Satya Shreshta
Kacham · Siddipet · RERA P01300005575
Satya Shreshta is a plotted development in Siddipet, in SIDDIPET (URBAN) mandal, Siddipet district. The registered promoter is Kacham Surya Prakash. The layout covers Ac. 53.42 gts; 216164.41 Sq. Mt. and comprises 777 plots; plot configurations and individual plot sizes are not stated. It is registered under TG-RERA number P01300005575, with a proposed completion date of 05/03/2025.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
10 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Record |
|---|---|
| Registered project name | Satya Shreshta |
| Project type | Plotted development / plotted layout RERA record RERA filing |
| Phase / registered portion | No separate phase designation is provided; TG-RERA registration is for the project identified below. |
| TG-RERA registration number | P01300005575 |
| Registration validity | Commenced 20/12/2022; certificate states validity ended 05/03/2025, unless extended by the Authority. The supplied record shows no extension. Registration validity is distinct from the project completion date. |
| Registered promoter | Kacham Surya Prakash |
| RERA status in supplied record | Certificate was granted under section 5; it is not shown as extended. |
Land and geographic identity
| Field | Record |
|---|---|
| Locality / village | Siddipet is the locality shown on the RERA certificate. The layout approval identifies Duddeda; the supplied records therefore identify both Siddipet and Duddeda in the project’s location materials. |
| Revenue village | Duddeda in the layout-approval document; the RERA certificate lists locality SIDDIPET. |
| Mandal / district / PIN | SIDDIPET (URBAN) / Siddipet / 502103 |
| Project survey numbers and subdivisions | Sy. No. 212(p), 214, 215, 216, 218(p), 219, 220, 222(p), 225(p), 226(p) |
| Site extent | Layout approval states Ac. 53.42 gts; 216164.41 Sq. Mt. |
| RERA-filed total / net area | Total area 216164.41 sqmts; net area 216164.41 sqmts; affected area recorded as 0 sqmts. RERA filing |
| Boundaries in RERA filing | East: Owners Leftover Land; West: Owners Land; North: Others Land; South: 20m wide Road. RERA filing |
Development identity
| Field | Record |
|---|---|
| Sanctioning authority | Siddipet Urban Development Authority (SUDA) |
| Principal layout approval | Draft - TLP.NO.3148/Duddeda/2021/0394 UDA; file Lr.Roc.No.3148/Duddeda/2021/0394; approved date 05 March, 2022. The document describes a draft technical layout pattern. |
| Approved built-up area | Not stated as a building measure for this plotted layout. The RERA filing lists Approved Built up Area (In Sqmts) 121510.27; the layout approval identifies this figure as plotted area. RERA filing |
| Building / tower count and floor configuration | Not applicable to the plotted layout in the supplied approval and RERA records; no building, tower or floor schedule is supplied. |
| Plot count | 777 plots stated in the layout-approval extraction. |
| Roads | Approval extraction identifies road widths of 18 mts and above. |
| Parking | No sanctioned parking count or parking layout is supplied. |
Offering and status
| Field | Record |
|---|---|
| Unit type | Plots; the RERA records supplied do not give plot-by-plot sizes or a RERA-filed saleable-area range. RERA record |
| Booked / available counts | Not supplied in the reviewed project data. The approval extraction states 777 plots; this is not a booked or available inventory count. |
| Construction / development stage | No independently verified site-progress assessment is supplied. RERA amenity entries show 0 progress for the listed facilities; the percentages do not establish physical completion. RERA amenities |
| Original completion date | RERA project information gives 05/03/2025. RERA filing |
| Promoter-declared completion undertaking | Form B states the project shall be completed within 3 Years, verified at Hyderabad on 7TH October, 2022. |
| Revised completion date | None supplied. |
| Occupancy / completion certificate | No occupancy or completion certificate is supplied. The project is a plotted layout; no phase- or plot-specific certificate status is recorded. Document index |
2. The project story
Satya Shreshta is presented in the TG-RERA record as a plotted development, rather than an apartment or tower project. The SUDA layout-approval document describes a 777-plot layout over Ac. 53.42 gts; 216164.41 Sq. Mt., on the listed Duddeda survey lands. The registered offering is plots; the supplied RERA material does not provide plot-by-plot dimensions, booking status, or a current construction-progress report. RERA record
The approval document records roads, social infrastructure and a mortgage area, and includes conditions for development works and eventual transfer of specified layout areas to the local body. Its extracted land-use figures and facilities are summarized below. The approval document calls the permission a draft technical layout pattern and expressly says the permission is not proof of title.
