Vasudha Aspire
VASUDHA DEVELOPERS · Medchal-Malkajgiri · RERA P02200005284
VASUDHA ASPIRE is a residential apartment project in Medchal Village, Medchal Mandal, Medchal-Malkajgiri District, developed by registered promoter VASUDHA DEVELOPERS. The project covers 535.04 sq. m. and comprises one building with one stilt plus five upper floors and 10 3BHK units. It is registered with TG-RERA as P02200005284, and the project header records a proposed completion date of 11/06/2027.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
7 items to check before you pay, 2 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Project record |
|---|---|
| Registered project name | VASUDHA ASPIRE RERA record |
| Project type | Residential apartment project RERA record RERA filing |
| Phase / registered portion | Phase not separately identified in the available record; registration is for the project. |
| TG-RERA registration number | P02200005284 |
| Registration validity | 28/10/2022 to 11/02/2027; the certificate states a four-year validity period, subject to extension by the Authority. This is the registration-validity period, not the construction completion date. |
| Registered promoter | VASUDHA DEVELOPERS; the RERA record identifies the organisation type as a partnership. RERA record Corporate record |
| RERA status | Registered; certificate Form C records registration under section 5. |
Land and geographic identity
| Field | Project record |
|---|---|
| Locality / revenue village | Medchal Village; the TG-RERA record also identifies the village as Medchal 1. RERA record |
| Mandal | Medchal RERA record |
| District | Medchal-Malkajgiri RERA record |
| PIN | 501401 RERA record |
| Project survey numbers and subdivisions | 153(p), 155, 156, 157 & 158. These are the survey identifiers stated in the RERA certificate and HMDA technical approval. |
| Plot | Plot No. 301 RERA filing |
| Registered site extent | 535.04 sq. m. RERA filing |
| Total / net land area | Total area 535.04 sq. m.; net area 535.04 sq. m. RERA filing |
| Boundaries | North: Plot No. 302; south: Plot No. 300; east: Plot No. 296; west: Road. RERA filing |
Development identity
| Field | Project record |
|---|---|
| Sanctioning authority | Hyderabad Metropolitan Development Authority (HMDA) Approvals record |
| Principal approval | HMDA technical approval / building permit reference 034360/MED/R1/U6/HMDA/19022020, dated 11/02/2021. The approval letter states the plans are to be sanctioned by the Executive Authority in conformity with HMDA’s technical approval. Approvals record |
| Approved built-up area | 1221.35 sq. m. (identified as “Built up Area” in the approval extraction). The same extraction separately records 1480.98 sq. m. as “Proposed Built-up Area”; these labels are retained as recorded and are not treated as interchangeable. |
| Building count | One building / one tower is recorded in the project information and unit summary. RERA filing RERA unit table |
| Floor configuration | One stilt plus five upper floors, as described in the HMDA technical approval extraction. |
| Parking levels / approved parking count | Not established in the available RERA filing extracts. |
| Unit count | HMDA approval conditions state that the sanctioned number of units must not be increased without prior GHMC approval; the approval extract does not state the sanctioned unit count. TG-RERA records 10 units. RERA unit table |
Offering and status
| Field | Project record |
|---|---|
| RERA-filed configuration | 3BHK RERA unit table |
| RERA-filed saleable area | 122.0 sq. m. per unit RERA unit table |
| RERA portal booking / availability | 0 booked; 10 available. The portal extract provides no as-of date for these counts, so they are indicative. RERA unit table |
| Construction stage | No independently verified site-progress information is available in the supplied records. RERA amenity-infrastructure entries show 0% progress where reported; this is a portal declaration, not an independent site inspection. RERA amenities |
| Completion date | The Form B declaration states completion by 11th February, 2027. The project header separately records a proposed completion date of 11/06/2027; the dates are shown as recorded, without reconciling them here. RERA record |
| Occupancy / completion certificate | No occupancy or completion certificate is identified in the supplied project documents. The HMDA approval letter says an occupancy certificate is compulsory before occupation. Document index |
2. The project story
VASUDHA ASPIRE is registered with TG-RERA as a residential apartment project on Plot No. 301 in Medchal Village, Medchal Mandal, Medchal-Malkajgiri District. The site is recorded as 535.04 sq. m. and the project identity covers survey numbers 153(p), 155, 156, 157 and 158. RERA record RERA filing
