Ashoka Elite Block E is a residential apartment project in Yellammagutta, NIZAMABAD SOUTH mandal, Nizamabad district, developed by the registered promoter Ashoka Elite. The project covers 749.96 m² and comprises one residential building with 1 Stilt + 5 upper floors and 15 homes: 10 2BHK units and 5 3BHK units. It is registered under TG-RERA number P03100005470, and the promoter’s Form B undertaking gives 28/04/2025 as the completion period.

01What we found

Period endedTG-RERA registration ran to 28 Apr 2025 - check its extension on TG-RERA
12documents on file - each fact links to its page
0court cases on this project's land in the court records searched
8items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

8 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

ItemRecord
Registered project nameAshoka Elite Block E
Project type / registered portionResidential apartment project; the registered portion is Block E. The building-construction approval identifies one residential building, Building A, associated with Yendala Laxmi Narayana. RERA record
TG-RERA registrationP03100005470
Registration validityCertificate states 07/12/2022–28/04/2025; no extension is recorded on the certificate. Registration validity is distinct from the project completion undertaking and from occupancy certification. The supplied record does not establish a current extension or a later registration status.
Registered promoterAshoka Elite
RERA status in supplied recordThe certificate records the registration period above.

Land and geographic identity

ItemRecord
Locality / revenue villageYellammagutta; the registration certificate gives locality and village as YELLAMMAGUTTA. RERA record
Mandal / district / PINNIZAMABAD SOUTH / Nizamabad / 503001 RERA record
Project survey number and subdivision89/A/4 RERA record Land records
Site area749.96 m² total and net area in the project filing and building approval. RERA filing
Boundaries in RERA filingEast: land of Smt Yendala Buchavva; west: remaining land of land owner Y Laxminarayana; north: 30ft wide road; south: neighbours’ land. RERA filing
Location description in building approvalVINAYAK NAGAR, NEAR AMMA NAGAR, NIZAMABAD; the approval identifies village NIZAMABAD, while the RERA certificate identifies YELLAMMAGUTTA.

Development identity

ItemRecord
Sanctioning authorityNizamabad Municipality/Municipal Corporation; the RERA filing lists DTCP as the authority for the plan approval. Approvals record
Principal building approval0027/BP/3072/2022, approved 28 April, 2022. File number: 003982/BP/DTCP/3072/0045/2022. Approvals record
Approved building formOne residential building; 1 Stilt + 5 upper floors.
Approved area and heightResidential upper-floor area: 1,761.35 m²; stilt area: 360.82 m²; building height: 14.72 m. These are approval-record figures, not carpet or saleable area.
Approved unitsThe project filing records 15 total units, and the approval condition says sanctioned units must not be increased without prior approval. A separate unit-count figure in the approval extraction is not provided. RERA unit table
ParkingThe building approval says cellar and stilt areas approved for parking must be used exclusively for vehicle parking; no parking-space count or allocation is supplied.
Approval conditions relevant to the buildingThe approval requires, among other items, an NMC mortgage over 184.00 sqmts. of fourth-floor built-up area, rainwater-harvesting structures, transformer space, a garbage house, and a tot-lot/greenery provision.

Offering and status

ItemRecord
RERA-filed configurations2BHK: 10 units; 3BHK: 5 units. RERA unit table
RERA-filed saleable area2BHK: 116.12 m²; 3BHK: 153.75 m². RERA unit table
Booked / availablePortal-derived counts show 0 booked / 10 available for 2BHK and 0 booked / 5 available for 3BHK. The portal record has no stated as-of date, so counts are indicative rather than a current availability confirmation. RERA unit table
Completion datePromoter’s Form B undertaking gives 28/04/2025 as the completion period.
Construction stageNo independently verified site-progress measurement is supplied. The amenity progress entries are recorded as 0%, which does not establish overall construction progress. RERA amenities
OC / completion certificateNo occupancy certificate or completion certificate is included in the supplied project documents. Document index

