Nath-Ashirwad
NATH LEGACY · Hyderabad · RERA P02500011324
NATH-ASHIRWAD is a residential apartment project in Bagh Amberpet, Amberpet mandal, Hyderabad district. It is being developed by NATH LEGACY, a partnership. The project covers a total plot area of 735.79 sq. m. and comprises one residential building with Stilt + 5 Upper Floors and 12 homes: 2 1BHK units and 10 3BHK units. Its TG-RERA registration is P02500011324, and the proposed completion date is 30/07/2029.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
10 items to check before you pay, 2 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Record |
|---|---|
| Registered project name | NATH-ASHIRWAD RERA record |
| Project type | Residential apartment project RERA record |
| Phase / registered portion | New Project; registration is for the project recorded under Survey No. 48/1. A separate phase name or phase number is not disclosed. RERA record |
| TG-RERA registration | P02500011324; certificate issued 16/10/2026 under section 5. |
| Registration validity | 31/07/2026 to 30/07/2029. This is the registration period, not a statement that the building has an occupancy certificate. |
| Registered promoter | NATH LEGACY, a partnership. RERA record Corporate record |
| TG-RERA status | Registered; the certificate records the registration and its conditions. |
Land and geographic identity
| Item | Record |
|---|---|
| Locality | Bagh Amberpet; the building permit describes the site as Durgabai Deshmukh Colony, Bagh Amberpet. RERA record |
| Revenue village | Bagh Amberpet. The building permit also uses “Amberpet” in its village field; the project record identifies Bagh Amberpet as the revenue village. RERA record Land records |
| Mandal / district / PIN | Amberpet / Hyderabad / 500013. RERA record |
| Project survey number(s) | 48/1; no subdivision is stated. RERA record Land records |
| Plot references | Plot No. 1-A, Block-M; 1-B, Block-M; 1-C, Block-M; 1-D; and 1-D/B, Block-M. RERA record |
| Site area | Total plot area 735.79 sq. m.; road-affected area 113.99 sq. m.; net plot area 621.8 sq. m. |
| Boundaries | East: H No. 2-2-18 by 31 by C Plot No. 2; West: 9 m wide main road; North: 12 m wide main road; South: MCH No. 2-2-18 by 33, Plot No. 1-D by A. Land records |
| Road-affected portion | The permit records 113.99 sq. m. as surrendered to GHMC free of cost. |
Development identity
| Item | Record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC). |
| Principal building permit | 4284/GHMC/SWBP/SEC1/2026, approved 31/07/2026. The associated file number is 016707/GHMC/07329/SWBP/SEC1/2026. |
| Approved building | One residential building, identified as 42/359 in the permit. |
| Sanctioned configuration | Stilt + 5 Upper Floors; stated building height 14.99 m. |
| Approved built-up area | 1889.55 sq. m. recorded for residential upper floors. The permit separately lists 194.6 sq. m. as the fifth-floor area under mortgage. |
| Approved dwelling units | 12. |
| Parking | Permit lists 387.64 sq. m. as total parking area; a number of parking spaces and their allocation are not stated in the supplied record. |
| Building plans / layout | A drawing is filed with TG-RERA as document 738391. The supplied record does not establish a separately approved layout plan. Document index |
Offering and status
| Item | Record |
|---|---|
| RERA-filed configurations | 1BHK: 2 units; 3BHK: 10 units. RERA unit table RERA unit table |
| RERA-filed saleable area | 1BHK: 61.31 sq. m.; 3BHK: 200.76 sq. m. RERA unit table RERA unit table |
| Booked / available | Portal data last read shows 0 booked and 2 available 1BHK units; 0 booked and 10 available 3BHK units. The portal record has no as-of date, so counts are indicative. RERA unit table |
| Construction stage | No independently verified construction-progress record is supplied. The building permit sets a commencement deadline of 27/01/2027 and a completion deadline of 31/07/2029. |
| Completion dates | GHMC permit: construction to be completed before 31/07/2029. Promoter Form B: undertaking to complete by 30/07/2029. |
| Occupancy / completion certificate | The supplied permit record says completion is not certified; no occupancy or completion certificate is supplied. The permit states that an occupancy certificate is compulsory before occupation. |
2. The project story
NATH-ASHIRWAD is a registered residential apartment project on Survey No. 48/1 in Bagh Amberpet, Amberpet mandal, Hyderabad. Its GHMC building permit covers one Stilt + 5 upper-floor building with 12 dwelling units. The project record lists ten 3BHK and two 1BHK units for sale. RERA record Land records RERA unit table
The supplied records establish a building permit and a promoter-stated completion commitment, but do not establish current construction progress or completion on site. See Offering and status above for the permit deadlines, Form B commitment, and occupancy-certificate status.
