SILICON CITY is an open plotted layout in MOGALAGIDA, Farooqnagar Mandal, Ranga Reddy District, developed by registered promoter SILICON CITY. The project covers a total site area of 60193.10 sq.mt and has 207 plots; plot sizes range from 111.48 sq.m to 439.74 sq.m. Its TG-RERA registration number is P02400010045, and the promoter’s declared completion date is 10-06-2028.

01What we found

RegisteredTG-RERA - valid till 10 Jun 2028
27documents on file - each fact links to its page
0court cases on this project's land in the court records searched
9items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

9 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Mogiligidda, Farooqnagar, Ranga Reddy · geocoded — approximate.

1. Project at a glance

Project identity

FieldProject record
Registered project nameSILICON CITY RERA record
Project typePlotted development / open plotted layout RERA record
Phase or registered portionNo separate phase designation is disclosed; the registration identifies the project land at Survey Nos. 211/PART and 224/PART
TG-RERA registrationP02400010045
Registration validity10/06/2025–10/06/2028, unless extended by the Authority
Registered promoterSILICON CITY; the Form B declaration identifies the promoter as M/S SILICON CITY REB
RERA statusRegistered; certificate states a three-year registration period. Registration validity is not a completion certificate or an occupancy certificate.

Land and geographic identity

FieldProject record
LocalityMOGALAGIDA RERA record
Revenue villageMogiligidda; the layout approval also spells the village MOGALIGIDDA
MandalFarooqnagar
DistrictRanga Reddy
PIN509216 in the project identity and registration certificate RERA record
Project survey numbers and subdivisions211/PART and 224/PART
Total site area60193.10 sq.mt
Road-affected area682.52 sq.mt
Net layout/site area59510.58 sq.mt
BoundariesNot disclosed in the supplied project record. Land records

Development identity

FieldProject record
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA)
Principal layout approvalDraft Layout Permit / approval no. 003422/LO/HMDA/1017/SMD/2025, dated 10 June, 2025
Approved built-up area0.00 proposed built-up area, both excluding and including parking, in the layout approval parameters
Plots207 individual sub-plots in the layout record
Buildings, floors and parking levelsNot disclosed; the submitted approval is for a plotted layout, not a building or apartment scheme.
RERA-declared unit countA separate unit-inventory table is not supplied in the evidence. The approved layout drawing records 207 plots.

Offering and status

FieldProject record
OfferingPlots within an open plotted layout
Plot count and sizesThe layout drawing’s plot schedule records 207 plots; software-measured sizes range from 111.48 sq.m to 439.74 sq.m, with a median of 167.27 sq.m. These are drawing-derived measurements, not RERA-filed saleable-area figures. Layout record
Booked / available countsNot disclosed in the supplied evidence.
Construction stageNo independently verified site-progress record is supplied. The promoter’s Form B declares completion by 10-06-2028.
Completion deadlinePromoter-declared date: 10-06-2028
Occupancy / completion certificateNo project occupancy or completion certificate is supplied. The layout approval directs development works to be completed within three years and refers to release of final layout plans; it is not an occupancy certificate.

2. The project story

  • Project identity and location: SILICON CITY is a plotted-layout project in Mogiligidda, Farooqnagar Mandal, Ranga Reddy District. The RERA registration identifies the land as Survey Nos. 211/PART and 224/PART; HMDA’s layout record describes an open layout with 207 plots.
  • Land and layout uses: The approved layout record covers a total site area of 60193.10 sq.mt, including 682.52 sq.mt affected by road widening, and gives a net layout area of 59510.58 sq.mt. It records roads, park/open space, social-infrastructure land and utility land as distinct layout uses.
  • Infrastructure and completion status: The record lists infrastructure and utility provisions, but the supplied materials do not establish their completion on site. The registration certificate is valid through 10/06/2028, while the promoter’s Form B separately declares a project completion date of 10-06-2028. Neither date establishes that the layout works are complete. No verified progress update, final layout release or occupancy/completion certificate is included in the materials reviewed here.

