Sri Anjaneya Enclave
RAJU KONTHAM AND OTHERS · Yadadri Bhuvanagiri · RERA P02000009932
SRI ANJANEYA ENCLAVE is a residential plotted development in ALER, Alair Mandal, Yadadri Bhuvanagiri District. The registered promoter is RAJU KONTHAM AND OTHERS. The project has a site extent of 6734.17 sq.mts and comprises 25 residential plots, with drawing-derived plot sizes from 90.9 sq.m to 271.52 sq.m; no building or floor configuration is disclosed. Its TG-RERA registration number is P02000009932, and the proposed completion date is 05/03/2025.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
6 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered project name | SRI ANJANEYA ENCLAVE RERA record |
| Project type | Plotted development / residential plotted layout RERA record |
| Phase or registered portion | Not separately identified; the registration and layout records describe the project as a whole. RERA record |
| TG-RERA registration number | P02000009932 RERA record |
| Registration validity | Certificate states 06/03/2023 to 05/03/2025; the certificate itself is dated 07/08/2025. No extension is recorded in the supplied certificate. Registration validity is distinct from the completion date. |
| Registered promoter | RAJU KONTHAM AND OTHERS RERA record |
| RERA status | Project record describes the project as On-Going Project. RERA record |
| Entity type | “Others” in the filing; legal entity form is not established in the supplied records. RERA filing |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality / revenue village | Filing identifies the village as ALER and also describes it as Alair Revenue Village. The RERA certificate lists ALER, Alair. RERA record RERA filing |
| Mandal | Alair RERA record |
| District | Yadadri Bhuvanagiri RERA record |
| PIN | 508115 RERA record |
| Survey number(s) in project filing and approval | 1030 RERA record |
| Subdivision references in title records | Title materials also refer to Sy. No. 1030e5, 1030c5, Sy. No. 1030AA5, Sy. No. 103QAA5, and Sy. No. 1030m5. These are reproduced as written in the supplied records; their parcel-level relationship is addressed in Land & Title. Land records |
| Site extent | RERA land details state 6734.17 sq.mts total and 6734.17 sq.mts net area. RERA filing |
| Approved layout extent | Tentative layout approval records 1 Acer 26.56 Gts (8054 Sq. Yds). |
| Boundaries in RERA filing | East: OTHERS; West: OTHERS; North: EXISTING 30 WIDE ROAD; South: STREAM BUFFUR AREA. RERA filing |
Development identity
| Item | Project record |
|---|---|
| Sanctioning authority | ALAIR Municipality/Municipal Corporation is named on the supplied tentative-layout approval. |
| Principal approval | Tentative layout approval 0014/LO/3102/2023, dated 03/06/2023 1:45:44 PM. Application number: 013040/LO/DTCP/3102/0017/2022. |
| Approved built-up area | 3326.11 sqmts is recorded in the RERA filing. RERA filing |
| Plot count | 25 plots in the layout approval and drawing-derived plot schedule. Layout record |
| Building / floor configuration | Not applicable to the supplied plotted-layout plan; no building or floor configuration is disclosed. |
| Mortgage area | RERA filing records 557.69 sq.mts; the layout approval records 0 Acer 5.51 Gts (667 Sq. Yds), comprising plots 14, 13, 12, 11 and 10. RERA filing |
Offering and status
| Item | Project record |
|---|---|
| Unit type | Residential plots; no apartment or villa configurations are established by the project records. Layout record |
| Plot sizes | Drawing-derived schedule: 25 plots, from 90.9 sq.m to 271.52 sq.m; median 124.97 sq.m. These are software-measured/read from the approved layout drawing, not RERA-filed saleable-area figures. Layout record |
| Booked / available plots | Not disclosed in the supplied project data. |
| Construction / development stage | RERA header says On-Going Project and records 80% completeness; this is a filed status, not independent site verification. RERA record |
| Completion date | Promoter’s Form B and RERA project record state 05/03/2025 as the completion date. RERA record |
| Occupancy / completion certificate | No occupancy certificate or completion certificate is included in the supplied documents. The supplied approval is a Tentative Layout Plan. |
2. The project story
SRI ANJANEYA ENCLAVE is registered as a residential plotted-layout project in Survey No. 1030, at Alair Revenue Village, Alair Mandal, Yadadri Bhuvanagiri District. The project record describes 25 plots rather than apartments or multi-storey buildings. RERA record
The layout drawing’s schedule and area statement show plots arranged with internal roads and designated areas for park/open space, utilities and social infrastructure. The approval requires the layout applicant to carry out the infrastructure and amenities works; the filing’s 80% completeness figure is a promoter/RERA-record status and is not an independently verified site inspection. Layout record RERA record
The promoter declared a completion date of 05/03/2025. The registration certificate gives the same date as the end of its stated validity period. No completion or occupancy certificate is present in the supplied records, so the evidence does not establish that the layout development has been certified complete.