3. Master plan, architecture & building design
The approved building permit records a single residential building, Stilt + 5 Upper Floors, with a height of 14.99 m and approved built-up area of 1889.55 sq. m. The site is recorded as 735.79 sq. m. total plot area, including 113.99 sq. m. road-affected area, leaving 621.8 sq. m. net plot area.
The filed drawing document 738391 is identified as a building-floor-plan document, and supplied software measurements were taken from its drawing geometry. Those measurements are not RERA area disclosures and are marked as needing review. The available record does not establish a complete architectural description of building footprint, number of flats per floor, lift or stair arrangements, entrances, circulation, landscaping, or phase organization. Floor plans
The permit specifies setbacks of Front 3.0 m, Rear 2.5 m, Side I 2.5 m and Side II 2.5 m. It records 0 sq. m. of NALA-affected area and 0 sq. m. of tot lot.
4. Homes, configurations & floor plans
The RERA filing lists 12 units in two configurations. Saleable area below is the RERA-filed figure. For the 3BHK, drawing-based carpet measurements are separately shown as software measurements—not RERA-filed areas—and require review. Saleable area and carpet area are distinct measures; the supplied drawing analysis notes that saleable area also includes the home’s share of common areas. RERA unit table RERA unit details Floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 1BHK | 2 | 0 | 2 | 61.31 sq. m. | Not supplied | Not supplied |
| 3BHK | 10 | 0 | 10 | 200.76 sq. m. | Software-measured range: 124.0–149.1 sq. m.; median 148.2 sq. m. (5 flat designs measured) | 26% supplied for the drawing analysis |
The supplied drawing measurements include a 3BHK example with bedrooms, kitchen, living/dining, sitout, toilets and dress areas; individual room dimensions are extracted for that example, but the overall drawing measurements are flagged for review. Balcony, utility and common-area components are not separately quantified in the supplied data. RERA unit table RERA unit details Floor plans
5. Parking & vehicle circulation
The building permit records 387.64 sq. m. of total parking area. It does not state a parking-space count, resident or visitor allocation, accessible spaces, two-wheeler provision, or unit-specific parking allotments. The sanctioned configuration includes a stilt level, but the supplied record does not specify parking layout, ramps, vehicle entrances or internal driveways. A drawn or designated parking area does not, by itself, establish exclusive ownership or allocation to a particular unit. Document index
6. Amenities, recreation & open spaces
The RERA amenities record lists 14 categories. It marks water supply, sewerage, storm-water drains, rainwater harvesting and an electrical meter room/sub-station/receiving station as “YES”; the listed progress figures are 0%. These are filed declarations, not evidence that the facilities are completed or independently verified. RERA amenities
| Facility | Green Strip/TOT LOT/Park; aggregate recreational open space |
|---|---|
| Description / size | No size supplied; permit records tot lot as 0 sq. m. |
| Evidence source | RERA amenities |
| Declared progress / verified status | Listed at 0%; completion not verified |
| Facility | Community Buildings |
|---|---|
| Description / size | No description or size supplied |
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; completion not verified |
| Facility | Internal Roads & Footpaths; Street Lighting |
|---|---|
| Description / size | No dimensions or quantities supplied |
| Evidence source | RERA amenities |
| Declared progress / verified status | Each listed at 0%; completion not verified |
No clubhouse, indoor recreation or sports facilities are identified in the supplied project records.
