Kumar Plaza
S V R CONSTRUCTIONS · Rangareddy · RERA P02400004130
KUMAR PLAZA is a residential apartment project in Himapuri Colony, Mansoorabad, Saroornagar, Ranga Reddy. It is being developed by the registered promoter S V R Constructions on a site of 501.42 m2, with one proposed residential building of 1 Stilt + 5 upper floors and 10 3BHK apartments. The project is registered under TG-RERA number P02400004130, and the promoter’s Form B declaration gives completion by 12/07/2027.
More from S V R Constructions · 3 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
10 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered name | KUMAR PLAZA RERA record |
| Project type | Residential apartment project RERA record |
| Phase / registered portion | No separate phase name is disclosed; the registration covers the project on Survey No. 10 PART |
| TG-RERA registration | P02400004130 |
| Registration validity | 15/02/2022 to 12/07/2027, subject to extension by the Authority; the certificate records no extension |
| Registered promoter | S V R Constructions |
| RERA status | Registered under section 5; the supplied record does not state that the project is completed or has an occupancy certificate |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality / address description | Himapuri Colony, Mansoorabad; the filing also records locality as “ROAD NO” RERA record RERA filing |
| Revenue village | Mansoorabad RERA record Land records |
| Mandal / district / PIN | Saroornagar / Ranga Reddy / 500068 RERA record |
| Survey number(s) and subdivision(s) | 10 PART Land records |
| Plot numbers | 10, 11 AND 12 |
| Registered site extent | 501.42 m2 in the GHMC building permit |
| Filed total / net area | RERA land details state total and net area of 501.42 sq m RERA filing |
| Permit area details | The permit lists site area 501.42 m2, road-affected area 0, nala-affected area 0, and net area 498.34 m2 |
| Boundaries | East: “PLOT NO S 1 AND 2 AND 3”; west: 30 FT ROAD; north: 30 FT ROAD; south: PLOT NO 9 RERA filing |
Development identity
| Item | Project record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC) |
| Principal building approval | Building permit 2/C3/08470/2021, approved 12 July, 2021 Approvals record |
| Permit file number | 2/C3/06231/2021 |
| Approved built-up area | 1,203.35 m2 RERA filing |
| Building count / sanctioned form | One proposed residential building, 1 Stilt + 5 upper floors; permit height 15 m |
| Parking provision recorded in permit | Stilt parking area 215.98 m2; number of parking spaces is not stated in the supplied permit extract |
| Unit count | GHMC permit parameters do not provide a unit count in the supplied extract; RERA filing records 1 building unit, while the unit schedule records 10 apartments RERA filing RERA unit table |
| Floor-by-floor arrangement | Not established by the supplied drawing extraction; no per-floor apartment count is available Document index Floor plans |
Offering and status
| Item | Project record |
|---|---|
| RERA-filed configuration | 3BHK, 10 units RERA unit table |
| RERA-filed saleable area | 71.11 sq m per filed 3BHK configuration RERA unit table |
| Booked / available | 0 booked / 10 available, as last read from the TG-RERA portal; no as-of date is supplied, so counts are indicative RERA unit table |
| Construction stage | No current construction-progress figure or independent site inspection is supplied Document index RERA amenities |
| Completion date | Promoter’s Form B declaration gives completion by 12/07/2027 |
| Registration expiry | 12/07/2027; this is the registration validity end date, separately recorded in the certificate |
| Occupancy / completion certificate | No occupancy certificate or completion certificate is included in the supplied project documents; status is therefore not established Document index |
2. The project story
KUMAR PLAZA is a RERA-registered residential apartment project on Survey No. 10 PART, comprising Plots 10, 11 AND 12 at Mansoorabad, Saroornagar Mandal, Ranga Reddy District. The GHMC permit describes one residential building at Himapuri Colony, with one stilt level and five upper floors. The RERA unit schedule records ten 3BHK apartments. RERA record Land records RERA unit table
