Sign in

Hari Hara Homes

HARI HARA CONSTRUCTIONS · Sangareddy · RERA P01100010087

HARI HARA HOMES is a residential project in PATANCHERU, Patancheru Mandal, Sangareddy District, developed by registered promoter HARI HARA CONSTRUCTIONS, a partnership. The registered site extent is 14405.06 sq.m, with 52 residential buildings of Ground Floor + 2 Floors and one amenity building of 1 Stilt + 2 Floors; the RERA filing lists 52 4BHK units. Its TG-RERA registration number is P01100010087, and the project information field states proposed completion as 21/12/2030.

01What we found

RegisteredTG-RERA - valid till 21 Aug 2030
15documents on file - each fact links to its page
0court cases on this project's land in the court records searched
7items to check - 2 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

7 items to check before you pay, 2 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Photo from squareyards.com

1. Project at a glance

Project identity

FieldRecord
Registered project nameHARI HARA HOMES RERA record
Project typeResidential; the GHMC permit describes the sanctioned development as “Layout With Housing Without Gated Community.” RERA record
Phase / registered portionNo separate phase name or phase number is disclosed in the supplied record. RERA record
TG-RERA registrationP01100010087; Form C registration certificate filed. RERA record
Registration validity21/08/2025 to 21/08/2030 (five years, unless extended by the Authority). This is the registration period, not the stated completion date. RERA record
Registered promoterHARI HARA CONSTRUCTIONS, a partnership. RERA record Corporate record
RERA statusNew Project; registration is recorded as valid through 21/08/2030. RERA record Approvals record
Site / construction statusThe permit and RERA records establish approval and registration; the supplied data does not state verified construction progress.

Land and geographic identity

FieldRecord
LocalityPATANCHERU RERA record RERA filing
Revenue villagePATANCHERU A in the RERA project identity; the GHMC permit identifies Patancheru village. RERA record
Mandal / district / PINPATANCHERU / Sangareddy / 502300 RERA record RERA filing
Project survey numbers and subdivisions45/1 PART, 46/1, 48/C/1/PART, 49/1/PART, 45/2 PART, 46/2, 48/C/2/PART, 49/2/PART, 48/B3/1, 48/B3/2 RERA record
Registered site extent14405.06 sq.m RERA record RERA filing
Area figures in the permitSite area 14405.06 sq.m; road-affected area 1064.36 sq.m; nala-affected area 107.32 sq.m; net area 13233.38 sq.m.
BoundariesNorth, south, east and west boundaries are recorded as “NA” in the supplied land record. Land records

Development identity

FieldRecord
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC) Approvals record
Principal permit number / date0817/GHMC/SWDL/SLP1/2025; 21/08/2025 RERA record Approvals record
GHMC file number001544/GHMC/00955/SWDL/SLP1/2025
Approved built-up areaTotal sanctioned built-up area: 13459.58 sq.m
Sanctioned building organization52 residential buildings, each recorded as Ground Floor + 2 Floors, and one amenity building recorded as 1 Stilt + 2 Floors. The permit’s height entry for the building is illegible.
Parking levels / countNo sanctioned vehicle-space count or detailed parking-level schedule is established in the supplied extracts. Layout conditions refer to cellar/stilt parking where approved in the plan.
Unit countsGHMC permit: 52 dwelling units. RERA unit table: 52 4BHK units plus one CLUB HOUSE row, which is a common facility rather than a home for sale. RERA unit table

Offering and status

FieldRecord
RERA-filed offering4BHK; 52 units; saleable area 275.53 sq.m per unit. RERA unit table RERA unit details
Booking / availabilityRERA portal snapshot lists 0 booked and 52 available; no as-of date is supplied, so these counts are indicative. RERA unit table RERA unit details
Completion dateForm B declares completion by 21-08-2030. The project information field separately states proposed completion as 21/12/2030; the supplied evidence does not explain the different dates. RERA record
Occupancy certificateNo occupancy certificate is identified in the supplied project records. The GHMC permit requires an OC before occupation.
Construction progressNot disclosed in the supplied RERA data; no independently verified site-progress information is supplied. RERA record RERA amenities

2. The project story

  • HARI HARA HOMES is registered as a residential project on land in PATANCHERU A, Patancheru Mandal, Sangareddy District. The GHMC permit characterizes the scheme as a “Layout With Housing Without Gated Community”: it sanctions 52 residential buildings, each Ground Floor + 2 Floors, and a separate amenity building. The RERA filing lists 52 4BHK homes; the additional CLUB HOUSE line in the unit table is not a sale home. RERA record RERA unit table
  • The sanctioned site area is 14405.06 sq.m, with a net area of 13233.38 sq.m after the recorded road- and nala-affected areas. The layout drawing allocates land to plots, roads, organized open space, an amenities plot and utility land. These are plan/document descriptions, not evidence that construction or facilities are complete. The available records do not provide a verified construction-stage report or occupancy certification for any building or phase. RERA record