The registration certificate gives an original completion date of 05/03/2025, while the promoter’s Form-B affidavit separately undertakes completion within 3 Years. Neither a current site inspection nor independently verified construction progress is supplied. The RERA registration certificate states its validity ended on 05/03/2025 unless extended; no extension or occupancy/completion certificate is included in the supplied records. RERA filing
3. Master plan, architecture & building design
This is a land layout, so the available design evidence concerns plot and land-use organization, not building architecture. The SUDA document identifies a total layout area of 216164.41 Sq. Mt. and lists 121510.27 Sq. Mt. as plotted area, 66044.74 Sq. Mt. as road area, 18904.85 Sq. Mt.; AC. 4.67 as mortgage area, and AC. 1.34; 5405.04 Sq. Mt. as social infrastructure. It records open space as 0% and utility as AC. 0. These are figures as extracted from the approval document, not independently measured site conditions.
The RERA-filed land-use table, software-read from the layout drawing, separately records 120880.57 sqm for plots, 66674.44 sqm for roads, 19567.94 sqm for parks / open space, 5405.04 sqm for social infrastructure, and 0.0 sqm for amenities, against a drawing-stated base of 216166.01 sqm. The drawing extraction notes that plot counts and sizes are incomplete and that the figures should be checked against the source drawing. Layout record
The approval extraction states 777 plots and roads 18 mts and above. It identifies a 15.00% of plotted area mortgage in favour of the Vice-Chairperson, SUDA–Siddipet, stated as AC. 4.67; 18904.85 Sq. Mt.; 15.56%. It also lists a separate 5.00% of saleable area/Plotted area allocation for SUDA Master Plan Facilities. The document’s conditions describe development, mortgage and gift-handover requirements.
No building footprint, floor configuration, parking levels, plot-size schedule or plot arrangement sufficient to describe individual lots is included in the supplied records. The two drawing sheets available to the measurement system are layout sheets; no flats were identified and no carpet-area measurements were made. Floor plans Layout record
4. Homes, configurations & floor plans
The project is offered as plots. No RERA configuration-count schedule, booked or available inventory, plot-size bands, or plot-by-plot saleable areas are supplied in the reviewed data. The approval extraction states 777 plots, but this is not an inventory-status statement. Document index
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Plots | 777 stated in approval extraction | Not supplied | Not supplied | Not supplied | Not applicable | Not supplied |
The available drawing records contain two layout sheets, with no plot-size measurements completed by the software. No apartment floor plans or room dimensions are supplied. Floor plans Layout record
5. Parking & vehicle circulation
No sanctioned parking count, visitor or accessible parking provision, parking allocation schedule, or parking-specific circulation plan is supplied. The approval extraction identifies layout roads 18 mts and above, but does not specify vehicle-entry arrangements, ramps, pedestrian separation or EV charging. A plot layout road provision does not establish a parking entitlement for any particular purchaser.
