Sree Nilayam
FORRTUNE GREENHOMES · Rangareddy · RERA P02400000065
SREE NILAYAM is a residential apartment project in Narsingi, Gandipet mandal, Ranga Reddy district, developed by the registered promoter Forrtune Greenhomes. It covers 1,421.20 Sq. Mt. and comprises 1 building configured as 1Stilt + 5 floors, with 30 apartments: 25 2BHK and 5 3BHK. Its TG-RERA registration is P02400000065, and its proposed completion date is 30/08/2020.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
7 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered project name | SREE NILAYAM RERA record |
| Project type / phase | Residential apartment project. Phase or separately registered portion is not disclosed. RERA record RERA filing |
| TG-RERA registration | P02400000065 |
| Registration validity | Issued 11/12/2018; valid through 30/08/2020. The certificate records no extension. This is the registration period, not the occupancy-certificate date. |
| Registered promoter | Forrtune Greenhomes; the project record identifies the promoter as a partnership. RERA record Corporate record |
| RERA-recorded project status | On-Going Project in the supplied project record. RERA filing |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality / revenue village | Narsingi; the approval document describes it as Narsingi-ORRGC. RERA record Land records |
| Mandal / district / PIN | Gandipet / Ranga Reddy / 500089. RERA record |
| Project survey numbers | 300, 301, 302, 303, 306, 311, 313, 314, 315. The RERA certificate lists these individually; the HMDA technical approval groups them as 300 TO 303, 306 To 311, 313 To 315. Land records |
| Plot numbers | 231, 232, 244 and 245. Land records |
| Registered site extent | 1,421.20 Sq. Mt. in the HMDA technical-approval extraction. The RERA land record gives total and net area as 1421.20 sqmts. Land records |
| Boundaries | East: 30 FEET WIDE ROAD; west: 60 FEET WIDE ROAD; north: PLOT NO 230 AND 246; south: PLOT NO 233 AND 243. Land records |
Development identity
| Item | Project record |
|---|---|
| Sanctioning / technical-approval authority | Hyderabad Metropolitan Development Authority (HMDA); the technical approval directs building plans to be sanctioned and released by the Narsingi Gram Panchayath Executive Authority. Approvals record |
| Principal approval | HMDA Technical Approval 002008/ZOA/R1/U6/HMDA/12072017, dated 31/08/2017. Approvals record |
| Approved built-up area | 2922.5 (as recorded in the project filing); the technical-approval extraction separately lists Built up Area: 2922.5. RERA filing |
| Building count / configuration | 1 building; approved configuration 1Stilt + 5 floors. RERA filing |
| Parking levels / provision | A stilt level is in the approved configuration. Parking-space counts and allocation details are not established in the supplied record. RERA filing |
| Approved versus RERA-declared units | The filing records 1 total building unit; its unit schedule records 30 apartments: 25 2BHK and 5 3BHK. The supplied evidence does not explain the “building units” field as an apartment count. RERA filing RERA unit table RERA unit details |
Offering and status
| Item | Project record |
|---|---|
| Configurations | 2BHK and 3BHK. RERA unit table RERA unit details |
| RERA-filed saleable areas | 2BHK: 70.12 sqm; 3BHK: 84.86 sqm. RERA unit table RERA unit details |
| Booked / available | 2BHK: 25 booked / 0 available; 3BHK: 5 booked / 0 available. Counts are as last read from the TG-RERA portal; no as-of date is supplied, so they are indicative. RERA unit table RERA unit details |
| Construction stage | An architect’s Form–1A extraction certifies overall project completion and records an HMDA occupancy certificate for S+5 Floors, completed 14th Feb 2019. This is a document-based completion statement, not an independent site inspection. |