The project’s registration remains valid through 12/07/2027. The promoter’s Form B gives that date as the completion undertaking, but the supplied record does not provide a current construction-progress assessment, a verified completion status, or an occupancy certificate. Registration validity, the stated completion date and occupancy certification are distinct matters; the latter is not established in the available documents. Document index
3. Master plan, architecture & building design
The GHMC building permit sanctions one proposed residential building of 1 Stilt + 5 upper floors, with a stated building height of 15 m and approved built-up area of 1,203.35 m2. The permit also records a stilt parking area of 215.98 m2. The supplied extraction does not establish the building footprint, apartment distribution by floor, lift or stair arrangement, or detailed circulation. RERA filing
The project is recorded on a site of 501.42 m2. The permit separately lists 498.34 m2 as net area, with road-affected and nala-affected areas each recorded as 0; the RERA land details list net and total area as 501.42 sq m. The supplied record does not identify an FSI-counted area or carpet area for the building. RERA filing
The permit lists a tot-lot area of 0 m2, 25 Trees, and 3 rainwater-harvesting structures. It also requires transformer space, a garbage house and an ETP. These are permit-record items and conditions; the supplied evidence does not establish their construction or present operational status.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 10 | 0 | 10 | 71.11 sq m | Not available: no measured flat design is reported | Not supplied |
The 3BHK configuration, unit count, booking count and saleable area are RERA-filed figures. The recorded available and booked counts are portal readings without an as-of date and should be treated as indicative. The floor-plan data identifies drawings as approved-plan drawings but reports 0 measured flat designs for the 3BHK configuration, so it provides no software-measured carpet area or room dimensions for reporting. Carpet area, saleable area and any share of common areas are different measures; no carpet-area or loading figure is established here. RERA unit table RERA unit details Floor plans
5. Parking & vehicle circulation
The GHMC permit records stilt parking with an area of 215.98 m2, within the sanctioned 1 Stilt + 5 upper-floor building. The supplied permit extract gives no parking-space count, resident/visitor allocation, accessible bays, ramp or driveway details, or unit-specific parking allocation.
The RERA unit schedule marks the 3BHK configuration as mortgaged, but the available record does not identify any particular parking bay or establish exclusive ownership or allocation to an apartment. RERA unit table
6. Amenities, recreation & open spaces
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Tot-lot | Permit records 0 m2 | Permit-recorded; completion not established | |
| Rainwater harvesting | 3 structures; permit specifies a percolation pit | Required / recorded in permit; completion not established | |
| Trees | 25 Trees recorded | Permit parameter; planting status not established | |
| Community buildings | Listed in RERA amenities schedule; no size or description supplied | RERA amenities | Schedule shows 0% progress; completion not established |
| Green strip / tot-lot / park | Listed in RERA amenities schedule; no area supplied | RERA amenities | Schedule shows 0% progress; completion not established |
The supplied permit and RERA amenities schedule do not establish a clubhouse, gym, swimming pool or other indoor or sports facility as an approved or delivered project feature. The RERA amenities schedule records the listed items at 0% progress; it does not independently verify site conditions. RERA amenities
7. Utilities, building services & safety
The building permit requires a rainwater-harvesting structure, space for a transformer, a garbage house and an ETP. It also records 3 rainwater-harvesting structures and 25 Trees among the sanctioned parameters. These are approval requirements or permit-recorded provisions, not evidence that the facilities have been installed or are operating.
