Sign in

Bhavani Infrastructure

CHEPYELA · Peddapalli · RERA P02900010875

BHAVANI INFRASTRUCTURE is a plotted development in Medipalli Revenue Village, PK RAMAIAH COLONY, INDIRAMMA CAMP, Ramagundam mandal, Peddapalli district. The registered promoter is CHEPYELA RAMA RAO. The layout approval states a site extent of 5 Acer 33.51 Gts 28255 Sq. Yds and 83 plots; building or floor configurations are not stated. The project is registered under TG-RERA number P02900010875, with proposed completion recorded as 09/01/2028.

01What we found

RegisteredTG-RERA - valid till 9 Sep 2027
14documents on file - each fact links to its page
0court cases on this project's land in the court records searched
9items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

9 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Project at a glance

Project identity

FieldProject record
Registered project nameBHAVANI INFRASTRUCTURE RERA record
Project typePlotted development / open layout RERA record RERA filing
Phase / registered portionA registered plotted-layout project; the supplied record does not identify a phase number. Approvals record
TG-RERA registration numberP02900010875 Approvals record
Registration validity09/09/2025 to 09/09/2027; the certificate states a two-year registration period. This is registration validity, not the completion deadline. Approvals record
Registered promoterCHEPYELA RAMA RAO
RERA statusRegistered; certificate conditions require quarterly updates. Approvals record

Land and geographic identity

FieldProject record
Locality / recorded addressMEDIPALLI REVENUE VILLAGE, RAMAGUNDAM MUNICIPAL CORPORATION; PK RAMAIAH COLONY, INDIRAMMA CAMP, Ramagundam, Peddapalli, Telangana 505215. RERA record RERA filing
Revenue village named in layout approvalMEDIPALLI Revenue Village. The project record also uses “PK RAMAIAH COLONY,INDHIRAMMA CAMP” as its village/city field.
Mandal / districtRamagundam / Peddapalli. The layout approval names Ramagundam Municipal Corporation; the RERA certificate records Ramagundam and Peddapalli. RERA filing
Survey numbers and subdivisionsSy. No. 598/2 and Sy. No. 598/3/1/1. Land records
Site extentLayout approval states 5 Acer 33.51 Gts 28255 Sq. Yds. The RERA land-details field records 23,624.27 sq.m total and net area. RERA filing
Boundaries recorded in RERA filingNorth: 30-0 WIDE ROAD AND OPEN LAND OF OTHERS; south: OPEN LAND OF CH LAXMAN RAO; east: OPEN LAND OF CH SHARATH RAO; west: OPEN LAND OF CH LAXMAN RAO. RERA filing
Recorded road-widening / FTL / nala-affected area00.00 sq.m in the RERA land-details field. RERA filing

Development identity

FieldProject record
Sanctioning authorityRamagundam Municipal Corporation is named on the tentative layout approval; the RERA project information lists DTCP as authority. RERA filing
Principal approvalTentative layout approval 0007/LO/3015/2025, dated 09 September 2025. Application number: 000671/LO/DTCP/3015/0001/2024. Approvals record
Plots83 plots are stated in the layout approval.
Approved built-up area14,186.91 sq.m recorded in the RERA filing. RERA filing
Building / floor configurationNot applicable to the approved plotted-layout description; no building count or floor configuration is supplied.
ParkingNo project-wide parking count or parking-level arrangement is supplied. Document index

Offering and status

FieldProject record
Offered property typePlots in an open layout; the layout approval states 83 plots.
Plot count and sizesThe approved drawing’s schedule is software-read as 83 plots: 92.17–276.45 sq.m (about 110.2–330.6 sq.yd), with a median of 167.38 sq.m (about 200.2 sq.yd). These are drawing-derived readings, not RERA-filed unit sale areas. Layout record
Booked / availableNot disclosed in the supplied RERA unit inventory. Document index Approvals record
Development stageThe layout is described as tentatively approved. No independently verified site-progress status is supplied.
Completion datesForm B declares completion by 09/09/2027; the RERA project header records proposed completion as 09/01/2028. RERA record
Occupancy / completion certificateNo occupancy or completion certificate is supplied. The evidence describes a tentative layout approval, not a completed development. Document index

The project story

BHAVANI INFRASTRUCTURE is registered as a plotted-development project on land identified as Sy. No. 598/2 and Sy. No. 598/3/1/1, at Medipalli Revenue Village, Ramagundam, Peddapalli. Its tentative layout approval describes an 83-plot layout. The drawing’s area statement allocates land to plots, roads, open space/park, utilities and social infrastructure. RERA record Layout record

