Shree Arunachala Apartments
VENKATA RAMANI NAGARAJAN · Medchal-Malkajgiri · RERA P02200009933
Shree Arunachala Apartments is a residential apartment project at Geetha Nagar, Safilguda / Malkajgiri, in Malkajgiri mandal, Medchal-Malkajgiri district. The registered promoter is VENKATA RAMANI NAGARAJAN. The project comprises one residential building on 738.37 sq. m, with 1 Stilt + 5 upper floors and 10 3BHK apartments. It is registered under TG-RERA number P02200009933, valid from 22/04/2025 to 22/04/2028, and proposed completion is by 22-04-2028.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
8 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered project name | Shree Arunachala Apartments RERA record |
| Project type and registered portion | Residential apartment project; the evidence identifies one building and one registered project. A separate phase name or phase-specific registration is not disclosed. RERA record |
| TG-RERA registration | P02200009933; valid from 22/04/2025 to 22/04/2028. This is the registration validity period, not a construction or occupancy certificate. RERA record |
| Registered promoter | VENKATA RAMANI NAGARAJAN. The Form B describes him as proprietor of HREEM KARANA NILAYA; the registered promoter’s legal-entity type is listed as proprietorship. RERA record Corporate record |
| RERA status | Registration certificate supplied; the record gives the project status as New Project. RERA record |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality | Geetha Nagar, Safilguda / Malkajgiri, as stated in the filed project and building-permit records. RERA filing |
| Revenue village | Malkajgiri is recorded in the project identity and building-permit extraction; the layout-plan extraction describes the site as Geetha Nagar, Safilguda. RERA record |
| Mandal / district / PIN | Malkajgiri mandal; Medchal-Malkajgiri district; 500011. RERA record |
| Survey number(s) | Sy. No. 304. No subdivision is disclosed in the project identity or supplied approval extracts. RERA filing |
| Premises / plot | 30-265/8/53, Plot No. 53. RERA filing |
| Registered site extent | 738.37 sq. m; net area 738.37 sq. m. The RERA land record also reports total area 738.37 sq. m and affected area 0 sq. m. RERA filing Land records |
| Boundaries recorded in the RERA project fields | North: Road; East: Road; West: Plot No. 63; South: Plot No. 52. RERA filing |
| Roads shown in the plan material | 9.00 MT WIDE and 9.00 M 30'0" WIDE ROAD; an 18 mt. road width is also referenced in the supplied plan/permit material. |
Development identity
| Item | Project record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC). Approvals record |
| Principal building approval | Building Permit Order 5209/GHMC/SEC/2025-BP, approved 22 April 2025; file no. 014480/GHMC/6633/SEC2/2024-BP. Approvals record |
| Building use and count | One residential building, named PROP (BUILDING) in the plan extraction. |
| Sanctioned configuration | 1 Stilt + 5 upper floors. The permit records building height 14.6; the plan extraction separately records total height 17.95 mt. from GL. |
| Approved built-up area | The plan extraction lists Total Proposed Built Up Area Excluding Parking: 2018.25, Total Proposed Built Up Area Including Parking: 2413.19, and Total BUA: 2483.33. The permit extraction separately lists residential upper floors 2,018.25, stilt 397.87, and total parking area 284.9. These are figures as recorded in the respective filed extracts; their area labels are retained as supplied. |
| Unit counts | 10 units in the RERA unit record; the plan extraction also states 10 units. The project identity fields separately show “Total Building Units (as per approved plan)” and “Proposed Building Units (as per agreement)” as 1 each, without clarifying that field’s unit-count basis. RERA unit table RERA filing |
| Parking | Stilt parking area is shown as 394.94 in the plan extraction; the building-permit extraction lists total parking area 284.9. A sanctioned space count and individual unit allocations are not provided in the supplied records. |
Offering and status
| Item | Project record |
|---|---|
| Configuration | 3BHK, 10 units. RERA unit table RERA unit details |
| RERA-filed saleable area | 206.0 sq. m for the 3BHK configuration. RERA unit table RERA unit details |
| Booked / available | 0 booked / 10 available, as last read from the TG-RERA portal; the record has no as-of date, so treat counts as indicative. RERA unit table |
| Construction stage | The project is recorded as a New Project; no construction-progress percentage or independently verified site-progress report is supplied. RERA record RERA amenities |
| Completion deadline | The Form B declaration gives completion by 22-04-2028; the building permit says construction is to be completed before 22 April, 2028. |
| Occupancy / completion certificate | The supplied building-permit extraction states completion_certified: false. No occupancy certificate is supplied. The permit requires an occupancy certificate before occupation. |
2. The project story
Shree Arunachala Apartments is a registered residential apartment project on Plot No. 53, premises 30-265/8/53, in Sy. No. 304, at Geetha Nagar, Safilguda, Malkajgiri. The supplied project and approval records describe a single building on a site recorded as 738.37 sq. m, with residential use and a sanctioned arrangement of one stilt level and five upper floors. RERA record RERA filing
The RERA unit record lists ten 3BHK apartments, with zero booked and ten available when the portal data was last read; that record has no as-of date. The sanctioned building permit sets a completion deadline of 22 April 2028, and the promoter’s Form B states the same date. The evidence pack does not provide a construction-progress percentage or an independently verified site inspection, so the current physical stage cannot be confirmed from these records. RERA unit table
The building permit requires completion notice and an occupancy certificate before occupation, and the supplied permit extraction does not record completion certification. Registration validity through 22/04/2028 is a separate matter from the construction deadline and does not establish that the building is complete or occupiable.