6. Amenities, recreation & open spaces
The RERA amenity record lists 14 project-infrastructure categories. Each listed percentage is 0; this is a declared progress field, not independent verification of completion. The approval extraction also identifies proposed layout facilities and land allocations. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Internal roads & footpaths | RERA amenity entry; approval extraction states road widths 18 mts and above. | RERA amenities | RERA progress 0; not independently verified. |
| Green strip / TOT LOT / park | RERA amenity entry. Approval extraction records open space 0%; the drawing-derived layout table separately lists parks / open space 19567.94 sqm. | RERA amenities Layout record | RERA progress 0; no verified delivery status. |
| Community buildings | Listed in RERA amenity record. | RERA amenities | Progress 0; no size or completion evidence supplied. |
| Social infrastructure | Approval extraction states AC. 1.34; 5405.04 Sq. Mt. | Allocation recorded in approval extraction; completion not verified. | |
| Avenue plantation | Listed among proposed layout works. | No completion evidence supplied. | |
| Park development | Listed among proposed layout works. | No completion evidence supplied. |
Third-party vendor material lists facilities including a gym, jogging track, swimming pool, children’s play area, garden and CCTV, but these are not established as RERA-filed or sanctioned project facilities in the supplied documents and are not treated here as delivered amenities. Promoter website
7. Utilities, building services & safety
The layout-approval extraction lists proposed infrastructure and utilities: storm water drains, underground drainage lines, common septic tank / STP, internal water supply pipelines, overhead tank, assured water supply source, electrical supply lines, street lights, transformer, avenue plantation, park development, and rain water harvesting pits. These are approval-document entries; no capacities, commissioning records or independent completion verification are supplied.
The RERA amenity record lists water supply, sewerage (chamber, lines, septic tank, STP), storm-water drains, street lighting, water conservation/rainwater harvesting, energy management, fire protection and safety requirements, electrical meter room/sub-station/receiving station, and solid-waste management. Each displayed progress percentage is 0. No detailed fire-system design, safety clearance, accessibility plan, utility capacity or waste-management operating record is supplied. RERA amenities
8. Location, access & connectivity
The project records identify Siddipet, Duddeda, SIDDIPET (URBAN) mandal, Siddipet district and PIN 502103. The cadastral parcel centroid is 18.127579410414604, 78.83880907393153. The RERA filing records the southern boundary as a 20m wide Road. RERA filing Cadastral map
The location dataset gives the nearest sampled Outer Ring Road interchange at approximately 67.1 km. This is a dataset distance, not a travel-time estimate. Location record
A third-party listing describes the location as near Haritha Minerva, Duddeda, Siddipet, but the supplied records do not provide measured distances to local schools, hospitals, shops or public transport. Promoter website
9. Developer & development status
The TG-RERA registration certificate names Kacham Surya Prakash as promoter. The available corporate record identifies GSTIN 36ABXAS5234M1ZL but does not establish the promoter’s legal-entity type. A registered office address, official project contact details and official website are not supplied. Corporate record
The promoter’s Form-B affidavit, verified at Hyderabad on 7TH October, 2022, declares a three-year completion period, a legal-title basis and undertakings concerning project funds, approvals and allottee treatment. These are promoter declarations, not independent verification of title, funding or completed development.
The certificate’s registration-validity end date is 05/03/2025; the project information also gives 05/03/2025 as proposed completion. No revised completion date, RERA registration extension, current construction-progress certification, or completion/occupancy certificate is supplied. RERA filing
10. Approvals, official records & documents
| Record | Supplied evidence |
|---|---|
| TG-RERA registration | FORM ‘C’ for Satya Shreshta, registration P01300005575, issued 20/12/2022, validity stated through 05/03/2025 unless extended. |
| Principal layout approval | SUDA communication for draft technical layout pattern, approval Draft - TLP.NO.3148/Duddeda/2021/0394 UDA, file Lr.Roc.No.3148/Duddeda/2021/0394, dated 05 March, 2022. |
| Promoter declaration | Form-B affidavit dated 7TH October, 2022, containing the promoter’s title, encumbrance, completion and project-fund declarations. |
| Approved layout drawing | Layout source document 264763, two sheets; software-extracted layout figures are incomplete and should be checked against the drawing. Layout record Floor plans |
| Completion / occupancy record | No completion or occupancy certificate supplied. Document index |
| Other construction approvals / building plans | No building or tower plan schedule is supplied for this plotted development. Document index |
The SUDA approval document states that its permission is not proof of title. The supplied records identify the relevant survey numbers as 212P, 214, 215, 216, 218P, 219, 220, 222P, 225P and 226P.