The RERA amenities schedule lists water supply, sewerage (including chambers, lines, septic tank and STP), storm-water drains, sewage and sullage treatment/disposal, solid-waste management, energy management, fire protection and safety, and an electrical meter room/sub-station/receiving station. The schedule records 0% progress for these items; water source and storage capacity, treatment capacity, electrical backup, lift details, fire-system specifications, security systems and accessible circulation are not established by the supplied records. RERA amenities
8. Location, access & connectivity
The registered location is Mansoorabad village, Saroornagar Mandal, Ranga Reddy District, Telangana, PIN 500068; the building permit locates the proposed building at Himapuri Colony, Mansoorabad. The project is bounded by 30 FT ROAD on the west and north. RERA record RERA filing RERA filing
A supplied location record gives the nearest sampled Outer Ring Road interchange as approximately 7.0 km away. This is a location-data distance, not a measured travel time. No further approach-road route, public-transport service or landmark distance is established in the supplied project records. Location record
9. Developer & development status
The registered promoter is S V R Constructions, recorded in the RERA filing as a partnership. The filing lists GSTIN 36ADPFS2777N1Z3. The supplied promoter address is New Samathapuri Colony, Himapuri Colony, Road No, Saroornagar, Ranga Reddy, PIN 500068; the project record does not provide an official telephone number, email address or website. RERA record RERA filing Corporate record Parties record
The building permit names Dr. A. Bhavani Reddy and others as owners/applicants and S.V.R. Constructions as developer/applicant representative. The project title materials describe a development agreement-cum-GPA; the permit itself records that permission does not confer ownership rights.
The promoter’s Form B declaration undertakes completion by 12/07/2027 and includes declarations concerning project funds, audits and approvals. No current construction progress or independently verified completion is supplied. Document index
10. Approvals, official records & documents
| Record | Supplied evidence |
|---|---|
| TG-RERA registration | Form C registration certificate for KUMAR PLAZA, P02400004130, issued 15/02/2022, valid through 12/07/2027 |
| GHMC building permit | Building Permit Order 2/C3/08470/2021, file 2/C3/06231/2021, approved 12 July, 2021; permits one residential building of 1 Stilt + 5 upper floors |
| RERA Form B declaration | Promoter declaration dated 12-10-2021, including the stated completion undertaking and project-fund declarations |
| Title materials filed with RERA | Advocate’s title report and development agreement-cum-GPA materials are listed in the project document record |
| Occupancy / completion certificate | Not present in the supplied documents; status not established Document index |
The supplied GHMC permit lists conditions including submission of a commencement notice before construction, a completion notice and occupancy certificate after completion, and occupancy certification before occupation. The permit also records rainwater harvesting, transformer space, a garbage house and ETP requirements.
1. Project at a glance
Project identity
Registered name: KUMAR PLAZA
Project type: Residential apartment project
Phase / registered portion: No separate phase name is disclosed; the registration covers the project on Survey No. 10 PART
TG-RERA registration: P02400004130
Registration validity: 15/02/2022 to 12/07/2027, subject to extension by the Authority; the certificate records no extension
Registered promoter: S V R Constructions
RERA status: Registered under section 5; the supplied record does not state that the project is completed or has an occupancy certificate
Land and geographic identity
Locality / address description: Himapuri Colony, Mansoorabad; the filing also records locality as “ROAD NO”
Revenue village: Mansoorabad
Mandal / district / PIN: Saroornagar / Ranga Reddy / 500068
Survey number(s) and subdivision(s): 10 PART
Plot numbers: 10, 11 AND 12
Registered site extent: 501.42 m2 in the GHMC building permit
Filed total / net area: RERA land details state total and net area of 501.42 sq m
Permit area details: The permit lists site area 501.42 m2, road-affected area 0, nala-affected area 0, and net area 498.34 m2
Boundaries: East: “PLOT NO S 1 AND 2 AND 3”; west: 30 FT ROAD; north: 30 FT ROAD; south: PLOT NO 9
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC)
Principal building approval: Building permit 2/C3/08470/2021, approved 12 July, 2021
Permit file number: 2/C3/06231/2021
Approved built-up area: 1,203.35 m2
Building count / sanctioned form: One proposed residential building, 1 Stilt + 5 upper floors; permit height 15 m
Parking provision recorded in permit: Stilt parking area 215.98 m2; number of parking spaces is not stated in the supplied permit extract