7. Utilities, building services & safety
The RERA amenities record marks Water Supply, Sewerage (Chamber, Lines, Septic Tank, STP), Storm Water Drains, Water Conservation, Rain water Harvesting, and Electrical Meter Room, Sub-Station, Receiving Station as “YES”; each has a listed progress figure of 0%. It does not identify water source, storage or treatment capacity, sewerage-treatment capacity, reuse arrangements, power-backup capacity or electrical-substation capacity. RERA amenities
The GHMC permit requires a rainwater-harvesting structure and specifies 3 rainwater-harvesting pits. It also identifies space for a transformer and a garbage house. These are permit-recorded provisions; the supplied materials do not verify installation or completion.
The permit requires an occupancy Fire NOC from the Director (EV&DM) before an occupancy certificate is issued and makes the occupancy certificate compulsory before occupation. The supplied record does not establish that the Fire NOC or occupancy certificate has been issued. It does not provide details of fire-fighting equipment, escape stairs, lift capacity, CCTV, waste segregation, accessibility features or security systems.
8. Location, access & connectivity
The registered project location is Bagh Amberpet, Amberpet mandal, Hyderabad district, PIN 500013; the building permit describes the site as Durgabai Deshmukh Colony, Bagh Amberpet. The site boundary description identifies a 9M wide main road on the west and a 12M wide main road on the north. The permit’s sanctioned parameters also list road widths as 18 mt. RERA record Land records
The supplied location record gives the nearest sampled Outer Ring Road interchange at approximately 14.4 km. No public-transport details, additional measured landmark distances or travel-time claims are supplied. Location record
9. Developer & development status
The registered promoter is NATH LEGACY, recorded as a partnership, with GSTIN 36AAZFN7654G1ZH. The project record identifies RAMESH DESHMUKH as authorized signatory and VANITHA RAMESH DESHMUKH as partner; a partner resolution authorizes RAMESH DESHMUKH to act for the project. Corporate record Parties record
The promoter’s registered office is recorded on the TG-RERA certificate as Village Kachiguda, Mandal Himayatha Nagar, District Hyderabad, PIN 500027. No official website, telephone number or email address is supplied.
The promoter’s Form B affidavit, dated 14 AUG 2026, states a completion commitment of 30/07/2029 and makes other statutory declarations. This is a promoter declaration; the supplied evidence does not independently establish construction progress.
10. Approvals, official records & documents
| Identifier / date | P02500011324; issued 16/10/2026; valid 31/07/2026–30/07/2029 |
|---|---|
| Scope and evidence | FORM C for NATH-ASHIRWAD, Survey No. 48/1; certificate records registration conditions. |
| Identifier / date | 4284/GHMC/SWBP/SEC1/2026; 31/07/2026 |
|---|---|
| Scope and evidence | Conditional permit for one Stilt + 5 upper-floor residential building, 12 units, on Survey No. 48/1. Associated file number: 016707/GHMC/07329/SWBP/SEC1/2026. |
| Identifier / date | Document 738391 |
|---|---|
| Scope and evidence | Filed drawing record used for the supplied software area measurements; measurements are not RERA disclosures and need review. Floor plans |
| Identifier / date | 2940/2026; 08/07/2026 |
|---|---|
| Scope and evidence | Permit record identifies a fifth-floor mortgaged area of 194.6 sq. m. |
| Identifier / date | Permit reference, page 4 |
|---|---|
| Scope and evidence | Records 113.99 sq. m. of road-affected site portion surrendered to GHMC free of cost. |
| Identifier / date | Dated 14 AUG 2026 |
|---|---|
| Scope and evidence | Promoter affidavit states the completion commitment and statutory undertakings. |
| Identifier / date | Project resolution |
|---|---|
| Scope and evidence | Partners’ resolution authorizes RAMESH DESHMUKH to sign and execute project-registration documents. |
| Identifier / date | Not supplied |
|---|---|
| Scope and evidence | The permit record states completion is not certified; it requires an occupancy certificate before occupation. |
The supplied evidence does not include an occupancy certificate, a separately established approved-layout record, or a site-progress verification.
