Mitra Colony
YEANNEPALLY SATHYANARAYANA REDDY AND OTHERS · Vikarabad · RERA P02100008743
MITRA COLONY is a plotted development at Gangaram, Vikarabad Mandal, Vikarabad District. The registered promoter developing it is YEANNEPALLY SATHYANARAYANA REDDY AND OTHERS. The project has a RERA-filed land extent of 16,692.45 sq. m and comprises 52 open residential plots; no tower or floor configuration is stated. It is registered under TG-RERA No. P02100008743, with proposed completion listed as 30/11/2026.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
8 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered project name | MITRA COLONY RERA record |
| Project type | Plotted development / residential layout RERA record RERA filing |
| Phase / registered portion | Phase not separately identified; registration is for the project land described below. RERA record |
| TG-RERA registration | P02100008743 RERA record |
| Registration validity | 6 September 2024 to 23 July 2026, unless extended by the Authority. This is the registration period, not a statement of the construction deadline or of occupancy certification. RERA record |
| Registered promoter | YEANNEPALLY SATHYANARAYANA REDDY AND OTHERS RERA record RERA filing |
| RERA status in supplied record | New Project; registration certificate on file. The supplied record does not establish whether the registration was extended after 23 July 2026. RERA record |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality / revenue village | Gangaram; the approval identifies Gangaram Revenue Village. RERA record RERA filing |
| Mandal / district / PIN | Vikarabad Mandal, Vikarabad District; PIN 501102 in the project record. RERA record RERA filing |
| Project survey numbers and subdivisions | 82/2/2/2, 82/2/1, 82/1/2/2, 82/2/2/1, 82/1/2/1/2, 82/1/2/1/1/2 and 82/1/2/1/1/1/2 RERA record |
| RERA-filed land extent | 16,692.45 sq. m RERA filing |
| Layout-plan area | 16,692.05 sq. m net layout area, as read from the layout drawing. Layout record |
| Boundaries as filed | East: LAND OF HANMANTHAPPA; West: LAND OF VEERANNA AND EXISTING DTCP LAYOUT; North: LAND OF OTHERS; South: OWNERS LAND. RERA filing |
| Cadastral location point | Parcel centroid reported at 17.328649958997627, 77.89752155283011; this is a mapped point, not a surveyed boundary description. Cadastral map |
Development identity
| Item | Project record |
|---|---|
| Sanctioning authority | TS-DTCP; the tentative layout approval is issued by Vikarabad Municipality/Municipal Corporation, with the approval record identifying delegation to Vikarabad Municipality. |
| Principal approval | Layout approval No. 0028/LO/3042/2023; drawing records file No. G/23/2014 and date 27-12-2023. Approvals record |
| Tentative layout approval | No. 0033/LO/3042/2024, approved 23 July 2024; application No. 014206/LO/DTCP/3042/0046/2023. Approvals record |
| Approved built-up area | 0.00 proposed built-up area, both excluding and including parking, in the layout-plan parameters. This is a plotted layout, not a building plan. |
| Building / floor configuration | Not disclosed for project buildings; the filed layout is for open plots. No tower count, building floors or parking levels are established by the project approval materials supplied. |
| Plot count | Layout drawing states 52 individual sub-plots; tentative-layout approval extraction also states 52 No's. |
Offering and status
| Item | Project record |
|---|---|
| Offering | Open residential plots; no RERA-filed unit configuration or saleable-area schedule is supplied in this evidence set. RERA record |
| Plot sizes | The layout drawing’s software-read schedule covers 52 plots: 94.88–436.96 sq. m (smallest to largest); the size bands are listed below. These are drawing-derived, not RERA-filed saleable-area figures. Layout record |
| Booked / available | Not established in the supplied project evidence. The registration certificate requires quarterly updates, but no inventory figures are provided here. |
| Construction / development stage | The project is registered and has a tentative layout approval. The evidence does not provide independently verified site progress or establish that the required infrastructure is complete. RERA record |
| Completion dates | Form B declares completion by 23 July 2026; the registration record lists proposed completion as 30/11/2026. These are recorded as separate supplied dates; the evidence does not establish a revised completion approval. RERA record |
| OC / completion certificate | No occupancy certificate or completion certificate is identified in the supplied project documents. For a plotted layout, the approval materials instead describe infrastructure completion and release of the tentative layout. |
2. The project story
Mitra Colony is a proposed residential plotted layout at Gangaram Revenue Village, Vikarabad Mandal, Vikarabad District, over the seven survey/subdivision entries set out in the identity table. The RERA filing describes 16,692.45 sq. m of land, while the approved drawing describes a net layout area of 16,692.05 sq. m. RERA filing
The layout drawing organizes the site into open plots, internal roads, park/open space, social-infrastructure land and utility land. It identifies 52 plots and no proposed built-up area.