HMDA’s technical approval describes a proposed apartment building with one stilt and five upper floors. The TG-RERA unit record lists one 3BHK configuration comprising 10 units, with no units booked and 10 available in the portal data; the portal does not provide an as-of date for that inventory snapshot. RERA unit table
The supplied material does not establish construction progress through an independent site inspection or identify an occupancy certificate. Accordingly, the building should be understood here as proposed in the approval record; completion and occupancy certification are not demonstrated by the supplied documents. Document index RERA amenities
3. Master plan, architecture & building design
The project is recorded on a 535.04 sq. m. site, with an approved built-up area of 1221.35 sq. m. The HMDA approval extraction also separately records proposed built-up area of 1480.98 sq. m.; the available evidence does not explain the basis for the separate figures. RERA filing
The technical approval describes one residential building with 1 Stilt + 5 Upper floors, on Plot No. 301. It records a building height of 14.99 (the extraction does not state a unit) and an 18 mt. road width. It also identifies a transformer, garbage house, rainwater-harvesting structures and ETP among the proposed amenities/utilities.
The supplied records do not provide a sufficiently extracted floor-by-floor plan to establish flats per floor, building footprint, lifts, stairs, detailed circulation, open-space dimensions or the residential/common-area breakdown. The master-plan zoning sheet for the area is image-only; the exact zone at the project survey parcel is not established in the available information. HMDA
4. Homes, configurations & floor plans
TG-RERA records 10 3BHK units, all shown as available and none booked in the portal extract; the inventory has no supplied as-of date. RERA-filed saleable area is 122.0 sq. m. per unit. RERA unit table
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 10 | 0 | 10 | 122.0 sq. m. | 87.0–100.9 sq. m.; median 97.7 sq. m. | 20% |
Carpet-area figures are software measurements from the drawing geometry in document 241344, not RERA-filed disclosures; four flat designs were measured and all four are marked as needing review. The measurement record identifies a typical floor-plan flat with three bedrooms, kitchen, toilets, balcony and utility. The balcony and utility are excluded from the measured carpet area. Floor plans
RERA saleable area and drawing-measured carpet area are different area measures: saleable area includes the home’s share of common areas, while the drawing measurement excludes the balcony and utility shown in the identified plan. The supplied record does not provide separate balcony or utility dimensions. Floor plans
5. Parking & vehicle circulation
The available project documents do not establish the sanctioned number of car or two-wheeler spaces, visitor or accessible parking provision, parking layout or the number of parking levels. The HMDA approval describes one stilt floor, but does not by itself establish the parking count or the allocation of spaces to individual units. Document index
The HMDA approval records mortgage areas within the building: 130.0 sq. m. in the second floor, under deed document No. 5737 of 2020, and 62.0 sq. m. described as a NALA conversion certificate area, under mortgage deed document No. 2210 of 2021. These entries do not establish parking allocations.
6. Amenities, recreation & open spaces
The HMDA technical approval extraction lists certain site utilities; the TG-RERA amenity record separately lists project infrastructure and progress fields. The supplied material does not establish independent completion of any facility. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Green strip / TOT LOT / park | Size not stated | TG-RERA amenity record RERA amenities | “YES” is recorded; progress 0%. Not independently verified. |
| Aggregate recreational open space | Size not stated | TG-RERA amenity record RERA amenities | Progress 0%; no completion evidence supplied. |
| Community buildings | No facility details or size stated | TG-RERA amenity record RERA amenities | Progress 0%; no completion evidence supplied. |
| Transformer | Size/capacity not stated | HMDA technical approval extraction | Listed as a proposed utility; completion not verified. |
| Garbage house | Size/capacity not stated | HMDA technical approval extraction | Listed; completion not verified. |
The TG-RERA amenity record does not provide evidence of a clubhouse, gym, swimming pool or indoor recreation facility. Those facilities are not included as confirmed project provision in this overview.
