Chaitanya Arcade
SRI CHAITANYARAM BUILDERS · Rangareddy · RERA P02400005451
CHAITANYA ARCADE is a residential apartment project in Madeenaguda, Serilingampally mandal, Ranga Reddy district, developed by the registered promoter SRI CHAITANYARAM BUILDERS. The project has a site area of 367.84 sq. m and one building with 1 Stilt + 5 upper floors. The RERA filing lists 10 homes: five 2BHK units of 111.48 sq. m each and five 3BHK units of 148.64 sq. m each. Its TG-RERA registration number is P02400005451, issued 07/12/2022, and the proposed completion date is 16 August 2025.
More from Sri Chaitanyaram Builders · 16 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
6 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered project name | CHAITANYA ARCADE RERA record |
| Project type | Residential apartment project RERA record |
| Phase / registered portion | A single building is recorded; no separate phase name is disclosed. RERA record |
| TG-RERA registration | P02400005451, issued 07/12/2022; certificate states validity from 07/12/2022 to 16/08/2025. The supplied record shows no extension. RERA record |
| Registered promoter | SRI CHAITANYARAM BUILDERS, a partnership. RERA record RERA filing |
| RERA status | The project is recorded as “New Project.” Registration validity ended on 16/08/2025; the supplied material does not establish a later extension or current registration status. RERA record |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality / revenue village | Madeenaguda; revenue village: Madeenaguda RERA record Land records |
| Mandal / district / PIN | Serilingampally / Ranga Reddy / 500049 RERA record |
| Project survey numbers | 38, 39, & 42. No project subdivision is identified in the RERA filing. RERA record Land records |
| Registered plot identity | Plot No. 29 |
| Site extent | 367.84 sq. m (also stated as 440 sq. yards in the filed title and development documents). The permit records total plot area and net plot area as 367.84 sq. m, with 0.0 sq. m road-affected and 0.0 sq. m nala-affected area. Land records |
| Boundaries | North: 40 Feet Wide Road; South: Plot No. 46; East: Plot No. 30; West: Plot No. 28. Land records |
| Landowner named in filed documents | Meka Papayamma, also named as Meka Papayamma alias Papamma Meka. |
Development identity
| Item | Project record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC) Approvals record |
| Principal building approval | 2753/GHMC/SLP/2022-BP, approved 16 August 2022; file no. 007646/GHMC/3782/SLP2/2022-BP Approvals record |
| Approved built-up area | 1,055.35 sq. m of residential upper-floor area, as recorded in the permit. RERA filing |
| Building count | One building is recorded. RERA filing |
| Sanctioned configuration | 1 Stilt + 5 upper floors; the permit also records one ground level and five residential upper floors. Building height is recorded as 14.99 m. |
| Parking | The permit records a total parking area of 211.1; it does not provide a parking-space count in the supplied extraction. Stilt and any approved cellar parking are to be used exclusively for parking under the permit conditions. |
| Unit count | 10 units in the RERA filing: five 2BHK and five 3BHK. The permit’s condition requires that sanctioned unit numbers not be increased without GHMC approval; a separate sanctioned unit count is not stated in the extracted permit data. RERA unit table |
Offering and status
| Item | Project record |
|---|---|
| RERA-filed configurations and saleable areas | 2BHK: 5 units, 111.48 sq. m each; 3BHK: 5 units, 148.64 sq. m each. RERA unit table |
| Booked / available | Portal-derived figures show 0 booked and 5 available in each configuration (10 available in total). The record has no as-of date, so these counts are indicative. RERA unit table |
| Construction stage | No independently verified site-progress information is supplied. The RERA amenity record shows 0% progress for its listed items; this does not by itself establish the building’s overall construction stage. RERA amenities |
| Completion deadline | The promoter’s Form B and RERA certificate state 16 August 2025 as the completion/validity end date. |
| Occupancy / completion certificate | Not supplied; the building permit requires an occupancy certificate before occupation. |
2. The project story
CHAITANYA ARCADE is a single-building residential apartment project on Plot No. 29 in Madeenaguda, Serilingampally mandal, Ranga Reddy district. The project land is identified in the RERA record as survey numbers 38, 39 and 42, with a stated site area of 367.84 sq. m. The GHMC building permit describes a residential building of one stilt level and five upper floors. RERA record Land records
The RERA filing lists ten homes: five 2BHK units and five 3BHK units. It records none as booked and all ten as available, but the portal-derived counts are undated and should be treated as indicative. No construction-progress evidence or occupancy/completion certificate is supplied, so the material reviewed does not establish whether the building is under construction, complete, or occupied. The promoter’s filed completion undertaking gives 16 August 2025; that date is separate from the certificate’s registration-validity period. RERA unit table
3. Master plan, architecture & building design
The approved building permit identifies a 367.84 sq. m plot, a net plot area of 367.84 sq. m, and 1,055.35 sq. m of residential upper-floor area. It describes one building, with 1 Stilt + 5 upper floors and a height of 14.99 m. The permit lists setbacks as Front 3, Rear 2, Side I 2 and Side II 2; units for these setback figures are not stated in the supplied extraction.
