SITAARA ONE is a plotted development in Malkapur Revenue Village, Kondapur Mandal, Sangareddy District, developed by SITAARA LIFE STYLE HOMES PRIVATE LIMITED. The layout has a net area of 22832.77 sq.m and 29 residential plots; buildings, towers and floors are not stated. TG-RERA registration P01100008394 gives a proposed completion date of 30/11/2026.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
9 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Record |
|---|---|
| Registered project name | SITAARA ONE RERA record |
| Project type | Plotted development / residential layout RERA filing |
| Phase or registered portion | Phase not separately identified; the registration concerns the plotted layout on Survey No. 298/PART |
| TG-RERA registration | P01100008394 RERA record |
| Registration validity | 22 June 2024 to 6 April 2026, unless extended by the Authority RERA record |
| Registered promoter | SITAARA LIFE STYLE HOMES PRIVATE LIMITED RERA record |
| RERA status in the supplied record | Registered project; the certificate gives the above validity period. No extension is included in the supplied evidence. |
Land and geographic identity
| Item | Record |
|---|---|
| Locality / revenue village | Malkapur (G.P. & V.) / MALKAPUR Revenue Village |
| Mandal | KONDAPUR |
| District | Sangareddy |
| PIN | 502306 RERA record |
| Project survey number(s) and subdivision(s) | 298/PART; the layout approval also writes this as Sy. Nos 298/part. No further project subdivision is stated in the registration certificate or layout approval. RERA record |
| Site extent | Approval record: 25135.02 sq.mt; the same record identifies road-affected area of 2302.25 and net area of 22832.77. RERA record |
| Layout area statement | The drawing-based layout record gives 22832.77 sq.m net layout area; its component figures are listed below under “Master plan, architecture & building design.” Layout record |
| Boundaries | East, west, north and south: “NEIGHBOURS LAND” in the RERA land details. RERA filing |
| Cadastral location | Parcel-centroid coordinates: 17.58192, 78.06666. Location record |
Development identity
| Item | Record |
|---|---|
| Sanctioning authority | Sangareddy DTCP Municipality/Municipal Corporation; the approval document identifies the authority as TS-DTCP. |
| Principal layout approval | Tentative Layout Plan No. 0001/LO/3154/2024, approved 06 April 2024. RERA record |
| Application number | 009790/LO/DTCP/3154/0002/2023. Approvals record |
| Other cited reference numbers | LTP licence CA/2009/46164; portal reference TS/075794/2023; receipts TS/25211/2023, TS/25212/2023, and TS/25441/2023. Approvals record |
| Layout plots | 29 plots, as stated in the approval record and layout drawing schedule. Layout record |
| Approved built-up area | 0.00 proposed built-up area, both excluding and including parking, in the tentative-layout sanctioned parameters. The RERA record separately lists approved built-up area of 14857.54 sqmts; the supplied evidence does not explain the basis of that field for this plotted project. RERA filing |
| Buildings / floors / parking levels | Not disclosed for buildings or parking levels; the project is registered as a plotted layout. RERA filing |
Offering and status
| Item | Record |
|---|---|
| Unit type | Residential plots. |
| RERA-filed plot size range / availability | Unit-level RERA inventory counts, booked and available counts, and filed plot-size range are not present in the supplied data. RERA filing |
| Drawing-derived plot sizes | Software-read from the approved layout drawing: 267.39–1105.99 sqm (smallest to largest); plot-count and size readings should be checked against the drawing. Layout record |
| Construction / development stage | The project is labelled “New Project”; the supplied evidence does not provide an independently verified site-progress measurement. RERA record RERA filing |
| Completion timeline | The RERA record states proposed completion 30/11/2026. The tentative-layout approval requires infrastructure and amenities to be completed within two years from approval, stated as 06 April 2026. These are separate recorded timelines. RERA record |
| Completion / occupancy certificate | No completion certificate or occupancy certificate is identified in the supplied documents. The approval is for a tentative layout, not an occupancy certificate. |
2. The project story
SITAARA ONE is registered as a plotted residential development in Malkapur Revenue Village, Kondapur Mandal, Sangareddy District, on Survey No. 298/PART. The tentative layout approval records 29 plots and an arrangement of plots, roads, open space/park, social-infrastructure land and utility land. Layout record
The project’s layout approval is tentative and sets out infrastructure and handover conditions. It calls for roads, storm-water drains, underground drainage, internal water-supply lines and an overhead tank, an assured water-supply source, electrical lines and street lights, a transformer, avenue planting, park development and rainwater-harvesting pits. The approval assigns development responsibility to the applicant and sets a two-year infrastructure-and-amenities period from 6 April 2024. These are approval requirements, not evidence that the works have been completed.
