Lake East - Parcel 2
POOJA CRAFTED HOMES PRIVATE LIMITED · Medchal-Malkajgiri · RERA P02200010128
Lake East - Parcel 2 is a plotted development in Cherlapally, Kapra Mandal, Medchal-Malkajgiri District. The registered promoter is POOJA CRAFTED HOMES PRIVATE LIMITED. The project records state a net area of 17,987.06 sq.m and a 31-plot layout, with plot sizes of 250.26–334.65 sq.m; towers, floors and home configurations are not disclosed. It is registered with TG-RERA as P02200010128, with proposed completion on 14/01/2029.
More from Pooja Crafted Homes Pvt Ltd · 7 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
8 items to check before you pay, 5 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
Project at a glance
Project identity
| Field | Record |
|---|---|
| Registered project name | Lake East - Parcel 2 RERA record |
| Project type | Plotted development / open layout RERA record |
| Phase / registered portion | “Parcel 2”; the registration identifies the listed survey portions. RERA record |
| TG-RERA registration | P02200010128; registered from 15/09/2025 to 14/09/2028. This is the registration-validity period, not the completion deadline. RERA record |
| Registered promoter | POOJA CRAFTED HOMES PRIVATE LIMITED RERA record |
| RERA status | Registered; the certificate requires quarterly updates and records the promoter’s obligations to enter into agreements for sale and execute registered conveyances. |
Land and geographic identity
| Field | Record |
|---|---|
| Locality / revenue village | Cherlapally is named in the GHMC layout-plan instrument; the RERA certificate’s location field says Kapra. The supplied records identify Kapra as both mandal and village in the project identity. RERA record |
| Mandal / district / PIN | Kapra Mandal; Medchal-Malkajgiri District (also rendered “Medchal Malakajigiri” in the plan); PIN 501301. RERA record |
| All project survey numbers / portions | 137 PART, 138 PART, 140PART, 166 PART, 167 PART, 168 PART, 170PART. RERA record Land records |
| Registered site extent | The project filing records 17,987.06 sq.m net area and 7,802.3 sq.m affected by road widening/FTL/nala widening. The layout plan separately states 182,045.73 sq.m total layout area, 17,987.06 sq.m net layout area, 8,075.79 sq.m road-widening area, and 155,652.08 sq.m leftover owners’ land area. RERA record RERA filing |
| Boundaries (RERA filing) | East: land in SY No. 138 part, 140 part, 166 and 167 part. West: land in SY No. 166 part, 168 part, 170 part and others. North: neighbours’ land in SY Nos. 134 and 142. South: land in SY No. 137 part and 166 part. RERA filing |
Development identity
| Field | Record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC). |
| Principal layout approval | 1063/GHMC/SWDL/LBN1/2025, dated 15/09/2025; file/application no. 001933/GHMC/01103/SWDL/LBN1/2025. The filed layout document is identified as a draft layout letter for a tentative layout. Approvals record |
| Plotted area / approved built-up area | Layout plan: 8,042.06 sq.m plotted area. The RERA filing separately records “Approved Built up Area” of 8042.06 sq.m; no building or villa configuration is disclosed in the supplied records. RERA filing |
| Layout scale and land use | 31 plots. Layout plan land-use figures: plotted area 8,042.06 sq.m (44.71%); roads 7,802.30 sq.m (43.38%); open space 1,448.07 sq.m (8.05%); social infrastructure 484.18 sq.m (2.69%); utility 209.92 sq.m (1.17%). Layout record |
| Building / floor configuration | Not disclosed in the supplied project records; this is a plotted layout, not a multi-storey apartment schedule. RERA record |
| Parking | The plan reports 0.00 sq.m common parking area. Individual plot parking provision or any parking allocation is not established in the supplied records. |
Offering and status
| Field | Record |
|---|---|
| Offered property | Plots; the plan schedule records 31 plots. Layout record |
| Plot-size range | Software-measured from the approved layout drawing: 250.26–334.65 sq.m (31 plots with sizes read from the drawing). These are drawing-derived measurements, not RERA-filed unit-size figures. Layout record |
