AADYA ONE is a residential apartment project in Ameenapur, AMEENPUR mandal, Sangareddy district, developed by the registered promoter AADYA DEVELOPERS. It is on a 576.00 sq.m site and comprises one residential building with 1 stilt + 5 upper floors and 21 2BHK apartments, each with a saleable area of 45.1 sq.m. The project is registered under TG-RERA registration P01100007961, with a proposed completion date of 30-3-2025.
More from Aadya Developers · 2 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
9 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Record |
|---|---|
| Registered project name | AADYA ONE RERA record |
| Project type / status | Residential apartment project; recorded as “New Project” RERA record RERA filing |
| Phase / registered portion | Phase is not separately identified in the supplied record. The registered development is described as one residential building RERA record |
| TG-RERA registration | P01100007961 RERA record |
| Registration validity | 24/03/2024 to 30/03/2025, unless extended by the Authority |
| Registered promoter | AADYA DEVELOPERS RERA record Corporate record |
| RERA status | Registration certificate is on file; the supplied evidence does not establish whether the registration was extended |
Land and geographic identity
| Item | Record |
|---|---|
| Locality / revenue village | Ameenpur / AMEENAPUR; the building-permit record also uses “AMEENPUR” RERA record RERA filing |
| Mandal / district / PIN | AMEENPUR mandal; Sangareddy district; 502032 RERA record RERA filing |
| Project survey numbers | Survey Nos. 107 and 108 RERA record Land records |
| Plot numbers identified in approval records | 385/Part, 386, 387/Part, 388, 389/Part, 402/Part and 403 |
| Project site extent | 576.00 sq.m Land records |
| Net / total area in RERA land details | Net area 576.00 sq.m; total area 576 sq.m; affected area shown as 0 sq.m Land records |
| Boundaries | East: 30ft Wide road; west: 40ft Wide road; north: Plot no 389P and Plot no 402P; south: Plot no 385P 386P 387P Land records |
Development identity
| Item | Record |
|---|---|
| Sanctioning / planning authorities | HMDA issued technical approval; Ameenpur Municipality issued the building G Permit Order |
| Principal building approval | HMDA technical approval 045389/SKP/R1/U6/HMDA/22042021, dated 04/01/2022; municipal building-permit order dated 31 03 2022 |
| Approved building configuration | 1 stilt + 5 upper floors |
| Building count | One residential building is recorded in the RERA land details RERA filing |
| Approved built-up area | 1439.19 sq.m (proposed net BUA in the HMDA-filed plan); the municipal permit records upper-floor area of 1439.19 m2 |
| Other area figures in approval records | Proposed coverage area: 284.73 sq.m (49.43%); HMDA technical approval records total built-up area 1714.52 sq.m, including mortgage areas |
| Parking provision | Parking is identified in the approval documents; the municipal order says cellar and stilt approved for parking. A count of spaces is not supplied |
| Unit count | RERA-filed: 21 units, all recorded as 2BHK RERA unit table RERA unit details |
Offering and status
| Item | Record |
|---|---|
| Configuration and RERA saleable area | 2BHK; 45.1 sq.m per unit RERA unit table RERA unit details |
| Booked / available | 0 booked; 21 available, as last read from the TG-RERA portal; no portal as-of date is supplied, so counts are indicative RERA unit table |
| Promoter’s filed completion undertaking | 30-3-2025 |
| Occupancy certificate | HMDA OC 007763/OC/HMDA/SKP/2025, dated 04 April, 2025; the certificate identifies the residential apartment in Survey Nos. 107 and 108 |
| Construction stage / completion evidence | An architect’s Form 1A states development work is complete; HMDA’s OC records the building as fit for occupation. These records indicate completion and occupancy certification for the identified building, not independent site verification by this report |
2. The project story
- AADYA ONE is recorded with TG-RERA as a residential apartment project on a 576.00 sq.m site in Ameenapur village, Ameenpur mandal, Sangareddy district. The registered land identity names Survey Nos. 107 and 108; building-approval documents further identify the site through plot numbers 385/Part, 386, 387/Part, 388, 389/Part, 402/Part and 403. RERA record Land records
- The filed and approved development is one residential building with a stilt and five upper floors. The RERA unit record lists 21 two-bedroom apartments, with a filed saleable area of 45.1 sq.m each. The portal’s booking figures show 0 booked and 21 available, but no “as of” date is attached to that snapshot. RERA filing RERA unit table RERA unit details
- The promoter’s Form B affidavit undertook completion by 30-3-2025. The supplied architect’s certificate and HMDA occupancy certificate are dated after that undertaking and record completed development and an OC for the building. Those documents are completion/authority records; they do not constitute an independent physical inspection for this report.