| Original / revised proposed completion | 30/08/2020 / 30/08/2020 in the project filing. RERA record RERA filing |
| Occupancy-certificate record | The Form–1A extraction records HMDA OC 018055/Z0A/OC/U6/HMDA/06122018, dated 14th Feb 2019, for S+5 floors. |
2. The project story
SREE NILAYAM is recorded with TG-RERA as a residential apartment project at Narsingi, Gandipet mandal, Ranga Reddy district, on plots 231, 232, 244 and 245 across the listed Narsingi survey numbers. The approved development is a single residential building configured as 1Stilt + 5 floors. RERA record Land records
The RERA unit schedule lists 25 two-bedroom and 5 three-bedroom apartments. Its booking figures show all 30 as booked, with no units available in the portal snapshot; the snapshot has no stated as-of date. RERA unit table RERA unit details
The project record calls the project on-going and gives 30/08/2020 as both original and revised proposed completion date. Separately, the architect’s Form–1A extraction certifies overall completion and records an HMDA occupancy certificate for the S+5-floor building, dated 14th Feb 2019. These are distinct records: the filing’s status and completion dates do not themselves establish physical progress, while the Form–1A is an architect’s certification rather than an independent site verification. RERA filing RERA record
3. Master plan, architecture & building design
The filed development is a single residential block on a recorded site extent of 1,421.20 Sq. Mt., with approved built-up area recorded as 2922.5. The HMDA technical-approval extraction describes a 1Stilt + 5 configuration and gives building height as 14.75; the supplied extraction does not state a measurement unit for that height. Land records RERA filing
The technical-approval extraction also lists Proposed Built-up Area: 3590.75, separately from Built up Area: 2922.5. The supplied evidence does not explain the basis or relationship between these figures; they are reported as separately labelled in that document, not treated as interchangeable area measures.
No usable measured floor-plan data is supplied: two drawing records are reported as having no flats, with 0 measured. Accordingly, the evidence here does not establish flat arrangements per floor, footprint, circulation, lifts, stairs, or internal common-area layout. Floor plans
4. Homes, configurations & floor plans
The TG-RERA unit schedule records 30 apartments: 25 2BHK and 5 3BHK. The stated areas below are RERA-filed saleable areas, not carpet-area measurements. RERA unit table RERA unit details
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 25 | 25 | 0 | 70.12 sqm | Not measured in supplied drawing data | Not supplied |
| 3BHK | 5 | 5 | 0 | 84.86 sqm | Not measured in supplied drawing data | Not supplied |
The booking and availability counts are portal figures without a supplied as-of date and should be treated as indicative. Floor-plan processing reports two drawings with no flats and zero measured, so there are no software-measured carpet or room dimensions available here. RERA unit table Floor plans
5. Parking & vehicle circulation
The approved configuration includes a stilt level, but the supplied records do not establish the number of car or two-wheeler spaces, visitor or accessible provision, parking allocation to individual apartments, or the vehicle-entry and internal-driveway arrangement. The technical-approval extraction lists a transformer and garbage house, but does not specify parking quantities. RERA filing
A stilt level in a plan does not, by itself, establish an apartment’s exclusive parking allocation. Confirm parking provision and any unit-specific entitlement from the approved plan and the buyer’s registered agreement.
