudhera Gram Panchayat RERA record RERA filing
Revenue villageBudhera RERA record
MandalMunipally (also recorded as MUNPALLY) RERA record
District / PINSangareddy / 502345 RERA record
Project survey numbers and subdivisions147/P, 148/P, 149/P, 150/P, 151/P, 152/P, 153/P and 155/P RERA record
Registered site extentRERA land details state 101171.41 sq.m total area and 101171.41 sq.m net area, with affected area recorded as 00 sq.m. RERA filing
Draft layout areaThe DTCP-filed draft layout approval states Ac. 25.00 Cents; 121000.00 Sq. Yds.
BoundariesNot disclosed in the supplied project identity record. RERA filing

Development identity

FieldRecord
Sanctioning authorityDirector of Town and Country Planning; the draft layout approval is delegated to Budhera Gram Panchayat. Approvals record
Principal approvalDraft - TLP.No.79/2023/H, dated 01-04-2023; file reference Lr.Roc.No.10049/1695/2023/e-Panchayat. Approvals record
Development described in approvalDraft technical layout pattern for 342 plots. The approval expressly identifies itself as draft and says it is not proof of land title.
Approved built-up areaNot disclosed as applicable to this plotted layout. RERA fields list 60083.67 sq.m as “Approved Built up Area” and 9052.18 sq.m as “Mortgage Area”; the supplied records do not explain the built-up-area field in relation to this plotted development. RERA filing
Towers / blocks / floor configurationNot applicable or not disclosed for this plotted layout; no building-floor schedule is supplied.
Layout land-use figures in draft approvalOpen space: Ac. 2.50 Cents; 12100.00 Sq. Yds. (10.00%). Road area: Ac. 7.653 Cents; 37040.52 Sq. Yds. (30.61%). Plotted area: Ac. 14.847 Cents; 71859.48 Sq. Yds. (59.39%). Mortgage area: Ac. 2.237 Cents; 10827.08 Sq. Yds. (15.06%).
ParkingNo parking-space count or parking arrangement is supplied for the layout.

Offering and status

FieldRecord
OfferingPlots; the draft approval records 342 plots.
RERA-filed plot sizes / inventoryPlot-size bands, plot-wise inventory, booked counts and available counts are not supplied in the reviewed data. RERA record Document index
Marketing-reported plot sizesThe promoter’s website listing reports plots of 1485 Sq. Ft. and 4428 Sq. Ft.; these are marketing details, not figures established by the supplied RERA inventory. Promoter website
Construction / development stageRERA amenity records show 0% progress for listed infrastructure items; this is a filed progress figure, not an independent site inspection. RERA amenities
Completion dateRERA header gives proposed completion 30/11/2026. Form B separately records an undertaking date of 01-04-2026. RERA record
Occupancy / completion certificateNo occupancy or completion certificate is supplied. The project is a plotted layout; the supplied record does not establish a phase-wise or plot-wise certificate status. Document index

2. The project story

GREENMETROs TULASI PRIDE is registered as a plotted development at Budhera Gram Panchayat, Budhera village, Munipally mandal, Sangareddy district. Its TG-RERA record identifies the land as survey subdivisions 147/P, 148/P, 149/P, 150/P, 151/P, 152/P, 153/P and 155/P, and records a proposed completion date of 30/11/2026. RERA record

The filed DTCP document describes a draft technical layout pattern for 342 plots. It allocates land to plotted area, roads, open space and a mortgage area, and lists infrastructure works including roads, drains, water supply, sewerage disposal, street lighting and rainwater-harvesting pits. These are approval-document provisions; the supplied records do not independently verify their completion. The RERA amenity table records 0% progress for its listed items, while marking some facilities “YES”; these are filing entries, not site-verified completion. RERA amenities

The registration certificate states validity through 01/04/2026, while the RERA header gives a proposed completion date of 30/11/2026. No extension or completion/occupancy certificate is included in the supplied documents. RERA record Document index

3. Master plan, architecture & building design

The supplied plan evidence is for a plotted layout, not a residential building or apartment scheme. The draft approval identifies 342 plots and gives a layout area of Ac. 25.00 Cents; 121000.00 Sq. Yds. Its stated land-use breakdown is:

Layout componentAreaShare stated in approval
Plotted areaAc. 14.847 Cents; 71859.48 Sq. Yds.59.39%
Road areaAc. 7.653 Cents; 37040.52 Sq. Yds.30.61%
Open spaceAc. 2.50 Cents; 12100.00 Sq. Yds.10.00%
Mortgage areaAc. 2.237 Cents; 10827.08 Sq. Yds.15.06% of saleable land, as described in the approval

The approval identifies mortgage plots as Plot Nos. 127 to 131, 235 to 243 and 314 to 342, in favour of Budhera Gram Panchayat. It also requires open-space and road areas to be transferred to the Gram Panchayat by registered gift deed before final layout release.