2. The project story

Ashoka Elite Block E is registered as a residential apartment project in Yellammagutta, Nizamabad South mandal, Nizamabad district. The RERA filing describes a 749.96 m² site in survey 89/A/4 and records a single-building, 15-unit offering comprising ten 2BHK and five 3BHK apartments. RERA record RERA filing RERA unit table

The building permit describes a stilt plus five upper-floor residential building. The promoter’s Form B gives 28/04/2025 as the intended completion date, but the supplied record does not provide an independently verified construction-progress assessment or an occupancy certificate. The approval itself requires an occupancy certificate before occupation and public utility connections. The amenity register lists progress as 0% for its reported items. RERA amenities

The project is therefore described here by its filed registration and sanction records; the material supplied does not establish which construction works have been completed on site. RERA amenities

3. Master plan, architecture & building design

The building-construction approval records a site area of 749.96 m², a residential upper-floor area of 1,761.35 m², a stilt area of 360.82 m², and a building height of 14.72 m. It describes one building with 1 Stilt + 5 upper floors. The supplied extraction does not identify basement or podium levels, flats per floor, lift or stair counts, building footprint, or a detailed internal circulation plan.

The approval lists setbacks of Front 3.50 m; Rear 3.02 m; Side I 3.50 m; Side II 3.50 m. It also requires a tot-lot to be fenced and maintained as greenery, a green strip around the site, rainwater-harvesting structures, transformer space, and a garbage house. The supplied record does not give measured open-space or landscaping areas.

A drawing record is identified as a layout plan, but it is marked as not extracted; no site layout dimensions or detailed circulation information are available in the supplied data. The stated upper-floor and stilt areas are approval figures and are not identified as carpet area or saleable area. Document index

4. Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK10010116.12 m²71.1–84.2 m²; median 77.6 m²33%
3BHK505153.75 m²103.5 m²33%

Unit counts, booking counts and saleable areas are from the TG-RERA filing; the portal-derived booking/availability figures have no stated as-of date. Carpet-area ranges and loading are software measurements from the supplied floor-plan drawing record, not RERA-filed figures, and the drawings’ measured areas require review. Saleable area and measured carpet area are different measures; the supplied floor-plan note states that saleable area also includes the home’s share of common areas. RERA unit table RERA unit details Floor plans

The drawing extraction shows a 2BHK example with two bedrooms, a hall, kitchen, two toilets and two balconies; a 3BHK example has three bedrooms, a hall, kitchen, three toilets, a utility and a balcony. The examples’ room dimensions are drawing-derived measurements. For example, the extracted 2BHK hall is 6.18 × 6.47 m and the 3BHK hall is 5.45 × 7.77 m. These are not separate RERA area disclosures. RERA unit details

5. Parking & vehicle circulation

The building approval states that cellar and stilt areas approved for parking must be used exclusively for vehicle parking, without partition walls or rolling shutters. The approved building description specifies a stilt; the supplied record does not state the number of parking spaces, whether a cellar is actually included in the approved configuration, visitor or accessible parking provision, parking allocation to particular units, or the location and design of vehicle ramps and driveways.

The approval separately records an NMC mortgage over 184.00 sqmts. of fourth-floor built-up area. That is a mortgage condition, not a parking allocation.

6. Amenities, recreation & open spaces

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Tot-lot / green areaApproval requires a fenced tot-lot maintained as greenery before an occupancy certificate is issued; no size supplied.Sanction conditionAmenity register lists “Green Strip/TOT LOT/Park” at 0%; no independent completion verification supplied. RERA amenities
Internal roads and footpathsNo dimensions supplied.RERA amenity register RERA amenities0%; not independently verified.
Community buildingsNo description or size supplied.RERA amenity register RERA amenities0%; not independently verified.
Aggregate recreational open spaceNo area supplied.RERA amenity register RERA amenities0%; not independently verified.
Street lightingNo details supplied.RERA amenity register RERA amenities0%; not independently verified.