6. Amenities, recreation & open spaces
The TG-RERA amenities record lists the following project facilities and infrastructure status. The supplied data gives percentages but no facility sizes, capacities, or independent completion verification. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Water Supply | No source, storage or capacity specified | TG-RERA amenities record | YES; 100% declared |
| Sewerage (Chamber, Lines, Septic Tank, STP) | No capacity or treatment details specified | TG-RERA amenities record | YES; 100% declared |
| Green Strip/TOT LOT/Park | No area or dimensions specified | TG-RERA amenities record | YES; 100% declared |
| Water Conservation, Rain water Harvesting | No system size or capacity specified | TG-RERA amenities record; HMDA technical-approval condition also calls for rainwater-harvesting structures | YES; 100% declared in amenities record |
| Energy management | No system or capacity specified | TG-RERA amenities record | YES; 100% declared |
| Electrical Meter Room, Sub-Station, Receiving Station | No capacity specified | TG-RERA amenities record | YES; 100% declared |
| Aggregate area of recreational Open Space | Area not supplied | TG-RERA amenities record | YES; 100% declared |
| Storm Water Drains | Details not supplied | TG-RERA amenities record | 0% recorded |
| Street Lighting | Details not supplied | TG-RERA amenities record | 0% recorded |
| Community Buildings | Details not supplied | TG-RERA amenities record | 0% recorded |
| Treatment and Disposal of Sewage and Sullage Water | Details not supplied | TG-RERA amenities record | 0% recorded |
| Solid Waste Management and Disposal | Details not supplied | TG-RERA amenities record | 0% recorded |
| Fire Protection and Fire Safety Requirements | Details not supplied | TG-RERA amenities record | 0% recorded |
| Internal Roads & Footpaths | Details not supplied | TG-RERA amenities record | 0% recorded |
7. Utilities, building services & safety
The TG-RERA amenities record marks water supply, sewerage, rainwater harvesting, energy management, and an electrical meter room/sub-station/receiving station as YES; 100%. It does not provide capacities or technical descriptions. HMDA’s technical-approval conditions require rainwater-harvesting structures and list a transformer and garbage house. RERA amenities
The same amenities record shows 0% for storm-water drains, treatment and disposal of sewage and sullage water, solid-waste management and disposal, and fire-protection and fire-safety requirements. The supplied evidence does not specify lift count or capacity, backup power, waste-segregation arrangements, security systems, accessible circulation, or fire-system details. RERA amenities
8. Location, access & connectivity
The registered project location is Narsingi, Narsingi revenue village, Gandipet mandal, Ranga Reddy district, PIN 500089. The filed site boundaries identify a 30 FEET WIDE ROAD on the east and a 60 FEET WIDE ROAD on the west. RERA record Land records
The supplied location record lists the Financial District (Nanakramguda) at 2.2 km, ICICI Bank at 1.6 km, Holy Mary College at 2.1 km, Sankaraya Eye Hospital at 0.6 km, Microchip Hyderabad at 1.7 km, an unnamed park at 0.1 km, and an unnamed school at 1.4 km. These are recorded distances; no travel times or public-transport details are supplied. Location record
9. Developer & development status
The registered promoter is Forrtune Greenhomes, identified in the project record as a partnership. The promoter’s recorded office address is TULASIS LAKSHMI NILAYAM, SANSKRUTHI TOWNSHIP, Narsingi, Narsingi, Gandipet, Ranga Reddy, 500089. The registration certificate gives the promoter office as Village: Neknapur, Mandal: Gandipet, District: Ranga Reddy, Pin: 500089. Corporate record Parties record
The supplied records identify SAMBIREDDY VANGA as a partner and SURESH VENKATA SOMISETTY as an authorized signatory. A Form B declaration dated 14* _day of November, 2018 is attributed to Sambireddy Vanga as managing partner and signatory; it includes declarations about title basis, encumbrances, fund handling, audit, approvals and allottee treatment. These are promoter declarations, not independent verification. Parties record
The RERA filing records the project as on-going and lists both original and revised proposed completion as 30/08/2020. The architect’s Form–1A extraction separately certifies overall completion and records the HMDA occupancy certificate for S+5 floors dated 14th Feb 2019. RERA filing RERA record
10. Approvals, official records & documents
| Record | Details | Source |
|---|---|---|
| TG-RERA registration | Form C; P02400000065; issued 11/12/2018, valid through 30/08/2020 | |
| HMDA technical approval | 002008/ZOA/R1/U6/HMDA/12072017, dated 31/08/2017; residential building, 1Stilt + 5 | |
| Architect’s overall-completion certificate | Form–1A extraction certifies overall completion; records S+5 floors and HMDA OC dated 14th Feb 2019 | |
| Occupancy certificate identifier recorded in Form–1A | 018055/Z0A/OC/U6/HMDA/06122018 | |
| Promoter declaration | Form B affidavit-cum-declaration attributed to SAMBIREDDY VANGA, managing partner/signatory |
The supplied material does not include a separately extracted building-plan drawing suitable for describing floor layouts. The HMDA technical-approval extraction states that building plans are to be sanctioned by the Narsingi Gram Panchayath Executive Authority in conformity with HMDA’s technically approved plans.