1. Project at a glance
Project identity
Registered project name: Satya Shreshta
Project type: Plotted development / plotted layout
Phase / registered portion: No separate phase designation is provided; TG-RERA registration is for the project identified below.
TG-RERA registration number: P01300005575
Registration validity: Commenced 20/12/2022; certificate states validity ended 05/03/2025, unless extended by the Authority. The supplied record shows no extension. Registration validity is distinct from the project completion date.
Registered promoter: Kacham Surya Prakash
RERA status in supplied record: Certificate was granted under section 5; it is not shown as extended.
Land and geographic identity
Locality / village: Siddipet is the locality shown on the RERA certificate. The layout approval identifies Duddeda; the supplied records therefore identify both Siddipet and Duddeda in the project’s location materials.
Revenue village: Duddeda in the layout-approval document; the RERA certificate lists locality SIDDIPET.
Mandal / district / PIN: SIDDIPET (URBAN) / Siddipet / 502103
Project survey numbers and subdivisions: Sy. No. 212(p), 214, 215, 216, 218(p), 219, 220, 222(p), 225(p), 226(p)
Site extent: Layout approval states Ac. 53.42 gts; 216164.41 Sq. Mt.
RERA-filed total / net area: Total area 216164.41 sqmts; net area 216164.41 sqmts; affected area recorded as 0 sqmts.
Boundaries in RERA filing: East: Owners Leftover Land; West: Owners Land; North: Others Land; South: 20m wide Road.
Development identity
Sanctioning authority: Siddipet Urban Development Authority (SUDA)
Principal layout approval: Draft - TLP.NO.3148/Duddeda/2021/0394 UDA; file Lr.Roc.No.3148/Duddeda/2021/0394; approved date 05 March, 2022. The document describes a draft technical layout pattern.
Approved built-up area: Not stated as a building measure for this plotted layout. The RERA filing lists Approved Built up Area (In Sqmts) 121510.27; the layout approval identifies this figure as plotted area.
Building / tower count and floor configuration: Not applicable to the plotted layout in the supplied approval and RERA records; no building, tower or floor schedule is supplied.
Plot count: 777 plots stated in the layout-approval extraction.
Roads: Approval extraction identifies road widths of 18 mts and above.
Parking: No sanctioned parking count or parking layout is supplied.
Offering and status
Unit type: Plots; the RERA records supplied do not give plot-by-plot sizes or a RERA-filed saleable-area range.
Booked / available counts: Not supplied in the reviewed project data. The approval extraction states 777 plots; this is not a booked or available inventory count.
Construction / development stage: No independently verified site-progress assessment is supplied. RERA amenity entries show 0 progress for the listed facilities; the percentages do not establish physical completion.
Original completion date: RERA project information gives 05/03/2025.
Promoter-declared completion undertaking: Form B states the project shall be completed within 3 Years, verified at Hyderabad on 7TH October, 2022.
Revised completion date: None supplied.
Occupancy / completion certificate: No occupancy or completion certificate is supplied. The project is a plotted layout; no phase- or plot-specific certificate status is recorded.
2. The project story
Satya Shreshta is presented in the TG-RERA record as a plotted development, rather than an apartment or tower project. The SUDA layout-approval document describes a 777-plot layout over Ac. 53.42 gts; 216164.41 Sq. Mt., on the listed Duddeda survey lands. The registered offering is plots; the supplied RERA material does not provide plot-by-plot dimensions, booking status, or a current construction-progress report.
The approval document records roads, social infrastructure and a mortgage area, and includes conditions for development works and eventual transfer of specified layout areas to the local body. Its extracted land-use figures and facilities are summarized below. The approval document calls the permission a draft technical layout pattern and expressly says the permission is not proof of title.