3. Master plan, architecture & building design
This is a plotted layout, not a building scheme. The tentative layout approval covers 1 Acer 26.56 Gts (8054 Sq. Yds) and records 25 plots. The drawing-derived area statement identifies 3325.83 sq.m as plotted area, 2481.15 sq.m as roads, 597.31 sq.m as parks/open space, 66.40 sq.m as utilities and 165.94 sq.m as social infrastructure. The drawing figures are software-read from the layout and should be checked against the approved drawing. Layout record
The approval records 3326.11 sqmts as approved built-up area in the RERA filing; this is not a plot saleable-area or carpet-area figure. The layout approval’s stated land-use allocation is 50.11% plotted area, 37.38% roads, 9% open space/park, 1% utilities and 2.5% social infrastructure. It records no amenity area. RERA filing Layout record
The approval describes a tentative layout and requires roads to be opened for neighbouring-site access. It also requires the applicant to develop the works and amenities and identifies the park, utilities and roads for handover to the municipality through registered gift deed before release of the tentative layout.
4. Homes, configurations & floor plans
No apartment or villa configuration is disclosed for this registered project. The supplied records describe a plotted layout with 25 plots. Layout record
| Plot information | Figure | Evidence / measurement status |
|---|---|---|
| Plot count | 25 | Approval and drawing schedule Layout record |
| Smallest plot | 90.9 sq.m (108.7 sq.yd) | Software-measured/read from layout drawing Layout record |
| Median plot | 124.97 sq.m (149.5 sq.yd) | Software-measured/read from layout drawing Layout record |
| Largest plot | 271.52 sq.m (324.7 sq.yd) | Software-measured/read from layout drawing Layout record |
| 100–150 sq.yd band | 16 plots | Drawing-derived size bands Layout record |
| 150–200 sq.yd band | 8 plots | Drawing-derived size bands Layout record |
| 300–400 sq.yd band | 1 plot | Drawing-derived size bands Layout record |
The supplied floor-plan set contains two layout sheets and no building floor plans from which home rooms or carpet areas could be measured. Plot dimensions above are drawing-derived; they are not RERA-filed apartment saleable areas. Floor plans Layout record
5. Parking & vehicle circulation
The project is a plotted layout, and the supplied data does not establish a parking-space count, resident or visitor parking allocation, accessible parking, or EV-charging provision. No parking-allotment arrangement for individual plots is supplied. Layout record
The tentative approval requires roads to be opened for access to neighbouring sites. The layout drawing includes a road-area allocation of 2481.15 sq.m (37.38% in the drawing’s area statement); road dimensions, vehicle-entry details, turning areas and pedestrian separation are not established by the supplied extracted data. Layout record
6. Amenities, recreation & open spaces
The approval specifies development works and facilities for the layout. The status entries below reflect the RERA filing or approval requirements; they do not independently verify completion on site.
