Manbhum - A Grove By The Lake

MANBHUM CONSTRUCTION COMPANY PRIVATE LIMITED · Medchal-Malkajgiri · RERA P02200004600

MANBHUM - A GROVE BY THE LAKE is a residential apartment project in Kailash Hills, Qutballapur Mandal, Medchal-Malkajgiri District. The registered promoter is MANBHUM CONSTRUCTION COMPANY PRIVATE LIMITED. The project has a site area of 11,488.34 m² and comprises two residential towers and one clubhouse building; Tower 1 has 2 Cellar + Stilt + 12 upper floors, Tower 2 has Stilt + 12 upper floors, and the clubhouse has Ground + 3 upper floors. The RERA unit record identifies 175 3BHK homes and 2 2BHK homes, and the project is registered under TG-RERA P02200004600 with proposed completion on 16/07/2028.

More from Manbhum Construction Company Pvt Ltd · 8 projects →

01What we found

RegisteredTG-RERA - valid till 16 Mar 2028
22documents on file - each fact links to its page
8court cases on this project's land (survey 281, 282, 283, 284, 288, 295 and 3 more, Kailash Hills)
6items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

6 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

ItemProject record
Registered project nameMANBHUM - A GROVE BY THE LAKE RERA record
Project type / registered portionResidential apartment project; the supplied registration record identifies a registered project but does not state a phase name or phase number. RERA record
TG-RERA registrationP02200004600
Registration validity13/06/2022 to 16/03/2028; certificate states five years, subject to the Act and rules. This is the registration-validity period, not an occupancy certificate.
Registered promoterMANBHUM CONSTRUCTION COMPANY PRIVATE LIMITED RERA record
RERA statusRegistration certificate supplied; no extension is recorded in that certificate.

Land and geographic identity

ItemProject record
LocalityKailash Hills RERA record RERA filing
Revenue villageGajularamaram Village, as stated in the filed building-permit and commencement-intimation documents. The RERA header separately records “Kailash Hills” as village/locality; the revenue-village identity is therefore presented here as the document-stated village. RERA record
Mandal / district / PINQutballapur / Medchal-Malkajgiri / 500055 RERA record
Survey numbersPart of 299, 300, 301 and 281 to 284, 288 & 295; permit lists 299, 300, 301, 281, 282, 283, 284, 288 and 295, and the commencement letter specifies “300, 301 Part.” RERA record
Plot numbers237, 240 & 241
Site extent11,488.34 m²; the permit records site area and net area as 11,488.34 m², road-affected area 0 m² and nala-affected area 0 m².
Boundaries in RERA land detailsNorth: 60 Feet Wide Public Road; East: 30 Feet Wide Public Road; West: Part of Sy Nos 299 300 301; South: Part of Sy Nos 299 and 301. RERA filing

Development identity

ItemProject record
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC)
Principal approvalBuilding Permit No. 1/C26/00247/2022, approved 16 March 2022; file no. 1/C26/08581/2021. Approvals record
Approved built-up area46,009 m² in the RERA project fields. The permit extraction separately gives a total of 44,509,595.73 in its sanctioned-parameters text; the supplied extraction does not label that total in a way that permits treating it as the approved built-up-area figure. RERA filing
BuildingsTwo residential towers and one clubhouse building are described in the GHMC permit. The project fields state two building units; the clubhouse is separately identified in the permit. RERA filing
Sanctioned floor configurationClubhouse: Ground + 3 upper floors; Tower 1: 2 Cellar + Stilt + 12 upper floors; Tower 2: Stilt + 12 upper floors.
Parking levelsTower 1 has two cellar levels and a stilt level; Tower 2 has a stilt level. The permit says cellar and stilt areas approved for parking are to be used exclusively for vehicle parking. Parking-space counts are not established in the supplied record.
Unit countsRERA fields state 288 total building units; the normalized sale configurations account for 177 homes (175 3BHK and 2 2BHK). The remaining 111 rows are listed as door-number entries, not sale configurations, and are not counted here as homes. RERA filing RERA unit table

Offering and status

ItemProject record
RERA-filed configurations3BHK and 2BHK RERA unit table
Filed saleable-area range127.88–159.8 m² across the two filed configurations RERA unit table
Booked / available54 booked and 123 available across the two recognized configurations: 3BHK—53 booked / 122 available; 2BHK—1 booked / 1 available. Portal counts are indicative; no as-of date is supplied. RERA unit table
Construction stageNo independently verified construction-stage evidence or site progress percentage is supplied. A promoter letter dated 16.05.2022 gives an intimation that construction was commencing; it does not establish present progress.
Completion datesGHMC permit states construction to be completed before 16 March 2028. The RERA header separately records proposed completion as 16/07/2028; the supplied record does not identify a revised-completion approval. RERA record
Occupancy / completion certificateNo occupancy or completion certificate is supplied for either tower or the clubhouse. The GHMC permit requires an occupancy certificate before occupation.

