Sunrise
ADITYA CONSTRUCTIONS · Medchal-Malkajgiri · RERA P02200002163
SUNRISE is a residential apartment project in Venkata ramana Colony Phase II, Uppal mandal, Medchal-Malkajgiri district, developed by the registered promoter ADITYA CONSTRUCTIONS. It is on 831.88 Sq.yds or 695.45 Sq.Meters and comprises one building with 1 Stilt + 5 upper floors and 15 apartments: five 2BHK and ten 3BHK. Its TG-RERA registration number is P02200002163, and the promoter’s completion undertaking is 13M March 2026.
More from Aditya Constructions · 5 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
7 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Project record |
|---|---|
| Registered project name | SUNRISE RERA record |
| Project type | Residential apartment project RERA record |
| Phase / registered portion | Phase not separately stated; registration identifies the project as SUNRISE |
| TG-RERA registration | P02200002163 |
| Registration validity | 16/09/2020 to 13/03/2026; the certificate says five years, subject to extension under the Act and rules. This is registration validity, not the project’s completion date. |
| Registered promoter | ADITYA CONSTRUCTIONS, a partnership firm Corporate record |
| RERA status in supplied record | Registration certificate issued; no extension is recorded in the supplied certificate. |
Land and geographic identity
| Field | Project record |
|---|---|
| Locality | Venkata ramana Colony Phase II; the building permit describes the site as Venkata Ramana Colony, Mallapur. RERA record |
| Revenue village | Mallapur RERA record |
| Mandal / district / PIN | Uppal / Medchal-Malkajgiri / 500076 RERA record |
| Project survey number(s) and subdivision(s) | Survey No. 111; no subdivision is specified in the registration identity. The permit identifies Plot No. 9 PART. RERA record |
| Registered site extent | 831.88 Sq.yds or 695.45 Sq.Meters |
| Land area figures | RERA land details state total and net area of 695.45 sq.m. The GHMC permit states site area 695.45 m² and net area 690.76 m². Land records |
| Boundaries filed with RERA | East: 9 M ROAD; West: PLOT NO 9 PART; North: 9 M ROAD; South: PLOT NO 8. Land records |
Development identity
| Field | Project record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC) |
| Principal building approval | Building Permit Order; approval no. 2/C1/03745/2020, file no. 2/C1/03100/2020, dated 13 March, 2020 |
| Sanctioned building | Building - A-1 (RESIDENTIAL BUILDING) |
| Sanctioned floor configuration | 1 Stilt + 5 upper floors; stated height 15.00 m |
| Approved-area figures in permit | Residential upper-floor area: 1,696.50 m²; stilt parking area: 339.13 m² |
| Buildings / blocks | One sanctioned building is identified; one block and one tower are recorded in the RERA unit summary. RERA unit table |
| Unit counts | 15 units in the RERA unit record; the permit says sanctioned unit count must not be increased without prior GHMC approval, but the extracted permit does not state that count. RERA unit table |
| Parking levels | Stilt parking is shown in the permit; a specific sanctioned parking-space count is not available in the supplied extraction. |
Offering and status
| Configuration | RERA-filed units | Booked / available* | RERA-filed saleable area |
|---|---|---|---|
| 2BHK | 5 | 0 / 5 | 108.88 m² |
| 3BHK | 10 | 0 / 10 | 138.65 m² |
\*The portal record has no as-of date; counts are indicative. RERA unit table RERA unit details
| Field | Project record |
|---|---|
| Promoter’s completion undertaking | 13M March 2026 as transcribed in the Form B declaration. |
| Occupancy certificate | GHMC OC no. 001086/GHMC/0639/LBN, recorded as 1/2021-OC, dated 23/08/2021. |
| Completion evidence | Architect’s Form–1A, dated 30.08.2021, certifies completion in all aspects; a separate promoter declaration dated 20.03.2022 states the project was 100% done. These are respectively an architect’s certificate and a promoter declaration, not an independent site inspection. |
2. The project story
- SUNRISE is a residential apartment development registered with TG-RERA on land identified as Plot No. 9 PART in Survey No. 111, Mallapur, Uppal mandal, Medchal-Malkajgiri district. The GHMC permit describes one residential building, A-1, with one stilt and five upper floors.
