Bm Enclave
BHRAMARAMBHA MALLIKARJUNA CONSTRUCTIONS · Rangareddy · RERA P02400001274
BM ENCLAVE is a residential apartment project in Miyapur, Kukatpally mandal, Ranga Reddy District, developed by registered promoter BHRAMARAMBHA MALLIKARJUNA CONSTRUCTIONS. The project is on 325.4 m² of land and comprises one building with a stilt level and five residential floors, containing 10 2BHK homes. It is registered under TG-RERA **P02400001274**, with proposed completion on 02/02/2025.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
10 items to check before you pay, 6 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Project record |
|---|---|
| Registered project name | BM ENCLAVE RERA record |
| Project type | Residential apartment project RERA record RERA filing |
| Phase / registered portion | Phase not separately identified in the supplied record; the registration is for BM ENCLAVE |
| TG-RERA registration | P02400001274 |
| Registration validity | 19/10/2019 to 02/02/2025; certificate states “5 years.” No extension is recorded in the supplied certificate |
| Registered promoter | BHRAMARAMBHA MALLIKARJUNA CONSTRUCTIONS RERA record Corporate record |
| Entity type | Partnership RERA filing |
| RERA status | The supplied certificate records registration through 02/02/2025. Current registration status is not established by the material supplied |
Land and geographic identity
| Field | Project record |
|---|---|
| Locality | Miyapur RERA record RERA filing |
| Revenue village | Miyapur; also written as “MIYAPUR VILLAGE” in the building-permit record RERA record |
| Mandal | Not disclosed in the project identity fields; registration certificate separately states Kukatpally mandal Land records |
| District | Ranga Reddy in the project identity and land records RERA record Land records |
| PIN | 500049 RERA record |
| Project survey number(s) / subdivision(s) | Survey No. 44/1; no subdivision is stated RERA record Land records |
| Registered site extent | 325.4 m² in the land and building-permit records Land records |
| Net / total area | Total area 325.4 m²; net area 325.40 m²; recorded road-affected and nala-affected areas are 0 RERA filing |
| Boundaries | East: ROAD WIDTH 40; West: PLOT NO 604 AND 621; North: PLOT NO 622; South: PLOT NO 603 RERA filing |
Development identity
| Field | Project record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC) Approvals record |
| Principal building approval | Approval No. 1/C21/02008/2019, approved 02 February 2019; permit order also identifies File No. 1/C21/13443/2018 Approvals record |
| Approved built-up area | 1,267.72 m² in the RERA project fields RERA filing |
| Sanctioned building arrangement | One proposed residential building, Stilt + 5; sanctioned height 14.89 m |
| Sanctioned areas by level | Stilt: 169.42 m²; residential upper floors (5): 915.25 m² |
| Building count | One building / one tower recorded RERA filing RERA unit table |
| Parking levels / provision | Stilt and cellar are identified in the permit conditions as parking areas; the supplied extraction does not state a parking-space count, and it does not establish a separate cellar level in the listed sanctioned floor configuration |
| Units | 10 units in the RERA unit record; the permit condition says sanctioned unit numbers must not be increased without prior GHMC approval RERA unit table |
Offering and status
| Field | Project record |
|---|---|
| Configuration | 2BHK RERA unit table |
| RERA-filed saleable area | 106.13 m² per unit RERA unit table |
| Booked / available | 0 booked and 10 available in the RERA portal-derived record; no as-of date is supplied, so these counts are indicative RERA unit table |
| Construction stage | No reliable project construction-progress update or independently verified site status is supplied Document index |
| Completion deadline | The registration certificate and Form B declaration state 02/02/2025 |
| Occupancy / completion certificate | No occupancy or completion certificate is identified in the supplied documents; the GHMC permit requires an occupancy certificate before occupation Document index |
2. The project story
BM ENCLAVE is recorded with TG-RERA as a residential apartment project on Plot No. 602 in Survey No. 44/1, Miyapur, with a single proposed Stilt + 5 residential building and 10 two-bedroom units. The building permit records a 325.4 m² site and 1,267.72 m² approved built-up area in the project fields. RERA record Land records RERA unit table RERA filing
The RERA unit record shows all 10 units as available, but it carries no as-of date. The registration certificate and promoter’s Form B declaration state a completion date of 02/02/2025. The material supplied does not establish construction progress, completed portions, or an issued occupancy certificate; accordingly, the project’s present physical stage cannot be confirmed from this evidence. RERA unit table
3. Master plan, architecture & building design
The filed project and GHMC permit records describe one proposed residential building on a 325.4 m² site, with a stilt level and five residential upper floors. The permit gives a building height of 14.89 m and records 169.42 m² for the stilt and 915.25 m² for the residential upper floors. The project fields separately report approved built-up area of 1,267.72 m². These are the figures as recorded; the supplied material does not provide a separate FSI-counted area or a verified footprint calculation. RERA filing
The permit conditions require construction to follow the sanctioned plan and call for a completion notice and occupancy certificate before occupation. It also records four rainwater-harvesting structures, 15 trees, transformer space and a garbage house; the tot-lot is listed as 0 m² in the permit extraction. Detailed floor-by-floor layouts, flat counts per floor, lift and stair arrangements, circulation dimensions and landscape/open-space plans are not available in the supplied drawing-derived information.