The supplied record contains no measured construction-progress report or verified completion evidence. The stated RERA completion date and the approval’s infrastructure deadline are presented separately in the identity table; neither establishes that the layout works are complete. RERA record
3. Master plan, architecture & building design
This is a plotted layout rather than a multi-storey building project in the supplied approval. The approved-layout drawing schedule states 29 plots and the following land-use allocation against a net layout area of 22832.77 sq.m. These are layout-drawing figures, not building floor-area or apartment measurements. Layout record
| Layout use | Area | Share |
|---|---|---|
| Plots | 14857.54 sq.m | 65.07% |
| Roads | 5108.60 sq.m | 22.37% |
| Parks / organized open space | 2061.76 sq.m | 9.03% |
| Social infrastructure | 574.14 sq.m | 2.51% |
| Utilities | 230.74 sq.m | 1.01% |
| Amenities | 0.00 sq.m | 0.00% |
The drawing lists internal road widths as 12.0M WIDE ROAD, 10.06M WIDE ROAD, 60'-0" WIDE ROAD and 300'-0" WIDE ROAD. The approval text also refers to roads of 18 mts and above. The supplied material does not provide a verified road-by-road layout interpretation.
No building footprint, floor configuration, tower arrangement, building height, apartment circulation or residential/commercial building mix is disclosed for this plotted layout. The sanctioned parameters state proposed built-up area of 0.00, excluding and including parking.
The layout drawing lists mortgage-reserved Plots 16, 9, 8, 17, 18 and 7; its stated proposed mortgage area is 2244.15, while the RERA land details list mortgage area of 2332.72 sqmts. The full approval conditions and the treatment of the mortgage are addressed in Approvals and Risk. RERA filing
4. Homes, configurations & floor plans
The RERA-filed project type is plotted development, and the approval records 29 plots. The supplied data does not include a plot-by-plot RERA inventory schedule with unit counts by size, booked status or availability.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Residential plots | 29 stated in the layout drawing/approval; RERA inventory count not separately supplied | Not disclosed | Not disclosed | Not disclosed | Not applicable | Not supplied |
The layout drawing was software-read as containing 29 plots with sizes: smallest 267.39 sqm (319.8 sq yd), median 440.2 sqm (526.5 sq yd), and largest 1105.99 sqm (1322.8 sq yd). The size readings and plot count should be verified against the drawing. Layout record
| Drawing-derived size band | Plot count |
|---|---|
| 300–400 sq yd (251–334 sqm) | 2 |
| 400–500 sq yd (334–418 sqm) | 10 |
| 500–1000 sq yd (418–836 sqm) | 13 |
| 1000+ sq yd (836+ sqm) | 4 |
For plots, “carpet area” and apartment common-area loading are not applicable in the supplied record. The floor-plan data says the two drawing sheets contain no flats and no apartment measurements. Floor plans
5. Parking & vehicle circulation
The layout approval’s land-use statement records 0.00 common-parking area. The supplied documents do not state a sanctioned count of resident or visitor parking spaces, plot-specific parking allocations, accessible parking, or mechanical, basement, stilt or podium parking.
Vehicle circulation is described through the approved layout’s road network; the approval requires roads to remain open for neighbouring-site access and prohibits a compound wall or fencing around the site. The evidence does not establish individual parking rights or plot-specific parking arrangements.
6. Amenities, recreation & open spaces
The layout approval and drawing record specify layout-level open space and infrastructure. Progress percentages in the supplied RERA amenities schedule are 0 where provided; they do not establish independent physical verification of completion. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Park / organized open space | 2061.76 sq.m, 9.03% of net layout area | Approved-layout drawing Layout record; tentative-layout approval | Required in the layout approval; completion not verified |
| Avenue plantation | Listed as part of the layout development works | Tentative-layout approval | Required work; progress not verified |
| Park development | Listed as part of the layout development works | Tentative-layout approval | Required work; progress not verified |
| Community buildings | RERA amenities schedule includes the category but gives no supplied size or facility detail | RERA amenities | Progress shown as 0; not verified complete |
| Recreation facilities | Mentioned in third-party vendor amenity text; no project-specific size or sanctioned detail supplied | Promoter website | Vendor-listed only; not verified |
No clubhouse, indoor recreation facility, sports facility or facility capacity is established by the supplied project approval evidence. Utility installations are summarized separately below.