- The RERA unit record lists 15 apartments: five 2BHK and ten 3BHK. The portal’s current-status fields show all 15 as available and none booked, but the record does not specify when those counts were captured. RERA unit table RERA unit details
- The project has an architect’s completion certificate and a GHMC occupancy certificate dated 23 August 2021; the promoter also declared it 100% complete in March 2022. These records indicate a completed, occupancy-certified project in the supplied documents, rather than an under-construction offering.
3. Master plan, architecture & building design
- The GHMC building permit sanctions a single residential building, A-1, with 1 Stilt + 5 upper floors and a stated height of 15.00 m. The permit records a site area of 695.45 m², a net area of 690.76 m², a residential upper-floor area of 1,696.50 m², and a stilt parking area of 339.13 m². These are permit figures; the supplied record does not separately identify FSI-counted area, gross built-up area, or a floor-by-floor area schedule.
- The extracted permit lists 30 Trees, 5 rain-water-harvesting structures, a tot-lot, transformer space, a garbage house and an ETP. A separate layout-plan file is present in the RERA filing, but its drawing content is not extracted here; details such as building footprint, apartment distribution per floor, circulation, lifts, stairs, and landscaped-area dimensions therefore cannot be confirmed from the supplied material. Document index
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available* | RERA saleable area | Measured carpet area** | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 5 | 0 | 5 | 108.88 m² | 67.9–77.2 m²; median 72.5 m² | 33% |
| 3BHK | 10 | 0 | 10 | 138.65 m² | 93.2–94.4 m²; median 93.8 m² | 32% |
\Portal figures have no recorded as-of date and are indicative. RERA unit details \*Carpet areas and loading are software measurements from floor-plan drawing geometry, not RERA-filed disclosures; the drawing measurement is marked as needing review. The plan set contains two drawings, one measured and one scan pending. Floor plans
- The measured 2BHK example shows two bedrooms, two toilet/WC spaces, a drawing room, dining/kitchen and a balcony. The measured 3BHK example shows three bedrooms, toilet/WC spaces, a wash area, drawing room, dining/kitchen and a balcony. These room details and dimensions come from software measurement of the supplied drawings, not from the RERA unit schedule. RERA unit details
- RERA saleable area and drawing-measured carpet area are distinct measures. The supplied drawing analysis describes carpet area as excluding the balcony and notes that saleable area also counts the home’s share of common areas. The filing does not provide a separate carpet-area figure. Floor plans RERA unit details
5. Parking & vehicle circulation
- The GHMC-sanctioned configuration includes a 339.13 m² stilt parking area. The supplied record does not establish the number of car or two-wheeler spaces, visitor or accessible parking, parking allocation to individual apartments, or whether any drawn bay is exclusively allocated.
- The permit also records road widths of 18 mt. and notes a 9 M ROAD on the east and north boundaries in the RERA land details. The supplied material does not describe a site ramp, separate vehicle entry and exit, internal driveways, pedestrian separation, mechanical parking, or EV charging. Land records
6. Amenities, recreation & open spaces
| Description / size | Permit requires a fenced tot-lot maintained as greenery before issue of OC; the permit also records 30 Trees. |
|---|---|
| Declared progress / verified status | Sanction condition; no independent verification of present condition supplied. |
| Description / size | 5 rain-water-harvesting structures (percolation pits) recorded in the permit. |
|---|---|
| Declared progress / verified status | Permit figure; RERA amenity record marks water conservation/rain-water harvesting YES, 100%. |
| Description / size | RERA amenity record: YES, 100%. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA-declared status; no independent service test supplied. |
| Description / size | RERA amenity record lists sewerage (chamber, lines, septic tank, STP): YES, 100%. The permit requires an ETP. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA-declared status; no independent verification or treatment capacity supplied. |
| Description / size | RERA amenity record: YES, 100%. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA-declared status; no independent verification supplied. |
| Description / size | RERA amenity record: YES, 100%; permit requires transformer space. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA-declared status; no independent verification supplied. |
| Description / size | RERA amenity record: YES, 0%; permit requires an Occupancy Fire NOC before issue of OC. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA status is recorded as 0%; the supplied materials do not include the Fire NOC or independent verification. |
