Lakshmi Anantha Nilayam
SRI KALYANI CONSTRUCTIONS · Hyderabad · RERA P02500010808
LAKSHMI ANANTHA NILAYAM is a residential apartment project at H NO1-9-328/2 PLOT NO 4, near Ramnagar Gundu, Vidya Nagar, Amberpet mandal, Hyderabad district. The registered promoter is SRI KALYANI CONSTRUCTIONS. The project has a gross plot area of 420.28 sq.m and one residential building, BUILDING-2, with 1 Stilt + 5 Floors and 10 2BHK units, each with a RERA-filed saleable area of 112.18 sq.m. It is registered under TG-RERA registration P02500010808, and the proposed completion date is 4 December 2028.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
7 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Record |
|---|---|
| Registered project name | LAKSHMI ANANTHA NILAYAM RERA record |
| Project type | Residential apartment project RERA record |
| Registered phase/portion | A single registered project/building is shown; no separate phase name is disclosed. RERA record |
| TG-RERA registration | P02500010808 RERA record |
| Registration validity | 04/12/2025 to 04/12/2028 (three years, unless extended by the Authority). This is the registration period, not the building-completion deadline. RERA record |
| Registered promoter | SRI KALYANI CONSTRUCTIONS, identified as a partnership firm RERA record RERA filing |
| RERA status | Registered; project status is recorded as “New Project.” RERA record Approvals record |
Land and geographic identity
| Field | Record |
|---|---|
| Registered locality and site description | H NO1-9-328/2 PLOT NO 4, near Ramnagar Gundu, Vidya Nagar, Hyderabad, PIN 500044 RERA record |
| Revenue village | VIDYA NAGAR is the village recorded in the project identity. No project survey number or subdivision is disclosed in the RERA land identity. RERA record Land records |
| Mandal / district | Amberpet / Hyderabad RERA record RERA filing |
| Survey/subdivision | Not disclosed in the project land identity. Land records |
| Site extent | GHMC plan record: gross plot area 420.28 sq.m; road-affected area 86.19 sq.m; net plot area 334.09 sq.m. |
| Boundaries in project record | North: H NO 1-9-328; South: H NO 1-9-328; East: H NO 1-9-328; West: 30 WIDE ROAD RERA filing |
Development identity
| Field | Record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC) |
| Principal building approval | 2117/GHMC/SWBP/SEC1/2025, approved 04/12/2025 Approvals record |
| File number | 004415/GHMC/02239/SWBP/SEC1/2025 |
| Approved building | One residential building, identified in the plan as BUILDING-2; 1 Stilt + 5 Floors |
| Approved built-up area | Proposed BUA excluding parking: 878.6 sq.m; including parking: 1054.24 sq.m. The plan also records gross BUA 1078.80 sq.m and net BUA 878.60 sq.m. These are distinct plan-record figures. |
| Building height | 17.8 m building height and 20.8 m total height in the plan parameters; another sanction parameter records height of building as 15.0 m. |
| Parking provision in sanction | Parking area 175.64 sq.m; 11.00 car parking spaces. |
| Units | 10 dwelling units in the GHMC permission and RERA configuration record. RERA unit table |
Offering and status
| Field | Record |
|---|---|
| RERA-filed configuration | 2BHK, 10 units RERA unit table |
| RERA-filed saleable area | 112.18 sq.m per unit RERA unit table |
| Portal booking status | 0 booked; 10 available, as last read from the TG-RERA portal. The record has no booking-count as-of date, so counts are indicative. RERA unit table |
| Completion deadline | Promoter’s Form B undertaking: 4 December 2028. GHMC plan record also states construction completion before 04/12/2028. |
| Construction stage | RERA amenity/infrastructure progress fields supplied here are all 0%. No independent site-progress verification is supplied. RERA amenities |
| Occupancy/completion certificate | No completion certificate is recorded in the supplied project documents; the GHMC permission requires an Occupancy Certificate before occupation. |
2. The project story
LAKSHMI ANANTHA NILAYAM is registered as a residential apartment project by SRI KALYANI CONSTRUCTIONS at H NO1-9-328/2, Plot No 4, near Ramnagar Gundu in Vidya Nagar, Hyderabad. The RERA record describes one registered building and a 2BHK offering; GHMC’s building-permit record sanctions 1 Stilt + 5 Floors and 10 dwelling units. RERA record
The plan records a gross plot area of 420.28 sq.m, with 86.19 sq.m affected by road widening, leaving a net plot area of 334.09 sq.m. The sanctioned plan includes 11.00 car parking spaces and a parking area of 175.64 sq.m.