3. Master plan, architecture & building design
The filed plan and GHMC permit describe one residential building on a site of 738.37 sq. m, with 1 Stilt + 5 upper floors. The plan extraction records Net Area of Plot: 738.37, Total Proposed Built Up Area Excluding Parking: 2018.25, Total Proposed Built Up Area Including Parking: 2413.19, Total BUA: 2483.33, and Parking Area: 394.94. It also lists balcony area 282.65, vacant plot area 316.43, and accessory use area 9.00. These are distinct labels from the supplied approval extraction and should not be treated as interchangeable area measures.
The building-permit extraction records plot area 738.37 sq. m, road-affected area 0.0, nala-affected area 0.0, net plot area 738.37 sq. m, residential upper floors 2,018.25, stilt 397.87, and total parking area 284.9. It describes the building height as 14.6. The plan extraction separately records total height 17.95 mt. from GL and building height 14.60 MT.
The supplied materials do not establish the number of apartments per floor, building footprint, internal circulation, lift count, stair configuration, or the detailed arrangement of common areas. The permit/plan list a lift, transformer space, a tot-lot and greenery-related conditions, but do not provide a complete architectural description of their layout.
4. Homes, configurations & floor plans
The RERA filing lists ten 3BHK units, with a saleable area of 206.0 sq. m per configuration; the RERA record reports zero booked and ten available, with no as-of date. RERA unit table RERA unit details
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 10 | 0 | 10 | 206.0 sq. m | Software-measured range: 130.2–141.8 sq. m; median 134.2 sq. m | 35% RERA unit table RERA unit details Floor plans |
The carpet-area figures are software measurements from the supplied floor-plan drawing geometry, not RERA-filed measurements, and the source flags them for review. The filing’s saleable area is a separate RERA figure and must not be read as carpet area. Saleable area can include the home’s share of common areas; the supplied records do not provide a RERA-filed carpet-area figure. Floor plans RERA unit details
The measured drawing set covers eight 3BHK flat designs. A measured example identifies bedrooms, toilets, kitchen, living/dining and utility; the utility is excluded from the software-measured carpet area. Dimensions and room areas in that example are drawing-based measurements, not RERA disclosures. RERA unit details Floor plans
5. Parking & vehicle circulation
The filed plan describes stilt parking and records a stilt parking area of 394.94; it also lists a Parking Area of 394.94. The GHMC building-permit extraction separately records Total Parking Area 284.9. These are area figures, not parking-space counts. The materials do not establish the number of car or two-wheeler spaces, visitor or accessible parking, unit-wise parking allocation, or whether any particular bay is exclusively allotted to a buyer.
The plan conditions state that stilt parking approved in the plan must be used exclusively for vehicle parking, without partition walls or rolling shutters, and not converted to another use. No detailed ramp, driveway, vehicle-entry or pedestrian-separation information is supplied. The plan contains an EV-charging requirement for parking places, but the evidence does not establish installation or operational status.