| Description / size | Internal roads and footpaths, street lighting, community buildings, sewage/sullage treatment and disposal, solid-waste management, energy management, and recreational open space appear in the RERA amenity schedule with 0% recorded. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA schedule entries; the supplied material does not establish that these facilities were provided or independently verified. |
7. Utilities, building services & safety
- The RERA amenity schedule marks water supply, sewerage, storm-water drains, rain-water harvesting/water conservation, and electrical meter room/substation/receiving station as YES and 100%. The GHMC permit also requires five rain-water-harvesting structures, transformer space, a garbage house and an ETP. These are filed or permit-recorded provisions; no capacities, operating records, or independent service tests are supplied. RERA amenities
- The permit makes an Occupancy Fire NOC a condition before issue of the occupancy certificate. The RERA amenity schedule lists fire protection and safety as YES but records 0%. The supplied documents do not include the Fire NOC, fire-system specifications, escape-stair details, lift counts or capacities, backup power details, CCTV, access-control or accessibility provisions. RERA amenities
8. Location, access & connectivity
- The registered location is Venkata ramana Colony Phase II, Mallapur, Uppal mandal, Medchal-Malkajgiri district, PIN 500076. The RERA filing gives the site boundaries as 9 M ROAD to the east and north, Plot No. 9 PART to the west, and Plot No. 8 to the south. RERA record Land records
- The supplied location record gives the nearest sampled Outer Ring Road interchange as approximately 48.2 km away. No other measured access distances, public-transport details, travel times or nearby-landmark distances are available in the supplied project record. Location record
9. Developer & development status
- The registered promoter is ADITYA CONSTRUCTIONS, recorded as a partnership firm. The RERA filing identifies YALA RAMCHANDER as authorized signatory and lists YALA RAMCHANDER, THOTA MUTHYALU, HANUMANLA NARESH and YALA NARESH as partners. Corporate record RERA record
- The registration certificate gives the promoter office as Village: Nacharam, Mandal: Uppal, District: Medchal-Malkajgiri, PIN: 500076. A Registrar of Firms acknowledgement in the filing records ADITYA CONSTRUCTIONS as firm no. 26724. The supplied record does not provide a verified official website or contact details.
- The architect’s Form–1A dated 30.08.2021 certifies completion in all aspects and records the GHMC occupancy certificate dated 23/08/2021. The promoter’s Form B declaration dated 20.03.2022 says the project was 100% done and states that all flats had been sold and mortgage flats released. Those statements are attributed to their respective filers; no independent site-progress inspection is supplied.
10. Approvals, official records & documents
| Identifier / date | P02200002163; issued 16/09/2020; valid to 13/03/2026 as stated on the certificate |
|---|---|
| What the supplied record establishes | Registration of SUNRISE; certificate conditions include the separate-account requirement. |
| Identifier / date | Approval no. 2/C1/03745/2020; file no. 2/C1/03100/2020; 13 March, 2020 |
|---|---|
| What the supplied record establishes | Sanction for Building A-1, 1 Stilt + 5 upper floors, subject to printed conditions. |
| Identifier / date | 001086/GHMC/0639/LBN; certificate also records 1/2021-OC; 23/08/2021 |
|---|---|
| What the supplied record establishes | Occupancy certificate recorded in the architect’s completion certificate. |
| Identifier / date | 30.08.2021 |
|---|---|
| What the supplied record establishes | Architect’s certification of completion in all aspects for SUNRISE. |
| Identifier / date | Signed by Y. Ramchander; completion undertaking transcribed as 13M March 2026 |
|---|---|
| What the supplied record establishes | Promoter’s declaration concerning title basis, encumbrances, project funds and completion undertaking. |
| Identifier / date | 1/C1/07859/2019/1080 |
|---|---|
| What the supplied record establishes | Reference stated in the GHMC permit; the supplied layout drawing content is not extracted. |
| Identifier / date | Firm no. 26724 |
|---|---|
| What the supplied record establishes | Registrar of Firms acknowledgement filed for ADITYA CONSTRUCTIONS. |
The supplied record does not provide an extracted detailed layout plan or a separate commencement-notice record. Permit conditions include requirements for commencement and completion notices, an Occupancy Fire NOC, rain-water harvesting, transformer space, garbage house and ETP; this overview does not establish separate compliance evidence for each condition.