The promoter’s Form B undertaking sets completion by 4 December 2028; the RERA registration remains valid to 04/12/2028. These are separate milestones. The supplied file does not establish completed construction or an issued OC; the GHMC conditions require an OC before occupation.
3. Master plan, architecture & building design
- The GHMC building-permit record describes BUILDING-2 as a residential building with 1 Stilt + 5 Floors. The plan lists a proposed coverage area of 176.38 sq.m (53%), total proposed BUA excluding parking of 878.6 sq.m, total proposed BUA including parking of 1054.24 sq.m, parking area of 175.64 sq.m, and gross BUA of 1078.80 sq.m. These are reported as separate figures in the supplied plan record and are not interchangeable.
- The plan’s floor-area schedule lists a stilt floor of 176.38 sq.m, floors 1–5 at 176.46 sq.m each, and terrace 20.12 sq.m; the fifth floor is labelled “TDR.” The plan also records front, rear and side setbacks of 3.00m, 2.00m, 2.00m and 2.00m, respectively.
- The approved plan identifies a lift and staircase, and the RERA-filed typical-floor-plan drawing labels 2BHK rooms and open-to-air balconies. The supplied material does not state a number of lifts, flats per floor, lift capacity, or a detailed circulation arrangement.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 10 | 0 | 10 | 112.18 sq.m | Median 62.2 sq.m; measured range 52.3–72.6 sq.m | 45% |
- The unit count, booking/availability figures and saleable area are from the RERA configuration record; booking figures have no supplied as-of date. The carpet-area figures are software-measured from the floor-plan drawings, not RERA-filed carpet-area disclosures, and are marked as needing review. The supplied drawing measurement covers 4 flat designs. RERA unit table RERA unit details Floor plans
- The RERA-filed saleable area is distinct from drawing-measured carpet area: the drawing-measurement note says saleable area also includes the home’s share of common areas. The supplied room schedule includes a dining area, bedrooms, kitchen, toilets, puja space, and open-to-air balconies; a utility area is separately labelled and excluded from the measured carpet area. Some room dimensions are absent from the extracted schedule. Floor plans RERA unit details
5. Parking & vehicle circulation
GHMC’s plan record provides 11.00 car parking spaces and a parking area of 175.64 sq.m; the sanctioned configuration is 1 Stilt + 5 Floors, with the stilt area recorded as 176.38 sq.m. The plan conditions state that cellar and stilt areas approved for parking must be used exclusively for vehicle parking and not converted or misused.
No separate resident/visitor or accessible-space counts, two-wheeler count, mechanical parking, EV-charger count, ramp arrangement, or unit-specific parking allocation is established in the supplied material. GHMC’s conditions require parking places in buildings to be provided with Electric Vehicle Charging Infrastructure, but the documents supplied do not establish installation or completion.