3. Master plan, architecture & building design
This is a plotted layout rather than an apartment or multi-storey building development. The drawing reports a net layout area of 16,692.05 sq. m and the following land-use allocation: Layout record
| Layout use | Area | Share shown on drawing |
|---|---|---|
| Plotted area | 9,601.28 sq. m | 57.52% |
| Roads | 4,828.62 sq. m | 28.93% |
| Organized open space / park | 1,592.21 sq. m | 9.54% |
| Social infrastructure | 500.16 sq. m | 3.00% |
| Utility area | 169.80 sq. m | 1.02% |
| Amenity area | 0.00 sq. m | 0.00% |
The drawing identifies 9 mts wide Internal Road, 18 mts wide Internal Road, 18.00 MT WIDE EXISTING ROAD and 18.00 MT WIDE PROPOSED ROAD. It also names “Area for Social Infrastructure Utility,” “Tot-lot,” “STP,” “WTP” and “Electrical Transformer” among the amenities/utilities labels; the supplied material does not confirm construction or commissioning of these facilities.
The layout approval describes a 2,257 sq. yd mortgage area, represented by plots 55, 53, 52, 51, 49, 48, 1, 47, 54 and 50; the approval records mortgage deed No. 2690/2024. The approval conditions require infrastructure completion and release of the mortgaged land before final layout release.
The drawing-derived plot schedule identifies 52 plots with sizes ranging from 94.88 sq. m to 436.96 sq. m. Size bands are: 3 plots at 100–150 sq. yd; 25 at 150–200 sq. yd; 20 at 200–250 sq. yd; 2 at 400–500 sq. yd; and 2 at 500–1000 sq. yd. These are software-read from the approved drawing and should be checked against the drawing schedule. Layout record
The tentative approval requires the layout owner/developer to complete infrastructure and amenities within two years of approval—stated as 23 July 2026—and provides for possible extension on application. The supplied materials do not establish current on-site completion or a final layout release.
4. Homes, configurations & floor plans
The RERA evidence identifies a plotted development, not apartment configurations. No RERA-filed unit-type, booked/available inventory or saleable-area schedule is supplied. The layout drawing’s software-read plot schedule reports: RERA record Layout record
| Offering | Count | Drawing-derived size information |
|---|---|---|
| Open plots | 52 | 94.88–436.96 sq. m; median 167.18 sq. m |
| 100–150 sq. yd band | 3 | 84–125 sq. m |
| 150–200 sq. yd band | 25 | 125–167 sq. m |
| 200–250 sq. yd band | 20 | 167–209 sq. m |
| 400–500 sq. yd band | 2 | 334–418 sq. m |
| 500–1000 sq. yd band | 2 | 418–836 sq. m |
The layout evidence describes land parcels only; it does not supply house designs, room layouts, carpet areas or building specifications. Plot sizes above are software-measured from the drawing, not RERA-filed saleable areas. No booked or available plot counts are established in the supplied material. Layout record
5. Parking & vehicle circulation
No common parking area is allocated in the layout-plan land-use schedule (0.00 sq. m). The supplied approval records no sanctioned parking-space count, visitor or accessible parking, or plot-specific parking allocation. The drawing identifies internal roads of 9 mts and 18 mts width and an existing and proposed 18.00 MT road; it does not establish parking arrangements or exclusive parking rights for individual plot purchasers.