7. Utilities, building services & safety
The HMDA technical approval extraction lists a transformer, rainwater-harvesting structures and an ETP; it also directs that ETP be provided as per standard specification. The TG-RERA amenity record marks water supply and water conservation/rainwater harvesting “YES”, while recording 0% progress for the relevant items. These are approval or portal-record statements, not verification that the facilities are complete or operational. RERA amenities
The TG-RERA amenity schedule also lists sewerage, storm-water drains, treatment and disposal of sewage and sullage water, solid-waste management, energy management, fire protection/fire safety, street lighting, and an electrical meter room/sub-station/receiving station. The supplied record shows 0% progress for these entries and does not provide capacities, detailed designs, completion evidence or clearances. RERA amenities
The building approval letter states that an occupancy certificate is compulsory before occupation and requires a completion notice after completion. The supplied material does not establish that an occupancy certificate has been issued.
8. Location, access & connectivity
The registered project location is Medchal Village (also recorded in the TG-RERA project identity as Medchal 1), Medchal Mandal, Medchal-Malkajgiri District, PIN 501401. The project is on Plot No. 301 and is bounded on the west by a road. RERA record RERA filing
The supplied location record gives the nearest sampled Outer Ring Road interchange at approximately 1.2 km. This is a supplied map-derived distance, not a travel-time estimate. Location record
No verified project-specific road-access plan or public-transport information is supplied in the RERA record extracts reviewed for this overview. Location record
9. Developer & development status
The registered promoter is VASUDHA DEVELOPERS, identified in the project record as a partnership. TG-RERA records GSTIN 36AASFV5122C1Z5. The registration certificate lists the promoter office as Village: Kukatpally, Mandal: Kukatpally, District: Medchal-Malkajgiri, PIN 500072; the project header separately gives the promoter’s Medchal address. Corporate record RERA record
The RERA record names PRUTHVI RAJ POTTAVATHINI as authorised signatory and identifies SRINIVAS YOGARAPU and RAMAKRISHNA REDDY ANNADI as partners. The Form B affidavit, signed by the authorised signatory, declares that the project will be completed by the date of permission, 11th February, 2027. Parties record
The project registration certificate remains valid through 11/02/2027; this is distinct from the completion date stated in the Form B declaration and the proposed completion date recorded in the project header. No independent construction-progress verification or occupancy certificate is present in the supplied evidence. RERA record Document index
10. Approvals, official records & documents
| Reference / scope | Form C; project VASUDHA ASPIRE, registration P02200005284, issued 28/10/2022; valid to 11/02/2027 |
|---|
| Reference / scope | Reference 034360/MED/R1/U6/HMDA/19022020, dated 11/02/2021; proposed residential building on Plot 301, survey numbers 153(P), 155, 156, 157 and 158 |
|---|
| Reference / scope | Sale deed for Plot 301, 535.04 sq. m., in the project survey numbers, in favour of M/s. VASUDHA DEVELOPERS |
|---|
| Reference / scope | Title-search report concerning Plot 301 and the submitted title documents |
|---|
| Reference / scope | Promoter affidavit dated 25 May 2022, including declared title, encumbrance, fund-account and completion statements |
|---|
| Reference / scope | Filed project encumbrance statement; statement reference 108922017 |
|---|
| Reference / scope | RERA-filed building-plan document; software measurements were made from the typical floor-plan drawing |
|---|
| Reference / scope | A layout-plan document is listed in the TG-RERA filing, but the supplied extraction does not establish its detailed contents. |
|---|---|
| Evidence in supplied file | Document index |
| Reference / scope | Not identified in the supplied documents. |
|---|---|
| Evidence in supplied file | Document index |
The HMDA record describes the approval as technical approval and states that building plans are to be sanctioned by the Executive Authority in conformity with the technically approved plans. The overview therefore identifies the HMDA record in that stated scope; it does not treat the supplied material as evidence of an occupancy certificate.
