SIKHARA ASTER is a residential apartment project on Plot No. 49 in Ameenpur, Ameenpur mandal, Sangareddy district. The registered promoter is SIKHARA INFRACON, recorded as a partnership. The project covers 335.26 Sq. Mt. and comprises 1 building with 1 Stilt + 5 upper floors and 10 units: 9 2BHK and 1 3BHK. Its TG-RERA registration number is P01100010204, and the proposed completion date is 16/02/2027.

More from Sikhara Infracon · 7 projects →

01What we found

Period endedTG-RERA registration ran to 16 Oct 2026 - check its extension on TG-RERA
18documents on file - each fact links to its page
0court cases on this project's land in the court records searched
8items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

8 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

ItemProject record
Registered name and typeSIKHARA ASTER — residential apartment project. RERA record
Phase / registered portionNo separate TG-RERA phase name is stated. The registration covers the project on Plot No. 49; the filed plan identifies the site as Sai Rajeswari (Phase-II). RERA record
TG-RERA registrationP01100010204, valid from 16/10/2024 to 16/10/2026. This is registration validity, not the project completion deadline. RERA record
Registered promoterSIKHARA INFRACON, recorded as a partnership. RERA record Corporate record
RERA status in supplied recordNew Project; registration certificate on file. Registration was captured on 2026-09-10. RERA record Approvals record

Land and geographic identity

ItemProject record
Locality / sitePlot No. 49, Ameenpur; plan record also names Sai Rajeswari (Phase-II).
Revenue villageAMEENAPUR (also rendered “Ameenpur” / “AMEENPUR VILLAGE” in approval documents).
Mandal / district / PINAMEENPUR, Sangareddy, 502032.
Project survey numbers and subdivisions109/P and 110/P. The filing does not identify a further subdivision beyond “/P”.
Registered site extent335.26 Sq. Mt.; the filed plan records both minimum plot area and net plot area as 335.26.
Boundaries in RERA filingNorth: Plot No. 48; South: Plot No. 50; East: Plot No. 58; West: Road. RERA filing

Development identity

ItemProject record
Sanctioning authority / principal approvalHyderabad Metropolitan Development Authority (HMDA) technical building-construction approval, 008379/BP/HMDA/2091/SKP/2024, dated 16 October 2024; the permit order is issued through Ameenpur Municipality / Municipal Corporation. Approvals record
Approved built-up area1,157.40 sq. m. total built-up area in the sanction extract. The filed drawing separately states 957.00 as net BUA and 1,148.40 as proposed BUA including parking.
Buildings / floors1 building; sanctioned configuration 1 Stilt + 5 upper floors, with the filed drawing describing the five upper floors as 4 upper floors + 1 TDR floor. Height recorded in the plan: 14.99 MT. RERA filing
Parking levelStilt floor is designated for parking in the filed plan. No basement or podium parking level is stated.
Unit count10 units in the filed plan and RERA unit record. RERA unit table
Occupancy / completion certificateNo occupancy or completion certificate is supplied; the building permit requires an occupancy certificate before occupation.

Offering and status

ItemProject record
RERA-filed configurations2BHK: 9 units; 3BHK: 1 unit. RERA unit table
RERA-filed saleable area109.16 sq. m. for each listed configuration. RERA unit table
Booked / availablePortal figures last read show 0 booked and 9 available for 2BHK, and 0 booked and 1 available for 3BHK. The portal record has no as-of date, so these counts are indicative. RERA unit table
Completion deadlineThe RERA project header states 16/02/2027 as proposed completion. A Form-B declaration dated 27' day of October, 2025 instead states completion by 16/10/2026. RERA record
Construction stageThe supplied evidence does not establish a verified on-site construction stage. The portal amenity/infrastructure progress entries shown are 0%; these are filing figures, not independent site verification. RERA amenities
Mortgage-related unit restrictionThe building approval records 10.00% of built-up area, including 108.06 sq. m. on the first floor, mortgaged to HMDA; the approval says mortgaged flats are not to be sold and the mortgaged area may be registered only after an occupancy certificate.

