Sign in

Knr Capitol

ANANYA HOMES · Nizamabad · RERA P03100004735

KNR CAPITOL is a residential apartment project located near Bypass Road, Armoor, Nizamabad district. The registered promoter developing it is Ananya Homes. The project has a recorded land area of 4104.44 sqmts, one building with 1 Stilt + 5 upper floors, and 51 homes: 11 3BHK units and 40 “THRIPLE BEDROOM” units. It is registered with TG-RERA under P03100004735, with proposed completion on 18/06/2027.

01What we found

RegisteredTG-RERA - valid till 18 Jun 2027
16documents on file - each fact links to its page
0court cases on this project's land in the court records searched
5items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

5 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldProject record
Registered project nameKNR CAPITOL RERA record
Project typeResidential apartment project RERA record
Phase / registered portionNo separate phase name is disclosed; the registration and completion certificate describe the registered project as a whole. RERA record
TG-RERA registrationP03100004735 Approvals record
Registration validity19/07/2022–18/06/2027; the registration certificate says “4 years.” Validity is separate from the completion deadline and does not itself establish completion. Approvals record
Registered promoterAnanya Homes; the project filing identifies it as a partnership. RERA record RERA filing
RERA statusThe project is recorded as “New Project”; the registration certificate records registration under section 5. RERA record

Land and geographic identity

FieldProject record
Locality / recorded location“NEAR BYPASS ROAD NIZAMBAD” in the RERA project fields; the building permit specifies “NEAR BYPASS ROAD, NIZAMABAD.” RERA record RERA filing
Revenue villageRERA land fields do not disclose a village. The building permit names GOOPAN PALLY VILL; these are the village words in the supplied records. Land records
Mandal / district / PINARMOOR / Nizamabad / 503003 in the project identity. RERA record RERA filing
Project survey numbers and subdivisions411/B, 411/B2, 411/85, 411/B3, 411/C4/2/1/2, 411/C4/2/2, 411/C4/2/1/1/2 as listed in the building permit.
Registered site extentThe building permit records 4105.44 m2 site area and 4105.44 m2 net area, with road-affected area recorded as 0.00 m2. RERA land fields record 4104.44 sqmts total and net area. RERA filing
Boundaries in RERA filingEast: ROAD; West, North and South: VACANT LAND. RERA filing

Development identity

FieldProject record
Sanctioning authorityNizamabad Urban Development Authority in the building permit.
Principal building permit3146/Nizambad/2021/0604, approved 18 June, 2021. Approvals record
RERA-filed plan approval number3146/NIZAMBAD/2021/0. RERA record RERA filing
Approved built-up areaThe project fields record 11849.22 sqmts as approved built-up area. The building permit separately lists “Area (m2) 9,491.60” and “Upper floors Area (m2) 2,227.69”; these are retained as the permit’s labelled figures, not reclassified here. RERA filing
Building count and arrangementOne approved and one proposed building unit in the RERA filing; the permit calls it Building - A (ANANYA HOMES). RERA filing
Sanctioned floors and height1 Stilt + 5 upper floors; permit height 14.75 m.
Parking / other levelsThe permit says cellar and stilts approved in the plan are to be used exclusively for vehicle parking; a cellar level is not included in the permit’s stated “1 Stilt + 5 upper floors” configuration.
Unit countThe RERA filing records 51 units; the approval document’s extract does not provide a sanctioned unit count. RERA unit table

Offering and status

FieldProject record
RERA-filed unit types and counts3BHK: 11 units; THRIPLE BEDROOM: 40 units. The normalized RERA configuration is 3BHK, 51 units in total. [unit_types] RERA unit table
RERA saleable areaFiled unit rows show 184.23 sqm for 11 3BHK units and 176.75 sqm for 40 “THRIPLE BEDROOM” units. [unit_types]
Booked / availablePortal-derived record shows 0 booked / 51 available, with no as-of date attached; treat counts as indicative. RERA unit table
Construction stageThe RERA amenity/status record reports internal roads and footpaths at 50% and lists other items at 0%; these are reported percentages, not independent site verification. RERA amenities
Completion deadlineThe building permit and Form-B declaration state completion by 18 June, 2027 / 18.06.2027. The project header gives proposed completion 18/06/2027. RERA record
Occupancy certificateForm 1A records OC 0091/0C/3072/2024, dated 11/12/2024, and certifies overall project construction completion. Its stated survey-number scope is listed in section 10 below; the certificate’s broader project scope should be confirmed against the original OC and property schedule.