The RERA filing identifies one building and ten proposed units. The supplied floor-plan record contains two drawings, but both are scans pending measurement; no drawing-based flat layouts, footprints, floor-by-floor unit arrangement, lift or stair details, circulation plan, or common-area measurements are available in the reviewed data. The approved permit also records a “Floor handed over; 2nd Floor” extent of 106.09 as mortgaged/reserved; the supplied extraction does not state the unit for that extent. RERA filing RERA unit details Floor plans
The figures above are distinct record categories: 1,055.35 sq. m is the permit’s residential upper-floor area, while the unit areas below are RERA-filed saleable areas. No carpet-area measurements are available. RERA unit table Floor plans
4. Homes, configurations & floor plans
The RERA filing lists five 2BHK and five 3BHK homes. The supplied drawings have not been measured, so no software-measured carpet areas or room dimensions can be reported. Saleable area is the RERA-filed unit figure; it is not a carpet-area measurement. RERA unit table RERA unit details Floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 5 | 0 | 5 | 111.48 sq. m | Not available; drawings pending measurement | Not supplied |
| 3BHK | 5 | 0 | 5 | 148.64 sq. m | Not available; drawings pending measurement | Not supplied |
Booking and availability counts are indicative because the portal-derived record does not state an as-of date. RERA unit table
5. Parking & vehicle circulation
The GHMC permit records a total parking area of 211.1 and requires approved stilt and cellar parking, where provided, to be used exclusively for vehicle parking. The supplied extraction does not specify the unit for the total parking-area figure, the number or type of spaces, visitor or accessible parking, EV charging, parking allocation to individual homes, or details of ramps and vehicle circulation. A stated parking area does not establish an exclusive parking right for any particular apartment.
6. Amenities, recreation & open spaces
The RERA amenity record lists 14 project-infrastructure categories. The supplied progress field is 0% for each item; where the record marks an item “YES,” that is an availability entry, not independent verification of completion. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Internal roads and footpaths | No size or specification supplied | RERA amenity record RERA amenities | 0%; completion not independently verified |
| Green strip / tot lot / park | Marked “YES” in RERA record; no area supplied | RERA amenity record RERA amenities; GHMC permit | 0%; completion not independently verified |
| Community buildings | No description or size supplied | RERA amenity record RERA amenities | 0%; completion not independently verified |
| Aggregate recreational open space | No area supplied | RERA amenity record RERA amenities | 0%; completion not independently verified |
The building permit separately requires a tot-lot to be fenced and maintained as greenery before issue of the occupancy certificate. It states “Tot Lot NA” in the permit’s amenity/utility extraction; no tot-lot size is provided.
7. Utilities, building services & safety
The RERA amenity record marks water supply, a green strip/tot lot/park, water conservation/rainwater harvesting, and an electrical meter room/substation/receiving station as “YES.” It lists sewerage, storm-water drains, sewage and sullage treatment/disposal, solid-waste management, energy management, and fire protection/safety, but does not provide capacities or completion evidence. The listed progress for these amenity categories is 0%. RERA amenities
The GHMC permit requires a rainwater-harvesting structure, a transformer space, and a garbage house within the premises. It also requires fire-fighting installations and an occupancy Fire NOC before issue of an occupancy certificate. The permit states that public water and electricity connections will be provided only on production of an occupancy certificate. These are permit conditions; the supplied records do not establish that the facilities or clearances have been completed or obtained.