| Description / size | Approval reserves 0 Acer 5.9 Gts (714 Sq. Yds); drawing-derived area statement records 597.31 sq.m and 9%. |
|---|---|
| Evidence source | Layout record |
| Declared progress / verified status | Approval condition requires development and municipal handover; completion not independently verified. |
| Description / size | Approval reserves 0 Acer 1.64 Gts (198 Sq. Yds); drawing-derived area statement records 165.94 sq.m and 2.5%. |
|---|---|
| Evidence source | Layout record |
| Declared progress / verified status | Reserved area is shown; facility/building completion is not established. |
| Description / size | Approval reserves 0 Acer 0.66 Gts (79 Sq. Yds); drawing-derived area statement records 66.40 sq.m and 1%. |
|---|---|
| Evidence source | Layout record |
| Declared progress / verified status | Reserved area is shown; completion is not independently verified. |
| Description / size | Approval records 0 Acer 24.52 Gts (2968 Sq. Yds); drawing-derived area statement records 2481.15 sq.m and 37.38%. |
|---|---|
| Evidence source | Layout record |
| Declared progress / verified status | Road formation is among the required development works; completion is not independently verified. |
| Description / size | No area or facility description supplied. RERA amenity record shows 0%. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | No completion evidence supplied. |
The approval’s required works include road formation with black top, storm-water drains, underground drainage lines and a common septic tank/STP, internal water-supply pipelines, overhead tank, assured water source, electrical supply lines, street lights, transformer, avenue plantation, park development and rainwater-harvesting pits. These are approval requirements, not evidence that each item has been completed.
7. Utilities, building services & safety
The tentative layout approval specifies internal water-supply pipelines, an overhead tank or sump, an assured water-supply source, underground drainage, a common septic tank/STP, storm-water drains, electrical supply lines, a transformer, street lights and rainwater-harvesting pits. It also refers to solid-waste management. The records do not supply capacities, source details, design specifications or independent completion evidence for these services.
The RERA amenity record marks water supply, sewerage (including chamber, lines, septic tank/STP), storm-water drains, water conservation/rainwater harvesting, street lighting and an electrical meter room/sub-station/receiving station as available at 100%; these are filing entries, not independent site verification. The same record shows 0% for treatment and disposal of sewage and sullage water, solid-waste management and disposal, energy management, and fire protection and fire-safety requirements. RERA amenities
No fire-system specifications, statutory fire clearance, accessibility details, security systems, CCTV, backup power, lift systems or waste-segregation arrangements are established for this plotted project by the supplied project-specific records. RERA amenities
8. Location, access & connectivity
The registered location is ALER / Alair Revenue Village, Alair Mandal, Yadadri Bhuvanagiri District, Telangana, PIN 508115. The filing records the north boundary as EXISTING 30 WIDE ROAD and the south boundary as STREAM BUFFUR AREA; east and west are recorded as OTHERS. RERA record RERA filing
The supplied location record geocodes the site area near State Bank of India, WARANGAL HIGHWAY, Aleru, Alair mandal, Yadadri Bhuvanagiri, Telangana, India. It lists the nearest sampled Outer Ring Road interchange at approximately 45.0 km. No public-transport details or further measured distances are supplied. Location record
9. Developer & development status
The registered promoter is RAJU KONTHAM AND OTHERS. The RERA filing classifies the organization as Others; the legal entity type, corporate registration identifiers, official website and project contact details are not established in the supplied records. RERA record RERA filing Corporate record
In Form B, Raju Kontham declared legal title and supporting title authentication and an owner-promoter development agreement, declared the land free from encumbrances, and undertook to complete the project by 05/03/2025. These are promoter declarations in the RERA-filed affidavit.
The project record reports 80% completeness, but no independent construction inspection or completion certificate is supplied. The registration certificate states validity from 06/03/2023 to 05/03/2025; that registration period should not be read as proof that the project was completed by its end date. RERA record
10. Approvals, official records & documents
| Record | What the supplied evidence establishes |
|---|---|
| TG-RERA registration | Form C registration for SRI ANJANEYA ENCLAVE, number P02000009932; stated validity 06/03/2023–05/03/2025. |
| Tentative layout approval | Approval for Tentative Layout Plan 0014/LO/3102/2023, application 013040/LO/DTCP/3102/0017/2022, issued by Alair Municipality/Municipal Corporation for Sy. No. 1030; dated 03/06/2023 1:45:44 PM. |
| Layout drawing | Two layout sheets; drawing-derived schedule records 25 plots and land-use areas. Layout record |
| Promoter declaration | Form B affidavit by Raju Kontham, dated 18 June 2025, including the promoter’s title, encumbrance, fund-management and completion declarations. |
| Completion / occupancy certificate | None included in the supplied documents. The approval record is a tentative layout approval. Document index |
The supplied layout approval expressly describes itself as tentative and states that it is not proof of land title. Detailed title and approval conditions are addressed in the corresponding report sections.