7. Utilities, building services & safety
The tentative-layout approval describes proposed layout infrastructure and requires the applicant to provide the listed works. The schedule does not establish their installed condition, capacity or operational status.
| Evidence in the project record | Approval calls for an assured water-supply source, internal water-supply pipelines, a water reservoir and an overhead tank. |
|---|---|
| Status / limitation | Proposed/required; source, storage capacity and completion are not supplied. |
| Evidence in the project record | Approval lists underground drainage lines, a common septic tank / STP, storm-water drains and drainage/channelization of nalas. |
|---|---|
| Status / limitation | Proposed/required; no capacity, commissioning or completion evidence supplied. |
| Evidence in the project record | Water-harvesting pits are listed in the approval. |
|---|---|
| Status / limitation | Proposed/required; completion not verified. |
| Evidence in the project record | Approval lists electrical supply lines, street lights and a transformer. |
|---|---|
| Status / limitation | Proposed/required; capacity and completion not supplied. |
| Evidence in the project record | Listed among the approval’s utility works. |
|---|---|
| Status / limitation | Proposed/required; system detail and completion not supplied. |
| Evidence in the project record | No project-specific fire system, access arrangement or clearance is established in the supplied approval records. |
|---|---|
| Status / limitation | Not disclosed in the supplied evidence. |
| Evidence in the project record | No project-specific security system or accessible-circulation detail is established in the supplied approval records. |
|---|---|
| Status / limitation | Not disclosed in the supplied evidence. |
Third-party vendor text mentions water supply, borewell, power backup, gas pipeline, fire safety and waste management, but the supplied project approval records do not establish these as sanctioned or completed project facilities. Promoter website
8. Location, access & connectivity
The registered location is MALKAPUR, Kondapur Mandal, Sangareddy District, Telangana, PIN 502306, on Survey No. 298/PART. The layout approval identifies the site as Malkapur (G.P. & V.) / Malkapur Revenue Village. RERA record
The layout approval requires roads to remain open to neighbouring sites and lists internal-road widths in the approved drawing. The only supplied measured connectivity reference is the nearest sampled Outer Ring Road interchange, approximately 21.3 km from the parcel-centroid location. Location record
9. Developer & development status
The registered promoter is SITAARA LIFE STYLE HOMES PRIVATE LIMITED, a private limited company. Its supplied corporate identifier is CIN: U70109TG2020PTC145253; GSTIN 36ABECS7531C1ZH. The RERA certificate gives the promoter address as Hyderabad, PIN 500081, while the project record lists an address at Silicon Towers, Image Gardens Road, Malkapur, Sangareddy, Kondapur, PIN 502306. Corporate record Parties record RERA filing
The RERA record labels the project “New Project.” It gives a proposed completion date of 30/11/2026; the tentative-layout approval separately requires infrastructure and amenities within two years from 6 April 2024, stated as 06 April, 2026. No project-specific, independently verified progress measurement or completion/occupancy certificate is supplied. RERA record RERA filing
10. Approvals, official records & documents
| Supplied evidence | Form C certificate, registration P01100008394 |
|---|---|
| What it establishes | Project registration for SITAARA ONE, promoter identity and stated validity period. |
| Supplied evidence | No. 0001/LO/3154/2024, dated 06 April 2024, Sangareddy DTCP Municipality/Municipal Corporation |
|---|---|
| What it establishes | Tentative approval for the 29-plot residential layout on Survey No. 298/part, subject to stated conditions. |
| Supplied evidence | Layout-plan document with reference TS/075794/2023 and licence CA/2009/46164 |
|---|---|
| What it establishes | Plot schedule, roads and layout land-use schedule as recorded in the drawing. |
| Supplied evidence | Application 009790/LO/DTCP/3154/0002/2023; receipts TS/25211/2023, TS/25212/2023, TS/25441/2023 |
|---|---|
| What it establishes | References recorded in the tentative-layout approval. |
| Supplied evidence | Mortgage deed No. 2250/2024, dated 20 March 2024 |
|---|---|
| What it establishes | Approval identifies Plots 16, 9, 8, 17, 18 and 7 as mortgaged to the Municipality/Municipal Corporation for layout-development obligations. |
| Supplied evidence | Form B dated 10 May 2024 |
|---|---|
| What it establishes | Promoter declaration and stated undertaking; it is not a completion certificate. |
The approval identifies the layout as tentative and requires infrastructure completion and subsequent steps before final layout release. No final layout release or completion/occupancy certificate is included in the supplied evidence.