2. The project story

SIKHARA ASTER is a single-building residential apartment project on Plot No. 49 in Ameenapur revenue village, Ameenpur mandal, Sangareddy district, covering Survey Nos. 109/P and 110/P. The site extent recorded in the filed plan is 335.26 (Sq. Mt. in the building-approval extract). The proposed building is a stilt-and-five-upper-floor structure, with residential use and 10 units in the RERA record. RERA unit table

The RERA filing records nine 2BHK units and one 3BHK unit. The available portal counts indicate all ten units as available when read, but the record has no as-of date. No verified construction-progress report or occupancy certificate is supplied here; therefore the building’s physical completion and present site stage cannot be confirmed from this evidence. The proposed completion date in the header and the completion date in the Form-B declaration are recorded separately above. RERA unit table RERA amenities RERA record

3. Master plan, architecture & building design

The filed plan depicts one residential building on a 335.26 plot, with a 1 Stilt + 5 upper floors configuration. It labels the floors as stilt plus four upper floors and one TDR floor, and records a building height of 14.99 MT. The plan extract states 957.00 as net BUA, 1,148.40 as proposed BUA including parking, and 1,157.40 as total BUA. These are distinct drawing figures; the supplied record does not provide a separate FSI-counted area or carpet-area total for the whole building.

The HMDA approval extract also records 1,157.40 sq. m. total built-up area and identifies a 10.00% built-up-area mortgage to HMDA, including 108.06 sq. m. on the first floor. The stilt is designated for parking; the plan also identifies a lift measuring 1.5 × 2.5M and 1.00M WIDE GREENERY. The supplied drawing-derived material does not establish flat distribution by floor, number of stairs or lifts beyond the listed lift, or a detailed internal circulation arrangement.

4. Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK909109.16 sq. m.Software-measured: median 66.3 sq. m.; range 61.6–68.2 sq. m.39%
3BHK101109.16 sq. m.Not suppliedNot supplied

RERA unit counts, booking figures and saleable areas come from the project filing; booking figures have no stated as-of date. The 2BHK carpet measurements are software measurements from the filed floor-plan drawing, not RERA disclosures, and are flagged for review in the supplied measurement record. Carpet area describes the measured internal unit area; saleable area is a different filed figure and may include the unit’s share of common areas. The supplied measurement record excludes the drawn balcony from carpet area. RERA unit table RERA unit details Floor plans

One measured 2BHK drawing labels a living/dining area (4.63 × 4.08 m), kitchen (2.8 × 2.58 m), wash area (1.2 × 2.58 m), two bedrooms (3.6 × 3.0 m and 4.0 × 3.0 m), a toilet (2.0 × 1.5 m) and a balcony. These are drawing-based measurements and labels, not separately stated RERA room-area disclosures. RERA unit details

5. Parking & vehicle circulation

The plan designates the stilt floor for parking and states that it must be used for parking only. The building-approval extract also says parking or construction is not permitted in setback areas. The supplied evidence does not establish a sanctioned parking-space count, visitor or accessible parking allocation, a parking allotment for any specific unit, or an exclusive ownership right in any drawn bay.

The approval documents list electric-vehicle charging infrastructure for the project. No details are supplied on the number or location of charging points, parking circulation, ramps, vehicle entry/exit arrangements, or separation of pedestrian and vehicle routes.

6. Amenities, recreation & open spaces

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Green strip1.00M WIDE GREENERY in the filed planPlan-listed; completion not verified
Green strip / tot lot / parkListed as available “YES” in the amenity recordRERA amenitiesProgress recorded as 0%; not independently verified
Rainwater harvestingRainwater-harvesting structures listed in the approval and planRequired/listed; completion not verified
Indoor / recreation facilitiesNo TG-RERA-filed clubhouse, indoor-games facility or sports facility is identified in the supplied project amenity recordRERA amenitiesNot established in the supplied RERA record
Community buildingsListed in the amenity recordRERA amenitiesProgress recorded as 0%; not independently verified

The vendor record lists kids’ play areas/sand pits, yoga areas, jogging/cycle track, indoor games and a park/central green. These are vendor-listed features rather than facilities established by the supplied sanctioned-plan or RERA amenity evidence. Promoter website

7. Utilities, building services & safety

The approval and plan records list an STP, septic tank, rainwater harvesting, transformer, garbage house and underground and terrace water tanks, each stated as 25,000 lts. in the HMDA approval extract. The plan also lists a sump and underground drainage. The approval records dual piping and electric-vehicle charging infrastructure. These are approval/document-listed provisions; no evidence supplied here confirms installation, operating status, or service capacity beyond the stated tank capacities.