3. Master plan, architecture & building design
- The HMDA-filed plan describes a residential apartment building on a 576.00 sq.m site, with 1 stilt + 5 upper floors. It records proposed coverage of 284.73 sq.m (49.43%) and proposed net built-up area of 1439.19 sq.m. HMDA’s technical-approval record separately lists total built-up area of 1714.52 sq.m, including a 149.40 sq.m mortgage area and a 73.63 sq.m additional mortgage area. These figures are reported under the labels used in the respective approval records; they are not interchangeable area measures.
- The municipal permit identifies a cellar as well as stilt and five upper floors, and states that cellar and stilt are approved for vehicle parking. The occupancy certificate describes the building as “Cellar Ground Stilt 5 Upper Floor.” The supplied material does not provide a complete architectural drawing set or enough detail to establish the floor-by-floor arrangement, footprint layout, flat count per floor, lift/stair configuration, entrances, or residential-to-common-area breakdown.
- The RERA record identifies one building. No approved site-plan detail establishing internal roads, landscape-area dimensions, or the arrangement of open spaces is supplied. The occupancy certificate lists tot-lot area as 0 m2. RERA filing
4. Homes, configurations & floor plans
The RERA filing lists 21 two-bedroom apartments, each with a saleable area of 45.1 sq.m. Booked and available figures are the portal snapshot supplied with the record and carry no as-of date. RERA unit table RERA unit details
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 21 | 0 | 21 | 45.1 sq.m | Not measured | Not supplied |
The floor-plan dataset contains two drawings, both still pending scan; no software-measured carpet or room dimensions are available. Saleable area is the RERA-filed unit figure. It should not be treated as carpet area: the supplied methodology notes that saleable area also includes a share of common areas, while carpet area is measured from the unit drawing geometry. Floor plans RERA unit details
5. Parking & vehicle circulation
- The filed plan identifies parking, and the Ameenpur Municipality order states that cellar and stilt areas approved for parking must be used exclusively for vehicles. The plan records proposed coverage of 284.73 sq.m, but no number of car or two-wheeler spaces, visitor or accessible spaces, or individual unit parking allocations is supplied. A drawn or sanctioned parking area does not, by itself, establish exclusive ownership or allotment to a particular apartment.
- The municipal order requires one entry and one exit, with a minimum width of 4.5mts. and height clearance of 5mts. The supplied evidence does not establish the final as-built vehicle circulation arrangement, ramp configuration, pedestrian separation, mechanical parking, or EV charging.
6. Amenities, recreation & open spaces
The RERA amenity record marks water supply, sewerage, green strip/tot lot/park, electrical meter room/sub-station/receiving station, and aggregate recreational open space as available; the same record shows progress figures of 0% for the listed amenities. These are filed portal entries, not verification that the facilities are physically complete. RERA amenities
| Description / size | RERA amenity record says available; municipal permit requires a fenced tot-lot maintained as greenery. OC lists tot-lot area as 0 m2. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA progress shown as 0%; physical delivery not independently verified |
| Description / size | Marked available in the RERA amenity record; no area supplied. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress shown as 0%; not independently verified |
| Description / size | Listed in the RERA amenity record; no dimensions supplied. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress shown as 0%; not independently verified |
| Description / size | Listed in the RERA amenity record; no facility or size specified. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress shown as 0%; not independently verified |
No clubhouse, indoor recreation facility, or sports facility is specified in the supplied RERA amenity data. Vendor-listed facilities are not treated here as RERA-declared or sanctioned amenities. RERA amenities Promoter website
7. Utilities, building services & safety
- The approval records identify a water pipeline and existing drainage line, and the HMDA application/intimation calls for an STP and septic tank. The Ameenpur Municipality permit also requires a rainwater-harvesting structure (percolation pit) and records 10 RWHPs. The occupancy certificate lists rainwater harvesting. These are records of stated requirements or entries; the supplied evidence does not establish utility capacities or independently verify operational status.