1. Project at a glance
Project identity
Registered project name: NATH-ASHIRWAD
Project type: Residential apartment project
Phase / registered portion: New Project; registration is for the project recorded under Survey No. 48/1. A separate phase name or phase number is not disclosed.
TG-RERA registration: P02500011324; certificate issued 16/10/2026 under section 5.
Registration validity: 31/07/2026 to 30/07/2029. This is the registration period, not a statement that the building has an occupancy certificate.
Registered promoter: NATH LEGACY, a partnership.
TG-RERA status: Registered; the certificate records the registration and its conditions.
Land and geographic identity
Locality: Bagh Amberpet; the building permit describes the site as Durgabai Deshmukh Colony, Bagh Amberpet.
Revenue village: Bagh Amberpet. The building permit also uses “Amberpet” in its village field; the project record identifies Bagh Amberpet as the revenue village.
Mandal / district / PIN: Amberpet / Hyderabad / 500013.
Project survey number(s): 48/1; no subdivision is stated.
Plot references: Plot No. 1-A, Block-M; 1-B, Block-M; 1-C, Block-M; 1-D; and 1-D/B, Block-M.
Site area: Total plot area 735.79 sq. m.; road-affected area 113.99 sq. m.; net plot area 621.8 sq. m.
Boundaries: East: H No. 2-2-18 by 31 by C Plot No. 2; West: 9 m wide main road; North: 12 m wide main road; South: MCH No. 2-2-18 by 33, Plot No. 1-D by A.
Road-affected portion: The permit records 113.99 sq. m. as surrendered to GHMC free of cost.
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC).
Principal building permit: 4284/GHMC/SWBP/SEC1/2026, approved 31/07/2026. The associated file number is 016707/GHMC/07329/SWBP/SEC1/2026.
Approved building: One residential building, identified as 42/359 in the permit.
Sanctioned configuration: Stilt + 5 Upper Floors; stated building height 14.99 m.
Approved built-up area: 1889.55 sq. m. recorded for residential upper floors. The permit separately lists 194.6 sq. m. as the fifth-floor area under mortgage.
Approved dwelling units: 12.
Parking: Permit lists 387.64 sq. m. as total parking area; a number of parking spaces and their allocation are not stated in the supplied record.
Building plans / layout: A drawing is filed with TG-RERA as document 738391. The supplied record does not establish a separately approved layout plan.
Offering and status
RERA-filed configurations: 1BHK: 2 units; 3BHK: 10 units.
RERA-filed saleable area: 1BHK: 61.31 sq. m.; 3BHK: 200.76 sq. m.
Booked / available: Portal data last read shows 0 booked and 2 available 1BHK units; 0 booked and 10 available 3BHK units. The portal record has no as-of date, so counts are indicative.
Construction stage: No independently verified construction-progress record is supplied. The building permit sets a commencement deadline of 27/01/2027 and a completion deadline of 31/07/2029.
Completion dates: GHMC permit: construction to be completed before 31/07/2029. Promoter Form B: undertaking to complete by 30/07/2029.
Occupancy / completion certificate: The supplied permit record says completion is not certified; no occupancy or completion certificate is supplied. The permit states that an occupancy certificate is compulsory before occupation.
2. The project story
NATH-ASHIRWAD is a registered residential apartment project on Survey No. 48/1 in Bagh Amberpet, Amberpet mandal, Hyderabad. Its GHMC building permit covers one Stilt + 5 upper-floor building with 12 dwelling units. The project record lists ten 3BHK and two 1BHK units for sale.
The supplied records establish a building permit and a promoter-stated completion commitment, but do not establish current construction progress or completion on site. See Offering and status above for the permit deadlines, Form B commitment, and occupancy-certificate status.
