SRI SAI DEVELOPERS is a plotted development in Kodad, Kodad Mandal, Suryapet District. The registered promoter is MALLEBOINA VENKATESWARLU & OTHERS. The tentative residential layout records a land area of 37251.14 sq. m and 86 plots, with plot sizes ranging from 123.85 sq. m to 367.95 sq. m; towers and floors are not applicable to the filed plotted-layout offering. The project is registered with TG-RERA under P01900006633, and the promoter-declared completion deadline is 11/02/2025.

01What we found

Period endedTG-RERA registration ran to 11 Feb 2025 - check its extension on TG-RERA
21documents on file - each fact links to its page
0court cases on this project's land in the court records searched
10items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

10 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Kodad, Kodad, Suryapet · geocoded — approximate.

1. Project at a glance

Project identity

FieldProject record
Registered project nameSRI SAI DEVELOPERS RERA record
Project typePlotted development; the filed layout approval describes a tentative residential layout with 86 plots. RERA record
Phase / registered portionRegistered portion is not separately named; the TG-RERA certificate covers the project land and survey numbers listed below.
TG-RERA registration numberP01900006633
Registration validity26/07/2023 to 11/02/2025; the supplied certificate records no extension. This is the registration period, not a construction-completion or occupancy date.
Registered promoterMALLEBOINA VENKATESWARLU & OTHERS RERA record
RERA statusThe project is recorded as “New Project”; the supplied certificate’s stated validity ended on 11/02/2025. Current registration status is not established by the supplied record. RERA record

Land and geographic identity

FieldProject record
LocalityKodad RERA record
Revenue villageKodad (the layout approval says “Kodada Revenue Village”). RERA record
MandalKodad (the layout approval says “Kodada Mandal”). RERA record
District / PINSuryapet / 508206 RERA record
Project survey numbers and subdivisions455/AA2, 455/EE2, 246/2, 246/1, 455/AA1/1, 248/A1, 455/AA1/2, 455/E, 248/E1/3, 248/E1/2, 244/2, 455/E4, 455/E2, 455/E1, 248/AA1, 248/AA2/1, 248/E1/1, 455/EE1/1/1, 455/EE1/2, 455/EE1/1/2, 456/1/1/2, 456/1/1/1, 454/U1, 455/34. The approval and registration certificate list the last entry as 455/?34 and 455/34, respectively.
Registered site extentThe layout approval prints 9 Acer 8.19 Gts and 44552 Sq. Yds.
RERA land areaTotal/net area recorded in the project data: 37251.14 sq. m; affected area reported as 0. RERA filing Land records
BoundariesEast: ROAD WIDTH 30; West: OTHERS LAND; North: ROAD WIDTH - 12; South: OTHERS LAND. RERA filing

Development identity

FieldProject record
Sanctioning authorityKODADA Municipality/Municipal Corporation
Principal approvalTentative Layout Plan No. 0031/LO/3046/2023; application No. 012047/LO/DTCP/3046/0032/2022. The approval record lists approved date 12/02/2023. Approvals record
Approved built-up areaNot disclosed in the supplied layout approval. RERA filing
Building / tower count and floorsNot applicable to the filed plotted-layout offering; building-by-building permissions are not supplied.
ParkingNo project-wide parking-space count or parking allocation is established by the supplied records.
Approved versus RERA-declared unitsThe tentative layout approval records 86 plots. A separate RERA inventory count is not supplied.

Offering and status

FieldProject record
Unit typePlots in a tentative residential layout
Plot count and sizes86 plots. Software measurement from the approved layout drawing identifies 86 plots with sizes: smallest 123.85 sq. m (148.1 sq. yd), median 222.03 sq. m (265.5 sq. yd), largest 367.95 sq. m (440.1 sq. yd). Layout record
Booked / available countsNot disclosed in the supplied records. Document index
Construction / development stageAn architect’s Form 1A filed with TG-RERA certifies the registered project complete in all aspects, with completion date 30/11/2024. This is a filed professional certificate, not an independent site inspection in the supplied evidence.
Promoter-declared completion deadline11/02/2025 in Form B
Occupancy certificateForm 1A identifies OC No. 001678/FLT/DTCP/3046/0009/2024. The supplied extract does not establish its phase or plot-level scope.

2. The project story

SRI SAI DEVELOPERS is filed as a plotted residential layout in Kodad, Suryapet District. Its tentative layout approval records 86 plots and reserves land for plots, roads, open space, social infrastructure and utilities. The approval requires the applicant to carry out layout infrastructure works and states that the approval itself is not proof of land title.