6. Amenities, recreation & open spaces
The project’s RERA amenities record lists 14 categories; the supplied progress values are 0 for the listed items, and this is not independent verification of site conditions. The GHMC plan/permit also lists facilities and conditions as shown below. RERA amenities
| Description / size | Tot-lot is listed in the plan; RERA amenity record says Green Strip/TOT LOT/Park available: YES. No size is supplied. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA-listed; progress value 0 in the amenities record. Plan requires the tot-lot to be fenced and maintained as greenery before occupancy certificate; completion is not verified. |
| Description / size | Plan requires tree plantation along the periphery and in front of the premises, and a maintained strip of greenery. |
|---|---|
| Declared progress / verified status | Requirement in approval material; completion not verified. |
| Description / size | Listed in the RERA amenities record. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress value 0; no further description or completion evidence supplied. |
| Description / size | Listed in the RERA amenities record. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress value 0; completion not verified. |
| Description / size | Listed in the RERA amenities record. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress value 0; no size or project-specific description supplied. |
| Description / size | Aggregate area is listed in the RERA amenities record. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress value 0; area not supplied. |
7. Utilities, building services & safety
The filed plan/permit lists rainwater harvesting, a septic tank, a transformer, generator, emergency lighting, fire-fighting installations, hose reel/down corner, automatic sprinkler system and a lift. It also specifies separate underground static water storage of 25,000 litres and a separate terrace tank of 25,000 litres for residential buildings. These are plan/declaration items; the supplied records do not establish installation, commissioning or current operating status.
The RERA amenities record marks water supply, sewerage (including chamber, lines, septic tank and STP), and water conservation/rainwater harvesting as YES, while recording progress 0 for the listed categories. The supplied plan extraction names a septic tank but does not provide an STP capacity or evidence of a functioning treatment plant. Storm-water drains, sewage/sullage treatment and disposal, solid-waste management, energy management, fire protection, and electrical meter/substation facilities are listed in the RERA record without evidence of completed implementation. RERA amenities
The GHMC permit requires an occupancy Fire NOC before issue of an occupancy certificate and calls for fire extinguishers on each floor. The plan also requires a garbage house within the premises, a transformer space, rainwater-harvesting provision, and CCTV installation. No supplied evidence confirms these works as completed or confirms statutory clearances.
8. Location, access & connectivity
The registered project location is Malkajgiri, Medchal-Malkajgiri, PIN 500011, with the site described in the approval material as Geetha Nagar, Safilguda, Plot No. 53, Sy. No. 304. The plan material shows roads of 9.00 MT and 9.00 M 30'0" and also refers to an 18 mt. road width. The supplied data does not establish public-transport details or verified distances to landmarks for this registered site. RERA record
9. Developer & development status
The registered promoter is VENKATA RAMANI NAGARAJAN, recorded as a proprietorship. His Form B identifies him as proprietor of HREEM KARANA NILAYA. The RERA record gives the promoter address as SN-79, Sainik Nagar, GEETHANAGAR, MALKAJGIRI, Malkajgiri, Medchal-Malkajgiri, 500011. A separate corporate registration identifier or official project website/contact details are not supplied. Corporate record Parties record
The promoter’s Form B declares that project completion is due by 22-04-2028. The GHMC permit likewise requires construction to be completed before 22 April, 2028, and records commencement before 22 October, 2025. No construction-progress percentage or independently verified construction update is provided in the supplied evidence.
10. Approvals, official records & documents
| Identifier / date | P02200009933; valid 22/04/2025–22/04/2028 |
|---|---|
| Evidence and scope | Form C certificate for Shree Arunachala Apartments and promoter VENKATA RAMANI NAGARAJAN. |
| Identifier / date | 5209/GHMC/SEC/2025-BP; approved 22 April, 2025 |
|---|---|
| Evidence and scope | Building permit for one residential building at Geetha Nagar, Malkajgiri; file no. 014480/GHMC/6633/SEC2/2024-BP. |
| Identifier / date | LTP licence TS/015986/2025 |
|---|---|
| Evidence and scope | Plan extraction for the proposed residential building on Plot No. 53, Sy. No. 304; includes the stated building configuration and approval conditions. |
| Identifier / date | Form B dated 2 July 2025 |
|---|---|
| Evidence and scope | Promoter’s declaration of title, encumbrance status, completion undertaking and RERA-related undertakings. |
| Identifier / date | No completion certification or occupancy certificate supplied |
|---|---|
| Evidence and scope | The permit requires an occupancy certificate before occupation; the supplied permit extraction records completion certification as false. |
The approval material lists additional references including LRS Proceeding No. LRS30012020053653, a contractor’s all-risk policy reference 31190/44/2025/241, and notarised affidavit reference 2310/2025. These are recorded identifiers in the filed permit extraction, not substitutes for a completion or occupancy certificate.