2. The project story

  • MANBHUM - A GROVE BY THE LAKE is registered with TG-RERA as a residential apartment project at Kailash Hills, with the filed permit documents locating the site at Gajularamaram Village, Qutballapur Mandal, Medchal-Malkajgiri District. The registered land identity covers Part of 299, 300, 301 and 281 to 284, 288 & 295, and the permit records Plot Nos. 237, 240 & 241. RERA record
  • GHMC’s building permit describes two residential towers and a separate clubhouse building. The RERA unit record identifies 175 3BHK and 2 2BHK homes. Although the portal fields state 288 total building units, the other 111 rows in its unit table are door-number entries rather than recognized home configurations, so they are not treated as additional saleable homes in this profile. RERA unit table
  • The available record shows the permit and a May 2022 commencement-intimation letter, but no current construction-progress certification or site verification. Accordingly, the project’s present construction stage cannot be confirmed from the supplied evidence. The permit’s completion deadline, RERA’s proposed completion date and the registration-validity end date are separate recorded dates; none establishes that a tower or the clubhouse has received an occupancy certificate. RERA record

3. Master plan, architecture & building design

The GHMC permit records a site area of 11,488.34 m², net area of 11,488.34 m², road-affected area of 0 m², and nala-affected area of 0 m². The RERA filing separately states approved built-up area of 46,009 m². These are distinct reported measures; the supplied evidence does not provide a verified FSI-counted area or carpet-area total. RERA filing

Permit-described buildingUseSanctioned floor configurationHeight recorded in permit extraction
BUILDING-1 (TOWER1)Residential2 Cellar + Stilt + 12 upper floors35.28 m
BUILDING-1 (TOWER 2)ResidentialStilt + 12 upper floors35.27 m
BUILDING-1 (CULB HOUSE)Commercial (as classified in permit extraction)Ground + 3 upper floors14.95 m
  • The permit extraction records cellar area 15,446.70, stilt areas 2,484.70 and 1,703.00, commercial area 993.81, and residential areas 25,317.39 and 17,997.69. These values are reproduced as transcribed; the supplied extraction does not specify a unit alongside each of these entries.
  • The permit identifies a tot-lot of 1,557 m², six rainwater-harvesting structures, 570 trees, space for a transformer, a garbage house and an ETP. It also requires the sanctioned plan to be followed and the tot-lot to be fenced and maintained as greenery before an occupancy certificate.
  • No floor-by-floor unit arrangement, flats-per-floor count, lift or stair details, tower-entry layout, internal circulation drawing, or measured building footprint is supplied. The floor-plan record says two drawings are present but neither contains flats available for software measurement; no software-measured carpet areas or room dimensions can therefore be reported. Floor plans

4. Homes, configurations & floor plans

The TG-RERA unit record identifies 177 homes in recognized configurations. Filed saleable area is not the same as carpet area: the supplied file has no software-measured carpet-area results, so carpet area and loading are not available for comparison. RERA unit table RERA unit details Floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK211127.88 m²Not measured in supplied drawingsNot supplied
3BHK17553122159.8 m²Not measured in supplied drawingsNot supplied

The filing also contains 111 entries that appear as door numbers, not recognized home configurations; they are excluded from the home count and configuration table. Booked/available figures are portal counts without a supplied as-of date and should be treated as indicative. RERA unit table RERA unit details

5. Parking & vehicle circulation

The GHMC permit describes two cellar levels beneath Tower 1 and stilt levels for both residential towers. It states that cellar and stilt areas approved for parking must be used exclusively for vehicle parking, without partition walls or rolling shutters. The supplied record does not establish the number of car or two-wheeler spaces, visitor or accessible spaces, EV provision in the sanctioned plan, parking allocation to individual homes, or internal ramp and driveway arrangements. A permit-level parking provision does not by itself establish an exclusive parking right for a particular unit.

6. Amenities, recreation & open spaces

Tot-lot / greenery
Description / size1,557 m²
Evidence sourceGHMC permit
Declared progress / verified statusPermit identifies provision; completion is not verified. Permit requires fencing and maintenance as greenery before occupancy certificate.
Rainwater harvesting
Description / size6 rainwater-harvesting structures
Evidence sourceGHMC permit
Declared progress / verified statusPermit-listed; completion not verified.
Trees
Description / size570 trees
Evidence sourceGHMC permit
Declared progress / verified statusPermit-listed; planting and survival not verified.
Clubhouse building
Description / sizeGround + 3 upper floors
Evidence sourceGHMC permit
Declared progress / verified statusSanctioned building description; internal facilities and completion status are not established.
Clubhouse, swimming pool, gym, yoga area, indoor game room, banquet hall, children’s play area, walking/jogging track, mini forest
Description / sizeSizes and capacities not supplied
Evidence sourcePromoter website/vendor material Promoter website
Declared progress / verified statusPromoter-marketed features; not established as sanctioned, delivered or independently verified by the supplied project record.