1. Project at a glance
Project identity
Registered project name: SITAARA ONE
Project type: Plotted development / residential layout
Phase or registered portion: Phase not separately identified; the registration concerns the plotted layout on Survey No. 298/PART
TG-RERA registration: P01100008394
Registration validity: 22 June 2024 to 6 April 2026, unless extended by the Authority
Registered promoter: SITAARA LIFE STYLE HOMES PRIVATE LIMITED
RERA status in the supplied record: Registered project; the certificate gives the above validity period. No extension is included in the supplied evidence.
Land and geographic identity
Locality / revenue village: Malkapur (G.P. & V.) / MALKAPUR Revenue Village
Mandal: KONDAPUR
District: Sangareddy
PIN: 502306
Project survey number(s) and subdivision(s): 298/PART; the layout approval also writes this as Sy. Nos 298/part. No further project subdivision is stated in the registration certificate or layout approval.
Site extent: Approval record: 25135.02 sq.mt; the same record identifies road-affected area of 2302.25 and net area of 22832.77.
Layout area statement: The drawing-based layout record gives 22832.77 sq.m net layout area; its component figures are listed below under “Master plan, architecture & building design.”
Boundaries: East, west, north and south: “NEIGHBOURS LAND” in the RERA land details.
Cadastral location: Parcel-centroid coordinates: 17.58192, 78.06666.
Development identity
Sanctioning authority: Sangareddy DTCP Municipality/Municipal Corporation; the approval document identifies the authority as TS-DTCP.
Principal layout approval: Tentative Layout Plan No. 0001/LO/3154/2024, approved 06 April 2024.
Application number: 009790/LO/DTCP/3154/0002/2023.
Other cited reference numbers: LTP licence CA/2009/46164; portal reference TS/075794/2023; receipts TS/25211/2023, TS/25212/2023, and TS/25441/2023.
Layout plots: 29 plots, as stated in the approval record and layout drawing schedule.
Approved built-up area: 0.00 proposed built-up area, both excluding and including parking, in the tentative-layout sanctioned parameters. The RERA record separately lists approved built-up area of 14857.54 sqmts; the supplied evidence does not explain the basis of that field for this plotted project.
Buildings / floors / parking levels: Not disclosed for buildings or parking levels; the project is registered as a plotted layout.
Offering and status
Unit type: Residential plots.
RERA-filed plot size range / availability: Unit-level RERA inventory counts, booked and available counts, and filed plot-size range are not present in the supplied data.
Drawing-derived plot sizes: Software-read from the approved layout drawing: 267.39–1105.99 sqm (smallest to largest); plot-count and size readings should be checked against the drawing.
Construction / development stage: The project is labelled “New Project”; the supplied evidence does not provide an independently verified site-progress measurement.
Completion timeline: The RERA record states proposed completion 30/11/2026. The tentative-layout approval requires infrastructure and amenities to be completed within two years from approval, stated as 06 April 2026. These are separate recorded timelines.
Completion / occupancy certificate: No completion certificate or occupancy certificate is identified in the supplied documents. The approval is for a tentative layout, not an occupancy certificate.
2. The project story
SITAARA ONE is registered as a plotted residential development in Malkapur Revenue Village, Kondapur Mandal, Sangareddy District, on Survey No. 298/PART. The tentative layout approval records 29 plots and an arrangement of plots, roads, open space/park, social-infrastructure land and utility land.
The project’s layout approval is tentative and sets out infrastructure and handover conditions. It calls for roads, storm-water drains, underground drainage, internal water-supply lines and an overhead tank, an assured water-supply source, electrical lines and street lights, a transformer, avenue planting, park development and rainwater-harvesting pits. The approval assigns development responsibility to the applicant and sets a two-year infrastructure-and-amenities period from 6 April 2024. These are approval requirements, not evidence that the works have been completed.
The supplied record contains no measured construction-progress report or verified completion evidence. The stated RERA completion date and the approval’s infrastructure deadline are presented separately in the identity table; neither establishes that the layout works are complete.