3. Master plan, architecture & building design
The approved building permit records a single residential building, Stilt + 5 Upper Floors, with a height of 14.99 m and approved built-up area of 1889.55 sq. m. The site is recorded as 735.79 sq. m. total plot area, including 113.99 sq. m. road-affected area, leaving 621.8 sq. m. net plot area.
The filed drawing document 738391 is identified as a building-floor-plan document, and supplied software measurements were taken from its drawing geometry. Those measurements are not RERA area disclosures and are marked as needing review. The available record does not establish a complete architectural description of building footprint, number of flats per floor, lift or stair arrangements, entrances, circulation, landscaping, or phase organization.
The permit specifies setbacks of Front 3.0 m, Rear 2.5 m, Side I 2.5 m and Side II 2.5 m. It records 0 sq. m. of NALA-affected area and 0 sq. m. of tot lot.
4. Homes, configurations & floor plans
The RERA filing lists 12 units in two configurations. Saleable area below is the RERA-filed figure. For the 3BHK, drawing-based carpet measurements are separately shown as software measurements—not RERA-filed areas—and require review. Saleable area and carpet area are distinct measures; the supplied drawing analysis notes that saleable area also includes the home’s share of common areas.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 1BHK | 2 | 0 | 2 | 61.31 sq. m. | Not supplied | Not supplied |
| 3BHK | 10 | 0 | 10 | 200.76 sq. m. | Software-measured range: 124.0–149.1 sq. m.; median 148.2 sq. m. (5 flat designs measured) | 26% supplied for the drawing analysis |
The supplied drawing measurements include a 3BHK example with bedrooms, kitchen, living/dining, sitout, toilets and dress areas; individual room dimensions are extracted for that example, but the overall drawing measurements are flagged for review. Balcony, utility and common-area components are not separately quantified in the supplied data.
5. Parking & vehicle circulation
The building permit records 387.64 sq. m. of total parking area. It does not state a parking-space count, resident or visitor allocation, accessible spaces, two-wheeler provision, or unit-specific parking allotments. The sanctioned configuration includes a stilt level, but the supplied record does not specify parking layout, ramps, vehicle entrances or internal driveways. A drawn or designated parking area does not, by itself, establish exclusive ownership or allocation to a particular unit.
6. Amenities, recreation & open spaces
The RERA amenities record lists 14 categories. It marks water supply, sewerage, storm-water drains, rainwater harvesting and an electrical meter room/sub-station/receiving station as “YES”; the listed progress figures are 0%. These are filed declarations, not evidence that the facilities are completed or independently verified.
| Facility | Green Strip/TOT LOT/Park; aggregate recreational open space |
|---|---|
| Description / size | No size supplied; permit records tot lot as 0 sq. m. |
| Declared progress / verified status | Listed at 0%; completion not verified |
| Facility | Community Buildings |
|---|---|
| Description / size | No description or size supplied |
| Declared progress / verified status | 0%; completion not verified |
| Facility | Internal Roads & Footpaths; Street Lighting |
|---|---|
| Description / size | No dimensions or quantities supplied |
| Declared progress / verified status | Each listed at 0%; completion not verified |
No clubhouse, indoor recreation or sports facilities are identified in the supplied project records.
7. Utilities, building services & safety
The RERA amenities record marks Water Supply, Sewerage (Chamber, Lines, Septic Tank, STP), Storm Water Drains, Water Conservation, Rain water Harvesting, and Electrical Meter Room, Sub-Station, Receiving Station as “YES”; each has a listed progress figure of 0%. It does not identify water source, storage or treatment capacity, sewerage-treatment capacity, reuse arrangements, power-backup capacity or electrical-substation capacity.
The GHMC permit requires a rainwater-harvesting structure and specifies 3 rainwater-harvesting pits. It also identifies space for a transformer and a garbage house. These are permit-recorded provisions; the supplied materials do not verify installation or completion.