The project’s layout plan is filed as a RERA document, but the supplied record does not provide an extracted layout description. The approval identifier to trace in Approvals is 1/C21/02008/2019; the permit also cites layout/subdivision number 2209/MP2/HUDA/1990. Approvals record Document index
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 10 | 0 | 10 | 106.13 m² | Software-measured median 76.4 m²; range 66.1–83.3 m² | 28% |
Unit count, booking count, availability and saleable area are from the RERA unit record; booking counts have no stated as-of date. Carpet-area measurements and loading are software-derived from the floor-plan drawing, are not RERA-filed disclosures, and are marked for review. Saleable area is the RERA-filed figure and is not interchangeable with carpet area; the supplied drawing data notes that saleable area includes a share of common areas. RERA unit table RERA unit details Floor plans
The measured first-floor plan for flat 01 shows a living/dining area, two bedrooms, kitchen, two toilets, wash area and foyer, with a balcony shown but excluded from carpet area. The supplied room measurements are drawing-based, not separately verified site measurements. RERA unit details
5. Parking & vehicle circulation
The GHMC permit states that the cellar and stilt approved for parking must be used exclusively for vehicle parking, without partition walls or rolling shutters. The permit extraction does not establish the number of sanctioned spaces, resident or visitor allocations, accessible spaces, two-wheeler provision, ramp arrangement or EV charging. No unit-specific parking allocation is documented in the material supplied; a drawn or approved parking area alone would not establish exclusive ownership.
6. Amenities, recreation & open spaces
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Tot-lot / green strip | Permit lists “Tot-lot (m2) 0”; condition says it is to be fenced and maintained as greenery before occupancy certificate | GHMC building permit | Required by permit condition; completion not established |
| Trees | 15 trees listed | GHMC building permit | Listed in permit extraction; planting or survival not verified |
| Street lighting | Listed in RERA amenities record; no size or count supplied | RERA amenities record | Progress percentage shown as 0; completion not established RERA amenities |
| Community buildings | Listed in RERA amenities record; no area supplied | RERA amenities record | Progress percentage shown as 0; completion not established RERA amenities |
| Recreational open space | Listed; aggregate area not supplied | RERA amenities record | Progress percentage shown as 0; completion not established RERA amenities |
| Internal roads and footpaths | Listed; dimensions not supplied | RERA amenities record | Progress percentage shown as 0; completion not established RERA amenities |
No project-specific evidence supplied here establishes a clubhouse, swimming pool, gym, jogging track or other indoor/sports facilities as sanctioned or delivered amenities. RERA amenities Document index
7. Utilities, building services & safety
The RERA amenities record lists water supply and sewerage (including chambers, lines, septic tank/STP) as available, but records progress as 0 for these entries. The same record lists storm-water drains, water conservation/rainwater harvesting, solid-waste management, energy management, and fire protection and safety requirements, without supplied capacities or verified completion status. RERA amenities
The GHMC permit specifically requires a rainwater-harvesting percolation pit, space for a transformer, and an ETP as per standard specification; it also lists four rainwater-harvesting structures and a garbage house. These are permit-recorded requirements or provisions, not evidence that the facilities have been installed or commissioned.