6. Amenities, recreation & open spaces
The RERA amenities record lists 14 infrastructure and amenity categories, each with 0% progress recorded. These percentages are declared record fields; no independent completion verification is supplied. RERA amenities
| Description / size | Tot-lot and greenery are specified; no size or capacity supplied |
|---|---|
| Evidence source | GHMC plan conditions; RERA amenity record RERA amenities |
| Declared progress / verified status | RERA progress 0%; completion not independently verified |
| Description / size | Listed as an amenity category; no building or size details supplied |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; completion not independently verified |
| Description / size | Listed as an amenity category; no dimensions supplied |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; completion not independently verified |
| Description / size | Listed as an amenity category |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; completion not independently verified |
| Description / size | Listed in vendor-provided amenity information; not established as delivered in the RERA progress record |
|---|---|
| Evidence source | Promoter website RERA amenities |
| Declared progress / verified status | Marketing/vendor information; RERA progress for green strip/tot-lot/park 0% |
| Description / size | Listed in vendor-provided amenity information; no project-specific completion evidence supplied |
|---|---|
| Evidence source | Promoter website |
| Declared progress / verified status | Not independently verified |
The GHMC plan conditions require a tot-lot to be fenced and maintained as greenery, tree planting along the periphery and in front of the premises, and maintenance of a peripheral greenery strip.
7. Utilities, building services & safety
- The GHMC plan calls for a rainwater-harvesting structure (percolation pit); the building-permit extract separately records 3 rainwater-harvesting pits and 10 trees. The plan also requires space for a transformer and a garbage house. These are plan requirements/recorded provisions, not confirmation that installation is complete.
- The RERA amenity record lists water supply, sewerage and treatment/disposal of sewage and sullage water, storm-water drains, solid-waste management, water conservation/rainwater harvesting, energy management, fire protection, and an electrical meter room/sub-station/receiving station; all supplied progress entries are 0%. No capacity, source, treatment process, backup-power specification, STP capacity, or completion evidence is supplied. RERA amenities
- The plan identifies a lift and staircase. GHMC’s conditions require services including sanitation, plumbing, fire safety, lifts and electrical installations to be carried out under qualified technical personnel supervision; they also require an Occupancy Fire NOC before issue of the OC. The documents supplied do not establish an issued Fire NOC or OC.
8. Location, access & connectivity
- The registered project location is H NO1-9-328/2 PLOT NO 4, Vidya Nagar, near Ramnagar Gundu, Hyderabad 500044, in Amberpet mandal, Hyderabad district. The supplied GHMC plan identifies the site as MCH No. 1-9-328/2, Street No. 07, near Ram Nagar Gundu, Vidyanagar. RERA record RERA filing
- The plan records an existing road width of 9.5m and a proposed road width of 18.0m; it also identifies the west boundary as a 30 WIDE ROAD. These are record descriptions, not independent measurements of current road conditions. RERA filing
- The location record gives HITEC City at 14.7 km. No travel time or public-transport route is supplied in the official location record. Location record
9. Developer & development status
- The registered promoter is SRI KALYANI CONSTRUCTIONS, identified in the RERA project information as a partnership. Its GSTIN is 36ACGFS0591L2ZP. The supplied Form B affidavit states that the firm is a partnership and gives a registered office at Flat No. 407, Plot No. 997, Sy No. 11/32, R R Residency, Ayyappa Society, Near Meridian School, Madhapur, Telangana 500081. RERA filing Corporate record
- The Form B declaration is signed by Sri Devulapalli Sobhanadri Seshasai, stated to be authorised for the promoter, and undertakes completion by 4 December 2028. No independent construction-progress report is supplied; the RERA amenity-progress entries provided are 0%. RERA amenities
10. Approvals, official records & documents
| Record | Details |
|---|---|
| TG-RERA registration certificate | Project LAKSHMI ANANTHA NILAYAM, registration P02500010808, valid 04/12/2025–04/12/2028 |
| GHMC building permission | Approval 2117/GHMC/SWBP/SEC1/2025, approved 04/12/2025; file 004415/GHMC/02239/SWBP/SEC1/2025 |
| Building-permit/plan material | Sanctions one residential building, 1 Stilt + 5 Floors, with 10 dwelling units |
| Form B declaration | Promoter declaration for the project, including the stated completion undertaking |
| Completion/occupancy records | No completion certificate or issued OC is included in the supplied records. GHMC conditions require an OC before occupation. |
The project evidence supplied here does not identify a project survey number or subdivision. The plan and permit conditions also specify that commencement and completion notices, an Occupancy Certificate and an Occupancy Fire NOC are required at the relevant stages; this overview does not treat those requirements as evidence that the certificates have been issued. Land records
1. Project at a glance
Project identity
Registered project name: LAKSHMI ANANTHA NILAYAM
Project type: Residential apartment project
Registered phase/portion: A single registered project/building is shown; no separate phase name is disclosed.