1. Project at a glance
Project identity
Registered project name: SUNRISE
Project type: Residential apartment project
Phase / registered portion: Phase not separately stated; registration identifies the project as SUNRISE
TG-RERA registration: P02200002163
Registration validity: 16/09/2020 to 13/03/2026; the certificate says five years, subject to extension under the Act and rules. This is registration validity, not the project’s completion date.
Registered promoter: ADITYA CONSTRUCTIONS, a partnership firm
RERA status in supplied record: Registration certificate issued; no extension is recorded in the supplied certificate.
Land and geographic identity
Locality: Venkata ramana Colony Phase II; the building permit describes the site as Venkata Ramana Colony, Mallapur.
Revenue village: Mallapur
Mandal / district / PIN: Uppal / Medchal-Malkajgiri / 500076
Project survey number(s) and subdivision(s): Survey No. 111; no subdivision is specified in the registration identity. The permit identifies Plot No. 9 PART.
Registered site extent: 831.88 Sq.yds or 695.45 Sq.Meters
Land area figures: RERA land details state total and net area of 695.45 sq.m. The GHMC permit states site area 695.45 m² and net area 690.76 m².
Boundaries filed with RERA: East: 9 M ROAD; West: PLOT NO 9 PART; North: 9 M ROAD; South: PLOT NO 8.
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC)
Principal building approval: Building Permit Order; approval no. 2/C1/03745/2020, file no. 2/C1/03100/2020, dated 13 March, 2020
Sanctioned building: Building - A-1 (RESIDENTIAL BUILDING)
Sanctioned floor configuration: 1 Stilt + 5 upper floors; stated height 15.00 m
Approved-area figures in permit: Residential upper-floor area: 1,696.50 m²; stilt parking area: 339.13 m²
Buildings / blocks: One sanctioned building is identified; one block and one tower are recorded in the RERA unit summary.
Unit counts: 15 units in the RERA unit record; the permit says sanctioned unit count must not be increased without prior GHMC approval, but the extracted permit does not state that count.
Parking levels: Stilt parking is shown in the permit; a specific sanctioned parking-space count is not available in the supplied extraction.
Offering and status
| Configuration | RERA-filed units | Booked / available* | RERA-filed saleable area |
|---|---|---|---|
| 2BHK | 5 | 0 / 5 | 108.88 m² |
| 3BHK | 10 | 0 / 10 | 138.65 m² |
\*The portal record has no as-of date; counts are indicative.
Promoter’s completion undertaking: 13M March 2026 as transcribed in the Form B declaration.
Occupancy certificate: GHMC OC no. 001086/GHMC/0639/LBN, recorded as 1/2021-OC, dated 23/08/2021.
Completion evidence: Architect’s Form–1A, dated 30.08.2021, certifies completion in all aspects; a separate promoter declaration dated 20.03.2022 states the project was 100% done. These are respectively an architect’s certificate and a promoter declaration, not an independent site inspection.
2. The project story
- SUNRISE is a residential apartment development registered with TG-RERA on land identified as Plot No. 9 PART in Survey No. 111, Mallapur, Uppal mandal, Medchal-Malkajgiri district. The GHMC permit describes one residential building, A-1, with one stilt and five upper floors.
- The RERA unit record lists 15 apartments: five 2BHK and ten 3BHK. The portal’s current-status fields show all 15 as available and none booked, but the record does not specify when those counts were captured.
- The project has an architect’s completion certificate and a GHMC occupancy certificate dated 23 August 2021; the promoter also declared it 100% complete in March 2022. These records indicate a completed, occupancy-certified project in the supplied documents, rather than an under-construction offering.
3. Master plan, architecture & building design
- The GHMC building permit sanctions a single residential building, A-1, with 1 Stilt + 5 upper floors and a stated height of 15.00 m. The permit records a site area of 695.45 m², a net area of 690.76 m², a residential upper-floor area of 1,696.50 m², and a stilt parking area of 339.13 m². These are permit figures; the supplied record does not separately identify FSI-counted area, gross built-up area, or a floor-by-floor area schedule.