No information is supplied on water source or storage capacity, treatment capacity, sewerage connection or reuse, electrical backup, lift number or capacity, CCTV, access control, accessibility features, or measured fire-escape arrangements. RERA amenities
8. Location, access & connectivity
The registered project location is Madeenaguda village, Serilingampally mandal, Ranga Reddy district, Telangana 500049. The site is identified as Plot No. 29 in survey numbers 38, 39 and 42 and is bounded to the north by a 40 Feet Wide Road. The GHMC permit records an 18 mt. road-width condition, but the supplied material does not identify the road to which it applies. RERA record Land records
The supplied location record gives the Financial District (Nanakramguda) as an anchor at 1.2 km. No public-transport routes, measured road-network distances, or travel times are provided. Location record
9. Developer & development status
The registered promoter is SRI CHAITANYARAM BUILDERS, identified as a partnership, with GSTIN 36ADHFS3993A1ZY. The RERA record gives the promoter’s address as Plot No. 84, Venkataramana Colony, Madeenaguda, Serilingampally, Ranga Reddy, 500049. G. Ramakoti Reddy is listed as authorized signatory. No official website or contact details are supplied. RERA filing Parties record Corporate record
The landowner named in the project documents is Meka Papayamma, also recorded as Meka Papayamma alias Papamma Meka. The filed development agreement-cum-GPA identifies Sri Chaitanyaram Builders as developer and records the project site; it is the project’s development arrangement, not a separate construction-progress record.
The promoter’s Form B states a completion undertaking of 16 August 2025. No independently verified construction progress or occupancy/completion certificate is included in the supplied material.
10. Approvals, official records & documents
| Identifier / date | P02400005451; issued 07/12/2022; stated validity through 16/08/2025 |
|---|---|
| What the supplied record establishes | Registration of CHAITANYA ARCADE by Sri Chaitanyaram Builders; no extension is recorded in the supplied certificate extraction. |
| Identifier / date | 2753/GHMC/SLP/2022-BP; 16 August 2022; file no. 007646/GHMC/3782/SLP2/2022-BP |
|---|---|
| What the supplied record establishes | Sanction for one residential building on a 367.84 sq. m plot, described as 1 Stilt + 5 upper floors. |
| Identifier / date | 5098/MP2/HUDA/1997, dated 08/01/2004 |
|---|---|
| What the supplied record establishes | Number appears in the permit’s other-number fields as “Approved Layout No. / LRS Proceeding No. / Sub division No.”; no separate layout drawing is supplied here. |
| Identifier / date | September 2022 |
|---|---|
| What the supplied record establishes | Promoter declaration identifying the landowner, development agreement-cum-GPA, fund-use undertakings, and completion date. |
| Identifier / date | Development agreement-cum-GPA No. 9566/2022 |
|---|---|
| What the supplied record establishes | Filed title-related and development documents for Plot No. 29 and survey numbers 38, 39 and 42. |
| Identifier / date | Not supplied |
|---|---|
| What the supplied record establishes | No certificate establishing completion or permission for occupation is included in the reviewed materials. |
Other identifiers recorded in the GHMC permit include Contractor’s All Risk Policy No. 551600442210000030 (shown as valid through 03 July 2028), Notarised Affidavit No. 13507/2022, Bk-1, CS No. 14010/2022, and DRC No. 00311/TDR/2020.
1. Project at a glance
Project identity
Registered project name: CHAITANYA ARCADE
Project type: Residential apartment project
Phase / registered portion: A single building is recorded; no separate phase name is disclosed.
TG-RERA registration: P02400005451, issued 07/12/2022; certificate states validity from 07/12/2022 to 16/08/2025. The supplied record shows no extension.
Registered promoter: SRI CHAITANYARAM BUILDERS, a partnership.
RERA status: The project is recorded as “New Project.” Registration validity ended on 16/08/2025; the supplied material does not establish a later extension or current registration status.
Land and geographic identity
Locality / revenue village: Madeenaguda; revenue village: Madeenaguda
Mandal / district / PIN: Serilingampally / Ranga Reddy / 500049
Project survey numbers: 38, 39, & 42. No project subdivision is identified in the RERA filing.
Registered plot identity: Plot No. 29
Site extent: 367.84 sq. m (also stated as 440 sq. yards in the filed title and development documents). The permit records total plot area and net plot area as 367.84 sq. m, with 0.0 sq. m road-affected and 0.0 sq. m nala-affected area.
Boundaries: North: 40 Feet Wide Road; South: Plot No. 46; East: Plot No. 30; West: Plot No. 28.
Landowner named in filed documents: Meka Papayamma, also named as Meka Papayamma alias Papamma Meka.
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC)
Principal building approval: 2753/GHMC/SLP/2022-BP, approved 16 August 2022; file no. 007646/GHMC/3782/SLP2/2022-BP
Approved built-up area: 1,055.35 sq. m of residential upper-floor area, as recorded in the permit.
Building count: One building is recorded.
Sanctioned configuration: 1 Stilt + 5 upper floors; the permit also records one ground level and five residential upper floors. Building height is recorded as 14.99 m.
Parking: The permit records a total parking area of 211.1; it does not provide a parking-space count in the supplied extraction. Stilt and any approved cellar parking are to be used exclusively for parking under the permit conditions.