1. Project at a glance
Project identity
Registered project name: Shree Arunachala Apartments
Project type and registered portion: Residential apartment project; the evidence identifies one building and one registered project. A separate phase name or phase-specific registration is not disclosed.
TG-RERA registration: P02200009933; valid from 22/04/2025 to 22/04/2028. This is the registration validity period, not a construction or occupancy certificate.
Registered promoter: VENKATA RAMANI NAGARAJAN. The Form B describes him as proprietor of HREEM KARANA NILAYA; the registered promoter’s legal-entity type is listed as proprietorship.
RERA status: Registration certificate supplied; the record gives the project status as New Project.
Land and geographic identity
Locality: Geetha Nagar, Safilguda / Malkajgiri, as stated in the filed project and building-permit records.
Revenue village: Malkajgiri is recorded in the project identity and building-permit extraction; the layout-plan extraction describes the site as Geetha Nagar, Safilguda.
Mandal / district / PIN: Malkajgiri mandal; Medchal-Malkajgiri district; 500011.
Survey number(s): Sy. No. 304. No subdivision is disclosed in the project identity or supplied approval extracts.
Premises / plot: 30-265/8/53, Plot No. 53.
Registered site extent: 738.37 sq. m; net area 738.37 sq. m. The RERA land record also reports total area 738.37 sq. m and affected area 0 sq. m.
Boundaries recorded in the RERA project fields: North: Road; East: Road; West: Plot No. 63; South: Plot No. 52.
Roads shown in the plan material: 9.00 MT WIDE and 9.00 M 30'0" WIDE ROAD; an 18 mt. road width is also referenced in the supplied plan/permit material.
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC).
Principal building approval: Building Permit Order 5209/GHMC/SEC/2025-BP, approved 22 April 2025; file no. 014480/GHMC/6633/SEC2/2024-BP.
Building use and count: One residential building, named PROP (BUILDING) in the plan extraction.
Sanctioned configuration: 1 Stilt + 5 upper floors. The permit records building height 14.6; the plan extraction separately records total height 17.95 mt. from GL.
Approved built-up area: The plan extraction lists Total Proposed Built Up Area Excluding Parking: 2018.25, Total Proposed Built Up Area Including Parking: 2413.19, and Total BUA: 2483.33. The permit extraction separately lists residential upper floors 2,018.25, stilt 397.87, and total parking area 284.9. These are figures as recorded in the respective filed extracts; their area labels are retained as supplied.
Unit counts: 10 units in the RERA unit record; the plan extraction also states 10 units. The project identity fields separately show “Total Building Units (as per approved plan)” and “Proposed Building Units (as per agreement)” as 1 each, without clarifying that field’s unit-count basis.
Parking: Stilt parking area is shown as 394.94 in the plan extraction; the building-permit extraction lists total parking area 284.9. A sanctioned space count and individual unit allocations are not provided in the supplied records.
Offering and status
Configuration: 3BHK, 10 units.
RERA-filed saleable area: 206.0 sq. m for the 3BHK configuration.
Booked / available: 0 booked / 10 available, as last read from the TG-RERA portal; the record has no as-of date, so treat counts as indicative.
Construction stage: The project is recorded as a New Project; no construction-progress percentage or independently verified site-progress report is supplied.
Completion deadline: The Form B declaration gives completion by 22-04-2028; the building permit says construction is to be completed before 22 April, 2028.
Occupancy / completion certificate: The supplied building-permit extraction states completion_certified: false. No occupancy certificate is supplied. The permit requires an occupancy certificate before occupation.
2. The project story
Shree Arunachala Apartments is a registered residential apartment project on Plot No. 53, premises 30-265/8/53, in Sy. No. 304, at Geetha Nagar, Safilguda, Malkajgiri. The supplied project and approval records describe a single building on a site recorded as 738.37 sq. m, with residential use and a sanctioned arrangement of one stilt level and five upper floors.
The RERA unit record lists ten 3BHK apartments, with zero booked and ten available when the portal data was last read; that record has no as-of date. The sanctioned building permit sets a completion deadline of 22 April 2028, and the promoter’s Form B states the same date. The evidence pack does not provide a construction-progress percentage or an independently verified site inspection, so the current physical stage cannot be confirmed from these records.