3. Master plan, architecture & building design

  • The GHMC permit records 13459.58 sq.m as total sanctioned built-up area. It sanctions 52 residential buildings of Ground Floor + 2 Floors and an amenity building of 1 Stilt + 2 Floors. The permit’s overall building-height entry is illegible; the layout-plan extract separately records residential-building height from ground level as 9.75 m and amenity-building height from ground level as 9.45 m.

The layout drawing states total layout area of 14405.06 sq.m and net layout area of 13233.38 sq.m. Its land-use statement records:

Layout useAreaShare of net layout area
Plotted area7901.80 sq.m59.71%
Road area3075.04 sq.m23.24%
Organized open space1730.14 sq.m13.07%
Amenities plot area273.35 sq.m2.07%
Utility area153.18 sq.m1.16%
Social infrastructure area0.00 sq.m0%
Common parking area0.00 sq.m0%
  • The permit’s sanctioned parameters describe 52 residential buildings at 253.12 sq.m gross built-up area and 246.10 sq.m net built-up area each, with one dwelling unit per building. For the amenity building, the drawing records gross built-up area of 542.89 sq.m, net built-up area of 347.66 sq.m and net parking area of 173.83 sq.m. These are drawing/permit area labels, not RERA-filed carpet or saleable areas.
  • The supplied layout drawing also labels six tot-lot areas: 578.05, 59.75, 65.46, 60.88, 525.91 and 440.08 sq.m, alongside a green strip. The drawing identifies internal roads and utility land; it does not establish that these spaces or works have been completed.

4. Homes, configurations & floor plans

  • The RERA filing lists 52 4BHK units, each with saleable area of 275.53 sq.m. The available drawing-measurement record does not provide a usable carpet-area measurement matched to this RERA configuration, so carpet area and loading are not reported. Saleable area is the filed figure; it should not be treated as carpet area. RERA unit table RERA unit details Floor plans
ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
4BHK52052275.53 sq.mNot available for this configurationNot supplied
  • The booking and availability counts are from the TG-RERA portal record, which has no stated as-of date. The project’s amenity building is not counted as a home. RERA unit table RERA unit details

5. Parking & vehicle circulation

  • The supplied extracts do not establish a total sanctioned number of car or two-wheeler spaces, visitor or accessible parking provision, or parking allocation to individual homes. The layout drawing records 173.83 sq.m as the amenity building’s net parking area and identifies cellar/stilt parking as subject to the sanctioned plan; this does not establish exclusive ownership or allocation of any bay.
  • The layout plan records road areas and road-width labels, including an 18 mt. road in the GHMC permit and other widths on the drawing. No complete, verified parking circulation or ramp/entry/exit schedule is supplied.

6. Amenities, recreation & open spaces

  • The RERA amenity schedule marks infrastructure and facility categories as available/proposed, while its progress fields show 0% for the listed items. Those entries do not establish completion. The layout drawing supplies additional facility labels and dimensions. RERA amenities
FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Amenity buildingSanctioned as 1 Stilt + 2 Floors; drawing records gross BUA 542.89 sq.m and net BUA 347.66 sq.mApproved; completion not established
Indoor games, library, gym, society officeNamed in the layout drawing; no individual areas suppliedDrawing labels only; completion not established
Tot-lotsSix areas: 578.05, 59.75, 65.46, 60.88, 525.91 and 440.08 sq.mDrawing labels only; completion not established
Green strip / organized open space1730.14 sq.m organized open space in the layout area statement; green strip also labelledPlanned/drawing-recorded; completion not established
Community buildingsListed in the RERA amenity schedule; amenity building is included in the GHMC permitRERA amenitiesSchedule records 0% progress; no independent completion evidence
Internal roads and footpathsListed in the RERA amenity schedule; layout road area 3075.04 sq.mRERA amenitiesSchedule records 0% progress; no independent completion evidence
  • The promoter’s marketing/vendor material lists additional features such as a swimming pool, clubhouse, children’s play area and jogging track. These are marketing claims, not established here as sanctioned or delivered facilities, and are not included as confirmed project amenities. Promoter website