The promoter’s Form B undertakes completion by 11/02/2025. Separately, an architect’s Form 1A filed with TG-RERA certifies completion of the registered project, dated 30/11/2024, and gives an occupancy-certificate number. These are distinct records: the deadline is the promoter’s undertaking, while Form 1A is an architect’s filed completion certification; the supplied material does not independently verify the works on site or establish the OC’s precise scope.

3. Master plan, architecture & building design

The filed development is a plotted layout, rather than an apartment or multi-building scheme. The tentative layout approval records 86 plots and the following land-use areas and shares:

Layout componentFigure in approvalShare
Plotted area4 Acer 31.52 Gts; 23174 Sq. Yds52.42%
Road area2 Acer 21.94 Gts; 12335 Sq. Yds27.9%
Open space (park)0 Acer 33.57 Gts; 4062 Sq. Yds9.19%
Social infrastructure0 Acer 13.42 Gts; 1624 Sq. Yds3.67%
Utilities0 Acer 3.72 Gts; 450 Sq. Yds1.02%
Mortgage area of plotted area0 Acer 42.18 Gts; 5104 Sq. Yds21.96%

Software measurement from the layout drawing identifies 86 plots; their areas range from 123.85 sq. m to 367.95 sq. m, with a median of 222.03 sq. m. These are drawing-derived measurements, not RERA-filed unit-area disclosures. Layout record

The approval identifies plots 65, 70, 57, 58, 59, 69, 56, 55, 72, 71, 63, 62, 61, 60, 66, 67, 68 and 64 as mortgaged to the Municipality/Municipal Corporation pending the stated layout-development and release process. The supplied drawing-derived record does not provide a building footprint, building height, floor configuration or building arrangement. Layout record

4. Homes, configurations & floor plans

This is a plotted offering, not a RERA-filed apartment configuration. The layout drawing’s software-measured plot sizes are shown below; no booked/available inventory split is supplied. The floor-plan data reports three drawings, but none contains a measured apartment plan suitable for deriving carpet areas. Layout record Floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
Plots, software-measured from layout drawing86Not disclosedNot disclosedNot disclosedNot applicableNot supplied
Drawing-derived plot-size bandPlot count
100–150 sq. yd (84–125 sq. m)1
150–200 sq. yd (125–167 sq. m)4
200–250 sq. yd (167–209 sq. m)21
250–300 sq. yd (209–251 sq. m)49
300–400 sq. yd (251–334 sq. m)10
400–500 sq. yd (334–418 sq. m)1

The individual-plot measurements and bands are software-derived from the approved layout drawing and should be checked against the drawing. No plot-specific allotment, saleable-area schedule or booking status is supplied. Layout record

5. Parking & vehicle circulation

The layout approval records 27.9% of the site as road area and requires all roads to be opened for access to neighbouring sites. It does not provide a parking-space count, visitor or accessible parking provision, parking allocation to individual plots, or EV charging details.

6. Amenities, recreation & open spaces

The project’s RERA amenity record marks the following items as available at 100%; this is a filed status, not independent verification of completion. The layout approval separately reserves land for park, social infrastructure and utilities. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Green strip / tot lot / parkOpen space reserved: 0 Acer 33.57 Gts; 4062 Sq. Yds; 9.19%RERA amenitiesRERA amenity record: 100%; independent completion verification not supplied
Social infrastructure site0 Acer 13.42 Gts; 1624 Sq. Yds; 3.67%Reserved in layout approval; facility details and delivery status not supplied
Community buildingsNo size or facility details suppliedRERA amenitiesRERA amenity record: 0%
Internal roads and footpathsRoad area: 2 Acer 21.94 Gts; 12335 Sq. Yds; 27.9%RERA amenitiesRERA amenity record: 100%; independent completion verification not supplied

7. Utilities, building services & safety

The tentative layout approval describes proposed layout works that include storm-water drains, underground drainage lines, common septic tank/STP, internal water-supply pipelines, an overhead tank, an assured water-supply source, electrical supply lines, street lights, transformer, avenue planting, park development and rainwater-harvesting pits. These are approval conditions and proposed works; the supplied record does not provide capacities or independent confirmation of installation or operation.