Unit count: GHMC permit parameters do not provide a unit count in the supplied extract; RERA filing records 1 building unit, while the unit schedule records 10 apartments
Floor-by-floor arrangement: Not established by the supplied drawing extraction; no per-floor apartment count is available
Offering and status
RERA-filed configuration: 3BHK, 10 units
RERA-filed saleable area: 71.11 sq m per filed 3BHK configuration
Booked / available: 0 booked / 10 available, as last read from the TG-RERA portal; no as-of date is supplied, so counts are indicative
Construction stage: No current construction-progress figure or independent site inspection is supplied
Completion date: Promoter’s Form B declaration gives completion by 12/07/2027
Registration expiry: 12/07/2027; this is the registration validity end date, separately recorded in the certificate
Occupancy / completion certificate: No occupancy certificate or completion certificate is included in the supplied project documents; status is therefore not established
2. The project story
KUMAR PLAZA is a RERA-registered residential apartment project on Survey No. 10 PART, comprising Plots 10, 11 AND 12 at Mansoorabad, Saroornagar Mandal, Ranga Reddy District. The GHMC permit describes one residential building at Himapuri Colony, with one stilt level and five upper floors. The RERA unit schedule records ten 3BHK apartments.
The project’s registration remains valid through 12/07/2027. The promoter’s Form B gives that date as the completion undertaking, but the supplied record does not provide a current construction-progress assessment, a verified completion status, or an occupancy certificate. Registration validity, the stated completion date and occupancy certification are distinct matters; the latter is not established in the available documents.
3. Master plan, architecture & building design
The GHMC building permit sanctions one proposed residential building of 1 Stilt + 5 upper floors, with a stated building height of 15 m and approved built-up area of 1,203.35 m2. The permit also records a stilt parking area of 215.98 m2. The supplied extraction does not establish the building footprint, apartment distribution by floor, lift or stair arrangement, or detailed circulation.
The project is recorded on a site of 501.42 m2. The permit separately lists 498.34 m2 as net area, with road-affected and nala-affected areas each recorded as 0; the RERA land details list net and total area as 501.42 sq m. The supplied record does not identify an FSI-counted area or carpet area for the building.
The permit lists a tot-lot area of 0 m2, 25 Trees, and 3 rainwater-harvesting structures. It also requires transformer space, a garbage house and an ETP. These are permit-record items and conditions; the supplied evidence does not establish their construction or present operational status.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 10 | 0 | 10 | 71.11 sq m | Not available: no measured flat design is reported | Not supplied |
The 3BHK configuration, unit count, booking count and saleable area are RERA-filed figures. The recorded available and booked counts are portal readings without an as-of date and should be treated as indicative. The floor-plan data identifies drawings as approved-plan drawings but reports 0 measured flat designs for the 3BHK configuration, so it provides no software-measured carpet area or room dimensions for reporting. Carpet area, saleable area and any share of common areas are different measures; no carpet-area or loading figure is established here.
5. Parking & vehicle circulation
The GHMC permit records stilt parking with an area of 215.98 m2, within the sanctioned 1 Stilt + 5 upper-floor building. The supplied permit extract gives no parking-space count, resident/visitor allocation, accessible bays, ramp or driveway details, or unit-specific parking allocation.
The RERA unit schedule marks the 3BHK configuration as mortgaged, but the available record does not identify any particular parking bay or establish exclusive ownership or allocation to an apartment.
6. Amenities, recreation & open spaces
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Tot-lot | Permit records 0 m2 | Permit-recorded; completion not established | |
| Rainwater harvesting | 3 structures; permit specifies a percolation pit | Required / recorded in permit; completion not established | |
| Trees | 25 Trees recorded | Permit parameter; planting status not established | |
| Community buildings | Listed in RERA amenities schedule; no size or description supplied | Schedule shows 0% progress; completion not established | |
| Green strip / tot-lot / park | Listed in RERA amenities schedule; no area supplied | Schedule shows 0% progress; completion not established |
The supplied permit and RERA amenities schedule do not establish a clubhouse, gym, swimming pool or other indoor or sports facility as an approved or delivered project feature. The RERA amenities schedule records the listed items at 0% progress; it does not independently verify site conditions.