The building permit requires completion notice and an occupancy certificate before occupation, and the supplied permit extraction does not record completion certification. Registration validity through 22/04/2028 is a separate matter from the construction deadline and does not establish that the building is complete or occupiable.
3. Master plan, architecture & building design
The filed plan and GHMC permit describe one residential building on a site of 738.37 sq. m, with 1 Stilt + 5 upper floors. The plan extraction records Net Area of Plot: 738.37, Total Proposed Built Up Area Excluding Parking: 2018.25, Total Proposed Built Up Area Including Parking: 2413.19, Total BUA: 2483.33, and Parking Area: 394.94. It also lists balcony area 282.65, vacant plot area 316.43, and accessory use area 9.00. These are distinct labels from the supplied approval extraction and should not be treated as interchangeable area measures.
The building-permit extraction records plot area 738.37 sq. m, road-affected area 0.0, nala-affected area 0.0, net plot area 738.37 sq. m, residential upper floors 2,018.25, stilt 397.87, and total parking area 284.9. It describes the building height as 14.6. The plan extraction separately records total height 17.95 mt. from GL and building height 14.60 MT.
The supplied materials do not establish the number of apartments per floor, building footprint, internal circulation, lift count, stair configuration, or the detailed arrangement of common areas. The permit/plan list a lift, transformer space, a tot-lot and greenery-related conditions, but do not provide a complete architectural description of their layout.
4. Homes, configurations & floor plans
The RERA filing lists ten 3BHK units, with a saleable area of 206.0 sq. m per configuration; the RERA record reports zero booked and ten available, with no as-of date.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 10 | 0 | 10 | 206.0 sq. m | Software-measured range: 130.2–141.8 sq. m; median 134.2 sq. m | 35% |
The carpet-area figures are software measurements from the supplied floor-plan drawing geometry, not RERA-filed measurements, and the source flags them for review. The filing’s saleable area is a separate RERA figure and must not be read as carpet area. Saleable area can include the home’s share of common areas; the supplied records do not provide a RERA-filed carpet-area figure.
The measured drawing set covers eight 3BHK flat designs. A measured example identifies bedrooms, toilets, kitchen, living/dining and utility; the utility is excluded from the software-measured carpet area. Dimensions and room areas in that example are drawing-based measurements, not RERA disclosures.
5. Parking & vehicle circulation
The filed plan describes stilt parking and records a stilt parking area of 394.94; it also lists a Parking Area of 394.94. The GHMC building-permit extraction separately records Total Parking Area 284.9. These are area figures, not parking-space counts. The materials do not establish the number of car or two-wheeler spaces, visitor or accessible parking, unit-wise parking allocation, or whether any particular bay is exclusively allotted to a buyer.
The plan conditions state that stilt parking approved in the plan must be used exclusively for vehicle parking, without partition walls or rolling shutters, and not converted to another use. No detailed ramp, driveway, vehicle-entry or pedestrian-separation information is supplied. The plan contains an EV-charging requirement for parking places, but the evidence does not establish installation or operational status.
6. Amenities, recreation & open spaces
The project’s RERA amenities record lists 14 categories; the supplied progress values are 0 for the listed items, and this is not independent verification of site conditions. The GHMC plan/permit also lists facilities and conditions as shown below.
| Description / size | Tot-lot is listed in the plan; RERA amenity record says Green Strip/TOT LOT/Park available: YES. No size is supplied. |
|---|---|
| Declared progress / verified status | RERA-listed; progress value 0 in the amenities record. Plan requires the tot-lot to be fenced and maintained as greenery before occupancy certificate; completion is not verified. |
| Description / size | Plan requires tree plantation along the periphery and in front of the premises, and a maintained strip of greenery. |
|---|---|
| Declared progress / verified status | Requirement in approval material; completion not verified. |
| Description / size | Listed in the RERA amenities record. |
|---|---|
| Declared progress / verified status | Progress value 0; no further description or completion evidence supplied. |
| Description / size | Listed in the RERA amenities record. |
|---|---|
| Declared progress / verified status | Progress value 0; completion not verified. |
| Description / size | Listed in the RERA amenities record. |
|---|---|
| Declared progress / verified status | Progress value 0; no size or project-specific description supplied. |
| Description / size | Aggregate area is listed in the RERA amenities record. |
|---|---|
| Declared progress / verified status | Progress value 0; area not supplied. |
7. Utilities, building services & safety
The filed plan/permit lists rainwater harvesting, a septic tank, a transformer, generator, emergency lighting, fire-fighting installations, hose reel/down corner, automatic sprinkler system and a lift. It also specifies separate underground static water storage of 25,000 litres and a separate terrace tank of 25,000 litres for residential buildings. These are plan/declaration items; the supplied records do not establish installation, commissioning or current operating status.