- The municipal permit specifies a generator as an alternate electricity source, emergency lighting in corridors/common passages and staircases, a transformer space, fire-safety equipment and systems, and separate underground and terrace water tanks of 25,000 litres each. It also specifies a hose reel and down corner, and an automatic sprinkler system if the basement area exceeds 200 Sq.mts. The records do not establish which systems have been installed or tested.
- A lift is listed in the plan’s amenities/utilities; no lift count, capacity, or service-lift provision is given. The approvals require fire-safety measures and emergency arrangements, but no supplied evidence establishes an independent fire-compliance inspection or current operational status.
8. Location, access & connectivity
- The project’s registered location is AMEENAPUR, AMEENPUR, Sangareddy, 502032. The RERA land record gives the site boundaries as a 30ft Wide road to the east and a 40ft Wide road to the west. Approval records also refer to plot numbers 385/Part, 386, 387/Part, 388, 389/Part, 402/Part and 403 within Survey Nos. 107 and 108. Land records
- A cadastral-parcel centroid is supplied at 17.536212311093237, 78.32977092678605. The nearest sampled Outer Ring Road interchange is recorded at 7.4 km (approx). The evidence does not provide verified public-transport routes, further measured landmark distances, or travel times. Location record Cadastral map
9. Developer & development status
- The registered promoter is AADYA DEVELOPERS, recorded as a partnership, with GSTIN 36ABPFM9604E1Z0. The supplied corporate record gives the promoter’s address as “na, Malakpet gunj road, Ameenpur, Ameenpur, AMEENPUR, Sangareddy, 502032.” An entity registration number and official contact details are not supplied here. Corporate record Parties record
- The promoter’s Form B affidavit, dated December 2023, states that the project would be completed by 30-3-2025 and includes declarations concerning title, encumbrances, approvals and the separate account. The RERA certificate records registration validity through 30/03/2025; the supplied data does not establish an extension. The architect’s completion certificate and HMDA OC record completion/occupancy for the identified building, with the OC dated 04 April, 2025.
10. Approvals, official records & documents
| Identifier / date | P01100007961; valid 24/03/2024–30/03/2025 |
|---|---|
| Scope and evidence | Form C certificate for AADYA ONE and Aadya Developers |
| Identifier / date | 045389/SKP/R1/U6/HMDA/22042021; 04/01/2022 |
|---|---|
| Scope and evidence | Residential building, 1 stilt + 5 upper floors; Survey Nos. 107 and 108 |
| Identifier / date | Approval no. SANSXPR AJGMMOA20(2021); approved date recorded as 04/17/2022 |
|---|---|
| Scope and evidence | Plan identifies residential building, 576.00 sq.m site and 1 stilt + 5 upper floors |
| Identifier / date | Application no. 199/2022; order dated 31 03 2022 |
|---|---|
| Scope and evidence | G Permit Order for the building on Survey Nos. 107, 108 and the listed plot portions |
| Identifier / date | 007763/OC/HMDA/SKP/2025; 04 April, 2025 |
|---|---|
| Scope and evidence | OC for the residential apartment in Survey Nos. 107 and 108; identifies a cellar, ground, stilt and five upper floors |
| Identifier / date | Form 1A; OC number recorded as 007 7 63 I OCIH M DA I SKP I 2O2s, dated 04.04.2025 |
|---|---|
| Scope and evidence | Architect’s certificate states completion of development work for AADYA ONE and cites HMDA occupancy certification |
| Identifier / date | Form B; December 2023 |
|---|---|
| Scope and evidence | Promoter declaration includes the 30-3-2025 completion undertaking |
The supplied documents include the registration certificate, technical approval, building permit, architect’s completion certificate and occupancy certificate. A separate approved-layout certificate or complete set of architectural drawings is not established by the materials summarized here; the HMDA-filed plan document and its stated building particulars are listed above. Document index
