Sri kalpa township
DEVENDER REDDY CONSTRUCTIONS · Jayashankar Bhupalpally · RERA P00500007034
Sri kalpa township is a residential plotted layout in Veshalapally, Bhupalpally Mandal, Jayashankar District, developed by the registered promoter DEVENDER REDDY CONSTRUCTIONS. The layout covers 9 Acer 30.74 Gts 47280 Sq. Yds and has 145 residential plots; towers, blocks and floors are not stated. TG-RERA registration number P00500007034 was issued on 29/09/2023, and the promoter’s Form B declares a completion deadline of 07-04-2024.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
8 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Record |
|---|---|
| Registered project name | Sri kalpa township RERA record |
| Project type | Plotted development / residential layout RERA record RERA filing |
| Phase or registered portion | Phase not separately identified; registration is for the plotted layout RERA record |
| TG-RERA registration | P00500007034; certificate issued 29/09/2023; stated validity 29/09/2023–07/04/2024; certificate records no extension Approvals record |
| Registered promoter | DEVENDER REDDY CONSTRUCTIONS RERA record Corporate record |
| RERA status | The supplied certificate records the dates above. The available record does not establish the project’s current registration status Approvals record |
Land and geographic identity
| Field | Record |
|---|---|
| Locality / revenue village | Veshalapally is recorded in the project identity and registration certificate; the tentative and final layout documents describe the land as BHUPALPALLY Revenue Village RERA record Approvals record |
| Mandal | Bhupalpally RERA record |
| District | Jayashankar; approval records use Jayashankar-Bhupalpally District RERA record |
| PIN | 506169 RERA record |
| Project survey numbers | 353, 354 and 356 Land records |
| Subdivisions cited in the final-layout record | 354/®, 354/c, 354/a, 354/6:, 356/A/1/1, 356/A/1/2, 356/A/2/1, 356/A/2/2, 356/A/3/1, 356/A/3/2, 356/A/4, 356/A/1, 356/A/c/2, 354/, 356/A1 and 356/A/ /2. These are transcribed as supplied; several are not clearly legible as survey identifiers |
| Extent | RERA land record: total area 39532.102 sq.m and net area 39532.10 sq.m Land records. Tentative-layout approval: 9 Acer 30.74 Gts 47280 Sq. Yds. Final-layout record also states Ac 9.77 Gts; 47280 Sq. Yds |
| Boundaries in project land record | East and south: “60 feet excesting road”; west and north: “others land” Land records |
| Main access context in filed material | The tentative-layout record states that layout roads must remain open for access to neighbouring sites |
Development identity
| Field | Record |
|---|---|
| Sanctioning authority | BHUPALPALLY Municipality/Municipal Corporation Approvals record |
| Principal tentative layout approval | 0004/LO/3001/2022, dated 06/07/2022; application 004321/LO/DTCP/3001/0003/2022 Approvals record |
| Final-layout approval | 0060/FLT/3001/2025, dated 18 September 2025; proceedings 001716/FLT/DTCP/3001/0002/2024 Approvals record |
| Layout scale | 145 plots in the tentative and final layout records |
| Approved built-up area | Not stated in the supplied plotted-layout approval extracts; building-level built-up area is not established here RERA filing |
| Buildings, floors and parking levels | Not applicable as a reported layout configuration; individual plot building permissions are to be considered separately under the final-layout conditions |
| Unit count | 145 plots in the approval records |
Offering and status
| Field | Record |
|---|---|
| Offering | Residential plots; no RERA-filed plot-size schedule or booked/available inventory count is supplied in this evidence set RERA filing |
| Layout-drawing plot data | Software-read drawing record reports 145 plots; sizes were available for 144: 91.44–313.41 sq.m (109.4–374.8 sq.yd), with drawing-derived size bands set out below Layout record |
| Construction / development stage | An architect’s Form–1A dated 30/06/2028 states the project is completed in all aspects; this is a professional certificate on file, not an independent site inspection |
| Completion undertaking | The promoter’s Form B declares a completion deadline of 07-04-2024 |
| Occupancy / completion record | The supplied architect’s certificate identifies an occupancy certificate for the layout dated 18/09/2025 and says the project is completed; the supplied final-layout document is dated 18 September 2025 |
2. The project story
Sri kalpa township is a residential plotted layout, rather than an apartment or multi-storey building project. The registration certificate identifies the project and its survey numbers as 353, 354 and 356; the tentative-layout approval describes 145 plots in BHUPALPALLY Revenue Village, Bhupalpally Mandal, Jayashankar-Bhupalpally District. The project identity and RERA certificate also use Veshalapally as the locality/revenue-village field RERA record.