No supplied project evidence specifies water source or storage capacity, STP capacity or treated-water reuse, electrical backup capacity, lift number or capacity, fire-system details, CCTV/access-control installation, waste-segregation arrangements, or accessible routes. The permit requires an occupancy certificate before occupation. Document index
8. Location, access & connectivity
The registered project location is Miyapur, Survey No. 44/1, Ranga Reddy District, Telangana, PIN 500049; the GHMC permit identifies Plot No. 602 in Miyapur village. RERA record Land records
The supplied location record identifies Financial District (Nanakramguda) at 1.2 km. No approach-road description, public-transport details or other measured landmark distances are supplied for this overview. Location record
9. Developer & development status
The registered promoter is BHRAMARAMBHA MALLIKARJUNA CONSTRUCTIONS, recorded as a partnership. The RERA record identifies Jagatapi Prasad as authorised signatory and Jagatapi Vani as partner; the Form B affidavit names Sri. Jagapathi Prasad as authorised signatory. The supplied evidence does not establish a registered office address or official contact details sufficient for this profile. Corporate record Parties record RERA filing
The promoter’s Form B declaration, dated 2 February 2019, undertakes completion by 2 February 2025 and includes declarations concerning project funds, accounts and pending approvals. This is a promoter declaration, not independent evidence of completion. The supplied records do not establish current construction progress or an occupancy certificate.
10. Approvals, official records & documents
| Identifier / date | P02400001274; issued 19/10/2019; valid through 02/02/2025 as stated on certificate |
|---|---|
| What the supplied record establishes | Registration certificate for BM ENCLAVE; the supplied copy records a five-year validity period and no extension |
| Identifier / date | Approval No. 1/C21/02008/2019; 02 February 2019; File No. 1/C21/13443/2018 |
|---|---|
| What the supplied record establishes | Permit for a proposed Stilt + 5 building at Plot No. 602, Survey No. 44/1, Miyapur |
| Identifier / date | 2209/MP2/HUDA/1990 |
|---|---|
| What the supplied record establishes | Number stated in the building-permit record; underlying layout approval details are not extracted here |
| Identifier / date | Dated 2 FEB 2019 |
|---|---|
| What the supplied record establishes | Promoter declaration including completion undertaking and statements about title, encumbrances and project obligations |
| Identifier / date | Document 54543 |
|---|---|
| What the supplied record establishes | Filed layout-plan document; supplied record does not include an extracted layout description Document index |
| Identifier / date | Not identified in supplied documents |
|---|---|
| What the supplied record establishes | The permit requires an occupancy certificate before occupation; no issued certificate is established here |
| Identifier / date | P02400001274 |
|---|---|
| What the supplied record establishes | RERA registration is the project’s principal registration identifier Approvals record |
The registration certificate records plot number 602, survey number 44/1 and PIN 500049. The supplied material does not include a current registration-status extract or an occupancy/completion certificate.
1. Project at a glance
Project identity
Registered project name: BM ENCLAVE
Project type: Residential apartment project
Phase / registered portion: Phase not separately identified in the supplied record; the registration is for BM ENCLAVE
TG-RERA registration: P02400001274
Registration validity: 19/10/2019 to 02/02/2025; certificate states “5 years.” No extension is recorded in the supplied certificate
Registered promoter: BHRAMARAMBHA MALLIKARJUNA CONSTRUCTIONS
Entity type: Partnership
RERA status: The supplied certificate records registration through 02/02/2025. Current registration status is not established by the material supplied
Land and geographic identity
Locality: Miyapur
Revenue village: Miyapur; also written as “MIYAPUR VILLAGE” in the building-permit record
Mandal: Not disclosed in the project identity fields; registration certificate separately states Kukatpally mandal
District: Ranga Reddy in the project identity and land records
PIN: 500049
Project survey number(s) / subdivision(s): Survey No. 44/1; no subdivision is stated
Registered site extent: 325.4 m² in the land and building-permit records
Net / total area: Total area 325.4 m²; net area 325.40 m²; recorded road-affected and nala-affected areas are 0
Boundaries: East: ROAD WIDTH 40; West: PLOT NO 604 AND 621; North: PLOT NO 622; South: PLOT NO 603
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC)
Principal building approval: Approval No. 1/C21/02008/2019, approved 02 February 2019; permit order also identifies File No. 1/C21/13443/2018
Approved built-up area: 1,267.72 m² in the RERA project fields
Sanctioned building arrangement: One proposed residential building, Stilt + 5; sanctioned height 14.89 m
Sanctioned areas by level: Stilt: 169.42 m²; residential upper floors (5): 915.25 m²
Building count: One building / one tower recorded
Parking levels / provision: Stilt and cellar are identified in the permit conditions as parking areas; the supplied extraction does not state a parking-space count, and it does not establish a separate cellar level in the listed sanctioned floor configuration
Units: 10 units in the RERA unit record; the permit condition says sanctioned unit numbers must not be increased without prior GHMC approval
Offering and status
Configuration: 2BHK
RERA-filed saleable area: 106.13 m² per unit
Booked / available: 0 booked and 10 available in the RERA portal-derived record; no as-of date is supplied, so these counts are indicative
Construction stage: No reliable project construction-progress update or independently verified site status is supplied
Completion deadline: The registration certificate and Form B declaration state 02/02/2025
Occupancy / completion certificate: No occupancy or completion certificate is identified in the supplied documents; the GHMC permit requires an occupancy certificate before occupation
2. The project story
BM ENCLAVE is recorded with TG-RERA as a residential apartment project on Plot No. 602 in Survey No. 44/1, Miyapur, with a single proposed Stilt + 5 residential building and 10 two-bedroom units. The building permit records a 325.4 m² site and 1,267.72 m² approved built-up area in the project fields.