1. Project at a glance
Project identity
Registered project name: SRI ANJANEYA ENCLAVE
Project type: Plotted development / residential plotted layout
Phase or registered portion: Not separately identified; the registration and layout records describe the project as a whole.
TG-RERA registration number: P02000009932
Registration validity: Certificate states 06/03/2023 to 05/03/2025; the certificate itself is dated 07/08/2025. No extension is recorded in the supplied certificate. Registration validity is distinct from the completion date.
Registered promoter: RAJU KONTHAM AND OTHERS
RERA status: Project record describes the project as On-Going Project.
Entity type: “Others” in the filing; legal entity form is not established in the supplied records.
Land and geographic identity
Locality / revenue village: Filing identifies the village as ALER and also describes it as Alair Revenue Village. The RERA certificate lists ALER, Alair.
Mandal: Alair
District: Yadadri Bhuvanagiri
PIN: 508115
Survey number(s) in project filing and approval: 1030
Subdivision references in title records: Title materials also refer to Sy. No. 1030e5, 1030c5, Sy. No. 1030AA5, Sy. No. 103QAA5, and Sy. No. 1030m5. These are reproduced as written in the supplied records; their parcel-level relationship is addressed in Land & Title.
Site extent: RERA land details state 6734.17 sq.mts total and 6734.17 sq.mts net area.
Approved layout extent: Tentative layout approval records 1 Acer 26.56 Gts (8054 Sq. Yds).
Boundaries in RERA filing: East: OTHERS; West: OTHERS; North: EXISTING 30 WIDE ROAD; South: STREAM BUFFUR AREA.
Development identity
Sanctioning authority: ALAIR Municipality/Municipal Corporation is named on the supplied tentative-layout approval.
Principal approval: Tentative layout approval 0014/LO/3102/2023, dated 03/06/2023 1:45:44 PM. Application number: 013040/LO/DTCP/3102/0017/2022.
Approved built-up area: 3326.11 sqmts is recorded in the RERA filing.
Plot count: 25 plots in the layout approval and drawing-derived plot schedule.
Building / floor configuration: Not applicable to the supplied plotted-layout plan; no building or floor configuration is disclosed.
Mortgage area: RERA filing records 557.69 sq.mts; the layout approval records 0 Acer 5.51 Gts (667 Sq. Yds), comprising plots 14, 13, 12, 11 and 10.
Offering and status
Unit type: Residential plots; no apartment or villa configurations are established by the project records.
Plot sizes: Drawing-derived schedule: 25 plots, from 90.9 sq.m to 271.52 sq.m; median 124.97 sq.m. These are software-measured/read from the approved layout drawing, not RERA-filed saleable-area figures.
Booked / available plots: Not disclosed in the supplied project data.
Construction / development stage: RERA header says On-Going Project and records 80% completeness; this is a filed status, not independent site verification.
Completion date: Promoter’s Form B and RERA project record state 05/03/2025 as the completion date.
Occupancy / completion certificate: No occupancy certificate or completion certificate is included in the supplied documents. The supplied approval is a Tentative Layout Plan.
2. The project story
SRI ANJANEYA ENCLAVE is registered as a residential plotted-layout project in Survey No. 1030, at Alair Revenue Village, Alair Mandal, Yadadri Bhuvanagiri District. The project record describes 25 plots rather than apartments or multi-storey buildings.
The layout drawing’s schedule and area statement show plots arranged with internal roads and designated areas for park/open space, utilities and social infrastructure. The approval requires the layout applicant to carry out the infrastructure and amenities works; the filing’s 80% completeness figure is a promoter/RERA-record status and is not an independently verified site inspection.
The promoter declared a completion date of 05/03/2025. The registration certificate gives the same date as the end of its stated validity period. No completion or occupancy certificate is present in the supplied records, so the evidence does not establish that the layout development has been certified complete.