1. Project at a glance
Project identity
Registered project name: SREE NILAYAM
Project type / phase: Residential apartment project. Phase or separately registered portion is not disclosed.
TG-RERA registration: P02400000065
Registration validity: Issued 11/12/2018; valid through 30/08/2020. The certificate records no extension. This is the registration period, not the occupancy-certificate date.
Registered promoter: Forrtune Greenhomes; the project record identifies the promoter as a partnership.
RERA-recorded project status: On-Going Project in the supplied project record.
Land and geographic identity
Locality / revenue village: Narsingi; the approval document describes it as Narsingi-ORRGC.
Mandal / district / PIN: Gandipet / Ranga Reddy / 500089.
Project survey numbers: 300, 301, 302, 303, 306, 311, 313, 314, 315. The RERA certificate lists these individually; the HMDA technical approval groups them as 300 TO 303, 306 To 311, 313 To 315.
Plot numbers: 231, 232, 244 and 245.
Registered site extent: 1,421.20 Sq. Mt. in the HMDA technical-approval extraction. The RERA land record gives total and net area as 1421.20 sqmts.
Boundaries: East: 30 FEET WIDE ROAD; west: 60 FEET WIDE ROAD; north: PLOT NO 230 AND 246; south: PLOT NO 233 AND 243.
Development identity
Sanctioning / technical-approval authority: Hyderabad Metropolitan Development Authority (HMDA); the technical approval directs building plans to be sanctioned and released by the Narsingi Gram Panchayath Executive Authority.
Principal approval: HMDA Technical Approval 002008/ZOA/R1/U6/HMDA/12072017, dated 31/08/2017.
Approved built-up area: 2922.5 (as recorded in the project filing); the technical-approval extraction separately lists Built up Area: 2922.5.
Building count / configuration: 1 building; approved configuration 1Stilt + 5 floors.
Parking levels / provision: A stilt level is in the approved configuration. Parking-space counts and allocation details are not established in the supplied record.
Approved versus RERA-declared units: The filing records 1 total building unit; its unit schedule records 30 apartments: 25 2BHK and 5 3BHK. The supplied evidence does not explain the “building units” field as an apartment count.
Offering and status
Configurations: 2BHK and 3BHK.
RERA-filed saleable areas: 2BHK: 70.12 sqm; 3BHK: 84.86 sqm.
Booked / available: 2BHK: 25 booked / 0 available; 3BHK: 5 booked / 0 available. Counts are as last read from the TG-RERA portal; no as-of date is supplied, so they are indicative.
Construction stage: An architect’s Form–1A extraction certifies overall project completion and records an HMDA occupancy certificate for S+5 Floors, completed 14th Feb 2019. This is a document-based completion statement, not an independent site inspection.
Original / revised proposed completion: 30/08/2020 / 30/08/2020 in the project filing.
Occupancy-certificate record: The Form–1A extraction records HMDA OC 018055/Z0A/OC/U6/HMDA/06122018, dated 14th Feb 2019, for S+5 floors.
2. The project story
SREE NILAYAM is recorded with TG-RERA as a residential apartment project at Narsingi, Gandipet mandal, Ranga Reddy district, on plots 231, 232, 244 and 245 across the listed Narsingi survey numbers. The approved development is a single residential building configured as 1Stilt + 5 floors.
The RERA unit schedule lists 25 two-bedroom and 5 three-bedroom apartments. Its booking figures show all 30 as booked, with no units available in the portal snapshot; the snapshot has no stated as-of date.
