MAILIKAS AYODHYA RAM is a residential apartment project at Plot No. 352/PART in Mailardevpally, Rajendranagar Mandal, Ranga Reddy District. The registered promoter is MAILIKA INFRA PROJECTS PRIVATE LIMITED. The project is on 394.83 sq. m of land and comprises one building and one block, recorded as “Existing Stilt + 4 upper floors and Proposed 1 upper floors,” with 10 TRIPLE BEDROOM apartments, each with a filed saleable area of 128.0 sq. m. Its TG-RERA registration number is P02400004898, and its proposed completion date is 27/05/2026.

More from Mailika Infra Projects Pvt Ltd · 4 projects →

01What we found

Period endedTG-RERA registration ran to 27 May 2026 - check its extension on TG-RERA
13documents on file - each fact links to its page
10court cases on this project's land (survey 160, 162, 163, 164, 165, Mailardevpally)
8items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

8 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Photo from magicbricks.com

1. Project at a glance

Project identity

FieldRecord
Registered project nameMAILIKAS AYODHYA RAM RERA record
Project type / registered portionResidential apartment project; the registration concerns the site identified as Plot No. 352/PART. A separate phase designation is not disclosed. RERA record
TG-RERA registrationP02400004898
Registration validity29/08/2022–27/05/2026, stated as three years, unless extended by the Authority. This is the registration period, not the construction completion date.
Registered promoterMAILIKA INFRA PROJECTS PRIVATE LIMITED, a company. RERA record Corporate record
RERA statusProject record identifies it as On-Going Project. The supplied registration certificate records the validity above; no extension is recorded in the supplied certificate. RERA record

Land and geographic identity

FieldRecord
LocalityMailardevpally / MAILARDEVPALLY RERA record
Revenue villageMailardevpally RERA record
Mandal / district / PINRajendranagar / Ranga Reddy / 500005 RERA record
Project survey numbers160, 162, 163/1, 164, 165/1 RERA record
SubdivisionsNo more specific project sub-divisions are identified in the supplied registration certificate; the site identifier is 352/PART. RERA record
Registered site extent394.83 sq. m RERA filing
Total / net area; affected areaTotal site area 394.83 sq. m; net area 394.83 sq. m; road-affected area 0 sq. m and nala-affected area 0 sq. m in the filed building-permit extraction. RERA filing
BoundariesEast: PLOT 355A 355B; West: ROAD; North: PLOT 352 P NORTHERN PART; South: PLOT 351. RERA filing

Development identity

FieldRecord
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC) Approvals record
Principal building approvalApproval No. 2/C11/05041/2020, dated 27 May, 2020; the related file number shown in the permit extraction is 2/C11/06530/2020. Approvals record
Approved building formOne proposed residential building, recorded as “Existing Stilt + 4 upper floors and Proposed 1 upper floors” in the 27 May 2020 permit extraction. The supplied record does not explain the “existing” and “proposed” wording further.
Height / approved built-up areaHeight 14.95 m; the supplied permit extraction includes a residential area of 234.99 m2 and an “Area (m2) second” figure of 103.44. It also contains a “Proposed Covered builtup area” entry of 11,750.00 without a clear unit in the extracted field. These entries are reproduced as recorded and should not be treated as interchangeable area measures.
Parking levelOne stilt floor is identified for parking, with 220.91 m2 recorded in the permit extraction. A sanctioned parking-space count is not supplied.
Approved versus RERA-declared unitsThe RERA filing records 10 apartments; the supplied building-permit extract does not state a unit count. RERA unit table

Offering and status

FieldRecord
RERA-filed configurationTRIPLE BEDROOM; 10 units; filed saleable area 128.0 sq. m per unit. RERA unit table RERA unit table
Booked / availablePortal-derived record: 0 booked / 10 available; the portal record has no as-of date, so these counts are indicative. RERA unit table
Construction stageRERA amenity/infrastructure progress entries show Water Supply 60%, Sewerage 30%, Storm Water Drains 10%, Rain water harvesting 30%, and Electrical Meter Room/Sub-Station/Receiving Station 30%. Other listed items show 0%. These are reported progress fields, not independent site verification. RERA amenities
Completion datesPromoter’s Form B undertaking states completion by 27/05/2026; the project record lists the original and revised proposed completion date as 27/05/2026. RERA record
Occupancy certificateA GHMC occupancy certificate, 006599/GHMC/3149/CHR2/2024-oc, dated 08/07/2024, is recorded for the building in an architect’s certificate dated 10-07-2024.

2. The project story

MAILIKAS AYODHYA RAM is registered as a residential apartment project at Plot No. 352/PART in Mailardevpally village, Rajendranagar Mandal, Ranga Reddy District. Its registered land identity lists survey numbers 160, 162, 163/1, 164 and 165/1, and the filed site extent is 394.83 sq. m. RERA record RERA filing

The GHMC permit record describes one residential building. The later permit extraction records “Existing Stilt + 4 upper floors and Proposed 1 upper floors”; the earlier permit extraction describes “1 Stilt + 4 upper floors.” The record also includes an architect’s certificate stating that construction work was completed and recording a GHMC occupancy certificate dated 08/07/2024 for the building.