1. Project at a glance
Project identity
Registered project name: VASUDHA ASPIRE
Project type: Residential apartment project
Phase / registered portion: Phase not separately identified in the available record; registration is for the project.
TG-RERA registration number: P02200005284
Registration validity: 28/10/2022 to 11/02/2027; the certificate states a four-year validity period, subject to extension by the Authority. This is the registration-validity period, not the construction completion date.
Registered promoter: VASUDHA DEVELOPERS; the RERA record identifies the organisation type as a partnership.
RERA status: Registered; certificate Form C records registration under section 5.
Land and geographic identity
Locality / revenue village: Medchal Village; the TG-RERA record also identifies the village as Medchal 1.
Mandal: Medchal
District: Medchal-Malkajgiri
PIN: 501401
Project survey numbers and subdivisions: 153(p), 155, 156, 157 & 158. These are the survey identifiers stated in the RERA certificate and HMDA technical approval.
Plot: Plot No. 301
Registered site extent: 535.04 sq. m.
Total / net land area: Total area 535.04 sq. m.; net area 535.04 sq. m.
Boundaries: North: Plot No. 302; south: Plot No. 300; east: Plot No. 296; west: Road.
Development identity
Sanctioning authority: Hyderabad Metropolitan Development Authority (HMDA)
Principal approval: HMDA technical approval / building permit reference 034360/MED/R1/U6/HMDA/19022020, dated 11/02/2021. The approval letter states the plans are to be sanctioned by the Executive Authority in conformity with HMDA’s technical approval.
Approved built-up area: 1221.35 sq. m. (identified as “Built up Area” in the approval extraction). The same extraction separately records 1480.98 sq. m. as “Proposed Built-up Area”; these labels are retained as recorded and are not treated as interchangeable.
Building count: One building / one tower is recorded in the project information and unit summary.
Floor configuration: One stilt plus five upper floors, as described in the HMDA technical approval extraction.
Parking levels / approved parking count: Not established in the available RERA filing extracts.
Unit count: HMDA approval conditions state that the sanctioned number of units must not be increased without prior GHMC approval; the approval extract does not state the sanctioned unit count. TG-RERA records 10 units.
Offering and status
RERA-filed configuration: 3BHK
RERA-filed saleable area: 122.0 sq. m. per unit
RERA portal booking / availability: 0 booked; 10 available. The portal extract provides no as-of date for these counts, so they are indicative.
Construction stage: No independently verified site-progress information is available in the supplied records. RERA amenity-infrastructure entries show 0% progress where reported; this is a portal declaration, not an independent site inspection.
Completion date: The Form B declaration states completion by 11th February, 2027. The project header separately records a proposed completion date of 11/06/2027; the dates are shown as recorded, without reconciling them here.
Occupancy / completion certificate: No occupancy or completion certificate is identified in the supplied project documents. The HMDA approval letter says an occupancy certificate is compulsory before occupation.
2. The project story
VASUDHA ASPIRE is registered with TG-RERA as a residential apartment project on Plot No. 301 in Medchal Village, Medchal Mandal, Medchal-Malkajgiri District. The site is recorded as 535.04 sq. m. and the project identity covers survey numbers 153(p), 155, 156, 157 and 158.
HMDA’s technical approval describes a proposed apartment building with one stilt and five upper floors. The TG-RERA unit record lists one 3BHK configuration comprising 10 units, with no units booked and 10 available in the portal data; the portal does not provide an as-of date for that inventory snapshot.