3. Master plan, architecture & building design

  • Layout and area statement: This is a plotted layout, not a multi-storey building project in the supplied approval record. HMDA’s draft layout record lists 207 individual sub-plots and a net layout area of 59510.58 sq.mt. It records 36088.28 sq.mt as plotted area, 16910.01 sq.mt as road area, 4510.15 sq.mt as organized open space/park area, 1532.45 sq.mt as social-infrastructure area and 469.69 sq.mt as utility area; the layout table lists amenity area as 0.00.
  • Roads and layout features: The drawing identifies roads of 9.14M, 18.0M, 30.00 MT and 45.00 MT widths, including an existing 30.00 MT road and proposed 45.00 MT road. The plan also names a cycle track and tot-lot among its amenity/utility items. No building footprint, floor configuration, apartment mix or building-height information is evidenced for this plotted project.
  • Mortgage and release conditions: The layout and related HMDA record identify land subject to mortgage for layout-development obligations: 5707.79 sq.m covering specified plots. The approval conditions state that mortgaged plots are not to be sold until released, and that roads, open spaces, social-infrastructure and utility areas are to be handed over as specified before release of final layout plans.

4. Homes, configurations & floor plans

The offering evidenced in the approved layout is plots, rather than apartments. The plan’s schedule records 207 plots. The following plot-size summary is software-measured from the layout drawing; it is not a RERA-filed saleable-area schedule. Layout record

Plot-size band (sq.yd, as supplied)Area band (sq.m, as supplied)Plots
100–15084–12516
150–200125–16785
200–250167–20980
250–300209–25113
300–400251–33410
400–500334–4182
500–1000418–8361

Across the measured schedule, the smallest plot is 111.48 sq.m (133.3 sq.yd), the median is 167.27 sq.m (200.1 sq.yd) and the largest is 439.74 sq.m (525.9 sq.yd). These measurements are derived from drawing text and should be checked against the approved drawing. The evidence does not provide a booked/available inventory count or a RERA-filed plot saleable-area schedule. Layout record

The supplied drawing set contains 2 layout sheets and no floor plans with homes; measured floor-plan count is 0. Carpet-area and apartment-configuration measurements therefore do not apply to the evidence provided for this plotted layout. Floor plans

5. Parking & vehicle circulation

The layout approval records 0.00 common-parking area and does not establish a project-wide parking-space count, visitor or accessible parking provision, or individual plot parking allocations.

The drawing identifies internal roads with widths of 9.14M and 18.0M, as well as existing/proposed roads of 30.00 MT and 45.00 MT. It does not specify ramps, dedicated pedestrian segregation, EV charging, or legally documented parking rights for individual plots.

6. Amenities, recreation & open spaces

The layout records park/open space and lists several layout features and utilities. The “available” fields and progress values in the supplied amenity data do not establish that facilities have been constructed or independently verified as complete. RERA amenities

CategoryFacilityDescription / sizeEvidence sourceDeclared progress / verified status
Landscape / open spaceOrganized open space / park4510.15 sq.mt; 7.58% of net layout areaIncluded in the layout record; completion not independently verified.
Sports / recreationTot-lotNamed in layout amenities/utilitiesNo completion evidence supplied.
Sports / recreationCycle trackNamed in layout amenities/utilitiesNo completion evidence supplied.
Convenience / communitySocial-infrastructure area1532.45 sq.mt; 2.58%Included in the layout record; handover/development status not independently verified.
Convenience / communityUtility area469.69 sq.mtIncluded in the layout record; completion not independently verified.

The plan’s area statement lists amenity area as 0.00; the evidence does not supply a separate clubhouse or community-building description, size or completion status.

7. Utilities, building services & safety

The layout and approval records identify infrastructure provisions but do not provide capacity data or independent commissioning evidence.