TG-RERA registration: P02500010808
Registration validity: 04/12/2025 to 04/12/2028 (three years, unless extended by the Authority). This is the registration period, not the building-completion deadline.
Registered promoter: SRI KALYANI CONSTRUCTIONS, identified as a partnership firm
RERA status: Registered; project status is recorded as “New Project.”
Land and geographic identity
Registered locality and site description: H NO1-9-328/2 PLOT NO 4, near Ramnagar Gundu, Vidya Nagar, Hyderabad, PIN 500044
Revenue village: VIDYA NAGAR is the village recorded in the project identity. No project survey number or subdivision is disclosed in the RERA land identity.
Mandal / district: Amberpet / Hyderabad
Survey/subdivision: Not disclosed in the project land identity.
Site extent: GHMC plan record: gross plot area 420.28 sq.m; road-affected area 86.19 sq.m; net plot area 334.09 sq.m.
Boundaries in project record: North: H NO 1-9-328; South: H NO 1-9-328; East: H NO 1-9-328; West: 30 WIDE ROAD
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC)
Principal building approval: 2117/GHMC/SWBP/SEC1/2025, approved 04/12/2025
File number: 004415/GHMC/02239/SWBP/SEC1/2025
Approved building: One residential building, identified in the plan as BUILDING-2; 1 Stilt + 5 Floors
Approved built-up area: Proposed BUA excluding parking: 878.6 sq.m; including parking: 1054.24 sq.m. The plan also records gross BUA 1078.80 sq.m and net BUA 878.60 sq.m. These are distinct plan-record figures.
Building height: 17.8 m building height and 20.8 m total height in the plan parameters; another sanction parameter records height of building as 15.0 m.
Parking provision in sanction: Parking area 175.64 sq.m; 11.00 car parking spaces.
Units: 10 dwelling units in the GHMC permission and RERA configuration record.
Offering and status
RERA-filed configuration: 2BHK, 10 units
RERA-filed saleable area: 112.18 sq.m per unit
Portal booking status: 0 booked; 10 available, as last read from the TG-RERA portal. The record has no booking-count as-of date, so counts are indicative.
Completion deadline: Promoter’s Form B undertaking: 4 December 2028. GHMC plan record also states construction completion before 04/12/2028.
Construction stage: RERA amenity/infrastructure progress fields supplied here are all 0%. No independent site-progress verification is supplied.
Occupancy/completion certificate: No completion certificate is recorded in the supplied project documents; the GHMC permission requires an Occupancy Certificate before occupation.
2. The project story
LAKSHMI ANANTHA NILAYAM is registered as a residential apartment project by SRI KALYANI CONSTRUCTIONS at H NO1-9-328/2, Plot No 4, near Ramnagar Gundu in Vidya Nagar, Hyderabad. The RERA record describes one registered building and a 2BHK offering; GHMC’s building-permit record sanctions 1 Stilt + 5 Floors and 10 dwelling units.
The plan records a gross plot area of 420.28 sq.m, with 86.19 sq.m affected by road widening, leaving a net plot area of 334.09 sq.m. The sanctioned plan includes 11.00 car parking spaces and a parking area of 175.64 sq.m.
The promoter’s Form B undertaking sets completion by 4 December 2028; the RERA registration remains valid to 04/12/2028. These are separate milestones. The supplied file does not establish completed construction or an issued OC; the GHMC conditions require an OC before occupation.