The actual layout drawing is not available in extracted form in the supplied evidence: the layout-plan document is listed but not extracted, and there is no layout-sheet record. Accordingly, plot arrangement, plot-by-plot dimensions, road widths, and the precise position of open spaces cannot be described here. Document index Floor plans

4. Homes, configurations & floor plans

This is a plotted project, not an apartment configuration schedule. The draft approval states 342 plots, but the supplied RERA data does not provide a plot-wise schedule, plot-size distribution, booked/available inventory, or RERA-filed saleable area by plot. RERA record

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
Plots342 in draft layout approvalNot disclosedNot disclosedNot disclosedNot applicableNot disclosed

The promoter’s website listing reports plot sizes of 1485 Sq. Ft. and 4428 Sq. Ft.; these are attributed marketing details, not RERA-filed plot-area measurements. Promoter website No software-measured plot dimensions or floor-plan measurements are available; the supplied drawing record says two drawings are pending scan and none has been measured. Floor plans

5. Parking & vehicle circulation

The supplied records do not establish a parking-space count, visitor or accessible parking provision, parking allotments, or a dedicated parking layout. The draft approval identifies road area and requires roads to be opened for accessibility to neighbouring sites; it does not provide road widths, driveway geometry, or a separate parking plan. Any parking drawn or advertised elsewhere would need to be distinguished from a legally documented exclusive plot entitlement; no such allocation evidence is supplied.

6. Amenities, recreation & open spaces

The draft layout approval lists planned infrastructure works, while the RERA amenity record contains availability entries and 0% progress figures. The supplied evidence does not establish any listed facility as independently verified complete.

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Open spaceAc. 2.50 Cents; 12100.00 Sq. Yds. (10.00%)Draft layout approvalApproval allocation; transfer by registered gift deed required before final layout release. Completion/transfer not verified.
Greenery / avenue plantationGreenery in the layout, including avenue plantation in public open spacesDraft layout approvalRequired/planned; no completed status verified.
Community buildingsListed as a RERA amenity itemRERA amenity record RERA amenities0%; not independently verified.
Internal roads and footpathsLayout road area stated as Ac. 7.653 Cents; 37040.52 Sq. Yds. (30.61%)Draft layout approvalRERA progress 0%; no independent completion verification.
Fencing of open spacesFencing of open spaces requiredDraft layout approvalRequired/planned; completion not verified.
Sports / recreation facilitiesNo specific sports facility or size established in the supplied RERA recordsRERA amenities Document indexNot established.

The promoter’s website listing mentions a swimming pool, gym, clubhouse, children’s play area and common garden, among other features; these are marketing claims and are not established here as approved or delivered facilities. Promoter website

7. Utilities, building services & safety

The draft layout approval lists the following infrastructure works. They should be read as approval-document requirements or planned works, not as confirmation of construction or operational service:

Water supply
Evidence in supplied recordsApproval lists a protected water supply system; RERA amenity record marks “Water Supply” available “YES” with 0% progress.
Status indicated by evidenceFiled/approval provision; source, capacity, storage and completed operation not established. RERA amenities
Sewerage and drainage
Evidence in supplied recordsApproval lists sewerage disposal, side drains, and construction of drains and channelization of nalas. RERA records “Sewerage … STP” and storm-water drains as “YES,” each with 0% progress.
Status indicated by evidenceNo STP capacity, design, reuse arrangement or completed status established. RERA amenities
Rainwater management
Evidence in supplied recordsApproval lists rainwater-harvesting pits; RERA marks water conservation/rainwater harvesting “YES” with 0% progress.
Status indicated by evidenceProvision recorded; completion not independently verified. RERA amenities
Electrical and street lighting
Evidence in supplied recordsApproval lists street lighting and electricity facilities; RERA marks electrical meter room/sub-station/receiving station “YES” with 0% progress.
Status indicated by evidenceProvision recorded; capacity, supply details and completion not established. RERA amenities
Energy management
Evidence in supplied recordsRERA amenity record marks energy management “YES” with 0% progress.
Status indicated by evidenceFiled entry only; system details and completion not established. RERA amenities
Fire safety
Evidence in supplied recordsRERA amenity record marks fire protection/fire safety requirements “YES” with 0% progress.
Status indicated by evidenceFiled entry only; specific systems, clearances and completion are not supplied. RERA amenities
Waste management
Evidence in supplied recordsRERA lists solid-waste management and disposal, with no supplied progress value establishing completion.
Status indicated by evidenceFacility details and status not established. RERA amenities
Accessibility
Evidence in supplied recordsDraft approval requires roads to be opened for access to neighbouring sites.
Status indicated by evidenceNo accessible routes, ramps or pedestrian-separation details supplied.