The tentative approval allocates land to plots, roads, park/open space, social infrastructure and utilities. Its conditions place responsibility for layout infrastructure and development on the applicant and require internal roads to remain open for neighbouring access. The final-layout record identifies 145 plots and specifies residential dwelling use, with individual building permissions to be considered separately.
The promoter’s filed Form B states a completion undertaking of 07-04-2024. Separately, the architect’s Form–1A, dated 30/06/2028, reports completion in all aspects and refers to an occupancy certificate dated 18/09/2025. These are filed statements and certificates; no independent physical inspection record is supplied.
3. Master plan, architecture & building design
The project is organized as a plotted layout with 145 plots, not as a disclosed set of towers or apartment blocks. The tentative approval records a layout extent of 9 Acer 30.74 Gts 47280 Sq. Yds and gives this land-use split:
| Layout use | Tentative approval area | Share |
|---|---|---|
| Plotted area | 5 Acer 34.67 Gts 28396 Sq. Yds | 60.37% |
| Road area | 2 Acer 22.65 Gts 12421 Sq. Yds | 26.41% |
| Open space (park) | 0 Acer 36.04 Gts 4361 Sq. Yds | 9.27% |
| Social infrastructure | 0 Acer 11.42 Gts 1382 Sq. Yds | 2.94% |
| Utilities | 0 Acer 3.91 Gts 473 Sq. Yds | 1.01% |
| Mortgage area of plotted area | 0 Acer 38.68 Gts 4681 Sq. Yds | 16.45% |
The software-read layout drawing reports a land-use base of 39324.28 sq.m, comprising plots 23741.58 sq.m, roads 10385.03 sq.m, parks/open space 3646.64 sq.m, utilities 395.27 sq.m and social infrastructure 1155.76 sq.m; it records amenity area as 0.00 sq.m Layout record. The final-layout record separately gives a net-layout figure of 39324.28 sq.m and lists the same land-use components.
The drawing-based plot schedule reports 145 plots; sizes were read for 144 plots. The drawing record cautions that plot count and sizes are software-read from the drawing and should be verified against it Layout record. The final-layout record identifies internal roads including “30' Road No. 4”, “60 Feet Wide Road”, “33' Road No. 1”, “30' Road No. 13” and “30' Road No. 14”; it also lists widths 9.14M, 10.06M and 18.29 MT.
No building footprints, apartment floor plans, tower heights, floor configuration or apartment common-area schedule are supplied. The final-layout approval states that building permissions are to be considered individually; it also requires prior approval for plot amalgamation or subdivision.
4. Homes, configurations & floor plans
The RERA certificate and layout approvals identify 145 residential plots; no RERA-filed plot-by-plot saleable-area or booking schedule is supplied here.
The drawing-derived size data is software-measured, not a RERA-filed saleable-area schedule. Sizes were available for 144 plots:
| Drawing-derived plot-size band | Plot count |
|---|---|
| 100–150 sq.yd (84–125 sq.m) | 3 |
| 150–200 sq.yd (125–167 sq.m) | 118 |
| 200–250 sq.yd (167–209 sq.m) | 10 |
| 250–300 sq.yd (209–251 sq.m) | 6 |
| 300–400 sq.yd (251–334 sq.m) | 7 |
The drawing record reports the smallest measured plot as 91.44 sq.m (109.4 sq.yd), the median as 153.49 sq.m (183.6 sq.yd) and the largest as 313.41 sq.m (374.8 sq.yd). Common sizes shown in the drawing data include 146.24 sq.m (49 plots), 167.17 sq.m (39), 144.22 sq.m (4), 165.16 sq.m (3) and 165.12 sq.m (3) Layout record.
These are plot areas, not apartment carpet or saleable areas. Booked and available plot counts are not provided in the supplied records. The final-layout conditions specify detached dwelling use for a single family per site and require approval for plot amalgamation or subdivision.
5. Parking & vehicle circulation
The supplied layout material does not establish a sanctioned count of resident, visitor or accessible parking spaces, nor does it provide plot-level parking allocations or EV-charging provision. The final-layout area statement records Common Parking Area 0.00.