Water
What the supplied record identifiesInternal water-supply pipelines, overhead tank and an “assured water supply source” are listed in the HMDA mortgage-letter extraction. The source, storage capacity and completion status are not stated.
Sewerage and drainage
What the supplied record identifiesCommon septic tank / STP and storm-water drainage/channelization of NALAs are identified in the approval materials. Capacity and completion status are not supplied.
Rainwater
What the supplied record identifiesRainwater-harvesting pits are listed; quantity and completion status are not supplied.
Electrical
What the supplied record identifiesElectrical supply lines, street lights, a transformer and transformer yard are listed. Capacity and completion status are not supplied.
Waste
What the supplied record identifiesBio-compost unit is listed in the layout record. Operating status is not supplied.
Fire and life safety
What the supplied record identifiesNo project-specific fire-system details or clearance are supplied for this plotted layout. RERA amenities
Accessibility and security
What the supplied record identifiesNo project-specific accessibility, CCTV or access-control design details are established in the supplied layout approval. RERA amenities

8. Location, access & connectivity

The registered project location is MOGALAGIDA, revenue village Mogiligidda, Farooqnagar Mandal, Ranga Reddy District, Telangana, PIN 509216. The supplied location record geocodes the site at 17.0861197, 78.1240904, with the geocoder label “Mogiligidda III, Pargi Road, Ayyawaripalle, Ramachandrapoor, Farooqnagar mandal, Ranga Reddy, Telangana, 509207, India.” RERA record Location record

  • The closest sampled Outer Ring Road interchange is listed at approximately 36.2 km. Location record
  • The layout drawing records internal road widths of 9.14M and 18.0M, along with existing/proposed 30.00 MT and 45.00 MT roads. No public-transport service details, landmark distances or verified travel times are supplied.

9. Developer & development status

  • Promoter: The TG-RERA registration identifies SILICON CITY as the registered promoter. The project filing describes the organization as a partnership; the supplied evidence does not establish a separate corporate registration identifier or a complete registered-office/contact profile. RERA record RERA filing
  • Representatives and partners: The layout approval names M/S SILICON CITY, represented by SHAIK SULTHAN and GOPIREDDY SUDEER REDDY; the project record identifies SHAIk SULTHAN as authorized signatory and lists VALA SRINIVAS RAO and GOPIREDDY SUDHEER REDDY as partners. Parties record
  • Declared completion and status: The promoter’s Form B declares that it will complete the project by 10-06-2028. No quarterly progress evidence or independently verified construction-stage assessment is included here, and no occupancy/completion certificate is supplied.

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP02400010045; valid 10/06/2025–10/06/2028
What it establishesRegistration of SILICON CITY and identification of the project land at Survey Nos. 211/PART and 224/PART in Mogiligidda, Farooqnagar, Ranga Reddy.
HMDA draft layout approval
Identifier / date003422/LO/HMDA/1017/SMD/2025; 10 June, 2025
What it establishesDraft open plotted layout for 207 plots, with stated land uses and approval conditions.
HMDA layout drawing / technical approval record
Identifier / datePermit reference 003422/LO/HMDA/1017/SMD/2025
What it establishesPlot schedule, road widths and layout-area breakdown; software-measured plot dimensions are drawing-derived. Layout record
HMDA mortgage letter
Identifier / dateMortgage deed 6230/2025, dated 07 May, 2025
What it establishesRecords the mortgage of specified layout plots in favour of the Metropolitan Commissioner, HMDA, and related conditions.
Form B promoter declaration
Identifier / dateFiled by MR SULTHAN SHAIK for M/S SILICON CITY REB
What it establishesPromoter declaration including stated completion date 10-06-2028 and project obligations.
Completion / occupancy certificate
Identifier / dateNot supplied
What it establishesNo project completion or occupancy certificate is evidenced in the reviewed documents. Document index

Frequently asked questions

Is SILICON CITY registered with Telangana RERA?

Yes. SILICON CITY is registered with the Telangana Real Estate Regulatory Authority as P02400010045; the registration status is New Project.

Who is the developer of SILICON CITY?

The promoter named in the RERA registration is SILICON CITY.

Where is SILICON CITY located?

SILICON CITY is in MOGALAGIDA, Mogiligidda, Farooqnagar, Rangareddy, Telangana (509216).

When will SILICON CITY be completed?

The promoter's proposed date of completion filed with RERA is 10/10/2028. This is the promoter's declaration, not a guarantee.