Pbel City Tower P

INDIS APPA TWO PROJECTS PRIVATE LIMITED · Rangareddy · RERA P02400003490

PBEL CITY TOWER P is a residential apartment project in PEERAMCHRUVU, Gandipet mandal, Ranga Reddy district, developed by INDIS APPA TWO PROJECTS PRIVATE LIMITED. The registered site area is 53,057.27 sq m, with one residential block comprising Cellars + Stilt + 30 Upper Floors and 271 homes. The RERA-recorded configurations are 2BHK, 3BHK, 4BHK and 6BHK. It is registered with TG-RERA as P02400003490, with a proposed completion date of 28/04/2026.

📘 Project brochure from the promoter’s website ↗

01What we found

Period endedTG-RERA registration ran to 28 Apr 2026 - check its extension on TG-RERA
26documents on file - each fact links to its page
0court cases on this project's land in the court records searched
9items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

9 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldProject record
Registered project namePBEL CITY TOWER P RERA record
Project typeResidential apartment project RERA record RERA filing
Phase / registered portionTower P; the registration is for the project named PBEL CITY TOWER P.
TG-RERA registrationP02400003490
Registration validity24/09/2021 to 28/04/2026; the certificate records four years and says extension is subject to Authority approval. The supplied certificate records no extension.
Registered promoterINDIS APPA TWO PROJECTS PRIVATE LIMITED, a private limited company RERA record Corporate record
RERA statusThe project is recorded as “New Project”; the registration certificate is the supplied registration evidence. RERA record

Land and geographic identity

FieldProject record
LocalityPEERAMCHRUVU RERA record RERA filing
Revenue villagePeeramchruvu in the RERA identity record; approval and completion documents also refer to Peerancheru / Peerancheru village. RERA record
MandalGandipet RERA record
DistrictRanga Reddy RERA record
PIN500091 RERA record
Survey numbers, as recorded for the project16 TO 18, 19/1, 19/2, 19/3, 21, 22, 23, 25/1, 25/3, 26, 27/1, 27/2, 28, 29, 30, 31, 32, 33/1 33/1, 34, 39, 40, 41, 42 & 43 RERA record RERA filing
Survey numbers on the registration certificate16 TO 18; 19/1; 19/2; 19/3; 21; 22; 23; 25/1; 25/3; 26; 27/1; 27/2; 28; 29; 30; 31; 32; 33/1; 34; 39; 40; 41; 42; 43
Registered site extent53,057.27 sq m; net area and total area are each recorded as 53,057.27 sq m, with road widening/FTL/Nala widening area recorded as 0. RERA filing
BoundariesNorth and east: PBEL City Promoter Land; south and west: Neighbors Land. RERA filing

Development identity

FieldProject record
Principal technical approvalHMDA approval 4339/P4/Plg./H/2009, dated 28-04-2021; the document identifies a P-block proposal and directs the applicant to obtain building-plan sanction from the municipal executive authority. Approvals record
Building permitBandlaguda Jagir Municipal Corporation revised building permit BA.NO: 14/2021-2022, dated 13 / 08 / 2021. Approvals record
Approved built-up area53,057.27 sq m, as stated in the building-permit extraction.
Sanctioned buildingOne residential P block / Building (Block - P), with Cellars + Stilt + 30 Upper Floors in the approval records.
Building height92.45, as recorded in the building-permit sanctioned parameters; the supplied extraction does not state a unit.
UnitsThe RERA project record lists 271 units; the project fields record one building and one proposed building unit. RERA unit table RERA filing
Parking and mortgage areasThe RERA filing records a mortgage area of 5,305.72 sq m. The supplied extracts do not give a count of parking spaces. RERA filing

Offering and status

FieldProject record
RERA-filed configurations2BHK, 3BHK, 4BHK and 6BHK; unit counts and filed saleable areas are detailed below. RERA unit table
Booked / availableThe portal-derived unit record shows 0 booked and 271 available, with no as-of date supplied; treat these counts as indicative, not current availability confirmation. RERA unit table
Completion date in project headerProposed completion date 28/04/2026. RERA record
Promoter’s Form B undertakingThe Form B affidavit dated 20 August 2021 undertakes completion of the phase on or before 30 November 2025.
Completion certificateAn architect’s completion certificate dated 29-12-2025 covers residential Tower P and states that the work is complete and the building is structurally safe and fit for occupation; it says the necessary Occupancy Certificate may be issued. It is not itself an OC.
Occupancy Certificate statusNo issued Occupancy Certificate is included in the supplied record.