1. Project at a glance
Project identity
Registered project name: AADYA ONE
Project type / status: Residential apartment project; recorded as “New Project”
Phase / registered portion: Phase is not separately identified in the supplied record. The registered development is described as one residential building
TG-RERA registration: P01100007961
Registration validity: 24/03/2024 to 30/03/2025, unless extended by the Authority
Registered promoter: AADYA DEVELOPERS
RERA status: Registration certificate is on file; the supplied evidence does not establish whether the registration was extended
Land and geographic identity
Locality / revenue village: Ameenpur / AMEENAPUR; the building-permit record also uses “AMEENPUR”
Mandal / district / PIN: AMEENPUR mandal; Sangareddy district; 502032
Project survey numbers: Survey Nos. 107 and 108
Plot numbers identified in approval records: 385/Part, 386, 387/Part, 388, 389/Part, 402/Part and 403
Project site extent: 576.00 sq.m
Net / total area in RERA land details: Net area 576.00 sq.m; total area 576 sq.m; affected area shown as 0 sq.m
Boundaries: East: 30ft Wide road; west: 40ft Wide road; north: Plot no 389P and Plot no 402P; south: Plot no 385P 386P 387P
Development identity
Sanctioning / planning authorities: HMDA issued technical approval; Ameenpur Municipality issued the building G Permit Order
Principal building approval: HMDA technical approval 045389/SKP/R1/U6/HMDA/22042021, dated 04/01/2022; municipal building-permit order dated 31 03 2022
Approved building configuration: 1 stilt + 5 upper floors
Building count: One residential building is recorded in the RERA land details
Approved built-up area: 1439.19 sq.m (proposed net BUA in the HMDA-filed plan); the municipal permit records upper-floor area of 1439.19 m2
Other area figures in approval records: Proposed coverage area: 284.73 sq.m (49.43%); HMDA technical approval records total built-up area 1714.52 sq.m, including mortgage areas
Parking provision: Parking is identified in the approval documents; the municipal order says cellar and stilt approved for parking. A count of spaces is not supplied
Unit count: RERA-filed: 21 units, all recorded as 2BHK
Offering and status
Configuration and RERA saleable area: 2BHK; 45.1 sq.m per unit
Booked / available: 0 booked; 21 available, as last read from the TG-RERA portal; no portal as-of date is supplied, so counts are indicative
Promoter’s filed completion undertaking: 30-3-2025
Occupancy certificate: HMDA OC 007763/OC/HMDA/SKP/2025, dated 04 April, 2025; the certificate identifies the residential apartment in Survey Nos. 107 and 108
Construction stage / completion evidence: An architect’s Form 1A states development work is complete; HMDA’s OC records the building as fit for occupation. These records indicate completion and occupancy certification for the identified building, not independent site verification by this report
2. The project story
- AADYA ONE is recorded with TG-RERA as a residential apartment project on a 576.00 sq.m site in Ameenapur village, Ameenpur mandal, Sangareddy district. The registered land identity names Survey Nos. 107 and 108; building-approval documents further identify the site through plot numbers 385/Part, 386, 387/Part, 388, 389/Part, 402/Part and 403.
- The filed and approved development is one residential building with a stilt and five upper floors. The RERA unit record lists 21 two-bedroom apartments, with a filed saleable area of 45.1 sq.m each. The portal’s booking figures show 0 booked and 21 available, but no “as of” date is attached to that snapshot.
- The promoter’s Form B affidavit undertook completion by 30-3-2025. The supplied architect’s certificate and HMDA occupancy certificate are dated after that undertaking and record completed development and an OC for the building. Those documents are completion/authority records; they do not constitute an independent physical inspection for this report.