Water
RERA/approval recordWater supply marked 100% in the RERA amenity record; approval specifies internal pipelines, overhead tank and assured source.
Declared progress / verificationFiled status; independent verification and capacity not supplied. RERA amenities
Sewerage and drainage
RERA/approval recordSewerage (chamber, lines, septic tank, STP), storm-water drains, and treatment/disposal of sewage and sullage water marked 100%; approval describes underground drainage and a common septic tank/STP.
Declared progress / verificationFiled status; independent verification, treatment capacity and reuse details not supplied. RERA amenities
Electrical
RERA/approval recordElectrical meter room/sub-station/receiving station and street lighting marked 100%; approval describes electrical lines and transformer.
Declared progress / verificationFiled status; independent verification and capacity not supplied. RERA amenities
Rainwater / water conservation
RERA/approval recordWater conservation and rainwater harvesting marked 100%; approval specifies harvesting pits.
Declared progress / verificationFiled status; independent verification not supplied. RERA amenities
Solid waste
RERA/approval recordSolid-waste management and disposal marked 100%; utility land is reserved for solid-waste management.
Declared progress / verificationFiled status; independent verification and operational details not supplied. RERA amenities
Fire and life safety
RERA/approval recordFire-protection/fire-safety requirement is recorded as 0% in the RERA amenity record.
Declared progress / verificationNo additional project-specific fire-system evidence supplied. RERA amenities
Lifts, backup, accessibility and security
RERA/approval recordNo project-specific evidence supplied.
Declared progress / verificationNot disclosed in the supplied project records. Document index

8. Location, access & connectivity

The registered project location is Kodad village/locality, Kodad Mandal, Suryapet District, PIN 508206. The approved layout describes a road-width boundary of 30 on the east and ROAD WIDTH - 12 on the north; it also requires internal roads to be opened for access to neighbouring sites. RERA record

The supplied connectivity record identifies Financial District (Nanakramguda), 1.2 km from a cadastral parcel centroid at 17.41528, 78.35459. The evidence does not establish a verified travel time or a project-specific transport or landmark route. Location record

9. Developer & development status

The registered promoter is MALLEBOINA VENKATESWARLU & OTHERS; the project record identifies the organization type as Proprietorship and MALLEBOINA VENKATESWARLU as authorized signatory. RERA record Corporate record Parties record

The TG-RERA certificate lists the promoter’s office as Village: Naidupeta, Mandal: Khammam (Rural) Mandal, District: Khammam, PIN 507003. The separate promoter-information address record gives B, Naidupeta, Kodad, Kodad, Suryapet, PIN 508206. Official project contacts or a project website are not supplied. Parties record RERA filing

The promoter’s Form B declares a completion undertaking of 11/02/2025. The architect’s Form 1A filed with TG-RERA certifies completion on 30/11/2024. The supplied material does not include an independent site-status inspection or establish the specific phase or plot scope of the cited occupancy certificate.

10. Approvals, official records & documents

TG-RERA registration certificate (Form C)
Identifier / dateP01900006633; issued 26/07/2023; validity to 11/02/2025
What the supplied record establishesRegistration certificate for SRI SAI DEVELOPERS; the certificate also states conditions concerning sale agreements, conveyance and the separate-account deposit.
Tentative layout approval
Identifier / date0031/LO/3046/2023; application 012047/LO/DTCP/3046/0032/2022
What the supplied record establishesTentative residential layout approval by KODADA Municipality/Municipal Corporation, recording 86 plots and layout reservations and conditions.
Form B promoter declaration
Identifier / dateFiled for SRI SAI DEVELOPERS
What the supplied record establishesPromoter declaration includes title and encumbrance assertions and a completion undertaking of 11/02/2025.
Architect’s Form 1A completion certificate
Identifier / dateDated 30/11/2024
What the supplied record establishesFiled architect certificate states the project is complete in all aspects and cites OC No. 001678/FLT/DTCP/3046/0009/2024. The supplied extract does not specify the certificate’s phase or plot-level scope.
Approved layout drawing
Identifier / dateDocument 336461
What the supplied record establishesDrawing-derived record supplies plot count, plot-size measurements and land-use split; measurements are software-derived and should be verified against the drawing. Layout record
Supporting project documents
Identifier / dateDocuments 336508, 337569, 337578, 336938
What the supplied record establishesAgreement-for-sale template; memorandum of understanding; advocate title-search report; and filed encumbrance statement, respectively. Document index

The supplied approval is expressly identified as a tentative layout plan. The approval extract also states that layout approval is not proof of title.

Frequently asked questions

Is SRI SAI DEVELOPERS registered with Telangana RERA?

Yes. SRI SAI DEVELOPERS is registered with the Telangana Real Estate Regulatory Authority as P01900006633; the registration status is New Project.

Who is the developer of SRI SAI DEVELOPERS?

The promoter named in the RERA registration is MALLEBOINA VENKATESWARLU & OTHERS.

Where is SRI SAI DEVELOPERS located?

SRI SAI DEVELOPERS is in KODAD, Suryapet, Telangana (508206).

When will SRI SAI DEVELOPERS be completed?

The promoter's proposed date of completion filed with RERA is 11/02/2025. This is the promoter's declaration, not a guarantee.