The project’s RERA filing lists 10 triple-bedroom apartments. Its portal-derived inventory shows 0 booked and 10 available, but the inventory capture has no as-of date. The supplied progress fields give percentages for selected infrastructure items; they do not establish independently verified current site progress. RERA unit table RERA amenities

3. Master plan, architecture & building design

The filed GHMC permit identifies a single proposed residential building on a 394.83 m2 site, with setbacks recorded as 2 m Side I, 2 m Side II, 3 m Front and 2 m Rear. The permit extraction records a height of 14.95 m, a stilt parking floor of 220.91 m2, residential area of 234.99 m2, and an additional “Area (m2) second” entry of 103.44. The extracted “Proposed Covered builtup area 11,750.00” does not include a clear unit, so it cannot be reliably interpreted as a comparable built-up-area measure.

The earlier GHMC building-permit extraction describes 1 Stilt + 4 upper floors, height 11.96 m, residential upper-floors area 939.96 m2, and stilt area 220.91 m2. These are permit-record entries; the supplied extracts do not provide a drawing-based floor-by-floor unit schedule or explain how the entries relate to the later permit.

The RERA filing identifies one building and one block. No project layout drawing, detailed circulation plan, landscaping plan, floor-by-floor flat arrangement, lift or stair schedule, or phase plan is available in the supplied extracted records. The permit conditions refer to a tot-lot, peripheral greenery, transformer space and garbage house; the permit extraction records the tot-lot area as 0 m2. RERA filing Document index

4. Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
3BHK / filed as TRIPLE BEDROOM10010128.0 sq. m94.1 sq. m median; range 83.9–96.1 sq. m27%

RERA configuration, unit count, booked/available count and saleable area are from the project filing; the booking snapshot has no stated as-of date. RERA unit table RERA unit table

The carpet-area figures are software-measured from approved floor-plan drawing geometry, not RERA-filed carpet-area disclosures. The measurement record covers 10 3BHK designs and marks all 10 as needing review. It also notes that saleable area includes the home’s share of common areas, whereas carpet area is smaller; the supplied record does not provide a separate balcony/utility total or a RERA-filed carpet-area figure. Floor plans RERA unit details

A measured fifth-floor flat plan identifies a balcony measuring 1.6 × 3.52 m (5.63 m2). The drawing extract also lists a bedroom at 3.36 × 3.47 m (11.66 m2), kitchen at 2.51 × 2.8 m (7.03 m2), wash area at 1.0 × 2.51 m (2.51 m2), and other bedroom/toilet areas. These are drawing-based measurements and should be checked against the actual approved plan. RERA unit details

5. Parking & vehicle circulation

The GHMC permit extraction identifies one stilt parking floor of 220.91 m2 and states that cellar and stilt areas approved for parking must be used exclusively for vehicle parking without partition walls or rolling shutters. The supplied records do not establish the number of car or two-wheeler spaces, visitor or accessible spaces, parking allocation to individual apartments, or a separate parking level.

The permit names an 18 mt. road and specifies that no front compound wall is allowed for a site abutting roads of that width; an iron grill or low-height greenery hedge is permitted instead. The supplied extracts do not give details of a vehicle ramp, internal driveway, pedestrian separation or EV charging.

6. Amenities, recreation & open spaces

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Water supplyListed as available; no source, storage or treatment capacity statedRERA amenity record RERA amenities60% reported
Sewerage / sewage treatmentRERA record groups chamber, lines, septic tank and STP; no capacity statedRERA amenity record RERA amenities; marketing/vendor listing Promoter website30% reported for sewerage; treatment/disposal item separately shows 0%
Storm-water drainsNo dimensions or capacity statedRERA amenity record RERA amenities10% reported
Rain-water harvestingPermit requires a rain-water harvesting structure (percolation pit); permit extraction records 6 RWHPsRERA progress field: 30%
Tot-lot / green strip / parkPermit records tot-lot area 0 m2 and requires it to be fenced and maintained as greenery; permit extract also lists 15 TreesRERA Green Strip/TOT LOT/Park: 0%
Transformer spacePermit requires space for a transformerRERA Electrical Meter Room/Sub-Station/Receiving Station: 30%
Garbage houseRequired by the permitSolid Waste Management and Disposal: 0% in RERA progress record
Indoor games / children’s play areaListed in a vendor amenity description; no size or capacity suppliedMarketing/vendor listing Promoter websiteNo RERA progress or independent completion evidence supplied
Security / power backup / RO waterListed in a vendor amenity description; no system capacity suppliedMarketing/vendor listing Promoter websiteNo RERA progress or independent completion evidence supplied

The permit also lists 15 Trees and six rain-water harvesting pits. The RERA progress schedule records Community Buildings, Street Lighting, Energy Management and Aggregate Area of Recreational Open Space at 0%. These figures are reported fields and do not establish present physical condition. RERA amenities

7. Utilities, building services & safety

The GHMC permit requires a rain-water harvesting structure, transformer space and garbage house. It also states that sanitation, plumbing, fire-safety requirements, lifts and electrical installations are to be executed under qualified technical supervision, and that a Fire NOC from the Director (EV&DM) is required before issue of an occupancy certificate. The supplied architect’s certificate records a GHMC occupancy certificate for the building, but the underlying Fire NOC is not included in the supplied material.