7. Utilities, building services & safety

  • The layout drawing names an STP, WTP, domestic-water sump of 55,000 L and drinking-water sump of 27,000 L. These are plan-recorded provisions; the supplied evidence does not verify installation, capacity in operation, water source, treatment performance or completion.
Water
Evidence in the supplied recordDomestic and drinking-water storage figures above; water supply is also listed in the RERA amenity schedule
Status limitationPlanned/recorded; source and operational status not established RERA amenities
Sewerage and drainage
Evidence in the supplied recordSTP and treatment/disposal of sewage are identified in the layout and RERA schedule; underground drainage is a stated layout condition
Status limitationCompletion and operation not established RERA amenities
Storm water / rainwater
Evidence in the supplied recordStorm-water drains and water conservation/rainwater harvesting appear in the RERA amenity schedule; the GHMC permit requires a rainwater-harvesting structure
Status limitationCompletion not established; the permit extract records “No.of Rain Water Harvesting Pits 0” RERA amenities
Electrical
Evidence in the supplied recordTransformer space, electrical meter/sub-station/receiving-station and energy-management categories are recorded
Status limitationInstallation or supply/backup capacity not established RERA amenities
Fire and life safety
Evidence in the supplied recordFire-protection requirements are listed in the RERA schedule; the layout conditions require fire-safety measures and an occupancy Fire NOC for the amenities building before OC
Status limitationNo Fire NOC or completed-system evidence supplied RERA amenities
Waste
Evidence in the supplied recordGarbage house is labelled in the layout drawing; solid-waste management is listed in the RERA schedule
Status limitationCompletion and operating arrangements not established RERA amenities
EV charging
Evidence in the supplied recordThe layout approval conditions refer to EV charging infrastructure in parking areas
Status limitationInstallation or charging-point count not established
Accessibility
Evidence in the supplied recordThe supplied extracts do not provide a project-specific accessible-circulation or facility schedule
Status limitationNot established in the supplied evidence

8. Location, access & connectivity

  • The registered location is PATANCHERU A, Patancheru Mandal, Sangareddy District, Telangana, PIN 502300. The RERA project record identifies the site by the ten survey numbers and subdivisions listed above. RERA record
  • A supplied location record gives the nearest sampled Outer Ring Road interchange at approximately 1.6 km. This is a measured location-data point, not a travel-time estimate. No RERA-filed public-transport schedule or verified landmark-distance list is supplied. Location record

9. Developer & development status

  • The registered promoter is HARI HARA CONSTRUCTIONS, identified in the RERA record as a partnership. Its GSTIN is 36AAGFH8491N1ZM. The RERA filing lists the project address as HARI HARA HOMES, KTR COLONY, Patancheru, Sangareddy, 502300; an official contact person or office telephone/email is not supplied here. Corporate record Parties record RERA filing
  • Form B is a promoter declaration signed by Bommireddy Srikanth Reddy as managing partner and authorised signatory. It declares legal title and that the land is free from encumbrances, and undertakes completion by 21-08-2030. These are promoter declarations; the supplied records do not provide verified construction progress.

10. Approvals, official records & documents

RecordDetails
TG-RERA registration certificateForm C for HARI HARA HOMES, registration P01100010087; validity recorded as 21/08/2025–21/08/2030.
GHMC permit“LAYOUT WITH HOUSING - PERMIT ORDER,” approval 0817/GHMC/SWDL/SLP1/2025, dated 21/08/2025; file 001544/GHMC/00955/SWDL/SLP1/2025.
Layout / sanctioned drawingRERA-filed layout drawing with land-use statement, roads, open space, amenity and utility labels.
Form B declarationPromoter affidavit-cum-declaration, including title, encumbrance and completion declarations.
Occupancy / completion certificateNone identified in the supplied documents. The GHMC permit states that an occupancy certificate is required before occupation.
Construction commencement / progress evidenceThe permit requires a commencement notice, but the supplied pack does not establish that notice was filed or document current construction progress.

The supplied evidence does not include a separately identified occupancy certificate, project-progress certificate or completed-facility verification.

Frequently asked questions

Is HARI HARA HOMES registered with Telangana RERA?

Yes. HARI HARA HOMES is registered with the Telangana Real Estate Regulatory Authority as P01100010087; the registration status is New Project.

Who is the developer of HARI HARA HOMES?

The promoter named in the RERA registration is HARI HARA CONSTRUCTIONS.

Where is HARI HARA HOMES located?

HARI HARA HOMES is in PATANCHERU, PATANCHERU A, Sangareddy, Telangana (502300).

When will HARI HARA HOMES be completed?

The promoter's proposed date of completion filed with RERA is 21/12/2030. This is the promoter's declaration, not a guarantee.

More projects in Patancheru A