The project record calls the project on-going and gives 30/08/2020 as both original and revised proposed completion date. Separately, the architect’s Form–1A extraction certifies overall completion and records an HMDA occupancy certificate for the S+5-floor building, dated 14th Feb 2019. These are distinct records: the filing’s status and completion dates do not themselves establish physical progress, while the Form–1A is an architect’s certification rather than an independent site verification.
3. Master plan, architecture & building design
The filed development is a single residential block on a recorded site extent of 1,421.20 Sq. Mt., with approved built-up area recorded as 2922.5. The HMDA technical-approval extraction describes a 1Stilt + 5 configuration and gives building height as 14.75; the supplied extraction does not state a measurement unit for that height.
The technical-approval extraction also lists Proposed Built-up Area: 3590.75, separately from Built up Area: 2922.5. The supplied evidence does not explain the basis or relationship between these figures; they are reported as separately labelled in that document, not treated as interchangeable area measures.
No usable measured floor-plan data is supplied: two drawing records are reported as having no flats, with 0 measured. Accordingly, the evidence here does not establish flat arrangements per floor, footprint, circulation, lifts, stairs, or internal common-area layout.
4. Homes, configurations & floor plans
The TG-RERA unit schedule records 30 apartments: 25 2BHK and 5 3BHK. The stated areas below are RERA-filed saleable areas, not carpet-area measurements.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 25 | 25 | 0 | 70.12 sqm | Not measured in supplied drawing data | Not supplied |
| 3BHK | 5 | 5 | 0 | 84.86 sqm | Not measured in supplied drawing data | Not supplied |
The booking and availability counts are portal figures without a supplied as-of date and should be treated as indicative. Floor-plan processing reports two drawings with no flats and zero measured, so there are no software-measured carpet or room dimensions available here.
5. Parking & vehicle circulation
The approved configuration includes a stilt level, but the supplied records do not establish the number of car or two-wheeler spaces, visitor or accessible provision, parking allocation to individual apartments, or the vehicle-entry and internal-driveway arrangement. The technical-approval extraction lists a transformer and garbage house, but does not specify parking quantities.
A stilt level in a plan does not, by itself, establish an apartment’s exclusive parking allocation. Confirm parking provision and any unit-specific entitlement from the approved plan and the buyer’s registered agreement.
6. Amenities, recreation & open spaces
The TG-RERA amenities record lists the following project facilities and infrastructure status. The supplied data gives percentages but no facility sizes, capacities, or independent completion verification.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Water Supply | No source, storage or capacity specified | TG-RERA amenities record | YES; 100% declared |
| Sewerage (Chamber, Lines, Septic Tank, STP) | No capacity or treatment details specified | TG-RERA amenities record | YES; 100% declared |
| Green Strip/TOT LOT/Park | No area or dimensions specified | TG-RERA amenities record | YES; 100% declared |
| Water Conservation, Rain water Harvesting | No system size or capacity specified | TG-RERA amenities record; HMDA technical-approval condition also calls for rainwater-harvesting structures | YES; 100% declared in amenities record |
| Energy management | No system or capacity specified | TG-RERA amenities record | YES; 100% declared |
| Electrical Meter Room, Sub-Station, Receiving Station | No capacity specified | TG-RERA amenities record | YES; 100% declared |
| Aggregate area of recreational Open Space | Area not supplied | TG-RERA amenities record | YES; 100% declared |
| Storm Water Drains | Details not supplied | TG-RERA amenities record | 0% recorded |
| Street Lighting | Details not supplied | TG-RERA amenities record | 0% recorded |
| Community Buildings | Details not supplied | TG-RERA amenities record | 0% recorded |
| Treatment and Disposal of Sewage and Sullage Water | Details not supplied | TG-RERA amenities record | 0% recorded |
| Solid Waste Management and Disposal | Details not supplied | TG-RERA amenities record | 0% recorded |
| Fire Protection and Fire Safety Requirements | Details not supplied | TG-RERA amenities record | 0% recorded |
| Internal Roads & Footpaths | Details not supplied | TG-RERA amenities record | 0% recorded |
7. Utilities, building services & safety
The TG-RERA amenities record marks water supply, sewerage, rainwater harvesting, energy management, and an electrical meter room/sub-station/receiving station as YES; 100%. It does not provide capacities or technical descriptions. HMDA’s technical-approval conditions require rainwater-harvesting structures and list a transformer and garbage house.