| Booked / available | Not disclosed in the supplied records. Document index |
| Construction stage | No independently verified site-progress evidence or construction percentage is supplied. RERA amenity entries show 0% progress for the listed items; they do not establish whether work has started. RERA amenities |
| Completion deadline | Header records proposed completion 14/01/2029. The Form B declaration’s completion undertaking is truncated (“14-09-”), so the complete declaration date is not available in the extracted text. RERA record |
| Occupancy / completion certificate | No occupancy or completion certificate is supplied. The layout plan states that completion notice and an occupancy certificate are required after completion and that occupancy certification is required before occupation. |
The project story
Lake East - Parcel 2 is registered as a plotted development at Cherlapally, Kapra Mandal, Medchal-Malkajgiri District. The RERA record identifies the project’s land as portions of Survey Nos. 137 PART, 138 PART, 140PART, 166 PART, 167 PART, 168 PART and 170PART. GHMC’s layout drawing depicts a 31-plot layout with internal roads, open space, social-infrastructure and utility areas. RERA record Land records
The filed records describe a proposed layout, not completed plots or delivered services. No site inspection, independently verified construction progress, booking inventory, or occupancy/completion certificate is included. RERA registration remains valid through 14/09/2028; the project header gives a proposed completion date of 14/01/2029. These are separate dates and describe different matters. RERA record RERA amenities
Master plan, architecture & building design
The approved layout drawing is the relevant design evidence for this plotted project. It shows 31 plots and a stated total layout area of 182,045.73 sq.m, with a net layout area of 17,987.06 sq.m. The land-use schedule allocates 8,042.06 sq.m to plots, 7,802.30 sq.m to roads, 1,448.07 sq.m to open space, 484.18 sq.m to social infrastructure and 209.92 sq.m to utilities. Layout record
The drawing lists road widths of 30.0 m, 30.00 M, 24.0M, 24.00 M, 18.00 M, 18.0 M, 12.01m, 12m, 9.0 M and 9.00 m, and shows existing 33'-0" and 30'-0" roads. The plan identifies a proposed mortgage area of 1,257.69 sq.m (15.64%).
No apartment plans, towers, floors, building footprints, or residential/commercial building mix are provided. The floor-plan set contains two layout sheets and no flats; apartment carpet-area measurements therefore do not apply. Floor plans
Homes, configurations & floor plans
This is a plotted layout, not an apartment project. The approved layout drawing’s plot schedule records 31 plots. Software measurement of plot areas from that drawing gives the following distribution; the drawing-derived areas should be checked against the stamped plan schedule. Layout record
| Plot-size band | Plot count |
|---|---|
| 250–300 sq.yd (209–251 sq.m) | 4 |
| 300–400 sq.yd (251–334 sq.m) | 25 |
| 400–500 sq.yd (334–418 sq.m) | 2 |
The software-measured range is 250.26 sq.m to 334.65 sq.m; the median is 251.48 sq.m. These are measurements read from the layout drawing, not RERA-filed saleable-area or carpet-area disclosures. No booked/available plot counts or plot-wise allotment details are supplied. Layout record Document index
Parking & vehicle circulation
The layout’s land-use schedule records 0.00 sq.m as common parking area. The GHMC plan conditions require parking places in buildings to provide electric-vehicle charging infrastructure, but the supplied records do not identify building parking spaces, visitor or accessible parking, individual plot parking arrangements, or EV charging installations. The drawing alone does not establish an exclusive parking entitlement for a buyer.
Internal layout roads are shown with widths from 9.0 M up to 30.0 m, alongside existing 33'-0" and 30'-0" roads. The records do not provide a detailed vehicle-circulation or pedestrian-separation plan beyond the layout drawing.