The supplied evidence establishes the approval and the promoter’s declared timetable, but does not establish construction progress through an independent site inspection. The layout approval sets an infrastructure-and-amenities completion period ending 09 September 2027 and contains conditions on development and handover of specified layout land. The promoter’s Form B also declares a 09/09/2027 completion date; the project header gives a proposed completion date of 09/01/2028. These are recorded separately from the certificate’s registration validity, which ends 09/09/2027. RERA record

Master plan, architecture & building design

The supplied approval is for a tentative layout plan, not a building plan. The layout approval states 83 plots on 5 Acer 33.51 Gts 28255 Sq. Yds. Its area statement allocates land as follows.

Layout useArea stated in approvalShare stated in approval
Plotted area3 Acer 20.23 Gts 16968 Sq. Yds60.05%
Roads1 Acer 22.06 Gts 7510 Sq. Yds26.58%
Open space (park)0 Acer 21.65 Gts 2620 Sq. Yds9.27%
Social infrastructure0 Acer 7.12 Gts 861 Sq. Yds3.05%
Utilities0 Acer 2.45 Gts 297 Sq. Yds1.05%
Mortgage area0 Acer 21.24 Gts 2570 Sq. Yds15.09% of plotted area

The layout drawing is software-read as containing 83 plots, with sizes from 92.17 sq.m to 276.45 sq.m; the median is 167.38 sq.m. The drawing-derived schedule lists 40 plots at 167.38 sq.m and 20 at 167.31 sq.m. These are software measurements from the drawing and should be checked against the drawing; they are not RERA-filed saleable or carpet areas. Layout record

No tower, building footprint, floor, basement, podium or building-parking configuration is provided for this plotted layout. The RERA filing lists an approved built-up area of 14,186.91 sq.m but does not provide a building configuration in the supplied evidence. RERA filing Document index

Homes, configurations & floor plans

This is a plotted layout, not an apartment configuration schedule. The registration evidence supplied does not include a booked/available plot inventory or RERA-filed plot sale-area schedule. The approved drawing’s plot schedule is software-read as 83 plots. Layout record

Plot informationDrawing-derived measurement
Plot count83
Smallest plot92.17 sq.m / 110.2 sq.yd
Median plot167.38 sq.m / 200.2 sq.yd
Largest plot276.45 sq.m / 330.6 sq.yd

The drawing-derived size bands are: 1 plot in 100–150 sq.yd, 12 in 150–200 sq.yd, 67 in 200–250 sq.yd, 2 in 250–300 sq.yd, and 1 in 300–400 sq.yd. Measurements are software-read from the approved layout drawing, not RERA-filed unit areas. Apartment carpet-area, balcony and loading comparisons do not apply to this plotted offering. Layout record

Parking & vehicle circulation

The layout approval allocates 26.58% of its stated area to roads and requires roads to remain open for access to neighbouring sites. It also specifies that layout roads are to be formed with black top. No separate visitor, accessible, two-wheeler or car-parking count, parking bay schedule, or parking-allocation terms are supplied. The approval identifies 12 plot numbers in the mortgaged reserved-plot schedule; that schedule is not a buyer parking allocation.

Amenities, recreation & open spaces

The layout approval describes planned layout infrastructure and amenities; the supplied records do not independently verify that these works have been completed.

Landscape / open space
Facility / provisionPark / open space
Description / size0 Acer 21.65 Gts 2620 Sq. Yds; 9.27% of the stated layout extent
Evidence sourceLayout record
Declared progress / verified statusReserved in tentative layout approval; completion not independently verified
Convenience / community
Facility / provisionSocial infrastructure
Description / size0 Acer 7.12 Gts 861 Sq. Yds; 3.05%
Evidence sourceLayout record
Declared progress / verified statusSite reserved; specific facility or delivery status not supplied
Sports / recreation
Facility / provisionPark development
Description / sizeNo further description or capacity supplied
Declared progress / verified statusApproval condition describes development; completion not independently verified

The approval also describes internal roads and footpaths, street lighting and avenue plantation. It requires the applicant to hand over the specified open-space, utility and road areas to the municipality by registered gift deed before release of the final layout.

Utilities, building services & safety

The tentative layout approval describes the following infrastructure as layout-development works. These are approval requirements or planned provisions; the supplied evidence does not independently establish their installation, capacity or operation.