The RERA unit record shows all 10 units as available, but it carries no as-of date. The registration certificate and promoter’s Form B declaration state a completion date of 02/02/2025. The material supplied does not establish construction progress, completed portions, or an issued occupancy certificate; accordingly, the project’s present physical stage cannot be confirmed from this evidence.
3. Master plan, architecture & building design
The filed project and GHMC permit records describe one proposed residential building on a 325.4 m² site, with a stilt level and five residential upper floors. The permit gives a building height of 14.89 m and records 169.42 m² for the stilt and 915.25 m² for the residential upper floors. The project fields separately report approved built-up area of 1,267.72 m². These are the figures as recorded; the supplied material does not provide a separate FSI-counted area or a verified footprint calculation.
The permit conditions require construction to follow the sanctioned plan and call for a completion notice and occupancy certificate before occupation. It also records four rainwater-harvesting structures, 15 trees, transformer space and a garbage house; the tot-lot is listed as 0 m² in the permit extraction. Detailed floor-by-floor layouts, flat counts per floor, lift and stair arrangements, circulation dimensions and landscape/open-space plans are not available in the supplied drawing-derived information.
The project’s layout plan is filed as a RERA document, but the supplied record does not provide an extracted layout description. The approval identifier to trace in Approvals is 1/C21/02008/2019; the permit also cites layout/subdivision number 2209/MP2/HUDA/1990.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 10 | 0 | 10 | 106.13 m² | Software-measured median 76.4 m²; range 66.1–83.3 m² | 28% |
Unit count, booking count, availability and saleable area are from the RERA unit record; booking counts have no stated as-of date. Carpet-area measurements and loading are software-derived from the floor-plan drawing, are not RERA-filed disclosures, and are marked for review. Saleable area is the RERA-filed figure and is not interchangeable with carpet area; the supplied drawing data notes that saleable area includes a share of common areas.
The measured first-floor plan for flat 01 shows a living/dining area, two bedrooms, kitchen, two toilets, wash area and foyer, with a balcony shown but excluded from carpet area. The supplied room measurements are drawing-based, not separately verified site measurements.
5. Parking & vehicle circulation
The GHMC permit states that the cellar and stilt approved for parking must be used exclusively for vehicle parking, without partition walls or rolling shutters. The permit extraction does not establish the number of sanctioned spaces, resident or visitor allocations, accessible spaces, two-wheeler provision, ramp arrangement or EV charging. No unit-specific parking allocation is documented in the material supplied; a drawn or approved parking area alone would not establish exclusive ownership.
6. Amenities, recreation & open spaces
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Tot-lot / green strip | Permit lists “Tot-lot (m2) 0”; condition says it is to be fenced and maintained as greenery before occupancy certificate | GHMC building permit | Required by permit condition; completion not established |
| Trees | 15 trees listed | GHMC building permit | Listed in permit extraction; planting or survival not verified |
| Street lighting | Listed in RERA amenities record; no size or count supplied | RERA amenities record | Progress percentage shown as 0; completion not established |
| Community buildings | Listed in RERA amenities record; no area supplied | RERA amenities record | Progress percentage shown as 0; completion not established |
| Recreational open space | Listed; aggregate area not supplied | RERA amenities record | Progress percentage shown as 0; completion not established |
| Internal roads and footpaths | Listed; dimensions not supplied | RERA amenities record | Progress percentage shown as 0; completion not established |
No project-specific evidence supplied here establishes a clubhouse, swimming pool, gym, jogging track or other indoor/sports facilities as sanctioned or delivered amenities.