The registration certificate gives an original completion date of 05/03/2025, while the promoter’s Form-B affidavit separately undertakes completion within 3 Years. Neither a current site inspection nor independently verified construction progress is supplied. The RERA registration certificate states its validity ended on 05/03/2025 unless extended; no extension or occupancy/completion certificate is included in the supplied records.
3. Master plan, architecture & building design
This is a land layout, so the available design evidence concerns plot and land-use organization, not building architecture. The SUDA document identifies a total layout area of 216164.41 Sq. Mt. and lists 121510.27 Sq. Mt. as plotted area, 66044.74 Sq. Mt. as road area, 18904.85 Sq. Mt.; AC. 4.67 as mortgage area, and AC. 1.34; 5405.04 Sq. Mt. as social infrastructure. It records open space as 0% and utility as AC. 0. These are figures as extracted from the approval document, not independently measured site conditions.
The RERA-filed land-use table, software-read from the layout drawing, separately records 120880.57 sqm for plots, 66674.44 sqm for roads, 19567.94 sqm for parks / open space, 5405.04 sqm for social infrastructure, and 0.0 sqm for amenities, against a drawing-stated base of 216166.01 sqm. The drawing extraction notes that plot counts and sizes are incomplete and that the figures should be checked against the source drawing.
The approval extraction states 777 plots and roads 18 mts and above. It identifies a 15.00% of plotted area mortgage in favour of the Vice-Chairperson, SUDA–Siddipet, stated as AC. 4.67; 18904.85 Sq. Mt.; 15.56%. It also lists a separate 5.00% of saleable area/Plotted area allocation for SUDA Master Plan Facilities. The document’s conditions describe development, mortgage and gift-handover requirements.
No building footprint, floor configuration, parking levels, plot-size schedule or plot arrangement sufficient to describe individual lots is included in the supplied records. The two drawing sheets available to the measurement system are layout sheets; no flats were identified and no carpet-area measurements were made.
4. Homes, configurations & floor plans
The project is offered as plots. No RERA configuration-count schedule, booked or available inventory, plot-size bands, or plot-by-plot saleable areas are supplied in the reviewed data. The approval extraction states 777 plots, but this is not an inventory-status statement.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Plots | 777 stated in approval extraction | Not supplied | Not supplied | Not supplied | Not applicable | Not supplied |
The available drawing records contain two layout sheets, with no plot-size measurements completed by the software. No apartment floor plans or room dimensions are supplied.
5. Parking & vehicle circulation
No sanctioned parking count, visitor or accessible parking provision, parking allocation schedule, or parking-specific circulation plan is supplied. The approval extraction identifies layout roads 18 mts and above, but does not specify vehicle-entry arrangements, ramps, pedestrian separation or EV charging. A plot layout road provision does not establish a parking entitlement for any particular purchaser.
6. Amenities, recreation & open spaces
The RERA amenity record lists 14 project-infrastructure categories. Each listed percentage is 0; this is a declared progress field, not independent verification of completion. The approval extraction also identifies proposed layout facilities and land allocations.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Internal roads & footpaths | RERA amenity entry; approval extraction states road widths 18 mts and above. | RERA progress 0; not independently verified. | |
| Green strip / TOT LOT / park | RERA amenity entry. Approval extraction records open space 0%; the drawing-derived layout table separately lists parks / open space 19567.94 sqm. | RERA progress 0; no verified delivery status. | |
| Community buildings | Listed in RERA amenity record. | Progress 0; no size or completion evidence supplied. | |
| Social infrastructure | Approval extraction states AC. 1.34; 5405.04 Sq. Mt. | Allocation recorded in approval extraction; completion not verified. | |
| Avenue plantation | Listed among proposed layout works. | No completion evidence supplied. | |
| Park development | Listed among proposed layout works. | No completion evidence supplied. |
Third-party vendor material lists facilities including a gym, jogging track, swimming pool, children’s play area, garden and CCTV, but these are not established as RERA-filed or sanctioned project facilities in the supplied documents and are not treated here as delivered amenities.