6. Amenities, recreation & open spaces
The layout drawing and tentative approval identify planned open-space, social-infrastructure, utility and site-service provisions. The supplied records do not establish that any item is complete or independently verified.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Park / organized open space | 1,592.21 sq. m; drawing states 9.54% | Layout record | Reserved in the plan; completion not established. |
| Tot-lot | Named on the layout drawing; no size stated | Drawing label only; completion not established. | |
| Social infrastructure | 500.16 sq. m; drawing states 3.00% | Layout record | Land reserved; specific facility and completion not established. |
| Utility area | 169.80 sq. m; drawing states 1.02% | Layout record | Land reserved; facility completion not established. |
| Water reservoir / overhead tank and water-treatment provision | Listed in tentative-layout approval conditions or drawing labels; no capacity stated | Required/planned provision; completion not established. | |
| Sewerage treatment / septic system | Approval lists septic tank and sewerage treatment plant; no capacity stated | Required/planned provision; completion not established. | |
| Electrical transformer | Named on drawing and in approval conditions | Planned provision; installation/commissioning not established. | |
| Roads and footpaths | Road area 4,828.62 sq. m; internal roads marked 9 mts and 18 mts | Layout record | Approved layout provision; physical completion not established. |
7. Utilities, building services & safety
The tentative-layout approval describes infrastructure to be provided by the layout applicant: road formation with black top, storm-water drains, underground drainage lines, a common septic tank/STP, internal water-supply pipelines and overhead tank, an assured water-supply source, electrical supply lines and street lights, avenue plantation, park development and rainwater-harvesting pits. It also names a water reservoir, solid-waste management and an electrical transformer. These are approval conditions or planned provisions; the evidence does not establish completion, capacities, commissioning or independent testing.
The RERA amenity checklist marks internal roads and footpaths, water supply, sewerage, storm-water drains, green strip/tot-lot/park, rainwater harvesting, electrical meter room/sub-station/receiving station and aggregate recreational open space as “YES”; the listed completion percentages are 0. No source, storage or treatment capacity, electrical-load information, backup system, fire-safety design, accessibility measures, security system or waste-management operating details are established by the project approval documents supplied. RERA amenities
8. Location, access & connectivity
The registered project location is Gangaram, Vikarabad Mandal, Vikarabad District, Telangana, PIN 501102. The approved layout describes the site as being in Gangaram Revenue Village. RERA record
The layout drawing marks internal roads of 9 mts and 18 mts, an existing 18.00 MT WIDE EXISTING ROAD and a 18.00 MT WIDE PROPOSED ROAD. A mapped cadastral parcel centroid is reported at 17.328649958997627, 77.89752155283011. The supplied location data gives the nearest sampled Outer Ring Road interchange as approximately 44.5 km; no other verified road, public-transport or landmark distances are provided. Location record Cadastral map
9. Developer & development status
The registered promoter is YEANNEPALLY SATHYANARAYANA REDDY AND OTHERS. The project record describes the organization type as “Others” and its description as partnership; the evidence does not supply a verified corporate registration number or registered-office details. RERA record RERA filing
A Form B affidavit dated 19 August 2024 is signed by Yeannepally Sathyanarayana Reddy as authorized signatory. It declares a completion period ending 23 July 2026, states that the land is free from encumbrances, and includes the prescribed project-fund and approval undertakings. These are promoter declarations, not independent verification of title, progress or completion.
The tentative-layout approval requires infrastructure and amenities to be completed within two years from 23 July 2024, and provides for a possible one-year extension on specific request and payment of 20% of the total fee paid at tentative-layout approval. The supplied evidence does not establish whether an extension was sought or granted, whether works are complete, or whether the final layout has been released.
10. Approvals, official records & documents
| Reference and scope | Form C for MITRA COLONY, registration No. P02100008743; validity stated as 6 September 2024 to 23 July 2026. |
|---|
| Reference and scope | TS-DTCP layout approval No. 0028/LO/3042/2023; file No. G/23/2014; drawing identifies date 27-12-2023. |
|---|
| Reference and scope | Vikarabad Municipality/Municipal Corporation No. 0033/LO/3042/2024, approved 23 July 2024; application No. 014206/LO/DTCP/3042/0046/2023. |
|---|
| Reference and scope | Two-sheet layout drawing for the listed Gangaram survey/subdivision parcels; includes plot schedule, land-use schedule and road markings. |
|---|
| Reference and scope | Form B affidavit dated 19 August 2024, signed by the authorized signatory. |
|---|
| Reference and scope | None identified in the supplied project documents. |
|---|---|
| Evidence | Document index |
| Reference and scope | Not identified in the supplied project documents; the tentative approval describes conditions to be met before release. |
|---|
1. Project at a glance
Project identity
Registered project name: MITRA COLONY
Project type: Plotted development / residential layout
Phase / registered portion: Phase not separately identified; registration is for the project land described below.