3. Master plan, architecture & building design
- The GHMC building-permit record describes BUILDING-2 as a residential building with 1 Stilt + 5 Floors. The plan lists a proposed coverage area of 176.38 sq.m (53%), total proposed BUA excluding parking of 878.6 sq.m, total proposed BUA including parking of 1054.24 sq.m, parking area of 175.64 sq.m, and gross BUA of 1078.80 sq.m. These are reported as separate figures in the supplied plan record and are not interchangeable.
- The plan’s floor-area schedule lists a stilt floor of 176.38 sq.m, floors 1–5 at 176.46 sq.m each, and terrace 20.12 sq.m; the fifth floor is labelled “TDR.” The plan also records front, rear and side setbacks of 3.00m, 2.00m, 2.00m and 2.00m, respectively.
- The approved plan identifies a lift and staircase, and the RERA-filed typical-floor-plan drawing labels 2BHK rooms and open-to-air balconies. The supplied material does not state a number of lifts, flats per floor, lift capacity, or a detailed circulation arrangement.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 10 | 0 | 10 | 112.18 sq.m | Median 62.2 sq.m; measured range 52.3–72.6 sq.m | 45% |
- The unit count, booking/availability figures and saleable area are from the RERA configuration record; booking figures have no supplied as-of date. The carpet-area figures are software-measured from the floor-plan drawings, not RERA-filed carpet-area disclosures, and are marked as needing review. The supplied drawing measurement covers 4 flat designs.
- The RERA-filed saleable area is distinct from drawing-measured carpet area: the drawing-measurement note says saleable area also includes the home’s share of common areas. The supplied room schedule includes a dining area, bedrooms, kitchen, toilets, puja space, and open-to-air balconies; a utility area is separately labelled and excluded from the measured carpet area. Some room dimensions are absent from the extracted schedule.
5. Parking & vehicle circulation
GHMC’s plan record provides 11.00 car parking spaces and a parking area of 175.64 sq.m; the sanctioned configuration is 1 Stilt + 5 Floors, with the stilt area recorded as 176.38 sq.m. The plan conditions state that cellar and stilt areas approved for parking must be used exclusively for vehicle parking and not converted or misused.
No separate resident/visitor or accessible-space counts, two-wheeler count, mechanical parking, EV-charger count, ramp arrangement, or unit-specific parking allocation is established in the supplied material. GHMC’s conditions require parking places in buildings to be provided with Electric Vehicle Charging Infrastructure, but the documents supplied do not establish installation or completion.
6. Amenities, recreation & open spaces
The RERA amenities record lists 14 infrastructure and amenity categories, each with 0% progress recorded. These percentages are declared record fields; no independent completion verification is supplied.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Green strip / tot-lot / park | Tot-lot and greenery are specified; no size or capacity supplied | GHMC plan conditions; RERA amenity record | RERA progress 0%; completion not independently verified |
| Community buildings | Listed as an amenity category; no building or size details supplied | 0%; completion not independently verified | |
| Internal roads and footpaths | Listed as an amenity category; no dimensions supplied | 0%; completion not independently verified | |
| Street lighting | Listed as an amenity category | 0%; completion not independently verified | |
| Landscape garden, park and children’s play area | Listed in vendor-provided amenity information; not established as delivered in the RERA progress record | Marketing/vendor information; RERA progress for green strip/tot-lot/park 0% | |
| Security, CCTV and waste disposal | Listed in vendor-provided amenity information; no project-specific completion evidence supplied | Not independently verified |
The GHMC plan conditions require a tot-lot to be fenced and maintained as greenery, tree planting along the periphery and in front of the premises, and maintenance of a peripheral greenery strip.
7. Utilities, building services & safety
- The GHMC plan calls for a rainwater-harvesting structure (percolation pit); the building-permit extract separately records 3 rainwater-harvesting pits and 10 trees. The plan also requires space for a transformer and a garbage house. These are plan requirements/recorded provisions, not confirmation that installation is complete.