The permit extraction identifies six rain-water harvesting pits and 15 trees. The RERA progress record reports water supply at 60%, sewerage at 30%, storm-water drains at 10%, rain-water harvesting at 30% and electrical meter room/sub-station/receiving station at 30%. These are project-record progress entries, not an independent inspection. RERA amenities

No verified capacities or detailed schemes are supplied for water storage/treatment, sewage treatment and reuse, electrical backup, lifts, fire-fighting equipment, waste segregation, CCTV, controlled access or accessibility. Fire-fighting equipment and 24-hour water/security are mentioned in the vendor description only. Promoter website

8. Location, access & connectivity

The registered location is Mailardevpally, Rajendranagar Mandal, Ranga Reddy District, Telangana, PIN 500005. The site is identified as Plot 352/PART and is bounded on the west by a road. The GHMC permit record refers to an 18 mt. road. RERA record RERA filing

The supplied location record places Rajiv Gandhi International Airport 8.8 km away. This is the available distance record; no travel time is supplied. A vendor listing separately names Krishnaveni Talent School (0.1 km), Sri Raghavendra Hospital (0.3 km), Zoo Logical Park (2.9 km) and Inner Ring Road (approximately 0.1 km); these are vendor-attributed figures, not independent measurements. Location record Promoter website

9. Developer & development status

The registered promoter is MAILIKA INFRA PROJECTS PRIVATE LIMITED, recorded as a company. The supplied corporate record identifies GSTIN 36AAGCM9423Q1ZR. The registration certificate gives a promoter-office address of Village: Mandal: Nampally, District: Hyderabad, Pin: 500028; the project record separately lists the promoter address as SAIVIHAR, SHANTHI NAGAR, PRAGATHI COLONY, MAILARDEVPALLY, Rajendranagar, Ranga Reddy, 500005. Corporate record RERA record

The promoter’s Form B affidavit, dated 29/07/2022, undertakes completion by 27/05/2026 and declares that the land is free from encumbrances. These are promoter declarations in the filed affidavit.

An architect’s certificate dated 10-07-2024 records completion of construction work and a GHMC occupancy certificate dated 08/07/2024 for the building. The RERA record nevertheless labels the project “On-Going Project” and carries a completion date of 27/05/2026. The supplied information does not specify separate tower or phase scopes beyond the single building identified in the permit and occupancy-certificate materials. RERA record

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP02400004898; issued 29/08/2022; valid to 27/05/2026 unless extended
Scope and sourceMAILIKAS AYODHYA RAM; survey numbers 160, 162, 163/1, 164, 165/1; Plot 352/PART.
GHMC building permit
Identifier / dateApproval No. 2/C11/05041/2020; 27 May, 2020; file No. 2/C11/06530/2020
Scope and sourceResidential building permit; survey numbers 160, 162, 163/1, 164, 165/1.
Earlier GHMC building permit
Identifier / dateApproval No. 2/C11/01630/2020; 07 February, 2020; file No. 2/C11/18861/2019
Scope and sourceResidential building permit for the same listed survey numbers.
GHMC occupancy certificate recorded in architect’s certificate
Identifier / date006599/GHMC/3149/CHR2/2024-oc; 08/07/2024
Scope and sourceBuilding scope, as recorded in Form–1A dated 10-07-2024.
RERA Form B declaration
Identifier / date29/07/2022
Scope and sourcePromoter’s title-basis, encumbrance, funding, audit, approvals and completion declarations.
Building-plan drawing records
Identifier / dateDocuments 236273 and 236274
Scope and sourceFloor-plan drawings used for software-measured unit-area information; one drawing remains unmeasured/scans pending in the supplied drawing summary. Document index Floor plans

The supplied records identify the building permits and an architect’s certificate recording the occupancy certificate. Detailed sanction conditions, land-title evidence and other project-specific regulatory matters are addressed in their respective report sections.

Frequently asked questions

Is MAILIKAS AYODHYA RAM registered with Telangana RERA?

Yes. MAILIKAS AYODHYA RAM is registered with the Telangana Real Estate Regulatory Authority as P02400004898; the registration status is On-Going Project.

Who is the developer of MAILIKAS AYODHYA RAM?

The promoter named in the RERA registration is MAILIKA INFRA PROJECTS PRIVATE LIMITED.

Where is MAILIKAS AYODHYA RAM located?

MAILIKAS AYODHYA RAM is in MAILARDEVPALLY, Rajendranagar, Rangareddy, Telangana (500005).

When will MAILIKAS AYODHYA RAM be completed?

The promoter's proposed date of completion filed with RERA is 27/05/2026. This is the promoter's declaration, not a guarantee.