TG-RERA registration: P02100008743
Registration validity: 6 September 2024 to 23 July 2026, unless extended by the Authority. This is the registration period, not a statement of the construction deadline or of occupancy certification.
Registered promoter: YEANNEPALLY SATHYANARAYANA REDDY AND OTHERS
RERA status in supplied record: New Project; registration certificate on file. The supplied record does not establish whether the registration was extended after 23 July 2026.
Land and geographic identity
Locality / revenue village: Gangaram; the approval identifies Gangaram Revenue Village.
Mandal / district / PIN: Vikarabad Mandal, Vikarabad District; PIN 501102 in the project record.
Project survey numbers and subdivisions: 82/2/2/2, 82/2/1, 82/1/2/2, 82/2/2/1, 82/1/2/1/2, 82/1/2/1/1/2 and 82/1/2/1/1/1/2
RERA-filed land extent: 16,692.45 sq. m
Layout-plan area: 16,692.05 sq. m net layout area, as read from the layout drawing.
Boundaries as filed: East: LAND OF HANMANTHAPPA; West: LAND OF VEERANNA AND EXISTING DTCP LAYOUT; North: LAND OF OTHERS; South: OWNERS LAND.
Cadastral location point: Parcel centroid reported at 17.328649958997627, 77.89752155283011; this is a mapped point, not a surveyed boundary description.
Development identity
Sanctioning authority: TS-DTCP; the tentative layout approval is issued by Vikarabad Municipality/Municipal Corporation, with the approval record identifying delegation to Vikarabad Municipality.
Principal approval: Layout approval No. 0028/LO/3042/2023; drawing records file No. G/23/2014 and date 27-12-2023.
Tentative layout approval: No. 0033/LO/3042/2024, approved 23 July 2024; application No. 014206/LO/DTCP/3042/0046/2023.
Approved built-up area: 0.00 proposed built-up area, both excluding and including parking, in the layout-plan parameters. This is a plotted layout, not a building plan.
Building / floor configuration: Not disclosed for project buildings; the filed layout is for open plots. No tower count, building floors or parking levels are established by the project approval materials supplied.
Plot count: Layout drawing states 52 individual sub-plots; tentative-layout approval extraction also states 52 No's.
Offering and status
Offering: Open residential plots; no RERA-filed unit configuration or saleable-area schedule is supplied in this evidence set.
Plot sizes: The layout drawing’s software-read schedule covers 52 plots: 94.88–436.96 sq. m (smallest to largest); the size bands are listed below. These are drawing-derived, not RERA-filed saleable-area figures.
Booked / available: Not established in the supplied project evidence. The registration certificate requires quarterly updates, but no inventory figures are provided here.
Construction / development stage: The project is registered and has a tentative layout approval. The evidence does not provide independently verified site progress or establish that the required infrastructure is complete.
Completion dates: Form B declares completion by 23 July 2026; the registration record lists proposed completion as 30/11/2026. These are recorded as separate supplied dates; the evidence does not establish a revised completion approval.
OC / completion certificate: No occupancy certificate or completion certificate is identified in the supplied project documents. For a plotted layout, the approval materials instead describe infrastructure completion and release of the tentative layout.
2. The project story
Mitra Colony is a proposed residential plotted layout at Gangaram Revenue Village, Vikarabad Mandal, Vikarabad District, over the seven survey/subdivision entries set out in the identity table. The RERA filing describes 16,692.45 sq. m of land, while the approved drawing describes a net layout area of 16,692.05 sq. m.
The layout drawing organizes the site into open plots, internal roads, park/open space, social-infrastructure land and utility land. It identifies 52 plots and no proposed built-up area.