8. Location, access & connectivity

The registered location is Budhera Gram Panchayat, Budhera village, Munipally mandal, Sangareddy district, Telangana, PIN 502345. RERA record The supplied cadastral geocode identifies a parcel centroid at 17.63790, 77.85068. Location record Cadastral map

The location dataset gives the nearest sampled Outer Ring Road interchange at approximately 45.0 km. Location record No other measured approach-road distances or public-transport details are supplied. The promoter’s website listing claims the project is next to NH65; this is a promoter-marketing statement and is not independently established by the supplied location records. Promoter website

9. Developer & development status

The registered promoter is GREENMETRO INFRATECH & PROJECTS PRIVATE LIMITED, a company. Its GSTIN is 36AAFCG5455R1ZW. The project record lists the promoter address as APURUPA TURBO, ROAD NO 36, BUDHERA, BUDHERA GRAMPANCHAYAT, MUNPALLY, Sangareddy, 502345. Corporate record RERA record

The RERA record identifies BEEJAN BEGUM as a landowner under a revenue-share arrangement. Parties record The approval document names M/s. Green Metro Infratech & Projects Pvt. Ltd. as applicant/developer and records Sri Boddu Ashok as representing the company in the application. The RERA Form B declaration is signed by B. ADITHYA, identified as an authorized signatory.

The RERA header gives proposed completion as 30/11/2026; the Form B declaration records 01-04-2026 as the completion undertaking. The supplied registration certificate states validity through 01/04/2026. These are separate filed dates; no extension, updated completion schedule, or occupancy/completion certificate is supplied. RERA record

10. Approvals, official records & documents

TG-RERA registration certificate
Supplied evidenceForm C, project P01100006584, dated 07/07/2023, valid through 01/04/2026
Scope / noteNames the registered project and survey numbers; current post-expiry status is not established by the certificate.
Principal layout approval
Supplied evidenceDTCP Draft - TLP.No.79/2023/H, dated 01-04-2023; file Lr.Roc.No.10049/1695/2023/e-Panchayat
Scope / noteDraft technical layout pattern for 342 plots; delegated to Budhera Gram Panchayat.
Application reference
Supplied evidence10049/1695 Approvals record
Scope / noteApplication number stated in the approval record.
Form B declaration
Supplied evidencePromoter affidavit/declaration, including land-title and encumbrance statements and completion undertaking
Scope / notePromoter declaration, not an independent title finding.
Layout plan
Supplied evidenceListed as a required project document but not extracted in the supplied record Document index
Scope / notePlot-by-plot drawing details are unavailable here.
Completion / occupancy certificate
Supplied evidenceNot supplied Document index
Scope / noteNo certificate or phase/plot scope can be confirmed from this evidence.

Frequently asked questions

Is GREENMETROs TULASI PRIDE registered with Telangana RERA?

Yes. GREENMETROs TULASI PRIDE is registered with the Telangana Real Estate Regulatory Authority as P01100006584; the registration status is New Project.

Who is the developer of GREENMETROs TULASI PRIDE?

The promoter named in the RERA registration is GREENMETRO INFRATECH & PROJECTS PRIVATE LIMITED.

Where is GREENMETROs TULASI PRIDE located?

GREENMETROs TULASI PRIDE is in BUDHERA GRAMPANCHAYAT, BUDHERA, MUNPALLY, Sangareddy, Telangana (502345).

When will GREENMETROs TULASI PRIDE be completed?

The promoter's proposed date of completion filed with RERA is 30/11/2026. This is the promoter's declaration, not a guarantee.

More projects in Budhera