- The RERA amenity record lists water supply, sewerage and treatment/disposal of sewage and sullage water, storm-water drains, solid-waste management, water conservation/rainwater harvesting, energy management, fire protection, and an electrical meter room/sub-station/receiving station; all supplied progress entries are 0%. No capacity, source, treatment process, backup-power specification, STP capacity, or completion evidence is supplied.
- The plan identifies a lift and staircase. GHMC’s conditions require services including sanitation, plumbing, fire safety, lifts and electrical installations to be carried out under qualified technical personnel supervision; they also require an Occupancy Fire NOC before issue of the OC. The documents supplied do not establish an issued Fire NOC or OC.
8. Location, access & connectivity
- The registered project location is H NO1-9-328/2 PLOT NO 4, Vidya Nagar, near Ramnagar Gundu, Hyderabad 500044, in Amberpet mandal, Hyderabad district. The supplied GHMC plan identifies the site as MCH No. 1-9-328/2, Street No. 07, near Ram Nagar Gundu, Vidyanagar.
- The plan records an existing road width of 9.5m and a proposed road width of 18.0m; it also identifies the west boundary as a 30 WIDE ROAD. These are record descriptions, not independent measurements of current road conditions.
- The location record gives HITEC City at 14.7 km. No travel time or public-transport route is supplied in the official location record.
9. Developer & development status
- The registered promoter is SRI KALYANI CONSTRUCTIONS, identified in the RERA project information as a partnership. Its GSTIN is 36ACGFS0591L2ZP. The supplied Form B affidavit states that the firm is a partnership and gives a registered office at Flat No. 407, Plot No. 997, Sy No. 11/32, R R Residency, Ayyappa Society, Near Meridian School, Madhapur, Telangana 500081.
- The Form B declaration is signed by Sri Devulapalli Sobhanadri Seshasai, stated to be authorised for the promoter, and undertakes completion by 4 December 2028. No independent construction-progress report is supplied; the RERA amenity-progress entries provided are 0%.
10. Approvals, official records & documents
TG-RERA registration certificate: Project LAKSHMI ANANTHA NILAYAM, registration P02500010808, valid 04/12/2025–04/12/2028
GHMC building permission: Approval 2117/GHMC/SWBP/SEC1/2025, approved 04/12/2025; file 004415/GHMC/02239/SWBP/SEC1/2025
Building-permit/plan material: Sanctions one residential building, 1 Stilt + 5 Floors, with 10 dwelling units
Form B declaration: Promoter declaration for the project, including the stated completion undertaking
Completion/occupancy records: No completion certificate or issued OC is included in the supplied records. GHMC conditions require an OC before occupation.
The project evidence supplied here does not identify a project survey number or subdivision. The plan and permit conditions also specify that commencement and completion notices, an Occupancy Certificate and an Occupancy Fire NOC are required at the relevant stages; this overview does not treat those requirements as evidence that the certificates have been issued.
Frequently asked questions
Is LAKSHMI ANANTHA NILAYAM registered with Telangana RERA?
Yes. LAKSHMI ANANTHA NILAYAM is registered with the Telangana Real Estate Regulatory Authority as P02500010808; the registration status is New Project.
Who is the developer of LAKSHMI ANANTHA NILAYAM?
The promoter named in the RERA registration is SRI KALYANI CONSTRUCTIONS.
Where is LAKSHMI ANANTHA NILAYAM located?
LAKSHMI ANANTHA NILAYAM is in NEAR RAMNAGAR GUNDU, VIDYA NAGAR, Amberpet, Hyderabad, Telangana (500044).
When will LAKSHMI ANANTHA NILAYAM be completed?
The promoter's proposed date of completion filed with RERA is 04/04/2029. This is the promoter's declaration, not a guarantee.
More projects in Amberpet