3. Master plan, architecture & building design
This is a plotted layout rather than a multi-storey building project in the supplied approval. The approved-layout drawing schedule states 29 plots and the following land-use allocation against a net layout area of 22832.77 sq.m. These are layout-drawing figures, not building floor-area or apartment measurements.
| Layout use | Area | Share |
|---|---|---|
| Plots | 14857.54 sq.m | 65.07% |
| Roads | 5108.60 sq.m | 22.37% |
| Parks / organized open space | 2061.76 sq.m | 9.03% |
| Social infrastructure | 574.14 sq.m | 2.51% |
| Utilities | 230.74 sq.m | 1.01% |
| Amenities | 0.00 sq.m | 0.00% |
The drawing lists internal road widths as 12.0M WIDE ROAD, 10.06M WIDE ROAD, 60'-0" WIDE ROAD and 300'-0" WIDE ROAD. The approval text also refers to roads of 18 mts and above. The supplied material does not provide a verified road-by-road layout interpretation.
No building footprint, floor configuration, tower arrangement, building height, apartment circulation or residential/commercial building mix is disclosed for this plotted layout. The sanctioned parameters state proposed built-up area of 0.00, excluding and including parking.
The layout drawing lists mortgage-reserved Plots 16, 9, 8, 17, 18 and 7; its stated proposed mortgage area is 2244.15, while the RERA land details list mortgage area of 2332.72 sqmts. The full approval conditions and the treatment of the mortgage are addressed in Approvals and Risk.
4. Homes, configurations & floor plans
The RERA-filed project type is plotted development, and the approval records 29 plots. The supplied data does not include a plot-by-plot RERA inventory schedule with unit counts by size, booked status or availability.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Residential plots | 29 stated in the layout drawing/approval; RERA inventory count not separately supplied | Not disclosed | Not disclosed | Not disclosed | Not applicable | Not supplied |
The layout drawing was software-read as containing 29 plots with sizes: smallest 267.39 sqm (319.8 sq yd), median 440.2 sqm (526.5 sq yd), and largest 1105.99 sqm (1322.8 sq yd). The size readings and plot count should be verified against the drawing.
300–400 sq yd (251–334 sqm): 2
400–500 sq yd (334–418 sqm): 10
500–1000 sq yd (418–836 sqm): 13
1000+ sq yd (836+ sqm): 4
For plots, “carpet area” and apartment common-area loading are not applicable in the supplied record. The floor-plan data says the two drawing sheets contain no flats and no apartment measurements.
5. Parking & vehicle circulation
The layout approval’s land-use statement records 0.00 common-parking area. The supplied documents do not state a sanctioned count of resident or visitor parking spaces, plot-specific parking allocations, accessible parking, or mechanical, basement, stilt or podium parking.
Vehicle circulation is described through the approved layout’s road network; the approval requires roads to remain open for neighbouring-site access and prohibits a compound wall or fencing around the site. The evidence does not establish individual parking rights or plot-specific parking arrangements.
6. Amenities, recreation & open spaces
The layout approval and drawing record specify layout-level open space and infrastructure. Progress percentages in the supplied RERA amenities schedule are 0 where provided; they do not establish independent physical verification of completion.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Park / organized open space | 2061.76 sq.m, 9.03% of net layout area | Approved-layout drawing; tentative-layout approval | Required in the layout approval; completion not verified |
| Avenue plantation | Listed as part of the layout development works | Tentative-layout approval | Required work; progress not verified |
| Park development | Listed as part of the layout development works | Tentative-layout approval | Required work; progress not verified |
| Community buildings | RERA amenities schedule includes the category but gives no supplied size or facility detail | Progress shown as 0; not verified complete | |
| Recreation facilities | Mentioned in third-party vendor amenity text; no project-specific size or sanctioned detail supplied | Vendor-listed only; not verified |
No clubhouse, indoor recreation facility, sports facility or facility capacity is established by the supplied project approval evidence. Utility installations are summarized separately below.