The vendor list also mentions electric-car charging, solar-powered common areas, water-saving measures and waste segregation; these are marketing-source descriptions, not evidence of installed or operational facilities. Promoter website

7. Utilities, building services & safety

Service / featureSupplied evidence and status
Water supplyRERA amenity fields mark water supply “YES”; source, storage and treatment capacity are not specified. RERA amenities
Sewerage and drainageRERA amenity fields mark sewerage, storm-water drains, and treatment/disposal of sewage and sullage water “YES.” The GHMC permit requires an ETP as per standard specification. No capacity or completion evidence is supplied. RERA amenities
Rainwater harvestingPermit lists six rainwater-harvesting structures and requires a rainwater-harvesting structure (percolation pit). Installation is not verified.
ElectricalPermit requires space for a transformer; RERA amenity fields mark an electrical meter room/sub-station/receiving station “YES.” Supply, backup power and installed capacity are not stated. RERA amenities
Lifts and vertical transportationNo lift count, service-lift details or capacity supplied. Document index
Fire and life safetyRERA amenity fields mark fire protection and fire-safety requirements “YES.” The permit requires an occupancy Fire NOC from the Director (EV&DM) before issue of an occupancy certificate. The supplied record does not include that NOC or establish compliance. RERA amenities
WastePermit requires a garbage house; RERA amenity fields mark solid-waste management and disposal “YES.” Completion and operating arrangements are not verified. RERA amenities
Accessibility and circulationNo accessible route, ramp or accessibility-specific facilities are established in the supplied record. Document index

8. Location, access & connectivity

The project’s RERA identity records Kailash Hills, Qutballapur Mandal, Medchal-Malkajgiri District, PIN 500055; the filed GHMC permit and commencement-intimation letter identify the revenue village as Gajularamaram. The permit records a 60 Feet Wide Public Road to the north and a 30 Feet Wide Public Road to the east. RERA record RERA filing

The supplied location dataset lists these measured distances from its location reference: ADP, 0.0 km; IndusInd Bank, 0.4 km; Nanakramguda Govt primary school, 0.5 km; Financial District (Nanakramguda), 1.2 km; unnamed park, 1.2 km; Manuu Polytechnic Hyderabad, 1.6 km; Sankaraya Eye Hospital, 1.6 km; unnamed bus station, 2.2 km; and South India Shopping Mall, 2.6 km. These are dataset distances, not travel-time estimates. Location record

9. Developer & development status

The registered legal promoter is MANBHUM CONSTRUCTION COMPANY PRIVATE LIMITED, a private limited company. Its supplied corporate identifier is GSTIN 36AAFCM1195G2ZF. The RERA record names P. Ramakrishna Rao as Managing Director/authorized signatory; the Form B declaration is signed by him on behalf of the company and declares a six-year completion period. Corporate record Parties record

The supplied registration certificate gives validity through 16/03/2028; the permit states completion before 16 March 2028, while the RERA header records a proposed completion date of 16/07/2028. No revised-completion order, current certified progress report or occupancy certificate is included. The promoter’s 16.05.2022 commencement intimation is evidence of a filing, not independent verification of construction commencement or present progress. RERA record

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP02200004600; issued 13/06/2022; valid to 16/03/2028
What it establishes in the supplied evidenceRegistration of MANBHUM - A GROVE BY THE LAKE and stated registration conditions.
GHMC Building Permit Order
Identifier / datePermit No. 1/C26/00247/2022; file no. 1/C26/08581/2021; approved 16 March 2022
What it establishes in the supplied evidenceBuilding sanction describing the two residential towers and clubhouse, site and survey identity, floor configurations and permit conditions.
Construction commencement intimation
Identifier / date16.05.2022; cites Permit No. 1/C26/00247/2022
What it establishes in the supplied evidencePromoter letter to GHMC stating construction work is commencing; not an independent progress verification.
Form B promoter declaration
Identifier / date16 May 2022
What it establishes in the supplied evidencePromoter declaration covering title/encumbrance statements, project completion undertaking and separate-account obligations.
Layout / subdivision reference
Identifier / dateLRS/1337/631/C-15/NZ/GHMC/2008
What it establishes in the supplied evidenceNumber recorded in the GHMC permit extraction; a separate approved layout plan is not available in the supplied records.
Occupancy / completion certificate
Identifier / dateNot supplied
What it establishes in the supplied evidenceNo tower- or clubhouse-specific certificate is available in the supplied record. Document index

The supplied evidence does not include an approved-layout drawing, current construction-progress certification, or occupancy/completion certificate. The GHMC permit itself states that occupancy certification is required before occupation.

Frequently asked questions

Is MANBHUM - A GROVE BY THE LAKE registered with Telangana RERA?

Yes. MANBHUM - A GROVE BY THE LAKE is registered with the Telangana Real Estate Regulatory Authority as P02200004600; the registration status is New Project.

Who is the developer of MANBHUM - A GROVE BY THE LAKE?

The promoter named in the RERA registration is MANBHUM CONSTRUCTION COMPANY PRIVATE LIMITED.

Where is MANBHUM - A GROVE BY THE LAKE located?

MANBHUM - A GROVE BY THE LAKE is in Kailash Hills, Qutballapur, Medchal-Malkajgiri, Telangana (500055).

When will MANBHUM - A GROVE BY THE LAKE be completed?

The promoter's proposed date of completion filed with RERA is 16/07/2028. This is the promoter's declaration, not a guarantee.