Amenities, recreation & open spaces
The RERA amenity schedule marks the following items “YES” where indicated and records 0% progress for the listed amenities. Those entries are filed availability declarations, not evidence of completed or independently verified facilities. RERA amenities
| Facility | Green strip / tot-lot / park |
|---|---|
| Description / size | Layout plan: open space 1,448.07 sq.m (8.05%); tot-lot also named in plan conditions and utility list. |
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA schedule: 0%; completion not independently verified. |
| Facility | Aggregate recreational open space |
|---|---|
| Description / size | Marked “YES”; no separate size beyond the layout open-space figure. |
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA schedule: 0%; completion not independently verified. |
| Facility | Community buildings / social infrastructure |
|---|---|
| Description / size | Social infrastructure area 484.18 sq.m (2.69%) on the layout plan. |
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA schedule: 0%; delivery not independently verified. |
| Facility | Internal roads and footpaths |
|---|---|
| Description / size | Road area 7,802.30 sq.m (43.38%) on the layout plan. |
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA schedule: 0%; completion not independently verified. |
No clubhouse or indoor recreation facilities are specifically identified in the supplied records.
Utilities, building services & safety
The RERA amenity schedule marks water supply, sewerage, storm-water drains, sewage/sullage treatment and disposal, rainwater harvesting, energy management, street lighting, and an electrical meter room/sub-station/receiving station as available; each listed item is recorded at 0% progress. This is a filed schedule, not confirmation that these services are installed or operating. RERA amenities
The GHMC layout-plan conditions require underground drainage, street lighting and avenue plantation before release of the final layout; identify a transformer space, rainwater-harvesting structure, garbage house and fenced tot-lot; and call for fire NOC before an occupancy certificate. The plan’s utilities list also names an STP and U.G. sump. No water-source or storage capacity, STP capacity, electrical load, backup-power capacity, fire-system specification, security system, or accessibility design is provided.
Location, access & connectivity
The project’s filed location is Cherlapally, Kapra Mandal, Medchal-Malkajgiri District, PIN 501301; the RERA certificate also identifies Kapra. The parcel-centroid coordinates supplied are 17.498701551094552, 78.57572146632462. RERA record Location record
The nearest sampled Outer Ring Road interchange is listed at approximately 4.9 km. The supplied records do not identify a specific approach-road route, public-transport service, or additional measured landmark distances. Location record
Developer & development status
The registered legal promoter is POOJA CRAFTED HOMES PRIVATE LIMITED, a company. Its listed office address is CRUX Building, Sai Aishwarya Layout, Cherlapally, Cherlapally, Kapra, Medchal-Malkajgiri, 501301; the promoter website supplied is poojacraftedhomes.in. Corporate record Parties record
The GHMC plan names the applicant as Pooja Crafted Homes Pvt. Ltd., formerly known as Pooja Ventures Pvt Ltd. The supplied corporate record says the company changed its name from Pooja Ventures Private Limited to Pooja Crafted Homes Private Limited; this identifies the legal entity, not a separate project brand.
The project header gives 14/01/2029 as the proposed completion date. The records supplied do not establish physical progress through an independent site review, bookings, or completion/occupancy certification. RERA record RERA amenities
Approvals, official records & documents
| Details | Lake East - Parcel 2; P02200010128; valid 15/09/2025–14/09/2028. |
|---|
| Details | 1063/GHMC/SWDL/LBN1/2025, dated 15/09/2025; file/application no. 001933/GHMC/01103/SWDL/LBN1/2025; layout drawing covers the project’s seven listed survey portions. |
|---|
| Details | Mortgage Deed No. 10859/2025, dated 01/08/2025, for a stated 1,257.69 sq.m proposed mortgage area in favour of GHMC. |
|---|
| Details | Affidavit dated 17-09-2025 by the promoter’s authorized signatory, containing declarations concerning title, encumbrances, completion and project funds; extracted completion wording is truncated. |
|---|
| Details | No certificate supplied. The GHMC plan states that completion notice and occupancy certification are required after completion and that occupancy certification is required before occupation. |
|---|
The layout plan also sets out requirements concerning roads, open spaces and social infrastructure, drainage, street lighting and avenue plantation. This overview lists the filed records and selected layout features; it is not a complete review of approval conditions.