2. The project story

KNR CAPITOL is recorded with TG-RERA as a residential apartment project promoted by Ananya Homes, with one building unit and 51 units in the filing. The building permit describes Building A as a residential building with 1 Stilt + 5 upper floors, on a site recorded in the permit as 4105.44 m2. RERA record RERA unit table

The RERA unit schedule records 11 units under “3BHK” and 40 under “THRIPLE BEDROOM.” The portal-derived snapshot shows all 51 as available and none booked, but has no recorded as-of date. [unit_types] RERA unit table

The permit requires an occupancy certificate before occupation. Separately, the filed Form 1A, dated 01/10/2025, certifies overall construction completion and records an occupancy certificate dated 11/12/2024. These are documentary records; this review does not independently verify physical completion or the OC’s parcel scope.

3. Master plan, architecture & building design

  • The permit describes one residential building, Building A, with 1 Stilt + 5 upper floors and a stated height of 14.75 m. It records setbacks of Front 10.07 m, Rear 6.09 m, Side I 6.1 m, Side I1 6.09 m, and a road width of 12.00 MT.
  • The permit lists Tot-lot (m2) 436.38, No. of RWHPs 19, space for a transformer and a garbage house. It also requires a strip of greenery on the site periphery and the tot-lot to be fenced and maintained as greenery. These are approval requirements, not confirmation of delivery.
  • The supplied layout-plan record is not extractable, and no drawing-derived building footprint, floor-by-floor flat count, lift or stair arrangement, circulation plan, open-space schedule or phase plan is available here. The permit separately labels Area (m2) 9,491.60, Ground Area (m2) 0.00 and Upper floors Area (m2) 2,227.69; no FSI-counted area or carpet-area total is supplied.

4. Homes, configurations & floor plans

RERA-filed unit counts and saleable areas are shown below. Drawing-based carpet measurements are software-measured from the supplied floor-plan record, not RERA disclosures; the record says those measurements need review. Saleable area is not interchangeable with carpet area: the supplied caveat states saleable area includes the home’s share of common areas. [unit_types] Floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
3BHK / “THRIPLE BEDROOM” (RERA labels)51051176.75–184.23 sqmSoftware-measured: 87.4–145.2 sqm; median 110.7 sqm39% (supplied for the 3BHK drawing measurement)

The RERA unit rows split the 51 units into 11 at 184.23 sqm saleable and 40 at 176.75 sqm saleable. The available drawing extraction describes bedrooms, hall, kitchen, toilets, utility and a 1.50 m-wide balcony for one measured 3BHK design; it does not establish that every unit has identical dimensions or arrangement. Drawing measurements are from document 215414 and should be checked against the drawing itself. [unit_types] RERA unit details Floor plans

5. Parking & vehicle circulation

  • The building permit states that cellar and stilt areas approved for parking must be used exclusively for vehicle parking, without partition walls or rolling shutters. It does not supply a parking-space count, type-wise allocation, accessible or visitor-space count, or unit-specific allocation.
  • The vendor-supplied description lists visitor’s parking and a 16' wide driveway, but these are not identified in the available permit extraction as sanctioned dimensions or allocation details. No supplied document establishes exclusive ownership of a particular parking bay. Promoter website

6. Amenities, recreation & open spaces

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Tot-lot / green area436.38 m2Building permitRequired by permit; delivery not independently verified.
Rainwater harvestingPermit specifies 19 rainwater harvesting pits (RWHPs).Building permitRequired by permit; completion not independently verified.
Internal roads & footpathsSize not suppliedRERA amenity/status record50% reported; not independently verified. RERA amenities
Water supplySize/capacity not suppliedRERA amenity/status recordListed “YES”; 0% reported. RERA amenities
Sewerage, treatment and disposalSystem capacity not suppliedRERA amenity/status recordListed “YES”; 0% reported. RERA amenities
Storm-water drainsSize/capacity not suppliedRERA amenity/status recordListed “YES”; 0% reported. RERA amenities
Street lightingQuantity/specification not suppliedRERA amenity/status recordListed “YES”; 0% reported. RERA amenities
Community buildingsType/size not suppliedRERA amenity/status recordListed “YES”; 0% reported. RERA amenities
Solid-waste management and disposalDetails not suppliedRERA amenity/status recordListed “YES”; 0% reported. RERA amenities
Energy managementDetails not suppliedRERA amenity/status record0% reported; availability not stated. RERA amenities
Fire protection and fire safetySystem details not suppliedRERA amenity/status recordListed “YES”; 0% reported. RERA amenities
Electrical meter room / substation / receiving stationCapacity/details not suppliedRERA amenity/status recordListed “YES”; 0% reported. RERA amenities
Visitor’s parking, reception/waiting lounge, guard room, green stripsSizes not suppliedVendor-supplied descriptionMarketing/vendor listing; no independent completion verification. Promoter website
Walkway and green stripVendor describes 10' wide walkway and 4' wide green stripVendor-supplied descriptionNot independently verified or established by the supplied permit extraction. Promoter website