The Ameenpur building-permit extract lists fire-fighting installations, a generator, emergency lighting, hose reel, down corner and an automatic sprinkler system. It also requires a fire-safety and structural-safety responsibility and states that an occupancy certificate is required before occupation. These approval conditions and listed systems do not, by themselves, establish that the systems have been completed or tested.

The filed drawing identifies one lift measuring 1.5 × 2.5M. The supplied material does not state lift capacity, backup duration, CCTV installation status, access-control arrangements, waste segregation arrangements, or accessible-ramp provision.

8. Location, access & connectivity

The registered site location is Plot No. 49, revenue village AMEENAPUR, mandal AMEENPUR, Sangareddy district, PIN 502032, in Survey Nos. 109/P and 110/P. The project filing gives the plot boundaries as Plot No. 48 to the north, Plot No. 50 to the south, Plot No. 58 to the east and a road to the west. RERA filing

The approval material refers to a minimum approach-road width as indicated in the plan; the filed drawing labels a 12.00 MT WIDE EXISTING road and a 12.00 MT WIDE PROPOSED ROAD. The HMDA approval also requires formation of a BT/CC road before release of the occupancy certificate.

A location record gives the nearest sampled Outer Ring Road interchange as approximately 7.0 km. This is a location-data estimate, not a promoter travel-time statement. No public-transport details or additional independently sourced landmark distances are provided in the supplied location record. Location record

9. Developer & development status

The registered promoter is SIKHARA INFRACON, recorded as a partnership, with GSTIN 36AENFS4605N1ZG. Its RERA-recorded address is SAI AMBIKA PHASE 2, PNR COLONY, AMEENPUR, AMEENPUR, AMEENPUR, Sangareddy, 502032. The project filing identifies Rajesh Nangineni as authorized signatory and Deepthi Nangineni as partner. Corporate record Parties record RERA filing

A Form-B declaration signed by Rajesh Nangineni states that the project would be completed by 16/10/2026; the project header separately records proposed completion as 16/02/2027. No independent site-progress verification or occupancy certificate is supplied here. RERA record

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / scopeSIKHARA ASTER; P01100010204; registration period 16/10/2024–16/10/2026
Building-construction technical approval
Identifier / scopeHMDA approval 008379/BP/HMDA/2091/SKP/2024, dated 16 October 2024; one residential building, Plot No. 49, Survey Nos. 109/P and 110/P
Building permit order
Identifier / scopeAmeenpur Municipality / Municipal Corporation order using approval number 008379/BP/HMDA/2091/SKP/ 2024, dated 16 October 2024
Building plan
Identifier / scopeProposed apartment plan for Plot No. 49, Survey Nos. 109/P and 110/P; plan extract identifies HMDA and file no. TS/038990/2024
Form-B declaration
Identifier / scopePromoter declaration concerning the project, dated 27' day of October, 2025
Occupancy / completion certificate
Identifier / scopeNone supplied in the reviewed evidence. The permit documents require an occupancy certificate before occupation.

Frequently asked questions

Is SIKHARA ASTER registered with Telangana RERA?

Yes. SIKHARA ASTER is registered with the Telangana Real Estate Regulatory Authority as P01100010204; the registration status is New Project.

Who is the developer of SIKHARA ASTER?

The promoter named in the RERA registration is SIKHARA INFRACON.

Where is SIKHARA ASTER located?

SIKHARA ASTER is in AMEENPUR, AMEENAPUR, Sangareddy, Telangana (502032).

When will SIKHARA ASTER be completed?

The promoter's proposed date of completion filed with RERA is 16/02/2027. This is the promoter's declaration, not a guarantee.