Project at a glance
Project identity
Registered project name: Lake East - Parcel 2
Project type: Plotted development / open layout
Phase / registered portion: “Parcel 2”; the registration identifies the listed survey portions.
TG-RERA registration: P02200010128; registered from 15/09/2025 to 14/09/2028. This is the registration-validity period, not the completion deadline.
Registered promoter: POOJA CRAFTED HOMES PRIVATE LIMITED
RERA status: Registered; the certificate requires quarterly updates and records the promoter’s obligations to enter into agreements for sale and execute registered conveyances.
Land and geographic identity
Locality / revenue village: Cherlapally is named in the GHMC layout-plan instrument; the RERA certificate’s location field says Kapra. The supplied records identify Kapra as both mandal and village in the project identity.
Mandal / district / PIN: Kapra Mandal; Medchal-Malkajgiri District (also rendered “Medchal Malakajigiri” in the plan); PIN 501301.
All project survey numbers / portions: 137 PART, 138 PART, 140PART, 166 PART, 167 PART, 168 PART, 170PART.
Registered site extent: The project filing records 17,987.06 sq.m net area and 7,802.3 sq.m affected by road widening/FTL/nala widening. The layout plan separately states 182,045.73 sq.m total layout area, 17,987.06 sq.m net layout area, 8,075.79 sq.m road-widening area, and 155,652.08 sq.m leftover owners’ land area.
Boundaries (RERA filing): East: land in SY No. 138 part, 140 part, 166 and 167 part. West: land in SY No. 166 part, 168 part, 170 part and others. North: neighbours’ land in SY Nos. 134 and 142. South: land in SY No. 137 part and 166 part.
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC).
Principal layout approval: 1063/GHMC/SWDL/LBN1/2025, dated 15/09/2025; file/application no. 001933/GHMC/01103/SWDL/LBN1/2025. The filed layout document is identified as a draft layout letter for a tentative layout.
Plotted area / approved built-up area: Layout plan: 8,042.06 sq.m plotted area. The RERA filing separately records “Approved Built up Area” of 8042.06 sq.m; no building or villa configuration is disclosed in the supplied records.
Layout scale and land use: 31 plots. Layout plan land-use figures: plotted area 8,042.06 sq.m (44.71%); roads 7,802.30 sq.m (43.38%); open space 1,448.07 sq.m (8.05%); social infrastructure 484.18 sq.m (2.69%); utility 209.92 sq.m (1.17%).
Building / floor configuration: Not disclosed in the supplied project records; this is a plotted layout, not a multi-storey apartment schedule.
Parking: The plan reports 0.00 sq.m common parking area. Individual plot parking provision or any parking allocation is not established in the supplied records.
Offering and status
Offered property: Plots; the plan schedule records 31 plots.
Plot-size range: Software-measured from the approved layout drawing: 250.26–334.65 sq.m (31 plots with sizes read from the drawing). These are drawing-derived measurements, not RERA-filed unit-size figures.
Booked / available: Not disclosed in the supplied records.
Construction stage: No independently verified site-progress evidence or construction percentage is supplied. RERA amenity entries show 0% progress for the listed items; they do not establish whether work has started.
Completion deadline: Header records proposed completion 14/01/2029. The Form B declaration’s completion undertaking is truncated (“14-09-”), so the complete declaration date is not available in the extracted text.
Occupancy / completion certificate: No occupancy or completion certificate is supplied. The layout plan states that completion notice and an occupancy certificate are required after completion and that occupancy certification is required before occupation.