7. Utilities, building services & safety
The tentative-layout approval describes proposed layout infrastructure and requires the applicant to provide the listed works. The schedule does not establish their installed condition, capacity or operational status.
| Evidence in the project record | Approval calls for an assured water-supply source, internal water-supply pipelines, a water reservoir and an overhead tank. |
|---|---|
| Status / limitation | Proposed/required; source, storage capacity and completion are not supplied. |
| Evidence in the project record | Approval lists underground drainage lines, a common septic tank / STP, storm-water drains and drainage/channelization of nalas. |
|---|---|
| Status / limitation | Proposed/required; no capacity, commissioning or completion evidence supplied. |
| Evidence in the project record | Water-harvesting pits are listed in the approval. |
|---|---|
| Status / limitation | Proposed/required; completion not verified. |
| Evidence in the project record | Approval lists electrical supply lines, street lights and a transformer. |
|---|---|
| Status / limitation | Proposed/required; capacity and completion not supplied. |
| Evidence in the project record | Listed among the approval’s utility works. |
|---|---|
| Status / limitation | Proposed/required; system detail and completion not supplied. |
| Evidence in the project record | No project-specific fire system, access arrangement or clearance is established in the supplied approval records. |
|---|---|
| Status / limitation | Not disclosed in the supplied evidence. |
| Evidence in the project record | No project-specific security system or accessible-circulation detail is established in the supplied approval records. |
|---|---|
| Status / limitation | Not disclosed in the supplied evidence. |
Third-party vendor text mentions water supply, borewell, power backup, gas pipeline, fire safety and waste management, but the supplied project approval records do not establish these as sanctioned or completed project facilities.
8. Location, access & connectivity
The registered location is MALKAPUR, Kondapur Mandal, Sangareddy District, Telangana, PIN 502306, on Survey No. 298/PART. The layout approval identifies the site as Malkapur (G.P. & V.) / Malkapur Revenue Village.
The layout approval requires roads to remain open to neighbouring sites and lists internal-road widths in the approved drawing. The only supplied measured connectivity reference is the nearest sampled Outer Ring Road interchange, approximately 21.3 km from the parcel-centroid location.
9. Developer & development status
The registered promoter is SITAARA LIFE STYLE HOMES PRIVATE LIMITED, a private limited company. Its supplied corporate identifier is CIN: U70109TG2020PTC145253; GSTIN 36ABECS7531C1ZH. The RERA certificate gives the promoter address as Hyderabad, PIN 500081, while the project record lists an address at Silicon Towers, Image Gardens Road, Malkapur, Sangareddy, Kondapur, PIN 502306.
The RERA record labels the project “New Project.” It gives a proposed completion date of 30/11/2026; the tentative-layout approval separately requires infrastructure and amenities within two years from 6 April 2024, stated as 06 April, 2026. No project-specific, independently verified progress measurement or completion/occupancy certificate is supplied.
10. Approvals, official records & documents
| Supplied evidence | Form C certificate, registration P01100008394 |
|---|---|
| What it establishes | Project registration for SITAARA ONE, promoter identity and stated validity period. |
| Supplied evidence | No. 0001/LO/3154/2024, dated 06 April 2024, Sangareddy DTCP Municipality/Municipal Corporation |
|---|---|
| What it establishes | Tentative approval for the 29-plot residential layout on Survey No. 298/part, subject to stated conditions. |
| Supplied evidence | Layout-plan document with reference TS/075794/2023 and licence CA/2009/46164 |
|---|---|
| What it establishes | Plot schedule, roads and layout land-use schedule as recorded in the drawing. |
| Supplied evidence | Application 009790/LO/DTCP/3154/0002/2023; receipts TS/25211/2023, TS/25212/2023, TS/25441/2023 |
|---|---|
| What it establishes | References recorded in the tentative-layout approval. |
| Supplied evidence | Mortgage deed No. 2250/2024, dated 20 March 2024 |
|---|---|
| What it establishes | Approval identifies Plots 16, 9, 8, 17, 18 and 7 as mortgaged to the Municipality/Municipal Corporation for layout-development obligations. |
| Supplied evidence | Form B dated 10 May 2024 |
|---|---|
| What it establishes | Promoter declaration and stated undertaking; it is not a completion certificate. |
The approval identifies the layout as tentative and requires infrastructure completion and subsequent steps before final layout release. No final layout release or completion/occupancy certificate is included in the supplied evidence.
Frequently asked questions
Is SITAARA ONE registered with Telangana RERA?
Yes. SITAARA ONE is registered with the Telangana Real Estate Regulatory Authority as P01100008394; the registration status is New Project.
Who is the developer of SITAARA ONE?
The promoter named in the RERA registration is SITAARA LIFE STYLE HOMES PRIVATE LIMITED.
Where is SITAARA ONE located?
SITAARA ONE is in SANGAREDDY, MALKAPUR, KONDAPUR, Telangana (502306).
When will SITAARA ONE be completed?
The promoter's proposed date of completion filed with RERA is 30/11/2026. This is the promoter's declaration, not a guarantee.