The tentative-layout conditions require roads to be opened for access to neighbouring sites and prohibit a compound wall or fencing around the site in the tentative approval. The final-layout record lists internal road identifiers and widths, but does not specify parking bays, driveway dimensions or pedestrian–vehicle separation.
6. Amenities, recreation & open spaces
The tentative and final layout records identify park/open space, social infrastructure and utility land. The tentative approval also describes layout-development works and infrastructure intended to be provided; the RERA amenity record separately lists declared availability percentages. The supplied records do not provide independent inspection evidence confirming the present condition of individual facilities RERA amenities.
| Description / size | Tentative approval: 0 Acer 36.04 Gts 4361 Sq. Yds (9.27%); software-read area: 3646.64 sq.m Layout record |
|---|---|
| Evidence source | Tentative and final layout records; drawing-derived area |
| Declared progress / verified status | RERA amenity record lists “Green Strip/TOT LOT/Park” at 100%; not independently verified RERA amenities |
| Description / size | 0 Acer 11.42 Gts 1382 Sq. Yds (2.94%) in tentative approval; 1155.76 sq.m in software-read area statement Layout record |
|---|---|
| Evidence source | Layout records |
| Declared progress / verified status | Land reservation shown; no facility-level completion evidence supplied |
| Description / size | Layout road area 2 Acer 22.65 Gts 12421 Sq. Yds (26.41%) in tentative approval; drawing-derived area 10385.03 sq.m Layout record |
|---|---|
| Evidence source | Layout approval and drawing |
| Declared progress / verified status | RERA amenity record lists internal roads and footpaths at 100%; not independently verified RERA amenities |
| Description / size | Size not stated RERA amenities |
|---|---|
| Evidence source | RERA amenity record; final-layout record lists “Tot-lot” RERA amenities |
| Declared progress / verified status | “Green Strip/TOT LOT/Park” listed at 100% in the RERA amenity record; not independently verified RERA amenities |
| Description / size | 0 Acer 3.91 Gts 473 Sq. Yds (1.01%) in tentative approval; drawing-derived area 395.27 sq.m Layout record |
|---|---|
| Evidence source | Layout approval and drawing |
| Declared progress / verified status | Land reservation shown; utility services are addressed below |
No clubhouse or indoor-recreation schedule is supplied. The final-layout record lists a common parking area as 0.00.
7. Utilities, building services & safety
The tentative-layout approval describes proposed layout infrastructure including road formation with black top, storm-water drains, underground drainage lines, common septic tank/STP, internal water-supply pipelines, overhead tank, an assured water source, electrical supply lines, street lights, transformer, avenue plantation and rainwater-harvesting pits. These are approval-condition descriptions of required development works, not independent confirmation that each item is installed or operational.
The RERA amenity record lists water supply and sewerage (chambers, lines, septic tank, STP) at 100%, while storm-water drains, street lighting, treatment/disposal of sewage and sullage, solid-waste management, water conservation/rainwater harvesting, energy management, fire-protection requirements and electrical meter room/substation/receiving station each show 0% in that record RERA amenities. No capacities, commissioning evidence, test certificates or independent verification are supplied.
The tentative approval also refers to a water reservoir, septic tank/STP, electric transformer and solid-waste management as utility infrastructure. The final-layout record lists rainwater-harvesting structures and a garbage bin among its utility/amenity entries. No evidence is supplied for lifts, building fire systems, emergency-access arrangements, CCTV, security controls or accessibility features; individual plot-building approvals and services are not detailed here.
8. Location, access & connectivity
The project is registered in Veshalapally, PIN 506169, with the project land described in the approval records as BHUPALPALLY Revenue Village, Bhupalpally Mandal, Jayashankar-Bhupalpally District RERA record. The supplied geocode is 18.4381466, 79.8684969, labelled Bhupalpally, Bhupalpally mandal, Jayashankar Bhupalapally, Telangana, 506169 Location record.
The project land record identifies 60-foot roads on the east and south boundaries Land records. The vendor record also describes existing 60-foot roads to the east and south; this is a vendor-supplied connectivity statement Promoter website. The supplied location data lists the nearest sampled Outer Ring Road interchange at approximately 167.0 km Location record. No other measured road, public-transport or landmark distances are supplied.