The project story
Lake East - Parcel 2 is registered as a plotted development at Cherlapally, Kapra Mandal, Medchal-Malkajgiri District. The RERA record identifies the project’s land as portions of Survey Nos. 137 PART, 138 PART, 140PART, 166 PART, 167 PART, 168 PART and 170PART. GHMC’s layout drawing depicts a 31-plot layout with internal roads, open space, social-infrastructure and utility areas.
The filed records describe a proposed layout, not completed plots or delivered services. No site inspection, independently verified construction progress, booking inventory, or occupancy/completion certificate is included. RERA registration remains valid through 14/09/2028; the project header gives a proposed completion date of 14/01/2029. These are separate dates and describe different matters.
Master plan, architecture & building design
The approved layout drawing is the relevant design evidence for this plotted project. It shows 31 plots and a stated total layout area of 182,045.73 sq.m, with a net layout area of 17,987.06 sq.m. The land-use schedule allocates 8,042.06 sq.m to plots, 7,802.30 sq.m to roads, 1,448.07 sq.m to open space, 484.18 sq.m to social infrastructure and 209.92 sq.m to utilities.
The drawing lists road widths of 30.0 m, 30.00 M, 24.0M, 24.00 M, 18.00 M, 18.0 M, 12.01m, 12m, 9.0 M and 9.00 m, and shows existing 33'-0" and 30'-0" roads. The plan identifies a proposed mortgage area of 1,257.69 sq.m (15.64%).
No apartment plans, towers, floors, building footprints, or residential/commercial building mix are provided. The floor-plan set contains two layout sheets and no flats; apartment carpet-area measurements therefore do not apply.
Homes, configurations & floor plans
This is a plotted layout, not an apartment project. The approved layout drawing’s plot schedule records 31 plots. Software measurement of plot areas from that drawing gives the following distribution; the drawing-derived areas should be checked against the stamped plan schedule.
250–300 sq.yd (209–251 sq.m): 4
300–400 sq.yd (251–334 sq.m): 25
400–500 sq.yd (334–418 sq.m): 2
The software-measured range is 250.26 sq.m to 334.65 sq.m; the median is 251.48 sq.m. These are measurements read from the layout drawing, not RERA-filed saleable-area or carpet-area disclosures. No booked/available plot counts or plot-wise allotment details are supplied.
Parking & vehicle circulation
The layout’s land-use schedule records 0.00 sq.m as common parking area. The GHMC plan conditions require parking places in buildings to provide electric-vehicle charging infrastructure, but the supplied records do not identify building parking spaces, visitor or accessible parking, individual plot parking arrangements, or EV charging installations. The drawing alone does not establish an exclusive parking entitlement for a buyer.
Internal layout roads are shown with widths from 9.0 M up to 30.0 m, alongside existing 33'-0" and 30'-0" roads. The records do not provide a detailed vehicle-circulation or pedestrian-separation plan beyond the layout drawing.
Amenities, recreation & open spaces
The RERA amenity schedule marks the following items “YES” where indicated and records 0% progress for the listed amenities. Those entries are filed availability declarations, not evidence of completed or independently verified facilities.
| Facility | Green strip / tot-lot / park |
|---|---|
| Description / size | Layout plan: open space 1,448.07 sq.m (8.05%); tot-lot also named in plan conditions and utility list. |
| Declared progress / verified status | RERA schedule: 0%; completion not independently verified. |
| Facility | Aggregate recreational open space |
|---|---|
| Description / size | Marked “YES”; no separate size beyond the layout open-space figure. |
| Declared progress / verified status | RERA schedule: 0%; completion not independently verified. |
| Facility | Community buildings / social infrastructure |
|---|---|
| Description / size | Social infrastructure area 484.18 sq.m (2.69%) on the layout plan. |
| Declared progress / verified status | RERA schedule: 0%; delivery not independently verified. |
| Facility | Internal roads and footpaths |
|---|---|
| Description / size | Road area 7,802.30 sq.m (43.38%) on the layout plan. |
| Declared progress / verified status | RERA schedule: 0%; completion not independently verified. |
No clubhouse or indoor recreation facilities are specifically identified in the supplied records.