3. Master plan, architecture & building design
- The HMDA-filed plan describes a residential apartment building on a 576.00 sq.m site, with 1 stilt + 5 upper floors. It records proposed coverage of 284.73 sq.m (49.43%) and proposed net built-up area of 1439.19 sq.m. HMDA’s technical-approval record separately lists total built-up area of 1714.52 sq.m, including a 149.40 sq.m mortgage area and a 73.63 sq.m additional mortgage area. These figures are reported under the labels used in the respective approval records; they are not interchangeable area measures.
- The municipal permit identifies a cellar as well as stilt and five upper floors, and states that cellar and stilt are approved for vehicle parking. The occupancy certificate describes the building as “Cellar Ground Stilt 5 Upper Floor.” The supplied material does not provide a complete architectural drawing set or enough detail to establish the floor-by-floor arrangement, footprint layout, flat count per floor, lift/stair configuration, entrances, or residential-to-common-area breakdown.
- The RERA record identifies one building. No approved site-plan detail establishing internal roads, landscape-area dimensions, or the arrangement of open spaces is supplied. The occupancy certificate lists tot-lot area as 0 m2.
4. Homes, configurations & floor plans
The RERA filing lists 21 two-bedroom apartments, each with a saleable area of 45.1 sq.m. Booked and available figures are the portal snapshot supplied with the record and carry no as-of date.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 21 | 0 | 21 | 45.1 sq.m | Not measured | Not supplied |
The floor-plan dataset contains two drawings, both still pending scan; no software-measured carpet or room dimensions are available. Saleable area is the RERA-filed unit figure. It should not be treated as carpet area: the supplied methodology notes that saleable area also includes a share of common areas, while carpet area is measured from the unit drawing geometry.
5. Parking & vehicle circulation
- The filed plan identifies parking, and the Ameenpur Municipality order states that cellar and stilt areas approved for parking must be used exclusively for vehicles. The plan records proposed coverage of 284.73 sq.m, but no number of car or two-wheeler spaces, visitor or accessible spaces, or individual unit parking allocations is supplied. A drawn or sanctioned parking area does not, by itself, establish exclusive ownership or allotment to a particular apartment.
- The municipal order requires one entry and one exit, with a minimum width of 4.5mts. and height clearance of 5mts. The supplied evidence does not establish the final as-built vehicle circulation arrangement, ramp configuration, pedestrian separation, mechanical parking, or EV charging.
6. Amenities, recreation & open spaces
The RERA amenity record marks water supply, sewerage, green strip/tot lot/park, electrical meter room/sub-station/receiving station, and aggregate recreational open space as available; the same record shows progress figures of 0% for the listed amenities. These are filed portal entries, not verification that the facilities are physically complete.
| Description / size | RERA amenity record says available; municipal permit requires a fenced tot-lot maintained as greenery. OC lists tot-lot area as 0 m2. |
|---|---|
| Declared progress / verified status | RERA progress shown as 0%; physical delivery not independently verified |
| Description / size | Marked available in the RERA amenity record; no area supplied. |
|---|---|
| Declared progress / verified status | Progress shown as 0%; not independently verified |
| Description / size | Listed in the RERA amenity record; no dimensions supplied. |
|---|---|
| Declared progress / verified status | Progress shown as 0%; not independently verified |
| Description / size | Listed in the RERA amenity record; no facility or size specified. |
|---|---|
| Declared progress / verified status | Progress shown as 0%; not independently verified |
No clubhouse, indoor recreation facility, or sports facility is specified in the supplied RERA amenity data. Vendor-listed facilities are not treated here as RERA-declared or sanctioned amenities.
7. Utilities, building services & safety
- The approval records identify a water pipeline and existing drainage line, and the HMDA application/intimation calls for an STP and septic tank. The Ameenpur Municipality permit also requires a rainwater-harvesting structure (percolation pit) and records 10 RWHPs. The occupancy certificate lists rainwater harvesting. These are records of stated requirements or entries; the supplied evidence does not establish utility capacities or independently verify operational status.
- The municipal permit specifies a generator as an alternate electricity source, emergency lighting in corridors/common passages and staircases, a transformer space, fire-safety equipment and systems, and separate underground and terrace water tanks of 25,000 litres each. It also specifies a hose reel and down corner, and an automatic sprinkler system if the basement area exceeds 200 Sq.mts. The records do not establish which systems have been installed or tested.