9. Developer & development status
The registered promoter is DEVENDER REDDY CONSTRUCTIONS, recorded as a Proprietorship. The registered project record identifies MOTHE DEVENDER REDDY as authorized signatory Corporate record Parties record. The registration certificate gives the promoter office as Village: GMH Hanmakonda, Mandal: Hanamkonda, District: Warangal Urban, PIN 506001; the project identity record separately lists the promoter address as DEVENDER REDDY BUILDING, NANDHI HILLS, Bhupalpally, Jayashankar, PIN 506169 Corporate record.
The registration certificate states that registration began on 29/09/2023 and ended on 07/04/2024, with no extension recorded in that certificate. The Form B declaration gives a completion undertaking of 07-04-2024. An architect’s Form–1A dated 30/06/2028 states that the project is completed in all aspects and identifies an occupancy certificate dated 18/09/2025. These are filed records; independent site verification is not supplied.
10. Approvals, official records & documents
| Identifier / date | P00500007034; issued 29/09/2023; validity stated through 07/04/2024 |
|---|---|
| What it evidences | Registration of Sri kalpa township as a plotted project; certificate states no extension |
| Identifier / date | 0004/LO/3001/2022, dated 06/07/2022; application 004321/LO/DTCP/3001/0003/2022 |
|---|---|
| What it evidences | Tentative residential layout approval for 145 plots over survey numbers 353, 354 and 356 |
| Identifier / date | 4385/2022, dated 07 June 2022 |
|---|---|
| What it evidences | Mortgage over specified plots in favour of the Municipality/Municipal Corporation for layout-condition purposes |
| Identifier / date | 0060/FLT/3001/2025, dated 18 September 2025; proceedings 001716/FLT/DTCP/3001/0002/2024 |
|---|---|
| What it evidences | Final residential-layout approval; record lists 145 plots and land-use allocation |
| Identifier / date | 5225 of 2025, dated 23 September 2025 |
|---|---|
| What it evidences | Registered release of mortgage over specified layout plots |
| Identifier / date | Dated 30/06/2028; cites occupancy certificate dated 18/09/2025 |
|---|---|
| What it evidences | Architect’s statement that the project is completed in all aspects |
| Identifier / date | Declaration date shown as 2023; day and month illegible |
|---|---|
| What it evidences | Promoter-declared title, project-fund, audit, approval and completion undertakings |
| Identifier / date | Document 321631; two layout sheets Layout record |
|---|---|
| What it evidences | Drawing-derived plot schedule and land-use data; software extraction notes that plot sizes and counts should be checked against the drawing |
The supplied approval records describe the layout and its conditions. Individual building permissions are to be considered separately under the final-layout conditions.
1. Project at a glance
Project identity
Registered project name: Sri kalpa township
Project type: Plotted development / residential layout
Phase or registered portion: Phase not separately identified; registration is for the plotted layout
TG-RERA registration: P00500007034; certificate issued 29/09/2023; stated validity 29/09/2023–07/04/2024; certificate records no extension
Registered promoter: DEVENDER REDDY CONSTRUCTIONS
RERA status: The supplied certificate records the dates above. The available record does not establish the project’s current registration status
Land and geographic identity
Locality / revenue village: Veshalapally is recorded in the project identity and registration certificate; the tentative and final layout documents describe the land as BHUPALPALLY Revenue Village
Mandal: Bhupalpally
District: Jayashankar; approval records use Jayashankar-Bhupalpally District
PIN: 506169
Project survey numbers: 353, 354 and 356
Subdivisions cited in the final-layout record: 354/®, 354/c, 354/a, 354/6:, 356/A/1/1, 356/A/1/2, 356/A/2/1, 356/A/2/2, 356/A/3/1, 356/A/3/2, 356/A/4, 356/A/1, 356/A/c/2, 354/, 356/A1 and 356/A/ /2. These are transcribed as supplied; several are not clearly legible as survey identifiers
Extent: RERA land record: total area 39532.102 sq.m and net area 39532.10 sq.m. Tentative-layout approval: 9 Acer 30.74 Gts 47280 Sq. Yds. Final-layout record also states Ac 9.77 Gts; 47280 Sq. Yds
Boundaries in project land record: East and south: “60 feet excesting road”; west and north: “others land”
Main access context in filed material: The tentative-layout record states that layout roads must remain open for access to neighbouring sites
Development identity