Utilities, building services & safety
The RERA amenity schedule marks water supply, sewerage, storm-water drains, sewage/sullage treatment and disposal, rainwater harvesting, energy management, street lighting, and an electrical meter room/sub-station/receiving station as available; each listed item is recorded at 0% progress. This is a filed schedule, not confirmation that these services are installed or operating.
The GHMC layout-plan conditions require underground drainage, street lighting and avenue plantation before release of the final layout; identify a transformer space, rainwater-harvesting structure, garbage house and fenced tot-lot; and call for fire NOC before an occupancy certificate. The plan’s utilities list also names an STP and U.G. sump. No water-source or storage capacity, STP capacity, electrical load, backup-power capacity, fire-system specification, security system, or accessibility design is provided.
Location, access & connectivity
The project’s filed location is Cherlapally, Kapra Mandal, Medchal-Malkajgiri District, PIN 501301; the RERA certificate also identifies Kapra. The parcel-centroid coordinates supplied are 17.498701551094552, 78.57572146632462.
The nearest sampled Outer Ring Road interchange is listed at approximately 4.9 km. The supplied records do not identify a specific approach-road route, public-transport service, or additional measured landmark distances.
Developer & development status
The registered legal promoter is POOJA CRAFTED HOMES PRIVATE LIMITED, a company. Its listed office address is CRUX Building, Sai Aishwarya Layout, Cherlapally, Cherlapally, Kapra, Medchal-Malkajgiri, 501301; the promoter website supplied is poojacraftedhomes.in.
The GHMC plan names the applicant as Pooja Crafted Homes Pvt. Ltd., formerly known as Pooja Ventures Pvt Ltd. The supplied corporate record says the company changed its name from Pooja Ventures Private Limited to Pooja Crafted Homes Private Limited; this identifies the legal entity, not a separate project brand.
The project header gives 14/01/2029 as the proposed completion date. The records supplied do not establish physical progress through an independent site review, bookings, or completion/occupancy certification.
Approvals, official records & documents
| Details | Lake East - Parcel 2; P02200010128; valid 15/09/2025–14/09/2028. |
|---|
| Details | 1063/GHMC/SWDL/LBN1/2025, dated 15/09/2025; file/application no. 001933/GHMC/01103/SWDL/LBN1/2025; layout drawing covers the project’s seven listed survey portions. |
|---|
| Details | Mortgage Deed No. 10859/2025, dated 01/08/2025, for a stated 1,257.69 sq.m proposed mortgage area in favour of GHMC. |
|---|
| Details | Affidavit dated 17-09-2025 by the promoter’s authorized signatory, containing declarations concerning title, encumbrances, completion and project funds; extracted completion wording is truncated. |
|---|
| Details | No certificate supplied. The GHMC plan states that completion notice and occupancy certification are required after completion and that occupancy certification is required before occupation. |
|---|
The layout plan also sets out requirements concerning roads, open spaces and social infrastructure, drainage, street lighting and avenue plantation. This overview lists the filed records and selected layout features; it is not a complete review of approval conditions.
Frequently asked questions
Is Lake East - Parcel 2 registered with Telangana RERA?
Yes. Lake East - Parcel 2 is registered with the Telangana Real Estate Regulatory Authority as P02200010128; the registration status is New Project.
Who is the developer of Lake East - Parcel 2?
The promoter named in the RERA registration is POOJA CRAFTED HOMES PRIVATE LIMITED.
Where is Lake East - Parcel 2 located?
Lake East - Parcel 2 is in Cherlapally, Kapra, Medchal-Malkajgiri, Telangana (501301).
When will Lake East - Parcel 2 be completed?
The promoter's proposed date of completion filed with RERA is 14/01/2029. This is the promoter's declaration, not a guarantee.
More projects in Kapra