2. The project story

PBEL CITY TOWER P is a residential apartment building registered with TG-RERA as P02400003490, for the PBEL City P-block portion in the Peeramchruvu / Peerancheru area of Gandipet mandal, Ranga Reddy district. The RERA land record gives a site extent of 53,057.27 sq m and identifies one building. RERA record RERA filing

The building approvals describe one high-rise residential block with cellars, a stilt level and 30 upper floors. The project’s RERA unit record lists 271 homes across four configurations. RERA unit table

The promoter’s Form B affidavit contains a completion undertaking for the phase by 30 November 2025. Separately, an architect’s completion certificate dated 29 December 2025 states that Tower P is complete and fit for occupation, and that the necessary OC may be issued. That document supports a reported completion status for Tower P; it does not establish that an OC has been issued.

3. Master plan, architecture & building design

The approval record describes a single residential P block. HMDA’s technical approval identifies Cellars + Stilt + 30 Upper Floors on a site of 53,057.27 sq m; the subsequent municipal building-permit record gives an approved built-up area of 53,057.27 sq m and building height of 92.45, without specifying the height unit in the supplied extraction.

The RERA filing records one building and a total approved building-unit count of one, with one proposed building unit as per agreement. It records 53,057.27 sq m as both total and net land area. The available evidence does not provide a drawing-derived building footprint, flats per floor, lift or stair count, detailed entry and exit layout, or measured open-space area. RERA filing Floor plans

HMDA’s approval conditions refer to common parking, internal circulation, protected open space, a sewage treatment plant, septic tank, rainwater harvesting and refuse-chute / garbage disposal provisions. These are conditions and provisions stated in the approval record; they do not establish that each facility is complete or operating.

The project record states approved built-up area; it does not supply separate verified figures for FSI-counted area, gross built-up area or carpet area. Floor-plan material is not yet measured: all 16 drawings are marked as scans pending, with zero measured drawings. Floor plans

4. Homes, configurations & floor plans

The following are RERA-recorded unit counts and saleable areas. The portal-derived booking figures have no supplied as-of date. RERA unit table RERA unit details

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK1100110155.48 sq mNot measured in supplied drawing reviewNot supplied
3BHK1110111209.57 sq mNot measured in supplied drawing reviewNot supplied
4BHK40040246.16 sq mNot measured in supplied drawing reviewNot supplied
6BHK10010567.49 sq mNot measured in supplied drawing reviewNot supplied

The RERA record labels these as 2BHK, 3BHK, 4BHK and 6BHK. The supplied floor-plan review says the 16 drawings remain unmeasured, so no software-measured carpet area, room dimensions or plan-based configuration comparison can be reported. RERA unit table RERA unit details Floor plans

RERA saleable area and carpet area are distinct measures: the supplied review describes saleable area as including the home’s share of common areas. No carpet-area or loading figures are available here to quantify that difference. Floor plans

5. Parking & vehicle circulation

The approval documents describe common parking and a building with cellars and stilt, but the supplied extracts do not state the sanctioned number of car or two-wheeler spaces, visitor or accessible parking provision, or parking allocation to individual homes. The RERA filing records a mortgage area of 5,305.72 sq m; it does not provide a parking-space count. RERA filing

The HMDA technical-approval extraction specifies one entry and one exit, each with a minimum width of 4.5 m and height clearance of 5 m. It also says the approved internal circulation and earmarked parking area are not to be altered. The available material does not establish individual parking ownership or unit-specific allotments.

6. Amenities, recreation & open spaces

The RERA amenity schedule marks the following as available, with percentage figures as recorded in that schedule. These entries are filing disclosures, not independent verification of delivery or operation. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Green Strip / TOT LOT / ParkNo size suppliedRERA amenity schedule“YES”; 100%; independent completion not established
Street LightingNo size suppliedRERA amenity schedule“YES”; 100%; independent completion not established
Community BuildingsNo size suppliedRERA amenity schedule“YES”; 100%; independent completion not established
Treatment and disposal of sewage and sullage waterNo capacity suppliedRERA amenity schedule“YES”; 100%; independent completion not established
Solid Waste Management and DisposalNo capacity suppliedRERA amenity schedule“YES”; 100%; independent completion not established
Water Conservation, Rain water HarvestingNo capacity suppliedRERA amenity schedule; approval conditions also refer to rainwater harvesting“YES”; 100%; independent completion not established
Energy managementNo system details suppliedRERA amenity schedule“YES”; 100%; independent completion not established
Fire Protection and Fire Safety RequirementsNo system details suppliedRERA amenity schedule; approval conditions refer to fire-safety requirements“YES”; 100%; independent completion not established
Electrical Meter Room, Sub-Station, Receiving StationNo capacity suppliedRERA amenity schedule“YES”; 100%; independent completion not established
Aggregate area of recreational Open SpaceArea not suppliedRERA amenity schedule“YES”; 0%
Internal Roads & FootpathsNo measurements suppliedRERA amenity schedule“YES”; 100%; independent completion not established
Water SupplySource and capacity not supplied in this scheduleRERA amenity schedule“YES”; 100%; independent completion not established
Sewerage (Chamber, Lines, Septic Tank, STP)Capacity not suppliedRERA amenity schedule; HMDA technical approval refers to STP and septic tank“YES”; 100%; independent completion not established
Storm Water DrainsNo measurements suppliedRERA amenity schedule“YES”; 100%; independent completion not established

7. Utilities, building services & safety

HMDA’s technical approval requires rainwater-harvesting structures, an STP and septic tank, with recycled water to be used for gardening, and a refuse-chute with proper garbage-disposal systems. The municipal building permit also requires a rainwater-harvesting percolation pit. These are approval-record provisions; the supplied documents do not verify capacities or operational status.