7. Utilities, building services & safety

  • The permit requires a rainwater-harvesting structure, transformer space, a garbage house and exclusive parking use of the cellar and stilt. The RERA amenity record lists water supply, sewerage and sewage/sullage treatment, storm-water drains, solid-waste management, energy management, fire protection and electrical facilities, but reports 0% for each listed item. These reported percentages do not independently establish whether a facility is installed or operational. RERA amenities
  • The supplied records do not specify water sources or storage capacity, an STP capacity or reuse arrangements, electrical or backup capacity, lift numbers or capacities, fire-system specifications, accessibility provisions, CCTV/security arrangements, or waste-segregation details. The building permit requires an occupancy certificate before occupation; the existence of an OC record is noted above, but does not by itself verify each service or statutory system.

8. Location, access & connectivity

  • The project identity records NEAR BYPASS ROAD NIZAMBAD, Armoor mandal, Nizamabad district, PIN 503003. The building permit describes the site as “NEAR BYPASS ROAD, NIZAMABAD” and names GOOPAN PALLY VILL. RERA record RERA filing
  • The supplied location record gives the Financial District (Nanakramguda) at 1.2 km from the cadastral parcel centroid. No approach-road route, public-transport information or other measured connectivity distances are supplied. Location record

9. Developer & development status

  • The registered promoter is Ananya Homes, recorded as a partnership, with GSTIN 36ABSFA0046M1Z6. The project filing gives its address as NEXT TO MELUHA SCHOOL, RAJENDER NAGAR, GOOPANPALLY VILLAGE, NEAR BYPASS ROAD NIZAMBAD, ARMOOR, Nizamabad, 503003. The supplied registration certificate lists a promoter office at Village: Rajendra nagar, Mandal: Rajendranagar, District: Ranga Reddy, Pin: 500075. Corporate record RERA filing
  • The Form-B declaration, signed for the promoter by managing partner Mr. Katpally Rahul Reddy, declares a completion period of 18.06.2027 and sets out project-fund and audit undertakings. It is a promoter declaration, not independent financial verification.
  • The portal-derived unit record indicates 0 booked and 51 available without an as-of date. The RERA amenity record reports internal roads and footpaths at 50%, while the other listed amenity items are at 0%; these are filed status figures rather than an independent construction inspection. RERA unit table RERA amenities

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP03100004735, issued 19/07/2022, valid to 18/06/2027
Scope and noteForm C certificate for KNR CAPITOL under section 5; it includes a separate-account condition.
Building permit order
Identifier / date3146/Nizambad/2021/0604, approved 18 June, 2021
Scope and noteNizamabad Urban Development Authority; residential Building A, 1 Stilt + 5 upper floors.
RERA-filed plan approval number
Identifier / date3146/NIZAMBAD/2021/0
Scope and noteRecorded in the project fields. RERA record RERA filing
Layout plan record
Identifier / dateDocument 215414
Scope and noteRequired filing record; the supplied item is not extractable, so its layout details cannot be summarized here.
Form-B declaration
Identifier / dateDocument 246140
Scope and notePromoter declaration of title, encumbrance status, completion period and financial undertakings; OCR provides no declaration date or place.
Occupancy certificate recorded in Form 1A
Identifier / date0091/0C/3072/2024, dated 11/12/2024
Scope and noteForm 1A dated 01/10/2025 records an architect’s certification of overall project construction completion. Its listed survey numbers are 411/B, 411/B2, 411/B5, 411/B3, 411/C4/2/1/2, 411/C4/2/2, 411/C4/2/1/1/2.
RERA title and project documents
Identifier / dateDocuments 215425, 215426, 215427, 215789–215792
Scope and noteFiled title-report and land-record material. Document index
Encumbrance statement
Identifier / date87309339, searched 01-10-2007 to 13-06-2022
Scope and noteFiled statement containing two parsed sale-deed entries; the document-number readings are marked unconfirmed in the supplied record. Land records

The building permit requires, among other conditions, compliance with the sanctioned plan, submission of a commencement notice and completion notice, an occupancy certificate before occupation, and separate prior approval for modifications.

Frequently asked questions

Is KNR CAPITOL registered with Telangana RERA?

Yes. KNR CAPITOL is registered with the Telangana Real Estate Regulatory Authority as P03100004735; the registration status is New Project.

Who is the developer of KNR CAPITOL?

The promoter named in the RERA registration is ANANYA HOMES.

Where is KNR CAPITOL located?

KNR CAPITOL is in NEAR BYPASS ROAD NIZAMBAD, ARMOOR, Nizamabad, Telangana (503003).

When will KNR CAPITOL be completed?

The promoter's proposed date of completion filed with RERA is 18/06/2027. This is the promoter's declaration, not a guarantee.

More projects in Armoor