Unit count: 10 units in the RERA filing: five 2BHK and five 3BHK. The permit’s condition requires that sanctioned unit numbers not be increased without GHMC approval; a separate sanctioned unit count is not stated in the extracted permit data.
Offering and status
RERA-filed configurations and saleable areas: 2BHK: 5 units, 111.48 sq. m each; 3BHK: 5 units, 148.64 sq. m each.
Booked / available: Portal-derived figures show 0 booked and 5 available in each configuration (10 available in total). The record has no as-of date, so these counts are indicative.
Construction stage: No independently verified site-progress information is supplied. The RERA amenity record shows 0% progress for its listed items; this does not by itself establish the building’s overall construction stage.
Completion deadline: The promoter’s Form B and RERA certificate state 16 August 2025 as the completion/validity end date.
Occupancy / completion certificate: Not supplied; the building permit requires an occupancy certificate before occupation.
2. The project story
CHAITANYA ARCADE is a single-building residential apartment project on Plot No. 29 in Madeenaguda, Serilingampally mandal, Ranga Reddy district. The project land is identified in the RERA record as survey numbers 38, 39 and 42, with a stated site area of 367.84 sq. m. The GHMC building permit describes a residential building of one stilt level and five upper floors.
The RERA filing lists ten homes: five 2BHK units and five 3BHK units. It records none as booked and all ten as available, but the portal-derived counts are undated and should be treated as indicative. No construction-progress evidence or occupancy/completion certificate is supplied, so the material reviewed does not establish whether the building is under construction, complete, or occupied. The promoter’s filed completion undertaking gives 16 August 2025; that date is separate from the certificate’s registration-validity period.
3. Master plan, architecture & building design
The approved building permit identifies a 367.84 sq. m plot, a net plot area of 367.84 sq. m, and 1,055.35 sq. m of residential upper-floor area. It describes one building, with 1 Stilt + 5 upper floors and a height of 14.99 m. The permit lists setbacks as Front 3, Rear 2, Side I 2 and Side II 2; units for these setback figures are not stated in the supplied extraction.
The RERA filing identifies one building and ten proposed units. The supplied floor-plan record contains two drawings, but both are scans pending measurement; no drawing-based flat layouts, footprints, floor-by-floor unit arrangement, lift or stair details, circulation plan, or common-area measurements are available in the reviewed data. The approved permit also records a “Floor handed over; 2nd Floor” extent of 106.09 as mortgaged/reserved; the supplied extraction does not state the unit for that extent.
The figures above are distinct record categories: 1,055.35 sq. m is the permit’s residential upper-floor area, while the unit areas below are RERA-filed saleable areas. No carpet-area measurements are available.
4. Homes, configurations & floor plans
The RERA filing lists five 2BHK and five 3BHK homes. The supplied drawings have not been measured, so no software-measured carpet areas or room dimensions can be reported. Saleable area is the RERA-filed unit figure; it is not a carpet-area measurement.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 5 | 0 | 5 | 111.48 sq. m | Not available; drawings pending measurement | Not supplied |
| 3BHK | 5 | 0 | 5 | 148.64 sq. m | Not available; drawings pending measurement | Not supplied |
Booking and availability counts are indicative because the portal-derived record does not state an as-of date.
5. Parking & vehicle circulation
The GHMC permit records a total parking area of 211.1 and requires approved stilt and cellar parking, where provided, to be used exclusively for vehicle parking. The supplied extraction does not specify the unit for the total parking-area figure, the number or type of spaces, visitor or accessible parking, EV charging, parking allocation to individual homes, or details of ramps and vehicle circulation. A stated parking area does not establish an exclusive parking right for any particular apartment.
6. Amenities, recreation & open spaces
The RERA amenity record lists 14 project-infrastructure categories. The supplied progress field is 0% for each item; where the record marks an item “YES,” that is an availability entry, not independent verification of completion.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Internal roads and footpaths | No size or specification supplied | RERA amenity record | 0%; completion not independently verified |
| Green strip / tot lot / park | Marked “YES” in RERA record; no area supplied | RERA amenity record; GHMC permit | 0%; completion not independently verified |
| Community buildings | No description or size supplied | RERA amenity record | 0%; completion not independently verified |
| Aggregate recreational open space | No area supplied | RERA amenity record | 0%; completion not independently verified |
The building permit separately requires a tot-lot to be fenced and maintained as greenery before issue of the occupancy certificate. It states “Tot Lot NA” in the permit’s amenity/utility extraction; no tot-lot size is provided.