The HMDA approval extraction specifies separate underground static water storage and terrace tanks, each recorded as 25,000 litres. It also refers to transformer provision, fire-safety requirements, structural-safety requirements, and a condition that permanent HMWS & SB and AP Transco connections are not to be provided until an Occupancy Certificate is produced.

The RERA amenity schedule marks water supply, sewerage, sewage treatment and disposal, storm-water drains, solid-waste management, energy management, fire protection and electrical meter/sub-station facilities as “YES.” The schedule does not provide capacities or demonstrate independent completion. RERA amenities

The supplied RERA-filed materials do not establish lift quantities or capacities, backup-power provision, EV charging, security/CCTV arrangements or accessible circulation. Document index RERA amenities

8. Location, access & connectivity

The registered location is PEERAMCHRUVU, Gandipet mandal, Ranga Reddy district, PIN 500091. The approval and completion documents identify the site as Peerancheru / Peerancheru village. The supplied location record gives a cadastral parcel-centroid coordinate of 17.415275719570207, 78.35458902767974. RERA record RERA filing Location record

The location data lists Financial District (Nanakramguda), 1.2 km as an anchor distance. Location record

9. Developer & development status

The registered promoter is INDIS APPA TWO PROJECTS PRIVATE LIMITED, a private limited company with GSTIN 36AAECI4130L1ZL. The project record gives the promoter address as “-, ROAD NO.44, GANDIPET, PEERAMCHRUVU, Gandipet, Ranga Reddy, 500091.” The listed authorized signatory is Soma Jagan Mohan Reddy; the listed directors are Metla Srinivas and Gummadi Anand Reddy. Corporate record Parties record

The promoter’s Form B affidavit, signed by its authorized signatory and dated 20 August 2021, declares the company to be the legal owner of the project land and undertakes to complete the phase by 30 November 2025. It also discloses a memorandum of deposit of title deeds dated 3 July 2018 in favour of Vistra ITCL (India) Limited (formerly IL&FS Trust Company Limited).

An architect’s completion certificate dated 29 December 2025 covers Tower P and reports the work complete and fit for occupation, while stating that the necessary OC may be issued. No issued OC is present in the supplied documents.

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP02400003490; issued 24/09/2021; validity through 28/04/2026
What the supplied record establishesRegistration of PBEL CITY TOWER P and stated registration conditions.
HMDA technical building approval
Identifier / date4339/P4/Plg./H/2009; 28-04-2021
What the supplied record establishesTechnical approval for the P-block high-rise proposal; directs the applicant to seek building-plan sanction from the municipal executive authority.
Municipal building permit
Identifier / dateBA.NO: 14/2021-2022; 13 / 08 / 2021; file G1/1583/2021-22
What the supplied record establishesRevised building permit for Building (Block - P), with Cellars + Stilt + 30 Upper Floors.
Architect’s completion certificate
Identifier / date29-12-2025
What the supplied record establishesCompletion certificate for residential Tower P; states the building is structurally safe and fit for occupation and that the necessary OC may be issued.
Promoter Form B affidavit
Identifier / date20 August 2021
What the supplied record establishesPromoter declarations on land ownership, disclosed encumbrance and phase completion undertaking.
RERA-filed title and encumbrance materials
Identifier / dateTitle report 181675; encumbrance statement 181616; title-report documents 181598 and 181599
What the supplied record establishesProject-filed title and encumbrance materials; their substantive review is addressed in the Land & Title section.
Floor-plan materials
Identifier / date16 drawings; scans pending
What the supplied record establishesNo drawing has been software-measured in the supplied floor-plan review. Floor plans

Frequently asked questions

Is PBEL CITY TOWER P registered with Telangana RERA?

Yes. PBEL CITY TOWER P is registered with the Telangana Real Estate Regulatory Authority as P02400003490; the registration status is New Project.

Who is the developer of PBEL CITY TOWER P?

The promoter named in the RERA registration is INDIS APPA TWO PROJECTS PRIVATE LIMITED.

Where is PBEL CITY TOWER P located?

PBEL CITY TOWER P is in PEERAMCHRUVU, Gandipet, Rangareddy, Telangana (500091).

When will PBEL CITY TOWER P be completed?

The promoter's proposed date of completion filed with RERA is 28/04/2026. This is the promoter's declaration, not a guarantee.