- A lift is listed in the plan’s amenities/utilities; no lift count, capacity, or service-lift provision is given. The approvals require fire-safety measures and emergency arrangements, but no supplied evidence establishes an independent fire-compliance inspection or current operational status.
8. Location, access & connectivity
- The project’s registered location is AMEENAPUR, AMEENPUR, Sangareddy, 502032. The RERA land record gives the site boundaries as a 30ft Wide road to the east and a 40ft Wide road to the west. Approval records also refer to plot numbers 385/Part, 386, 387/Part, 388, 389/Part, 402/Part and 403 within Survey Nos. 107 and 108.
- A cadastral-parcel centroid is supplied at 17.536212311093237, 78.32977092678605. The nearest sampled Outer Ring Road interchange is recorded at 7.4 km (approx). The evidence does not provide verified public-transport routes, further measured landmark distances, or travel times.
9. Developer & development status
- The registered promoter is AADYA DEVELOPERS, recorded as a partnership, with GSTIN 36ABPFM9604E1Z0. The supplied corporate record gives the promoter’s address as “na, Malakpet gunj road, Ameenpur, Ameenpur, AMEENPUR, Sangareddy, 502032.” An entity registration number and official contact details are not supplied here.
- The promoter’s Form B affidavit, dated December 2023, states that the project would be completed by 30-3-2025 and includes declarations concerning title, encumbrances, approvals and the separate account. The RERA certificate records registration validity through 30/03/2025; the supplied data does not establish an extension. The architect’s completion certificate and HMDA OC record completion/occupancy for the identified building, with the OC dated 04 April, 2025.
10. Approvals, official records & documents
| Identifier / date | P01100007961; valid 24/03/2024–30/03/2025 |
|---|---|
| Scope and evidence | Form C certificate for AADYA ONE and Aadya Developers |
| Identifier / date | 045389/SKP/R1/U6/HMDA/22042021; 04/01/2022 |
|---|---|
| Scope and evidence | Residential building, 1 stilt + 5 upper floors; Survey Nos. 107 and 108 |
| Identifier / date | Approval no. SANSXPR AJGMMOA20(2021); approved date recorded as 04/17/2022 |
|---|---|
| Scope and evidence | Plan identifies residential building, 576.00 sq.m site and 1 stilt + 5 upper floors |
| Identifier / date | Application no. 199/2022; order dated 31 03 2022 |
|---|---|
| Scope and evidence | G Permit Order for the building on Survey Nos. 107, 108 and the listed plot portions |
| Identifier / date | 007763/OC/HMDA/SKP/2025; 04 April, 2025 |
|---|---|
| Scope and evidence | OC for the residential apartment in Survey Nos. 107 and 108; identifies a cellar, ground, stilt and five upper floors |
| Identifier / date | Form 1A; OC number recorded as 007 7 63 I OCIH M DA I SKP I 2O2s, dated 04.04.2025 |
|---|---|
| Scope and evidence | Architect’s certificate states completion of development work for AADYA ONE and cites HMDA occupancy certification |
| Identifier / date | Form B; December 2023 |
|---|---|
| Scope and evidence | Promoter declaration includes the 30-3-2025 completion undertaking |
The supplied documents include the registration certificate, technical approval, building permit, architect’s completion certificate and occupancy certificate. A separate approved-layout certificate or complete set of architectural drawings is not established by the materials summarized here; the HMDA-filed plan document and its stated building particulars are listed above.
Frequently asked questions
Is AADYA ONE registered with Telangana RERA?
Yes. AADYA ONE is registered with the Telangana Real Estate Regulatory Authority as P01100007961; the registration status is New Project.
Who is the developer of AADYA ONE?
The promoter named in the RERA registration is AADYA DEVELOPERS.
Where is AADYA ONE located?
AADYA ONE is in Ameenpur, AMEENAPUR, Sangareddy, Telangana (502032).
When will AADYA ONE be completed?
The promoter's proposed date of completion filed with RERA is 30/03/2025. This is the promoter's declaration, not a guarantee.
More projects in Ameenapur