- The extracted permit lists 30 Trees, 5 rain-water-harvesting structures, a tot-lot, transformer space, a garbage house and an ETP. A separate layout-plan file is present in the RERA filing, but its drawing content is not extracted here; details such as building footprint, apartment distribution per floor, circulation, lifts, stairs, and landscaped-area dimensions therefore cannot be confirmed from the supplied material.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available* | RERA saleable area | Measured carpet area** | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 5 | 0 | 5 | 108.88 m² | 67.9–77.2 m²; median 72.5 m² | 33% |
| 3BHK | 10 | 0 | 10 | 138.65 m² | 93.2–94.4 m²; median 93.8 m² | 32% |
\Portal figures have no recorded as-of date and are indicative. \*Carpet areas and loading are software measurements from floor-plan drawing geometry, not RERA-filed disclosures; the drawing measurement is marked as needing review. The plan set contains two drawings, one measured and one scan pending.
- The measured 2BHK example shows two bedrooms, two toilet/WC spaces, a drawing room, dining/kitchen and a balcony. The measured 3BHK example shows three bedrooms, toilet/WC spaces, a wash area, drawing room, dining/kitchen and a balcony. These room details and dimensions come from software measurement of the supplied drawings, not from the RERA unit schedule.
- RERA saleable area and drawing-measured carpet area are distinct measures. The supplied drawing analysis describes carpet area as excluding the balcony and notes that saleable area also counts the home’s share of common areas. The filing does not provide a separate carpet-area figure.
5. Parking & vehicle circulation
- The GHMC-sanctioned configuration includes a 339.13 m² stilt parking area. The supplied record does not establish the number of car or two-wheeler spaces, visitor or accessible parking, parking allocation to individual apartments, or whether any drawn bay is exclusively allocated.
- The permit also records road widths of 18 mt. and notes a 9 M ROAD on the east and north boundaries in the RERA land details. The supplied material does not describe a site ramp, separate vehicle entry and exit, internal driveways, pedestrian separation, mechanical parking, or EV charging.
6. Amenities, recreation & open spaces
| Description / size | Permit requires a fenced tot-lot maintained as greenery before issue of OC; the permit also records 30 Trees. |
|---|---|
| Declared progress / verified status | Sanction condition; no independent verification of present condition supplied. |
| Description / size | 5 rain-water-harvesting structures (percolation pits) recorded in the permit. |
|---|---|
| Declared progress / verified status | Permit figure; RERA amenity record marks water conservation/rain-water harvesting YES, 100%. |
| Description / size | RERA amenity record: YES, 100%. |
|---|---|
| Declared progress / verified status | RERA-declared status; no independent service test supplied. |
| Description / size | RERA amenity record lists sewerage (chamber, lines, septic tank, STP): YES, 100%. The permit requires an ETP. |
|---|---|
| Declared progress / verified status | RERA-declared status; no independent verification or treatment capacity supplied. |
| Description / size | RERA amenity record: YES, 100%. |
|---|---|
| Declared progress / verified status | RERA-declared status; no independent verification supplied. |
| Description / size | RERA amenity record: YES, 100%; permit requires transformer space. |
|---|---|
| Declared progress / verified status | RERA-declared status; no independent verification supplied. |
| Description / size | RERA amenity record: YES, 0%; permit requires an Occupancy Fire NOC before issue of OC. |
|---|---|
| Declared progress / verified status | RERA status is recorded as 0%; the supplied materials do not include the Fire NOC or independent verification. |
| Description / size | Internal roads and footpaths, street lighting, community buildings, sewage/sullage treatment and disposal, solid-waste management, energy management, and recreational open space appear in the RERA amenity schedule with 0% recorded. |
|---|---|
| Declared progress / verified status | RERA schedule entries; the supplied material does not establish that these facilities were provided or independently verified. |
7. Utilities, building services & safety
- The RERA amenity schedule marks water supply, sewerage, storm-water drains, rain-water harvesting/water conservation, and electrical meter room/substation/receiving station as YES and 100%. The GHMC permit also requires five rain-water-harvesting structures, transformer space, a garbage house and an ETP. These are filed or permit-recorded provisions; no capacities, operating records, or independent service tests are supplied.