The supplied material does not establish construction progress through an independent site inspection or identify an occupancy certificate. Accordingly, the building should be understood here as proposed in the approval record; completion and occupancy certification are not demonstrated by the supplied documents.
3. Master plan, architecture & building design
The project is recorded on a 535.04 sq. m. site, with an approved built-up area of 1221.35 sq. m. The HMDA approval extraction also separately records proposed built-up area of 1480.98 sq. m.; the available evidence does not explain the basis for the separate figures.
The technical approval describes one residential building with 1 Stilt + 5 Upper floors, on Plot No. 301. It records a building height of 14.99 (the extraction does not state a unit) and an 18 mt. road width. It also identifies a transformer, garbage house, rainwater-harvesting structures and ETP among the proposed amenities/utilities.
The supplied records do not provide a sufficiently extracted floor-by-floor plan to establish flats per floor, building footprint, lifts, stairs, detailed circulation, open-space dimensions or the residential/common-area breakdown. The master-plan zoning sheet for the area is image-only; the exact zone at the project survey parcel is not established in the available information.
4. Homes, configurations & floor plans
TG-RERA records 10 3BHK units, all shown as available and none booked in the portal extract; the inventory has no supplied as-of date. RERA-filed saleable area is 122.0 sq. m. per unit.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 10 | 0 | 10 | 122.0 sq. m. | 87.0–100.9 sq. m.; median 97.7 sq. m. | 20% |
Carpet-area figures are software measurements from the drawing geometry in document 241344, not RERA-filed disclosures; four flat designs were measured and all four are marked as needing review. The measurement record identifies a typical floor-plan flat with three bedrooms, kitchen, toilets, balcony and utility. The balcony and utility are excluded from the measured carpet area.
RERA saleable area and drawing-measured carpet area are different area measures: saleable area includes the home’s share of common areas, while the drawing measurement excludes the balcony and utility shown in the identified plan. The supplied record does not provide separate balcony or utility dimensions.
5. Parking & vehicle circulation
The available project documents do not establish the sanctioned number of car or two-wheeler spaces, visitor or accessible parking provision, parking layout or the number of parking levels. The HMDA approval describes one stilt floor, but does not by itself establish the parking count or the allocation of spaces to individual units.
The HMDA approval records mortgage areas within the building: 130.0 sq. m. in the second floor, under deed document No. 5737 of 2020, and 62.0 sq. m. described as a NALA conversion certificate area, under mortgage deed document No. 2210 of 2021. These entries do not establish parking allocations.
6. Amenities, recreation & open spaces
The HMDA technical approval extraction lists certain site utilities; the TG-RERA amenity record separately lists project infrastructure and progress fields. The supplied material does not establish independent completion of any facility.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Green strip / TOT LOT / park | Size not stated | TG-RERA amenity record | “YES” is recorded; progress 0%. Not independently verified. |
| Aggregate recreational open space | Size not stated | TG-RERA amenity record | Progress 0%; no completion evidence supplied. |
| Community buildings | No facility details or size stated | TG-RERA amenity record | Progress 0%; no completion evidence supplied. |
| Transformer | Size/capacity not stated | HMDA technical approval extraction | Listed as a proposed utility; completion not verified. |
| Garbage house | Size/capacity not stated | HMDA technical approval extraction | Listed; completion not verified. |
The TG-RERA amenity record does not provide evidence of a clubhouse, gym, swimming pool or indoor recreation facility. Those facilities are not included as confirmed project provision in this overview.
7. Utilities, building services & safety
The HMDA technical approval extraction lists a transformer, rainwater-harvesting structures and an ETP; it also directs that ETP be provided as per standard specification. The TG-RERA amenity record marks water supply and water conservation/rainwater harvesting “YES”, while recording 0% progress for the relevant items. These are approval or portal-record statements, not verification that the facilities are complete or operational.