3. Master plan, architecture & building design
This is a plotted layout rather than an apartment or multi-storey building development. The drawing reports a net layout area of 16,692.05 sq. m and the following land-use allocation:
| Layout use | Area | Share shown on drawing |
|---|---|---|
| Plotted area | 9,601.28 sq. m | 57.52% |
| Roads | 4,828.62 sq. m | 28.93% |
| Organized open space / park | 1,592.21 sq. m | 9.54% |
| Social infrastructure | 500.16 sq. m | 3.00% |
| Utility area | 169.80 sq. m | 1.02% |
| Amenity area | 0.00 sq. m | 0.00% |
The drawing identifies 9 mts wide Internal Road, 18 mts wide Internal Road, 18.00 MT WIDE EXISTING ROAD and 18.00 MT WIDE PROPOSED ROAD. It also names “Area for Social Infrastructure Utility,” “Tot-lot,” “STP,” “WTP” and “Electrical Transformer” among the amenities/utilities labels; the supplied material does not confirm construction or commissioning of these facilities.
The layout approval describes a 2,257 sq. yd mortgage area, represented by plots 55, 53, 52, 51, 49, 48, 1, 47, 54 and 50; the approval records mortgage deed No. 2690/2024. The approval conditions require infrastructure completion and release of the mortgaged land before final layout release.
The drawing-derived plot schedule identifies 52 plots with sizes ranging from 94.88 sq. m to 436.96 sq. m. Size bands are: 3 plots at 100–150 sq. yd; 25 at 150–200 sq. yd; 20 at 200–250 sq. yd; 2 at 400–500 sq. yd; and 2 at 500–1000 sq. yd. These are software-read from the approved drawing and should be checked against the drawing schedule.
The tentative approval requires the layout owner/developer to complete infrastructure and amenities within two years of approval—stated as 23 July 2026—and provides for possible extension on application. The supplied materials do not establish current on-site completion or a final layout release.
4. Homes, configurations & floor plans
The RERA evidence identifies a plotted development, not apartment configurations. No RERA-filed unit-type, booked/available inventory or saleable-area schedule is supplied. The layout drawing’s software-read plot schedule reports:
| Offering | Count | Drawing-derived size information |
|---|---|---|
| Open plots | 52 | 94.88–436.96 sq. m; median 167.18 sq. m |
| 100–150 sq. yd band | 3 | 84–125 sq. m |
| 150–200 sq. yd band | 25 | 125–167 sq. m |
| 200–250 sq. yd band | 20 | 167–209 sq. m |
| 400–500 sq. yd band | 2 | 334–418 sq. m |
| 500–1000 sq. yd band | 2 | 418–836 sq. m |
The layout evidence describes land parcels only; it does not supply house designs, room layouts, carpet areas or building specifications. Plot sizes above are software-measured from the drawing, not RERA-filed saleable areas. No booked or available plot counts are established in the supplied material.
5. Parking & vehicle circulation
No common parking area is allocated in the layout-plan land-use schedule (0.00 sq. m). The supplied approval records no sanctioned parking-space count, visitor or accessible parking, or plot-specific parking allocation. The drawing identifies internal roads of 9 mts and 18 mts width and an existing and proposed 18.00 MT road; it does not establish parking arrangements or exclusive parking rights for individual plot purchasers.
6. Amenities, recreation & open spaces
The layout drawing and tentative approval identify planned open-space, social-infrastructure, utility and site-service provisions. The supplied records do not establish that any item is complete or independently verified.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Park / organized open space | 1,592.21 sq. m; drawing states 9.54% | Reserved in the plan; completion not established. | |
| Tot-lot | Named on the layout drawing; no size stated | Drawing label only; completion not established. | |
| Social infrastructure | 500.16 sq. m; drawing states 3.00% | Land reserved; specific facility and completion not established. | |
| Utility area | 169.80 sq. m; drawing states 1.02% | Land reserved; facility completion not established. | |
| Water reservoir / overhead tank and water-treatment provision | Listed in tentative-layout approval conditions or drawing labels; no capacity stated | Required/planned provision; completion not established. | |
| Sewerage treatment / septic system | Approval lists septic tank and sewerage treatment plant; no capacity stated | Required/planned provision; completion not established. | |
| Electrical transformer | Named on drawing and in approval conditions | Planned provision; installation/commissioning not established. | |
| Roads and footpaths | Road area 4,828.62 sq. m; internal roads marked 9 mts and 18 mts | Approved layout provision; physical completion not established. |
7. Utilities, building services & safety
The tentative-layout approval describes infrastructure to be provided by the layout applicant: road formation with black top, storm-water drains, underground drainage lines, a common septic tank/STP, internal water-supply pipelines and overhead tank, an assured water-supply source, electrical supply lines and street lights, avenue plantation, park development and rainwater-harvesting pits. It also names a water reservoir, solid-waste management and an electrical transformer. These are approval conditions or planned provisions; the evidence does not establish completion, capacities, commissioning or independent testing.