7. Utilities, building services & safety
The RERA amenities record lists water supply and sewerage (including chambers, lines, septic tank/STP) as available, but records progress as 0 for these entries. The same record lists storm-water drains, water conservation/rainwater harvesting, solid-waste management, energy management, and fire protection and safety requirements, without supplied capacities or verified completion status.
The GHMC permit specifically requires a rainwater-harvesting percolation pit, space for a transformer, and an ETP as per standard specification; it also lists four rainwater-harvesting structures and a garbage house. These are permit-recorded requirements or provisions, not evidence that the facilities have been installed or commissioned.
No supplied project evidence specifies water source or storage capacity, STP capacity or treated-water reuse, electrical backup capacity, lift number or capacity, fire-system details, CCTV/access-control installation, waste-segregation arrangements, or accessible routes. The permit requires an occupancy certificate before occupation.
8. Location, access & connectivity
The registered project location is Miyapur, Survey No. 44/1, Ranga Reddy District, Telangana, PIN 500049; the GHMC permit identifies Plot No. 602 in Miyapur village.
The supplied location record identifies Financial District (Nanakramguda) at 1.2 km. No approach-road description, public-transport details or other measured landmark distances are supplied for this overview.
9. Developer & development status
The registered promoter is BHRAMARAMBHA MALLIKARJUNA CONSTRUCTIONS, recorded as a partnership. The RERA record identifies Jagatapi Prasad as authorised signatory and Jagatapi Vani as partner; the Form B affidavit names Sri. Jagapathi Prasad as authorised signatory. The supplied evidence does not establish a registered office address or official contact details sufficient for this profile.
The promoter’s Form B declaration, dated 2 February 2019, undertakes completion by 2 February 2025 and includes declarations concerning project funds, accounts and pending approvals. This is a promoter declaration, not independent evidence of completion. The supplied records do not establish current construction progress or an occupancy certificate.
10. Approvals, official records & documents
| Identifier / date | P02400001274; issued 19/10/2019; valid through 02/02/2025 as stated on certificate |
|---|---|
| What the supplied record establishes | Registration certificate for BM ENCLAVE; the supplied copy records a five-year validity period and no extension |
| Identifier / date | Approval No. 1/C21/02008/2019; 02 February 2019; File No. 1/C21/13443/2018 |
|---|---|
| What the supplied record establishes | Permit for a proposed Stilt + 5 building at Plot No. 602, Survey No. 44/1, Miyapur |
| Identifier / date | 2209/MP2/HUDA/1990 |
|---|---|
| What the supplied record establishes | Number stated in the building-permit record; underlying layout approval details are not extracted here |
| Identifier / date | Dated 2 FEB 2019 |
|---|---|
| What the supplied record establishes | Promoter declaration including completion undertaking and statements about title, encumbrances and project obligations |
| Identifier / date | Document 54543 |
|---|---|
| What the supplied record establishes | Filed layout-plan document; supplied record does not include an extracted layout description |
| Identifier / date | Not identified in supplied documents |
|---|---|
| What the supplied record establishes | The permit requires an occupancy certificate before occupation; no issued certificate is established here |
| Identifier / date | P02400001274 |
|---|---|
| What the supplied record establishes | RERA registration is the project’s principal registration identifier |
The registration certificate records plot number 602, survey number 44/1 and PIN 500049. The supplied material does not include a current registration-status extract or an occupancy/completion certificate.
Frequently asked questions
Is BM ENCLAVE registered with Telangana RERA?
Yes. BM ENCLAVE is registered with the Telangana Real Estate Regulatory Authority as P02400001274; the registration status is New Project.
Who is the developer of BM ENCLAVE?
The promoter named in the RERA registration is BHRAMARAMBHA MALLIKARJUNA CONSTRUCTIONS.
Where is BM ENCLAVE located?
BM ENCLAVE is in MIYAPUR, Rangareddy, Telangana (500049).
When will BM ENCLAVE be completed?
The promoter's proposed date of completion filed with RERA is 02/02/2025. This is the promoter's declaration, not a guarantee.