Sanctioning authority: BHUPALPALLY Municipality/Municipal Corporation
Principal tentative layout approval: 0004/LO/3001/2022, dated 06/07/2022; application 004321/LO/DTCP/3001/0003/2022
Final-layout approval: 0060/FLT/3001/2025, dated 18 September 2025; proceedings 001716/FLT/DTCP/3001/0002/2024
Layout scale: 145 plots in the tentative and final layout records
Approved built-up area: Not stated in the supplied plotted-layout approval extracts; building-level built-up area is not established here
Buildings, floors and parking levels: Not applicable as a reported layout configuration; individual plot building permissions are to be considered separately under the final-layout conditions
Unit count: 145 plots in the approval records
Offering and status
Offering: Residential plots; no RERA-filed plot-size schedule or booked/available inventory count is supplied in this evidence set
Layout-drawing plot data: Software-read drawing record reports 145 plots; sizes were available for 144: 91.44–313.41 sq.m (109.4–374.8 sq.yd), with drawing-derived size bands set out below
Construction / development stage: An architect’s Form–1A dated 30/06/2028 states the project is completed in all aspects; this is a professional certificate on file, not an independent site inspection
Completion undertaking: The promoter’s Form B declares a completion deadline of 07-04-2024
Occupancy / completion record: The supplied architect’s certificate identifies an occupancy certificate for the layout dated 18/09/2025 and says the project is completed; the supplied final-layout document is dated 18 September 2025
2. The project story
Sri kalpa township is a residential plotted layout, rather than an apartment or multi-storey building project. The registration certificate identifies the project and its survey numbers as 353, 354 and 356; the tentative-layout approval describes 145 plots in BHUPALPALLY Revenue Village, Bhupalpally Mandal, Jayashankar-Bhupalpally District. The project identity and RERA certificate also use Veshalapally as the locality/revenue-village field.
The tentative approval allocates land to plots, roads, park/open space, social infrastructure and utilities. Its conditions place responsibility for layout infrastructure and development on the applicant and require internal roads to remain open for neighbouring access. The final-layout record identifies 145 plots and specifies residential dwelling use, with individual building permissions to be considered separately.
The promoter’s filed Form B states a completion undertaking of 07-04-2024. Separately, the architect’s Form–1A, dated 30/06/2028, reports completion in all aspects and refers to an occupancy certificate dated 18/09/2025. These are filed statements and certificates; no independent physical inspection record is supplied.
3. Master plan, architecture & building design
The project is organized as a plotted layout with 145 plots, not as a disclosed set of towers or apartment blocks. The tentative approval records a layout extent of 9 Acer 30.74 Gts 47280 Sq. Yds and gives this land-use split:
| Layout use | Tentative approval area | Share |
|---|---|---|
| Plotted area | 5 Acer 34.67 Gts 28396 Sq. Yds | 60.37% |
| Road area | 2 Acer 22.65 Gts 12421 Sq. Yds | 26.41% |
| Open space (park) | 0 Acer 36.04 Gts 4361 Sq. Yds | 9.27% |
| Social infrastructure | 0 Acer 11.42 Gts 1382 Sq. Yds | 2.94% |
| Utilities | 0 Acer 3.91 Gts 473 Sq. Yds | 1.01% |
| Mortgage area of plotted area | 0 Acer 38.68 Gts 4681 Sq. Yds | 16.45% |
The software-read layout drawing reports a land-use base of 39324.28 sq.m, comprising plots 23741.58 sq.m, roads 10385.03 sq.m, parks/open space 3646.64 sq.m, utilities 395.27 sq.m and social infrastructure 1155.76 sq.m; it records amenity area as 0.00 sq.m. The final-layout record separately gives a net-layout figure of 39324.28 sq.m and lists the same land-use components.
The drawing-based plot schedule reports 145 plots; sizes were read for 144 plots. The drawing record cautions that plot count and sizes are software-read from the drawing and should be verified against it. The final-layout record identifies internal roads including “30' Road No. 4”, “60 Feet Wide Road”, “33' Road No. 1”, “30' Road No. 13” and “30' Road No. 14”; it also lists widths 9.14M, 10.06M and 18.29 MT.
No building footprints, apartment floor plans, tower heights, floor configuration or apartment common-area schedule are supplied. The final-layout approval states that building permissions are to be considered individually; it also requires prior approval for plot amalgamation or subdivision.
