GREEN CITY is a plotted development in Karkalpahad Revenue village, Kadthal Mandal, Ranga Reddy District, developed by registered promoter Naipunya Developers. The draft-layout approval states a land area of Ac. 5.125 Cents; 24805.00 Sq. Yds. and 72 residential plots; plot configurations are not stated. The project is registered with TG-RERA under P02400006143, and the promoter’s declared completion date is 4th August 2024.

01What we found

Period endedTG-RERA registration ran to 4 Aug 2024 - check its extension on TG-RERA
25documents on file - each fact links to its page
2court cases on this project's land (survey 23, Karkalpahad)
9items to check - 5 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

9 items to check before you pay, 5 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Project at a glance

Project identity

FieldRecord
Registered project nameGREEN CITY RERA record
Project typePlotted development; the DTCP document describes a draft technical layout for residential plots. RERA record
Registered phase / portionNot separately identified in the supplied TG-RERA record. The registration and draft-layout document refer to the project over Survey Nos. 19/P and 23/P.
TG-RERA registrationP02400006143, granted under section 5; valid 24/04/2023–04/08/2024. Registration validity is not the same as a completion certificate or occupancy certificate.
Registered promoterNaipunya Developers.
RERA status in supplied recordThe certificate’s validity ended on 04/08/2024; it records no extension. A later registration-status update is not supplied.

Land and geographic identity

FieldRecord
LocalityKarkalpahad; the layout approval also describes the site as Narlakunta Thanda. RERA record
Revenue villageKarkalpahad Revenue village.
Mandal / district / PINKadthal / Ranga Reddy / 509358. RERA record
Project survey numbers19/P, 23/P.
Registered land areaRERA land details state total area 20,740.13 sq. m, affected area 2,076.03 sq. m, and net area 18,664.10 sq. m. Land records
Area stated in draft-layout documentAc. 5.125 Cents; 24805.00 Sq. Yds.
BoundariesEast: 33 FEET WIDEROAD; West: OWNERS LAND; North: OTHERS LAND; South: OTHERS LAND. Land records

Development identity

FieldRecord
Sanctioning authorityDirector of Town and Country Planning; the document states it was delegated to Narlakunta Thanda Gram Panchayat. Approvals record
Principal approvalDraft - TLP.No.264/2022/ H, approved 04-08-2022; file Lr.Roc.No.20064/766/2022/e-Panchayat; application 20064/766. Approvals record
Approval scopeDraft technical layout pattern for residential plots; the filed document states 72 plots. It is identified as a draft layout, not a final layout release.
Approved built-up areaRERA fields state 12,249.83 sq. m; the supplied record does not identify this as plot saleable area or give a drawing-based breakdown. RERA filing
Buildings, floors and parking levelsNot applicable to the plotted layout as described in the supplied approval; no building or parking-level configuration is disclosed.
Plot count72 plots in the draft-layout approval.

Offering and status

FieldRecord
OfferingResidential plots; the draft-layout document states 72 plots. Plot-wise sizes, booked/available counts and RERA-filed saleable-area bands are not supplied.
Construction / development stageRERA amenity entries contain percentage figures, but the supplied data does not establish independently verified site progress. RERA amenities
Completion deadlinePromoter’s Form-B declaration states 4th August 2024 as the intended completion date.
Registration validity24/04/2023–04/08/2024; this is the RERA registration period, not an OC or completion certificate.
OC / completion certificateNot disclosed in the supplied project documents. Document index

The project story

GREEN CITY is registered with TG-RERA as a plotted-development project in Karkalpahad Revenue village, Kadthal Mandal, Ranga Reddy District, over Survey Nos. 19/P and 23/P. Its filed DTCP document describes a draft technical layout for 72 residential plots and lists separate areas for plotted land, roads, open space and mortgaged land. RERA record

The promoter declared a completion deadline of 4th August 2024. The supplied records do not establish the present construction or infrastructure status through independent site verification, nor do they include an occupancy or completion certificate. RERA amenity-progress entries are declarations in the project record, not independent confirmation of delivery. RERA amenities Document index

Master plan, architecture & building design

This is a plotted layout rather than a disclosed apartment or multi-building development. The draft-layout document states an overall layout area of Ac. 5.125 Cents; 24805.00 Sq. Yds., with the following land-use split:

Layout componentArea / share stated in document
Plotted areaAc. 3.027 Cents; 14650.68 Sq. Yds. (59.23 %)
Road areaAc. 1.585 Cents; 7671.40 Sq. Yds (30.77 %)
Open spaceAc. 0.513 Cents; 2482.92 Sq. Yds. (10.00 %)
Mortgage areaAc. 0.465 Cents; 2250.60 Sq. Yds. (15.36 %)

The document identifies Plot Nos. 30 to 32 and 35 to 42 as mortgaged to Karlakunta Thanda Gram Panchayat, and identifies the open-space and road areas for handover to the Gram Panchayat by registered gift deed before final layout release. It describes the plan as a draft and states that permission is not proof of land title.