3. Master plan, architecture & building design
This is a plotted layout, not a building scheme. The tentative layout approval covers 1 Acer 26.56 Gts (8054 Sq. Yds) and records 25 plots. The drawing-derived area statement identifies 3325.83 sq.m as plotted area, 2481.15 sq.m as roads, 597.31 sq.m as parks/open space, 66.40 sq.m as utilities and 165.94 sq.m as social infrastructure. The drawing figures are software-read from the layout and should be checked against the approved drawing.
The approval records 3326.11 sqmts as approved built-up area in the RERA filing; this is not a plot saleable-area or carpet-area figure. The layout approval’s stated land-use allocation is 50.11% plotted area, 37.38% roads, 9% open space/park, 1% utilities and 2.5% social infrastructure. It records no amenity area.
The approval describes a tentative layout and requires roads to be opened for neighbouring-site access. It also requires the applicant to develop the works and amenities and identifies the park, utilities and roads for handover to the municipality through registered gift deed before release of the tentative layout.
4. Homes, configurations & floor plans
No apartment or villa configuration is disclosed for this registered project. The supplied records describe a plotted layout with 25 plots.
| Plot information | Figure | Evidence / measurement status |
|---|---|---|
| Plot count | 25 | Approval and drawing schedule |
| Smallest plot | 90.9 sq.m (108.7 sq.yd) | Software-measured/read from layout drawing |
| Median plot | 124.97 sq.m (149.5 sq.yd) | Software-measured/read from layout drawing |
| Largest plot | 271.52 sq.m (324.7 sq.yd) | Software-measured/read from layout drawing |
| 100–150 sq.yd band | 16 plots | Drawing-derived size bands |
| 150–200 sq.yd band | 8 plots | Drawing-derived size bands |
| 300–400 sq.yd band | 1 plot | Drawing-derived size bands |
The supplied floor-plan set contains two layout sheets and no building floor plans from which home rooms or carpet areas could be measured. Plot dimensions above are drawing-derived; they are not RERA-filed apartment saleable areas.
5. Parking & vehicle circulation
The project is a plotted layout, and the supplied data does not establish a parking-space count, resident or visitor parking allocation, accessible parking, or EV-charging provision. No parking-allotment arrangement for individual plots is supplied.
The tentative approval requires roads to be opened for access to neighbouring sites. The layout drawing includes a road-area allocation of 2481.15 sq.m (37.38% in the drawing’s area statement); road dimensions, vehicle-entry details, turning areas and pedestrian separation are not established by the supplied extracted data.
6. Amenities, recreation & open spaces
The approval specifies development works and facilities for the layout. The status entries below reflect the RERA filing or approval requirements; they do not independently verify completion on site.
| Description / size | Approval reserves 0 Acer 5.9 Gts (714 Sq. Yds); drawing-derived area statement records 597.31 sq.m and 9%. |
|---|---|
| Declared progress / verified status | Approval condition requires development and municipal handover; completion not independently verified. |
| Description / size | Approval reserves 0 Acer 1.64 Gts (198 Sq. Yds); drawing-derived area statement records 165.94 sq.m and 2.5%. |
|---|---|
| Declared progress / verified status | Reserved area is shown; facility/building completion is not established. |
| Description / size | Approval reserves 0 Acer 0.66 Gts (79 Sq. Yds); drawing-derived area statement records 66.40 sq.m and 1%. |
|---|---|
| Declared progress / verified status | Reserved area is shown; completion is not independently verified. |
| Description / size | Approval records 0 Acer 24.52 Gts (2968 Sq. Yds); drawing-derived area statement records 2481.15 sq.m and 37.38%. |
|---|---|
| Declared progress / verified status | Road formation is among the required development works; completion is not independently verified. |
| Description / size | No area or facility description supplied. RERA amenity record shows 0%. |
|---|---|
| Declared progress / verified status | No completion evidence supplied. |
The approval’s required works include road formation with black top, storm-water drains, underground drainage lines and a common septic tank/STP, internal water-supply pipelines, overhead tank, assured water source, electrical supply lines, street lights, transformer, avenue plantation, park development and rainwater-harvesting pits. These are approval requirements, not evidence that each item has been completed.