7. Utilities, building services & safety
The layout-approval extraction lists proposed infrastructure and utilities: storm water drains, underground drainage lines, common septic tank / STP, internal water supply pipelines, overhead tank, assured water supply source, electrical supply lines, street lights, transformer, avenue plantation, park development, and rain water harvesting pits. These are approval-document entries; no capacities, commissioning records or independent completion verification are supplied.
The RERA amenity record lists water supply, sewerage (chamber, lines, septic tank, STP), storm-water drains, street lighting, water conservation/rainwater harvesting, energy management, fire protection and safety requirements, electrical meter room/sub-station/receiving station, and solid-waste management. Each displayed progress percentage is 0. No detailed fire-system design, safety clearance, accessibility plan, utility capacity or waste-management operating record is supplied.
8. Location, access & connectivity
The project records identify Siddipet, Duddeda, SIDDIPET (URBAN) mandal, Siddipet district and PIN 502103. The cadastral parcel centroid is 18.127579410414604, 78.83880907393153. The RERA filing records the southern boundary as a 20m wide Road.
The location dataset gives the nearest sampled Outer Ring Road interchange at approximately 67.1 km. This is a dataset distance, not a travel-time estimate.
A third-party listing describes the location as near Haritha Minerva, Duddeda, Siddipet, but the supplied records do not provide measured distances to local schools, hospitals, shops or public transport.
9. Developer & development status
The TG-RERA registration certificate names Kacham Surya Prakash as promoter. The available corporate record identifies GSTIN 36ABXAS5234M1ZL but does not establish the promoter’s legal-entity type. A registered office address, official project contact details and official website are not supplied.
The promoter’s Form-B affidavit, verified at Hyderabad on 7TH October, 2022, declares a three-year completion period, a legal-title basis and undertakings concerning project funds, approvals and allottee treatment. These are promoter declarations, not independent verification of title, funding or completed development.
The certificate’s registration-validity end date is 05/03/2025; the project information also gives 05/03/2025 as proposed completion. No revised completion date, RERA registration extension, current construction-progress certification, or completion/occupancy certificate is supplied.
10. Approvals, official records & documents
TG-RERA registration: FORM ‘C’ for Satya Shreshta, registration P01300005575, issued 20/12/2022, validity stated through 05/03/2025 unless extended.
Principal layout approval: SUDA communication for draft technical layout pattern, approval Draft - TLP.NO.3148/Duddeda/2021/0394 UDA, file Lr.Roc.No.3148/Duddeda/2021/0394, dated 05 March, 2022.
Promoter declaration: Form-B affidavit dated 7TH October, 2022, containing the promoter’s title, encumbrance, completion and project-fund declarations.
Approved layout drawing: Layout source document 264763, two sheets; software-extracted layout figures are incomplete and should be checked against the drawing.
Completion / occupancy record: No completion or occupancy certificate supplied.
Other construction approvals / building plans: No building or tower plan schedule is supplied for this plotted development.
The SUDA approval document states that its permission is not proof of title. The supplied records identify the relevant survey numbers as 212P, 214, 215, 216, 218P, 219, 220, 222P, 225P and 226P.
Frequently asked questions
Is Satya Shreshta registered with Telangana RERA?
Yes. Satya Shreshta is registered with the Telangana Real Estate Regulatory Authority as P01300005575; the registration status is New Project.
Who is the developer of Satya Shreshta?
The promoter named in the RERA registration is Kacham.
Where is Satya Shreshta located?
Satya Shreshta is in Siddipet, SIDDIPET (URBAN), Telangana (502103).
When will Satya Shreshta be completed?
The promoter's proposed date of completion filed with RERA is 05/03/2025. This is the promoter's declaration, not a guarantee.
More projects in Siddipet