4. Homes, configurations & floor plans
The RERA certificate and layout approvals identify 145 residential plots; no RERA-filed plot-by-plot saleable-area or booking schedule is supplied here.
The drawing-derived size data is software-measured, not a RERA-filed saleable-area schedule. Sizes were available for 144 plots:
100–150 sq.yd (84–125 sq.m): 3
150–200 sq.yd (125–167 sq.m): 118
200–250 sq.yd (167–209 sq.m): 10
250–300 sq.yd (209–251 sq.m): 6
300–400 sq.yd (251–334 sq.m): 7
The drawing record reports the smallest measured plot as 91.44 sq.m (109.4 sq.yd), the median as 153.49 sq.m (183.6 sq.yd) and the largest as 313.41 sq.m (374.8 sq.yd). Common sizes shown in the drawing data include 146.24 sq.m (49 plots), 167.17 sq.m (39), 144.22 sq.m (4), 165.16 sq.m (3) and 165.12 sq.m (3).
These are plot areas, not apartment carpet or saleable areas. Booked and available plot counts are not provided in the supplied records. The final-layout conditions specify detached dwelling use for a single family per site and require approval for plot amalgamation or subdivision.
5. Parking & vehicle circulation
The supplied layout material does not establish a sanctioned count of resident, visitor or accessible parking spaces, nor does it provide plot-level parking allocations or EV-charging provision. The final-layout area statement records Common Parking Area 0.00.
The tentative-layout conditions require roads to be opened for access to neighbouring sites and prohibit a compound wall or fencing around the site in the tentative approval. The final-layout record lists internal road identifiers and widths, but does not specify parking bays, driveway dimensions or pedestrian–vehicle separation.
6. Amenities, recreation & open spaces
The tentative and final layout records identify park/open space, social infrastructure and utility land. The tentative approval also describes layout-development works and infrastructure intended to be provided; the RERA amenity record separately lists declared availability percentages. The supplied records do not provide independent inspection evidence confirming the present condition of individual facilities.
| Description / size | Tentative approval: 0 Acer 36.04 Gts 4361 Sq. Yds (9.27%); software-read area: 3646.64 sq.m |
|---|---|
| Evidence source | Tentative and final layout records; drawing-derived area |
| Declared progress / verified status | RERA amenity record lists “Green Strip/TOT LOT/Park” at 100%; not independently verified |
| Description / size | 0 Acer 11.42 Gts 1382 Sq. Yds (2.94%) in tentative approval; 1155.76 sq.m in software-read area statement |
|---|---|
| Evidence source | Layout records |
| Declared progress / verified status | Land reservation shown; no facility-level completion evidence supplied |
| Description / size | Layout road area 2 Acer 22.65 Gts 12421 Sq. Yds (26.41%) in tentative approval; drawing-derived area 10385.03 sq.m |
|---|---|
| Evidence source | Layout approval and drawing |
| Declared progress / verified status | RERA amenity record lists internal roads and footpaths at 100%; not independently verified |
| Description / size | Size not stated |
|---|---|
| Evidence source | RERA amenity record; final-layout record lists “Tot-lot” |
| Declared progress / verified status | “Green Strip/TOT LOT/Park” listed at 100% in the RERA amenity record; not independently verified |
| Description / size | 0 Acer 3.91 Gts 473 Sq. Yds (1.01%) in tentative approval; drawing-derived area 395.27 sq.m |
|---|---|
| Evidence source | Layout approval and drawing |
| Declared progress / verified status | Land reservation shown; utility services are addressed below |
No clubhouse or indoor-recreation schedule is supplied. The final-layout record lists a common parking area as 0.00.
7. Utilities, building services & safety
The tentative-layout approval describes proposed layout infrastructure including road formation with black top, storm-water drains, underground drainage lines, common septic tank/STP, internal water-supply pipelines, overhead tank, an assured water source, electrical supply lines, street lights, transformer, avenue plantation and rainwater-harvesting pits. These are approval-condition descriptions of required development works, not independent confirmation that each item is installed or operational.
The RERA amenity record lists water supply and sewerage (chambers, lines, septic tank, STP) at 100%, while storm-water drains, street lighting, treatment/disposal of sewage and sullage, solid-waste management, water conservation/rainwater harvesting, energy management, fire-protection requirements and electrical meter room/substation/receiving station each show 0% in that record. No capacities, commissioning evidence, test certificates or independent verification are supplied.