The same amenities record shows 0% for storm-water drains, treatment and disposal of sewage and sullage water, solid-waste management and disposal, and fire-protection and fire-safety requirements. The supplied evidence does not specify lift count or capacity, backup power, waste-segregation arrangements, security systems, accessible circulation, or fire-system details.
8. Location, access & connectivity
The registered project location is Narsingi, Narsingi revenue village, Gandipet mandal, Ranga Reddy district, PIN 500089. The filed site boundaries identify a 30 FEET WIDE ROAD on the east and a 60 FEET WIDE ROAD on the west.
The supplied location record lists the Financial District (Nanakramguda) at 2.2 km, ICICI Bank at 1.6 km, Holy Mary College at 2.1 km, Sankaraya Eye Hospital at 0.6 km, Microchip Hyderabad at 1.7 km, an unnamed park at 0.1 km, and an unnamed school at 1.4 km. These are recorded distances; no travel times or public-transport details are supplied.
9. Developer & development status
The registered promoter is Forrtune Greenhomes, identified in the project record as a partnership. The promoter’s recorded office address is TULASIS LAKSHMI NILAYAM, SANSKRUTHI TOWNSHIP, Narsingi, Narsingi, Gandipet, Ranga Reddy, 500089. The registration certificate gives the promoter office as Village: Neknapur, Mandal: Gandipet, District: Ranga Reddy, Pin: 500089.
The supplied records identify SAMBIREDDY VANGA as a partner and SURESH VENKATA SOMISETTY as an authorized signatory. A Form B declaration dated 14* _day of November, 2018 is attributed to Sambireddy Vanga as managing partner and signatory; it includes declarations about title basis, encumbrances, fund handling, audit, approvals and allottee treatment. These are promoter declarations, not independent verification.
The RERA filing records the project as on-going and lists both original and revised proposed completion as 30/08/2020. The architect’s Form–1A extraction separately certifies overall completion and records the HMDA occupancy certificate for S+5 floors dated 14th Feb 2019.
10. Approvals, official records & documents
| Record | Details | Source |
|---|---|---|
| TG-RERA registration | Form C; P02400000065; issued 11/12/2018, valid through 30/08/2020 | |
| HMDA technical approval | 002008/ZOA/R1/U6/HMDA/12072017, dated 31/08/2017; residential building, 1Stilt + 5 | |
| Architect’s overall-completion certificate | Form–1A extraction certifies overall completion; records S+5 floors and HMDA OC dated 14th Feb 2019 | |
| Occupancy certificate identifier recorded in Form–1A | 018055/Z0A/OC/U6/HMDA/06122018 | |
| Promoter declaration | Form B affidavit-cum-declaration attributed to SAMBIREDDY VANGA, managing partner/signatory |
The supplied material does not include a separately extracted building-plan drawing suitable for describing floor layouts. The HMDA technical-approval extraction states that building plans are to be sanctioned by the Narsingi Gram Panchayath Executive Authority in conformity with HMDA’s technically approved plans.
Frequently asked questions
Is SREE NILAYAM registered with Telangana RERA?
Yes. SREE NILAYAM is registered with the Telangana Real Estate Regulatory Authority as P02400000065; the registration status is On-Going Project.
Who is the developer of SREE NILAYAM?
The promoter named in the RERA registration is FORRTUNE GREENHOMES.
Where is SREE NILAYAM located?
SREE NILAYAM is in Narsingi, Gandipet, Rangareddy, Telangana (500089).
When will SREE NILAYAM be completed?
The promoter's proposed date of completion filed with RERA is 30/08/2020. This is the promoter's declaration, not a guarantee.
More projects in Narsingi