The RERA amenity checklist marks internal roads and footpaths, water supply, sewerage, storm-water drains, green strip/tot-lot/park, rainwater harvesting, electrical meter room/sub-station/receiving station and aggregate recreational open space as “YES”; the listed completion percentages are 0. No source, storage or treatment capacity, electrical-load information, backup system, fire-safety design, accessibility measures, security system or waste-management operating details are established by the project approval documents supplied.
8. Location, access & connectivity
The registered project location is Gangaram, Vikarabad Mandal, Vikarabad District, Telangana, PIN 501102. The approved layout describes the site as being in Gangaram Revenue Village.
The layout drawing marks internal roads of 9 mts and 18 mts, an existing 18.00 MT WIDE EXISTING ROAD and a 18.00 MT WIDE PROPOSED ROAD. A mapped cadastral parcel centroid is reported at 17.328649958997627, 77.89752155283011. The supplied location data gives the nearest sampled Outer Ring Road interchange as approximately 44.5 km; no other verified road, public-transport or landmark distances are provided.
9. Developer & development status
The registered promoter is YEANNEPALLY SATHYANARAYANA REDDY AND OTHERS. The project record describes the organization type as “Others” and its description as partnership; the evidence does not supply a verified corporate registration number or registered-office details.
A Form B affidavit dated 19 August 2024 is signed by Yeannepally Sathyanarayana Reddy as authorized signatory. It declares a completion period ending 23 July 2026, states that the land is free from encumbrances, and includes the prescribed project-fund and approval undertakings. These are promoter declarations, not independent verification of title, progress or completion.
The tentative-layout approval requires infrastructure and amenities to be completed within two years from 23 July 2024, and provides for a possible one-year extension on specific request and payment of 20% of the total fee paid at tentative-layout approval. The supplied evidence does not establish whether an extension was sought or granted, whether works are complete, or whether the final layout has been released.
10. Approvals, official records & documents
| Reference and scope | Form C for MITRA COLONY, registration No. P02100008743; validity stated as 6 September 2024 to 23 July 2026. |
|---|
| Reference and scope | TS-DTCP layout approval No. 0028/LO/3042/2023; file No. G/23/2014; drawing identifies date 27-12-2023. |
|---|
| Reference and scope | Vikarabad Municipality/Municipal Corporation No. 0033/LO/3042/2024, approved 23 July 2024; application No. 014206/LO/DTCP/3042/0046/2023. |
|---|
| Reference and scope | Two-sheet layout drawing for the listed Gangaram survey/subdivision parcels; includes plot schedule, land-use schedule and road markings. |
|---|
| Reference and scope | Form B affidavit dated 19 August 2024, signed by the authorized signatory. |
|---|
| Reference and scope | None identified in the supplied project documents. |
|---|
| Reference and scope | Not identified in the supplied project documents; the tentative approval describes conditions to be met before release. |
|---|
Frequently asked questions
Is MITRA COLONY registered with Telangana RERA?
Yes. MITRA COLONY is registered with the Telangana Real Estate Regulatory Authority as P02100008743; the registration status is New Project.
Who is the developer of MITRA COLONY?
The promoter named in the RERA registration is YEANNEPALLY SATHYANARAYANA REDDY AND OTHERS.
Where is MITRA COLONY located?
MITRA COLONY is in Gangaram, Vikarabad, Telangana (501102).
When will MITRA COLONY be completed?
The promoter's proposed date of completion filed with RERA is 30/11/2026. This is the promoter's declaration, not a guarantee.