- The permit makes an Occupancy Fire NOC a condition before issue of the occupancy certificate. The RERA amenity schedule lists fire protection and safety as YES but records 0%. The supplied documents do not include the Fire NOC, fire-system specifications, escape-stair details, lift counts or capacities, backup power details, CCTV, access-control or accessibility provisions.
8. Location, access & connectivity
- The registered location is Venkata ramana Colony Phase II, Mallapur, Uppal mandal, Medchal-Malkajgiri district, PIN 500076. The RERA filing gives the site boundaries as 9 M ROAD to the east and north, Plot No. 9 PART to the west, and Plot No. 8 to the south.
- The supplied location record gives the nearest sampled Outer Ring Road interchange as approximately 48.2 km away. No other measured access distances, public-transport details, travel times or nearby-landmark distances are available in the supplied project record.
9. Developer & development status
- The registered promoter is ADITYA CONSTRUCTIONS, recorded as a partnership firm. The RERA filing identifies YALA RAMCHANDER as authorized signatory and lists YALA RAMCHANDER, THOTA MUTHYALU, HANUMANLA NARESH and YALA NARESH as partners.
- The registration certificate gives the promoter office as Village: Nacharam, Mandal: Uppal, District: Medchal-Malkajgiri, PIN: 500076. A Registrar of Firms acknowledgement in the filing records ADITYA CONSTRUCTIONS as firm no. 26724. The supplied record does not provide a verified official website or contact details.
- The architect’s Form–1A dated 30.08.2021 certifies completion in all aspects and records the GHMC occupancy certificate dated 23/08/2021. The promoter’s Form B declaration dated 20.03.2022 says the project was 100% done and states that all flats had been sold and mortgage flats released. Those statements are attributed to their respective filers; no independent site-progress inspection is supplied.
10. Approvals, official records & documents
| Identifier / date | P02200002163; issued 16/09/2020; valid to 13/03/2026 as stated on the certificate |
|---|---|
| What the supplied record establishes | Registration of SUNRISE; certificate conditions include the separate-account requirement. |
| Identifier / date | Approval no. 2/C1/03745/2020; file no. 2/C1/03100/2020; 13 March, 2020 |
|---|---|
| What the supplied record establishes | Sanction for Building A-1, 1 Stilt + 5 upper floors, subject to printed conditions. |
| Identifier / date | 001086/GHMC/0639/LBN; certificate also records 1/2021-OC; 23/08/2021 |
|---|---|
| What the supplied record establishes | Occupancy certificate recorded in the architect’s completion certificate. |
| Identifier / date | 30.08.2021 |
|---|---|
| What the supplied record establishes | Architect’s certification of completion in all aspects for SUNRISE. |
| Identifier / date | Signed by Y. Ramchander; completion undertaking transcribed as 13M March 2026 |
|---|---|
| What the supplied record establishes | Promoter’s declaration concerning title basis, encumbrances, project funds and completion undertaking. |
| Identifier / date | 1/C1/07859/2019/1080 |
|---|---|
| What the supplied record establishes | Reference stated in the GHMC permit; the supplied layout drawing content is not extracted. |
| Identifier / date | Firm no. 26724 |
|---|---|
| What the supplied record establishes | Registrar of Firms acknowledgement filed for ADITYA CONSTRUCTIONS. |
The supplied record does not provide an extracted detailed layout plan or a separate commencement-notice record. Permit conditions include requirements for commencement and completion notices, an Occupancy Fire NOC, rain-water harvesting, transformer space, garbage house and ETP; this overview does not establish separate compliance evidence for each condition.
Frequently asked questions
Is SUNRISE registered with Telangana RERA?
Yes. SUNRISE is registered with the Telangana Real Estate Regulatory Authority as P02200002163; the registration status is New Project.
Who is the developer of SUNRISE?
The promoter named in the RERA registration is ADITYA CONSTRUCTIONS.
Where is SUNRISE located?
SUNRISE is in Venkata ramana Colony Phase II, Mallapur, Uppal, Medchal-Malkajgiri, Telangana (500076).
When will SUNRISE be completed?
The promoter's proposed date of completion filed with RERA is 13/03/2026. This is the promoter's declaration, not a guarantee.
More projects in Mallapur