The TG-RERA amenity schedule also lists sewerage, storm-water drains, treatment and disposal of sewage and sullage water, solid-waste management, energy management, fire protection/fire safety, street lighting, and an electrical meter room/sub-station/receiving station. The supplied record shows 0% progress for these entries and does not provide capacities, detailed designs, completion evidence or clearances.
The building approval letter states that an occupancy certificate is compulsory before occupation and requires a completion notice after completion. The supplied material does not establish that an occupancy certificate has been issued.
8. Location, access & connectivity
The registered project location is Medchal Village (also recorded in the TG-RERA project identity as Medchal 1), Medchal Mandal, Medchal-Malkajgiri District, PIN 501401. The project is on Plot No. 301 and is bounded on the west by a road.
The supplied location record gives the nearest sampled Outer Ring Road interchange at approximately 1.2 km. This is a supplied map-derived distance, not a travel-time estimate.
No verified project-specific road-access plan or public-transport information is supplied in the RERA record extracts reviewed for this overview.
9. Developer & development status
The registered promoter is VASUDHA DEVELOPERS, identified in the project record as a partnership. TG-RERA records GSTIN 36AASFV5122C1Z5. The registration certificate lists the promoter office as Village: Kukatpally, Mandal: Kukatpally, District: Medchal-Malkajgiri, PIN 500072; the project header separately gives the promoter’s Medchal address.
The RERA record names PRUTHVI RAJ POTTAVATHINI as authorised signatory and identifies SRINIVAS YOGARAPU and RAMAKRISHNA REDDY ANNADI as partners. The Form B affidavit, signed by the authorised signatory, declares that the project will be completed by the date of permission, 11th February, 2027.
The project registration certificate remains valid through 11/02/2027; this is distinct from the completion date stated in the Form B declaration and the proposed completion date recorded in the project header. No independent construction-progress verification or occupancy certificate is present in the supplied evidence.
10. Approvals, official records & documents
| Reference / scope | Form C; project VASUDHA ASPIRE, registration P02200005284, issued 28/10/2022; valid to 11/02/2027 |
|---|
| Reference / scope | Reference 034360/MED/R1/U6/HMDA/19022020, dated 11/02/2021; proposed residential building on Plot 301, survey numbers 153(P), 155, 156, 157 and 158 |
|---|
| Reference / scope | Sale deed for Plot 301, 535.04 sq. m., in the project survey numbers, in favour of M/s. VASUDHA DEVELOPERS |
|---|
| Reference / scope | Title-search report concerning Plot 301 and the submitted title documents |
|---|
| Reference / scope | Promoter affidavit dated 25 May 2022, including declared title, encumbrance, fund-account and completion statements |
|---|
| Reference / scope | Filed project encumbrance statement; statement reference 108922017 |
|---|
| Reference / scope | RERA-filed building-plan document; software measurements were made from the typical floor-plan drawing |
|---|
| Reference / scope | A layout-plan document is listed in the TG-RERA filing, but the supplied extraction does not establish its detailed contents. |
|---|
| Reference / scope | Not identified in the supplied documents. |
|---|
The HMDA record describes the approval as technical approval and states that building plans are to be sanctioned by the Executive Authority in conformity with the technically approved plans. The overview therefore identifies the HMDA record in that stated scope; it does not treat the supplied material as evidence of an occupancy certificate.
Frequently asked questions
Is VASUDHA ASPIRE registered with Telangana RERA?
Yes. VASUDHA ASPIRE is registered with the Telangana Real Estate Regulatory Authority as P02200005284; the registration status is New Project.
Who is the developer of VASUDHA ASPIRE?
The promoter named in the RERA registration is VASUDHA DEVELOPERS.
Where is VASUDHA ASPIRE located?
VASUDHA ASPIRE is in Medchal Village, Medchal 1, Medchal, Medchal-Malkajgiri, Telangana (501401).
When will VASUDHA ASPIRE be completed?
The promoter's proposed date of completion filed with RERA is 11/06/2027. This is the promoter's declaration, not a guarantee.