7. Utilities, building services & safety
The building permit requires a rainwater-harvesting structure, space for a transformer, a garbage house and an ETP. It also records 3 rainwater-harvesting structures and 25 Trees among the sanctioned parameters. These are approval requirements or permit-recorded provisions, not evidence that the facilities have been installed or are operating.
The RERA amenities schedule lists water supply, sewerage (including chambers, lines, septic tank and STP), storm-water drains, sewage and sullage treatment/disposal, solid-waste management, energy management, fire protection and safety, and an electrical meter room/sub-station/receiving station. The schedule records 0% progress for these items; water source and storage capacity, treatment capacity, electrical backup, lift details, fire-system specifications, security systems and accessible circulation are not established by the supplied records.
8. Location, access & connectivity
The registered location is Mansoorabad village, Saroornagar Mandal, Ranga Reddy District, Telangana, PIN 500068; the building permit locates the proposed building at Himapuri Colony, Mansoorabad. The project is bounded by 30 FT ROAD on the west and north.
A supplied location record gives the nearest sampled Outer Ring Road interchange as approximately 7.0 km away. This is a location-data distance, not a measured travel time. No further approach-road route, public-transport service or landmark distance is established in the supplied project records.
9. Developer & development status
The registered promoter is S V R Constructions, recorded in the RERA filing as a partnership. The filing lists GSTIN 36ADPFS2777N1Z3. The supplied promoter address is New Samathapuri Colony, Himapuri Colony, Road No, Saroornagar, Ranga Reddy, PIN 500068; the project record does not provide an official telephone number, email address or website.
The building permit names Dr. A. Bhavani Reddy and others as owners/applicants and S.V.R. Constructions as developer/applicant representative. The project title materials describe a development agreement-cum-GPA; the permit itself records that permission does not confer ownership rights.
The promoter’s Form B declaration undertakes completion by 12/07/2027 and includes declarations concerning project funds, audits and approvals. No current construction progress or independently verified completion is supplied.
10. Approvals, official records & documents
TG-RERA registration: Form C registration certificate for KUMAR PLAZA, P02400004130, issued 15/02/2022, valid through 12/07/2027
GHMC building permit: Building Permit Order 2/C3/08470/2021, file 2/C3/06231/2021, approved 12 July, 2021; permits one residential building of 1 Stilt + 5 upper floors
RERA Form B declaration: Promoter declaration dated 12-10-2021, including the stated completion undertaking and project-fund declarations
Title materials filed with RERA: Advocate’s title report and development agreement-cum-GPA materials are listed in the project document record
Occupancy / completion certificate: Not present in the supplied documents; status not established
The supplied GHMC permit lists conditions including submission of a commencement notice before construction, a completion notice and occupancy certificate after completion, and occupancy certification before occupation. The permit also records rainwater harvesting, transformer space, a garbage house and ETP requirements.
Frequently asked questions
Is KUMAR PLAZA registered with Telangana RERA?
Yes. KUMAR PLAZA is registered with the Telangana Real Estate Regulatory Authority as P02400004130; the registration status is New Project.
Who is the developer of KUMAR PLAZA?
The promoter named in the RERA registration is S V R CONSTRUCTIONS.
Where is KUMAR PLAZA located?
KUMAR PLAZA is in ROAD NO, Mansoorabad, Saroornagar, Rangareddy, Telangana (500068).
When will KUMAR PLAZA be completed?
The promoter's proposed date of completion filed with RERA is 12/11/2027. This is the promoter's declaration, not a guarantee.