The RERA amenities record marks water supply, sewerage (including chamber, lines, septic tank and STP), and water conservation/rainwater harvesting as YES, while recording progress 0 for the listed categories. The supplied plan extraction names a septic tank but does not provide an STP capacity or evidence of a functioning treatment plant. Storm-water drains, sewage/sullage treatment and disposal, solid-waste management, energy management, fire protection, and electrical meter/substation facilities are listed in the RERA record without evidence of completed implementation.
The GHMC permit requires an occupancy Fire NOC before issue of an occupancy certificate and calls for fire extinguishers on each floor. The plan also requires a garbage house within the premises, a transformer space, rainwater-harvesting provision, and CCTV installation. No supplied evidence confirms these works as completed or confirms statutory clearances.
8. Location, access & connectivity
The registered project location is Malkajgiri, Medchal-Malkajgiri, PIN 500011, with the site described in the approval material as Geetha Nagar, Safilguda, Plot No. 53, Sy. No. 304. The plan material shows roads of 9.00 MT and 9.00 M 30'0" and also refers to an 18 mt. road width. The supplied data does not establish public-transport details or verified distances to landmarks for this registered site.
9. Developer & development status
The registered promoter is VENKATA RAMANI NAGARAJAN, recorded as a proprietorship. His Form B identifies him as proprietor of HREEM KARANA NILAYA. The RERA record gives the promoter address as SN-79, Sainik Nagar, GEETHANAGAR, MALKAJGIRI, Malkajgiri, Medchal-Malkajgiri, 500011. A separate corporate registration identifier or official project website/contact details are not supplied.
The promoter’s Form B declares that project completion is due by 22-04-2028. The GHMC permit likewise requires construction to be completed before 22 April, 2028, and records commencement before 22 October, 2025. No construction-progress percentage or independently verified construction update is provided in the supplied evidence.
10. Approvals, official records & documents
| Identifier / date | P02200009933; valid 22/04/2025–22/04/2028 |
|---|---|
| Evidence and scope | Form C certificate for Shree Arunachala Apartments and promoter VENKATA RAMANI NAGARAJAN. |
| Identifier / date | 5209/GHMC/SEC/2025-BP; approved 22 April, 2025 |
|---|---|
| Evidence and scope | Building permit for one residential building at Geetha Nagar, Malkajgiri; file no. 014480/GHMC/6633/SEC2/2024-BP. |
| Identifier / date | LTP licence TS/015986/2025 |
|---|---|
| Evidence and scope | Plan extraction for the proposed residential building on Plot No. 53, Sy. No. 304; includes the stated building configuration and approval conditions. |
| Identifier / date | Form B dated 2 July 2025 |
|---|---|
| Evidence and scope | Promoter’s declaration of title, encumbrance status, completion undertaking and RERA-related undertakings. |
| Identifier / date | No completion certification or occupancy certificate supplied |
|---|---|
| Evidence and scope | The permit requires an occupancy certificate before occupation; the supplied permit extraction records completion certification as false. |
The approval material lists additional references including LRS Proceeding No. LRS30012020053653, a contractor’s all-risk policy reference 31190/44/2025/241, and notarised affidavit reference 2310/2025. These are recorded identifiers in the filed permit extraction, not substitutes for a completion or occupancy certificate.
Frequently asked questions
Is Shree Arunachala Apartments registered with Telangana RERA?
Yes. Shree Arunachala Apartments is registered with the Telangana Real Estate Regulatory Authority as P02200009933; the registration status is New Project.
Who is the developer of Shree Arunachala Apartments?
The promoter named in the RERA registration is VENKATA RAMANI NAGARAJAN.
Where is Shree Arunachala Apartments located?
Shree Arunachala Apartments is in MALKAJGIRI, Medchal-Malkajgiri, Telangana (500011).
When will Shree Arunachala Apartments be completed?
The promoter's proposed date of completion filed with RERA is 22/08/2028. This is the promoter's declaration, not a guarantee.
More projects in Malkajgiri