The permit requires an occupancy Fire NOC from the Director (EV&DM) before an occupancy certificate is issued and makes the occupancy certificate compulsory before occupation. The supplied record does not establish that the Fire NOC or occupancy certificate has been issued. It does not provide details of fire-fighting equipment, escape stairs, lift capacity, CCTV, waste segregation, accessibility features or security systems.
8. Location, access & connectivity
The registered project location is Bagh Amberpet, Amberpet mandal, Hyderabad district, PIN 500013; the building permit describes the site as Durgabai Deshmukh Colony, Bagh Amberpet. The site boundary description identifies a 9M wide main road on the west and a 12M wide main road on the north. The permit’s sanctioned parameters also list road widths as 18 mt.
The supplied location record gives the nearest sampled Outer Ring Road interchange at approximately 14.4 km. No public-transport details, additional measured landmark distances or travel-time claims are supplied.
9. Developer & development status
The registered promoter is NATH LEGACY, recorded as a partnership, with GSTIN 36AAZFN7654G1ZH. The project record identifies RAMESH DESHMUKH as authorized signatory and VANITHA RAMESH DESHMUKH as partner; a partner resolution authorizes RAMESH DESHMUKH to act for the project.
The promoter’s registered office is recorded on the TG-RERA certificate as Village Kachiguda, Mandal Himayatha Nagar, District Hyderabad, PIN 500027. No official website, telephone number or email address is supplied.
The promoter’s Form B affidavit, dated 14 AUG 2026, states a completion commitment of 30/07/2029 and makes other statutory declarations. This is a promoter declaration; the supplied evidence does not independently establish construction progress.
10. Approvals, official records & documents
| Identifier / date | P02500011324; issued 16/10/2026; valid 31/07/2026–30/07/2029 |
|---|---|
| Scope and evidence | FORM C for NATH-ASHIRWAD, Survey No. 48/1; certificate records registration conditions. |
| Identifier / date | 4284/GHMC/SWBP/SEC1/2026; 31/07/2026 |
|---|---|
| Scope and evidence | Conditional permit for one Stilt + 5 upper-floor residential building, 12 units, on Survey No. 48/1. Associated file number: 016707/GHMC/07329/SWBP/SEC1/2026. |
| Identifier / date | Document 738391 |
|---|---|
| Scope and evidence | Filed drawing record used for the supplied software area measurements; measurements are not RERA disclosures and need review. |
| Identifier / date | 2940/2026; 08/07/2026 |
|---|---|
| Scope and evidence | Permit record identifies a fifth-floor mortgaged area of 194.6 sq. m. |
| Identifier / date | Permit reference, page 4 |
|---|---|
| Scope and evidence | Records 113.99 sq. m. of road-affected site portion surrendered to GHMC free of cost. |
| Identifier / date | Dated 14 AUG 2026 |
|---|---|
| Scope and evidence | Promoter affidavit states the completion commitment and statutory undertakings. |
| Identifier / date | Project resolution |
|---|---|
| Scope and evidence | Partners’ resolution authorizes RAMESH DESHMUKH to sign and execute project-registration documents. |
| Identifier / date | Not supplied |
|---|---|
| Scope and evidence | The permit record states completion is not certified; it requires an occupancy certificate before occupation. |
The supplied evidence does not include an occupancy certificate, a separately established approved-layout record, or a site-progress verification.
Frequently asked questions
Is NATH-ASHIRWAD registered with Telangana RERA?
Yes. NATH-ASHIRWAD is registered with the Telangana Real Estate Regulatory Authority as P02500011324; the registration status is New Project.
Who is the developer of NATH-ASHIRWAD?
The promoter named in the RERA registration is NATH LEGACY.
Where is NATH-ASHIRWAD located?
NATH-ASHIRWAD is in BAGH AMBERPET, Amberpet, Hyderabad, Telangana (500013).
When will NATH-ASHIRWAD be completed?
The promoter's proposed date of completion filed with RERA is 30/07/2029. This is the promoter's declaration, not a guarantee.
More projects in Bagh Amberpet