The RERA fields separately report 12,249.83 sq. m as approved built-up area; the supplied records do not explain how that figure relates to the plotted layout or provide a plan-based plot-by-plot area schedule. No final layout plan, building arrangement, or phase-wise plan is available in the supplied materials. RERA filing

Homes, configurations & floor plans

The project is recorded as plotted development. The draft-layout document gives a total of 72 plots, but plot-wise configurations, plot size bands, booked and available counts, and RERA-filed saleable areas are not supplied.

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
Residential plots72 plots stated in draft-layout approvalNot disclosedNot disclosedNot disclosedNot applicableNot disclosed

The two supplied floor-plan drawings are pending scan review and no plot or home measurements have been software-measured. Floor plans

Parking & vehicle circulation

The supplied project record does not establish a parking-space count, dedicated visitor or accessible parking, parking allocation to individual plots, or a parking arrangement. The draft-layout document identifies road area and requires roads to be opened for access to neighbouring sites, but does not provide a road-width schedule or vehicle-circulation drawing in the available extraction.

Amenities, recreation & open spaces

The draft-layout document identifies public open spaces, rainwater-harvesting pits, street lighting and electricity facilities, sewerage disposal, and protected water supply as layout provisions. These are document-stated provisions; the supplied record does not independently verify completion.

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Public open spaceAc. 0.513 Cents; 2482.92 Sq. Yds. (10.00 %)Draft-layout approvalProvision stated; completion not independently verified
Internal roadsAc. 1.585 Cents; 7671.40 Sq. Yds (30.77 %)Draft-layout approvalProvision stated; completion not independently verified
Rainwater harvesting pitsSize and quantity not statedDraft-layout approvalProvision stated; completion not independently verified
Street lighting and electricity facilitiesDetails and capacities not statedDraft-layout approvalProvision stated; completion not independently verified
Sewerage disposal systemDetails and capacity not statedDraft-layout approvalProvision stated; completion not independently verified
Protected water supply systemSource and capacity not statedDraft-layout approvalProvision stated; completion not independently verified

Other RERA-listed amenity categories include a green strip / TOT LOT / park and water supply. Their RERA entries show percentage values, but these are not independent verification of delivery. RERA amenities

Utilities, building services & safety

The layout-approval document lists a protected water supply system, sewerage disposal system, rainwater-harvesting pits, street lighting and electricity facilities. It does not provide source, capacity, treatment specifications, storage details, or evidence of completion.

The RERA amenity schedule lists water supply, sewerage, storm-water drains, street lighting, water conservation/rainwater harvesting, and electrical meter room/sub-station/receiving station categories; it also lists fire protection and safety requirements. The supplied entries do not establish capacities, installed systems, clearances, or completed works. RERA amenities

Location, access & connectivity

The official project location is Karkalpahad Revenue village, Kadthal Mandal, Ranga Reddy District, Telangana, PIN 509358. The draft-layout document also names Narlakunta Thanda. The RERA-recorded east boundary is a 33 FEET WIDEROAD. RERA record Land records

A supplied location record places the project geocode at 16.9847566, 78.4997445 and lists the nearest sampled Outer Ring Road interchange at 28.3 km. Location record

Developer & development status

The registered promoter is Naipunya Developers, identified in the project record as a partnership. The supplied corporate identifier is GSTIN 36AAUFN5103D1ZC. The record gives a promoter address at 19-907/2, Reddy Colony, Narlakunta Thanda, Karkalpahad, Kadthal, Ranga Reddy, 509358; the TG-RERA certificate separately states the promoter office as Village: Mandal: District: Nalgonda, Pin: 508208. Corporate record Parties record

The promoter’s Form-B declaration states a completion target of 4th August 2024. The supplied evidence does not establish the current project-development stage, an extension of registration, or an occupancy/completion certificate.

Approvals, official records & documents

RecordWhat the supplied document establishes
TG-RERA registration certificate, P02400006143Form C registration of GREEN CITY under section 5, valid 24/04/2023–04/08/2024; the certificate includes a separate-account condition.
Draft layout approval, Draft - TLP.No.264/2022/ HDirector of Town and Country Planning approval dated 04-08-2022 for a draft technical layout pattern for residential plots in Survey Nos. 19/P and 23/P; the document states 72 plots and land-use details.
Form-B affidavit-cum-declarationPromoter declaration concerning title, encumbrances, project completion and other undertakings; it is a promoter declaration, not an independent title determination.
Layout plan document, 300201A requested layout-plan/approval document is listed, but its content was not extracted.
Completion / occupancy certificateNot included in the supplied project documents. Document index

Frequently asked questions

Is GREEN CITY registered with Telangana RERA?

Yes. GREEN CITY is registered with the Telangana Real Estate Regulatory Authority as P02400006143; the registration status is New Project.

Who is the developer of GREEN CITY?

The promoter named in the RERA registration is NAIPUNYA DEVELOPERS.

Where is GREEN CITY located?

GREEN CITY is in karkalpahad, Kadthal, Rangareddy, Telangana (509358).

When will GREEN CITY be completed?

The promoter's proposed date of completion filed with RERA is 04/08/2024. This is the promoter's declaration, not a guarantee.