The amenity register lists 14 infrastructure and facility categories, but provides no capacities or facility sizes. RERA amenities

The building approval also requires rainwater harvesting, transformer space and a garbage house; these are site services, addressed below.

7. Utilities, building services & safety

The RERA amenity register marks water supply, sewerage, storm-water drains, rainwater harvesting and electrical meter room/substation/receiving station as available, while recording 0% progress for each listed item. These are filing entries; the supplied record does not independently verify installation or operation, or specify water sources, storage, treatment capacity, sewerage treatment capacity, reuse arrangements, drainage design, power capacity or backup. RERA amenities

The building approval requires 5 rainwater-harvesting structures and a space for a transformer, and calls for a garbage house within the premises. It also places responsibility for structural and fire safety on the owner, builder/developer, architect and site engineer; it requires services including sanitation, plumbing, fire-safety requirements, lifts and electrical installations to be executed under qualified technical personnel. No lift count or capacity, fire-system specification, emergency-access detail, accessibility provision, CCTV or security specification is supplied.

The approval states that occupancy is not permitted before an occupancy certificate and that public water-supply and electricity connections will be provided only on production of that certificate.

8. Location, access & connectivity

The registered location is Yellammagutta, NIZAMABAD SOUTH, Nizamabad, Telangana, 503001. The RERA filing identifies the site’s northern boundary as a 30ft wide road. The building approval describes the location as Vinayak Nagar, near Amma Nagar, Nizamabad. RERA filing

The supplied location record gives one measured connectivity distance: Outer Ring Road (nearest sampled interchange, approx): 122.8 km. No public-transport routes, nearby facilities, other measured distances or travel times are provided. Location record

9. Developer & development status

The registered promoter is Ashoka Elite, recorded in the project filing as a partnership. The supplied corporate identifier is GSTIN 36ABWFA8379H1ZL. The registration certificate gives the promoter office as Village: YELLAMMAGUTTA, Mandal: NIZAMABAD SOUTH, District: Nizamabad, Pin: 503001. No separate official website or project contact details are supplied. Corporate record

The promoter’s Form B is a self-declaration that gives 28/04/2025 as the project completion period and includes declarations concerning project funds and approvals. The supplied documents do not establish actual completion progress, a revised completion date or an occupancy-certified building. Document index

10. Approvals, official records & documents

RecordSupplied evidence
TG-RERA registrationForm C registration certificate for Ashoka Elite Block E, registration P03100005470, issued 07/12/2022; validity through 28/04/2025.
Building-construction approvalApproval 0027/BP/3072/2022, dated 28 April, 2022, issued by Nizamabad Municipality/Municipal Corporation; file 003982/BP/DTCP/3072/0045/2022.
RERA-filed project land and unit detailsFiling identifies survey 89/A/4, site area 749.96 m², and 15 apartment units. RERA filing RERA unit table
Promoter declarationForm B affidavit by Mr. Thirupathi Reddy as authorized signatory for Ashoka Elite; includes a stated completion period ending 28/04/2025.
Floor-plan / layout recordLayout-plan document is listed but not extracted; the floor-plan drawing record used for software measurements is document 270700. Document index
Occupancy / completion certificateNo such certificate is present in the supplied documents. Document index

The building approval includes construction, safety, insurance, parking-use and occupancy conditions; the table above identifies the principal project records rather than reproducing all conditions.

Other registrations of Ashoka Elite

Frequently asked questions

Is Ashoka Elite Block E registered with Telangana RERA?

Yes. Ashoka Elite Block E is registered with the Telangana Real Estate Regulatory Authority as P03100005470; the registration status is New Project.

Who is the developer of Ashoka Elite Block E?

The promoter named in the RERA registration is Ashoka Elite.

Where is Ashoka Elite Block E located?

Ashoka Elite Block E is in Yellammagutta, NIZAMABAD SOUTH, Nizamabad, Telangana (503001).

When will Ashoka Elite Block E be completed?

The promoter's proposed date of completion filed with RERA is 28/04/2025. This is the promoter's declaration, not a guarantee.