Water
Evidence-backed descriptionInternal water-supply pipelines, an assured water-supply source, water reservoir and overhead tank/sump are specified.
Status in supplied recordApproval condition; capacity and completed status not supplied
Sewerage and drainage
Evidence-backed descriptionUnderground drainage lines, common septic tank / STP and storm-water drains are specified.
Status in supplied recordApproval condition; capacity and completed status not supplied
Electrical
Evidence-backed descriptionElectrical supply lines, street lights and an electric transformer are specified; the RERA amenity record lists an electrical meter room/sub-station/receiving station.
Status in supplied recordListed in the records; installation/completion not independently verified
Rainwater
Evidence-backed descriptionRainwater-harvesting pits are specified.
Status in supplied recordApproval condition; quantity and completed status not supplied
Waste
Evidence-backed descriptionThe approval and RERA amenity record refer to solid-waste management and disposal.
Status in supplied recordThe RERA amenity record shows 0%; the approval describes the provision. Completion is not independently verified. RERA amenities
Fire and accessibility
Evidence-backed descriptionNo layout-specific fire-safety system, accessible circulation or accessibility provision is described in the supplied evidence.
Status in supplied recordNot disclosed

Location, access & connectivity

The registered location is MEDIPALLI REVENUE VILLAGE, RAMAGUNDAM MUNICIPAL CORPORATION, with the project address recorded as PK RAMAIAH COLONY, INDIRAMMA CAMP, Ramagundam, Peddapalli, Telangana 505215. The layout approval also names Medipalli Revenue Village. RERA record RERA filing

The RERA land-details field records a 30-0 wide road along the northern boundary. The layout approval requires roads to remain open for neighbouring-site access and describes road formation with black top. The supplied location data gives the nearest sampled Outer Ring Road interchange as approximately 164.2 km away. No public-transport details or further verified approach-road information are supplied. RERA filing Location record

Developer & development status

The registered promoter named in the TG-RERA certificate is CHEPYELA RAMA RAO, an individual; the certificate gives an address at House No. 4-6-199, Bheemuni Patnam, Ramagundam, Peddapalli, 505215. The project filing lists CHEPYELA as the promoter name, while the registration certificate identifies CHEPYELA RAMA RAO. Corporate record

The promoter’s Form B, dated 28 April 2026, declares a completion date of 09/09/2027. The tentative layout approval requires infrastructure and amenities to be completed within two years of its 09 September 2025 approval date, also ending 09 September 2027. No independent site-progress certification is supplied here.

Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP02900010875; valid 09/09/2025–09/09/2027
What it establishesRegistration of BHAVANI INFRASTRUCTURE and certificate conditions.
Tentative layout approval
Identifier / date0007/LO/3015/2025, 09 September 2025; application 000671/LO/DTCP/3015/0001/2024
What it establishesTentative approval for a plotted layout on Sy. Nos. 598/2 and 598/3/1/1, stating 83 plots and layout conditions.
Form B promoter declaration
Identifier / date28 April 2026
What it establishesPromoter’s declarations, including the stated completion date and encumbrance declaration.
Layout drawing
Identifier / dateDocument 681094, two sheets
What it establishesDrawing-derived plot count, plot-size readings and area statement. Measurements are software-read and should be checked against the drawing. Layout record
Occupancy / completion certificate
Identifier / dateNot supplied
What it establishesNo such certificate is established by the documents provided. Document index

The layout approval expressly identifies itself as tentative and states that it is not proof of title. Its detailed conditions and the title evidence are addressed in the relevant report sections.

Frequently asked questions

Is BHAVANI INFRASTRUCTURE registered with Telangana RERA?

Yes. BHAVANI INFRASTRUCTURE is registered with the Telangana Real Estate Regulatory Authority as P02900010875; the registration status is New Project.

Who is the developer of BHAVANI INFRASTRUCTURE?

The promoter named in the RERA registration is CHEPYELA.

Where is BHAVANI INFRASTRUCTURE located?

BHAVANI INFRASTRUCTURE is in MEDIPALLI REVENUE VILLAGE,RAMAGUNDAM MUNICIPAL CORPORATION, PK RAMAIAH COLONY,INDHIRAMMA CAMP, Ramagundam, Peddapalli, Telangana (505215).

When will BHAVANI INFRASTRUCTURE be completed?

The promoter's proposed date of completion filed with RERA is 09/01/2028. This is the promoter's declaration, not a guarantee.

More projects in Ramagundam