7. Utilities, building services & safety
The tentative layout approval specifies internal water-supply pipelines, an overhead tank or sump, an assured water-supply source, underground drainage, a common septic tank/STP, storm-water drains, electrical supply lines, a transformer, street lights and rainwater-harvesting pits. It also refers to solid-waste management. The records do not supply capacities, source details, design specifications or independent completion evidence for these services.
The RERA amenity record marks water supply, sewerage (including chamber, lines, septic tank/STP), storm-water drains, water conservation/rainwater harvesting, street lighting and an electrical meter room/sub-station/receiving station as available at 100%; these are filing entries, not independent site verification. The same record shows 0% for treatment and disposal of sewage and sullage water, solid-waste management and disposal, energy management, and fire protection and fire-safety requirements.
No fire-system specifications, statutory fire clearance, accessibility details, security systems, CCTV, backup power, lift systems or waste-segregation arrangements are established for this plotted project by the supplied project-specific records.
8. Location, access & connectivity
The registered location is ALER / Alair Revenue Village, Alair Mandal, Yadadri Bhuvanagiri District, Telangana, PIN 508115. The filing records the north boundary as EXISTING 30 WIDE ROAD and the south boundary as STREAM BUFFUR AREA; east and west are recorded as OTHERS.
The supplied location record geocodes the site area near State Bank of India, WARANGAL HIGHWAY, Aleru, Alair mandal, Yadadri Bhuvanagiri, Telangana, India. It lists the nearest sampled Outer Ring Road interchange at approximately 45.0 km. No public-transport details or further measured distances are supplied.
9. Developer & development status
The registered promoter is RAJU KONTHAM AND OTHERS. The RERA filing classifies the organization as Others; the legal entity type, corporate registration identifiers, official website and project contact details are not established in the supplied records.
In Form B, Raju Kontham declared legal title and supporting title authentication and an owner-promoter development agreement, declared the land free from encumbrances, and undertook to complete the project by 05/03/2025. These are promoter declarations in the RERA-filed affidavit.
The project record reports 80% completeness, but no independent construction inspection or completion certificate is supplied. The registration certificate states validity from 06/03/2023 to 05/03/2025; that registration period should not be read as proof that the project was completed by its end date.
10. Approvals, official records & documents
TG-RERA registration: Form C registration for SRI ANJANEYA ENCLAVE, number P02000009932; stated validity 06/03/2023–05/03/2025.
Tentative layout approval: Approval for Tentative Layout Plan 0014/LO/3102/2023, application 013040/LO/DTCP/3102/0017/2022, issued by Alair Municipality/Municipal Corporation for Sy. No. 1030; dated 03/06/2023 1:45:44 PM.
Layout drawing: Two layout sheets; drawing-derived schedule records 25 plots and land-use areas.
Promoter declaration: Form B affidavit by Raju Kontham, dated 18 June 2025, including the promoter’s title, encumbrance, fund-management and completion declarations.
Completion / occupancy certificate: None included in the supplied documents. The approval record is a tentative layout approval.
The supplied layout approval expressly describes itself as tentative and states that it is not proof of land title. Detailed title and approval conditions are addressed in the corresponding report sections.
Frequently asked questions
Is SRI ANJANEYA ENCLAVE registered with Telangana RERA?
Yes. SRI ANJANEYA ENCLAVE is registered with the Telangana Real Estate Regulatory Authority as P02000009932; the registration status is On-Going Project.
Who is the developer of SRI ANJANEYA ENCLAVE?
The promoter named in the RERA registration is RAJU KONTHAM AND OTHERS.
Where is SRI ANJANEYA ENCLAVE located?
SRI ANJANEYA ENCLAVE is in ALAIR MANDAL, ALER, Alair, Yadadri Bhuvanagiri, Telangana (508115).
When will SRI ANJANEYA ENCLAVE be completed?
The promoter's proposed date of completion filed with RERA is 05/03/2025. This is the promoter's declaration, not a guarantee.