7. Utilities, building services & safety
The RERA amenity record marks water supply, a green strip/tot lot/park, water conservation/rainwater harvesting, and an electrical meter room/substation/receiving station as “YES.” It lists sewerage, storm-water drains, sewage and sullage treatment/disposal, solid-waste management, energy management, and fire protection/safety, but does not provide capacities or completion evidence. The listed progress for these amenity categories is 0%.
The GHMC permit requires a rainwater-harvesting structure, a transformer space, and a garbage house within the premises. It also requires fire-fighting installations and an occupancy Fire NOC before issue of an occupancy certificate. The permit states that public water and electricity connections will be provided only on production of an occupancy certificate. These are permit conditions; the supplied records do not establish that the facilities or clearances have been completed or obtained.
No information is supplied on water source or storage capacity, treatment capacity, sewerage connection or reuse, electrical backup, lift number or capacity, CCTV, access control, accessibility features, or measured fire-escape arrangements.
8. Location, access & connectivity
The registered project location is Madeenaguda village, Serilingampally mandal, Ranga Reddy district, Telangana 500049. The site is identified as Plot No. 29 in survey numbers 38, 39 and 42 and is bounded to the north by a 40 Feet Wide Road. The GHMC permit records an 18 mt. road-width condition, but the supplied material does not identify the road to which it applies.
The supplied location record gives the Financial District (Nanakramguda) as an anchor at 1.2 km. No public-transport routes, measured road-network distances, or travel times are provided.
9. Developer & development status
The registered promoter is SRI CHAITANYARAM BUILDERS, identified as a partnership, with GSTIN 36ADHFS3993A1ZY. The RERA record gives the promoter’s address as Plot No. 84, Venkataramana Colony, Madeenaguda, Serilingampally, Ranga Reddy, 500049. G. Ramakoti Reddy is listed as authorized signatory. No official website or contact details are supplied.
The landowner named in the project documents is Meka Papayamma, also recorded as Meka Papayamma alias Papamma Meka. The filed development agreement-cum-GPA identifies Sri Chaitanyaram Builders as developer and records the project site; it is the project’s development arrangement, not a separate construction-progress record.
The promoter’s Form B states a completion undertaking of 16 August 2025. No independently verified construction progress or occupancy/completion certificate is included in the supplied material.
10. Approvals, official records & documents
| Identifier / date | P02400005451; issued 07/12/2022; stated validity through 16/08/2025 |
|---|---|
| What the supplied record establishes | Registration of CHAITANYA ARCADE by Sri Chaitanyaram Builders; no extension is recorded in the supplied certificate extraction. |
| Identifier / date | 2753/GHMC/SLP/2022-BP; 16 August 2022; file no. 007646/GHMC/3782/SLP2/2022-BP |
|---|---|
| What the supplied record establishes | Sanction for one residential building on a 367.84 sq. m plot, described as 1 Stilt + 5 upper floors. |
| Identifier / date | 5098/MP2/HUDA/1997, dated 08/01/2004 |
|---|---|
| What the supplied record establishes | Number appears in the permit’s other-number fields as “Approved Layout No. / LRS Proceeding No. / Sub division No.”; no separate layout drawing is supplied here. |
| Identifier / date | September 2022 |
|---|---|
| What the supplied record establishes | Promoter declaration identifying the landowner, development agreement-cum-GPA, fund-use undertakings, and completion date. |
| Identifier / date | Development agreement-cum-GPA No. 9566/2022 |
|---|---|
| What the supplied record establishes | Filed title-related and development documents for Plot No. 29 and survey numbers 38, 39 and 42. |
| Identifier / date | Not supplied |
|---|---|
| What the supplied record establishes | No certificate establishing completion or permission for occupation is included in the reviewed materials. |
Other identifiers recorded in the GHMC permit include Contractor’s All Risk Policy No. 551600442210000030 (shown as valid through 03 July 2028), Notarised Affidavit No. 13507/2022, Bk-1, CS No. 14010/2022, and DRC No. 00311/TDR/2020.
Frequently asked questions
Is CHAITANYA ARCADE registered with Telangana RERA?
Yes. CHAITANYA ARCADE is registered with the Telangana Real Estate Regulatory Authority as P02400005451; the registration status is New Project.
Who is the developer of CHAITANYA ARCADE?
The promoter named in the RERA registration is SRI CHAITANYARAM BUILDERS.
Where is CHAITANYA ARCADE located?
CHAITANYA ARCADE is in Madeenaguda, Serilingampally, Rangareddy, Telangana (500049).
When will CHAITANYA ARCADE be completed?
The promoter's proposed date of completion filed with RERA is 16/08/2025. This is the promoter's declaration, not a guarantee.