The tentative approval also refers to a water reservoir, septic tank/STP, electric transformer and solid-waste management as utility infrastructure. The final-layout record lists rainwater-harvesting structures and a garbage bin among its utility/amenity entries. No evidence is supplied for lifts, building fire systems, emergency-access arrangements, CCTV, security controls or accessibility features; individual plot-building approvals and services are not detailed here.
8. Location, access & connectivity
The project is registered in Veshalapally, PIN 506169, with the project land described in the approval records as BHUPALPALLY Revenue Village, Bhupalpally Mandal, Jayashankar-Bhupalpally District. The supplied geocode is 18.4381466, 79.8684969, labelled Bhupalpally, Bhupalpally mandal, Jayashankar Bhupalapally, Telangana, 506169.
The project land record identifies 60-foot roads on the east and south boundaries. The vendor record also describes existing 60-foot roads to the east and south; this is a vendor-supplied connectivity statement. The supplied location data lists the nearest sampled Outer Ring Road interchange at approximately 167.0 km. No other measured road, public-transport or landmark distances are supplied.
9. Developer & development status
The registered promoter is DEVENDER REDDY CONSTRUCTIONS, recorded as a Proprietorship. The registered project record identifies MOTHE DEVENDER REDDY as authorized signatory. The registration certificate gives the promoter office as Village: GMH Hanmakonda, Mandal: Hanamkonda, District: Warangal Urban, PIN 506001; the project identity record separately lists the promoter address as DEVENDER REDDY BUILDING, NANDHI HILLS, Bhupalpally, Jayashankar, PIN 506169.
The registration certificate states that registration began on 29/09/2023 and ended on 07/04/2024, with no extension recorded in that certificate. The Form B declaration gives a completion undertaking of 07-04-2024. An architect’s Form–1A dated 30/06/2028 states that the project is completed in all aspects and identifies an occupancy certificate dated 18/09/2025. These are filed records; independent site verification is not supplied.
10. Approvals, official records & documents
| Identifier / date | P00500007034; issued 29/09/2023; validity stated through 07/04/2024 |
|---|---|
| What it evidences | Registration of Sri kalpa township as a plotted project; certificate states no extension |
| Identifier / date | 0004/LO/3001/2022, dated 06/07/2022; application 004321/LO/DTCP/3001/0003/2022 |
|---|---|
| What it evidences | Tentative residential layout approval for 145 plots over survey numbers 353, 354 and 356 |
| Identifier / date | 4385/2022, dated 07 June 2022 |
|---|---|
| What it evidences | Mortgage over specified plots in favour of the Municipality/Municipal Corporation for layout-condition purposes |
| Identifier / date | 0060/FLT/3001/2025, dated 18 September 2025; proceedings 001716/FLT/DTCP/3001/0002/2024 |
|---|---|
| What it evidences | Final residential-layout approval; record lists 145 plots and land-use allocation |
| Identifier / date | 5225 of 2025, dated 23 September 2025 |
|---|---|
| What it evidences | Registered release of mortgage over specified layout plots |
| Identifier / date | Dated 30/06/2028; cites occupancy certificate dated 18/09/2025 |
|---|---|
| What it evidences | Architect’s statement that the project is completed in all aspects |
| Identifier / date | Declaration date shown as 2023; day and month illegible |
|---|---|
| What it evidences | Promoter-declared title, project-fund, audit, approval and completion undertakings |
| Identifier / date | Document 321631; two layout sheets |
|---|---|
| What it evidences | Drawing-derived plot schedule and land-use data; software extraction notes that plot sizes and counts should be checked against the drawing |
The supplied approval records describe the layout and its conditions. Individual building permissions are to be considered separately under the final-layout conditions.
Frequently asked questions
Is Sri kalpa township registered with Telangana RERA?
Yes. Sri kalpa township is registered with the Telangana Real Estate Regulatory Authority as P00500007034; the registration status is New Project.
Who is the developer of Sri kalpa township?
The promoter named in the RERA registration is DEVENDER REDDY CONSTRUCTIONS.
Where is Sri kalpa township located?
Sri kalpa township is in bhupalpally, Veshalapally, Jayashankar Bhupalpally, Telangana (506169).
When will Sri kalpa township be completed?
The promoter's proposed date of completion filed with RERA is 07/04/2024. This is the promoter's declaration, not a guarantee.