Sign in

Greater Infras Gardenia

GREATER INFRA PROJECTS PRIVATE LIMITED · Sangareddy · RERA P01100006696

GREATER INFRAS GARDENIA is a residential apartment project in Ameenapur Village, Ameenpur Mandal, Sangareddy District. It is being developed by GREATER INFRA PROJECTS PRIVATE LIMITED on a site of 3,010 sq. m, with one residential building comprising 1 Cellar + 1 Stilt + 5 upper floors and 65 homes: 35 2BHK units of 102.85 sq. m each and 30 3BHK units of 157.31 sq. m each. The project is registered with TG-RERA under P01100006696, with proposed completion on 30/11/2026.

📘 Project brochure from the promoter’s website ↗

More from Greater Infra Projects Pvt Ltd · 24 projects →

01What we found

Period endedTG-RERA registration ran to 20 May 2026 - check its extension on TG-RERA
29documents on file - each fact links to its page
0court cases on this project's land in the court records searched
7items to check - 2 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

7 items to check before you pay, 2 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

ItemProject record
Registered nameGREATER INFRAS GARDENIA RERA record
Project type / phaseResidential apartment project; registered phase or separately named portion: not disclosed RERA record
TG-RERA registrationP01100006696; Form C registration under section 5, issued 17/08/2023; captured in the supplied RERA record on 10/09/2026 RERA record
Registration validityRecorded as valid from 17/08/2023 to 20/05/2026; the supplied certificate says it is not extended. This is registration validity, not the construction-completion date. RERA record
Registered promoterGREATER INFRA PROJECTS PRIVATE LIMITED, a company RERA record Corporate record
RERA statusThe project is recorded as “New Project”; current registration status after the recorded expiry date is not established by the supplied evidence. RERA record

Land and geographic identity

ItemProject record
Locality / revenue villageAmeenapur (also written Ameenpur in project documents); one revenue village is identified: Ameenapur Village. RERA record Land records
Mandal / district / PINAmeenpur Mandal; Sangareddy District; 502032 RERA record
Survey numbers / plot numbersProject land is identified as Sy.No. 333 (also written Survey No. 333), plots 93 to 104 inclusive. No project subdivision is specified in the RERA filing or supplied building-permit extraction. Land records
Registered site extent3,010 sq. m in the RERA land record; HMDA building-permit extraction gives 3,010.06 Sq. Mt. Land records
Net / total areaRERA land record: total and net area 3010.00 sq. m; occupancy-certificate extraction: net site area 3010.06. Land records
Boundaries recorded in RERA land detailsNorth and south: 30 FEET WIDE ROAD; east: NEIGHBORS LAND; west: PLOT NOS 92 AND 105 Land records

Development identity

ItemProject record
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA) Approvals record
Building permit011529/BP/HMDA/2391/SKP/2022, approved 20 May, 2023; HMDA building permit order for plots 93–104 in Sy.No. 333 Approvals record
Approved area figuresPermit extraction lists Built-up Area: 7,678.20 Sq.mts and Total Built up Area: 10,525.05 Sq.mts as separate sanctioned parameters. The RERA filing records approved built-up area as 10,525 sq. m. RERA filing
Building count / floor configurationOne residential building: 1 Cellar + 1 Stilt + 5 upper floors; the occupancy-certificate extraction specifies 1 cellar, 1 stilt, 0 ground and 5 upper floors. RERA filing
ParkingStilt and cellar are designated for vehicle parking in the building-permit conditions. The supplied record does not establish a sanctioned space count or unit-by-unit allocation.
Unit countsRERA filing records 65 units: 35 2BHK and 30 3BHK. The filing also records one total building unit; its meaning is not further explained in the supplied data. RERA unit table RERA filing

Offering and status

ItemProject record
RERA-filed configurations and saleable area2BHK: 35 units, 102.85 sq. m each; 3BHK: 30 units, 157.31 sq. m each RERA unit table
Booked / availablePortal-derived counts show 0 booked and 35 available 2BHK units; 0 booked and 30 available 3BHK units. These counts have no supplied as-of date and are indicative. RERA unit table
Construction stageThe RERA project record labels the project “New Project”; no independently verified construction-progress report or site inspection is supplied. RERA record
Completion datesThe RERA project record gives proposed completion as 30/11/2026. The Form B declaration says the project shall be completed by 20th May, 2026. The evidence does not identify a revised completion date. RERA record
Occupancy-certificate status and scopeHMDA occupancy-certificate records identify the residential building GREATER INFRA, plots 93–104, Sy.No. 333. The supplied extraction records approval number 011393/HMDA/03333/SWOC/SKP2/2025, completion date 05/12/2025, and an occupancy certificate. This concerns the identified single building; the evidence does not establish the current RERA registration status.

2. The project story

GREATER INFRAS GARDENIA is registered with TG-RERA as a residential apartment project on plots 93–104 in Survey No. 333, Ameenapur Village, Ameenpur Mandal, Sangareddy District. The RERA land record identifies a site of 3010.00 sq. m, and the HMDA building-permit record describes one residential building with a cellar, stilt and five upper floors. RERA record Land records

The RERA unit schedule lists 35 two-bedroom and 30 three-bedroom apartments. Portal-derived booking figures show all 65 as available and none booked, but the record carries no as-of date. RERA unit table The supplied occupancy-certificate extraction records an HMDA certificate for the named building and plots in this survey. No independent site-progress evidence is supplied, so construction progress should not be inferred from the project’s “New Project” label or the certificate alone. RERA record

3. Master plan, architecture & building design

The permit extraction separately lists Built-up Area: 7,678.20 Sq.mts and Total Built up Area: 10,525.05 Sq.mts; the RERA filing records approved built-up area as 10525 sq. m. These are source-labelled built-up figures; the supplied evidence does not define them as FSI-counted, gross, carpet or saleable area. RERA filing

The supplied drawing-derived record reports that a floor-plan document was partly measured: 14 2BHK and 11 3BHK designs were software-measured from document 331338, while one drawing remains pending scanning. The data supplies sample room dimensions and configuration-level carpet-area estimates, but not enough extracted plan detail to describe building footprint, flats per floor, lift or stair arrangement, entrances, circulation or open-space layout. Software measurements are not RERA disclosures and require review against the drawings. Floor plans RERA unit details

4. Homes, configurations & floor plans

The table presents unit counts and saleable areas recorded in the TG-RERA unit schedule. Carpet-area figures are software-measured from the supplied floor-plan drawing record, not RERA-filed areas; the measurement record notes that saleable area includes the home’s share of common areas and is not interchangeable with carpet area. RERA unit table Floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK35035102.85 sq. m61.9–70.0 sq. m; median 69.1 sq. m (667–753 sq. ft; median 744 sq. ft)33%
3BHK30030157.31 sq. m94.9–106.9 sq. m; median 100.9 sq. m (1,022–1,150 sq. ft; median 1,087 sq. ft)36%

The drawing-derived sample 2BHK plan shows bedrooms, two toilets, dining, drawing room, kitchen and a utility area; the sample utility is excluded from the carpet measurement. The sample 3BHK plan shows three bedrooms, three toilets, drawing room, living/dining, kitchen, balcony and utility; balcony and utility are excluded from the measured carpet area. These are examples from individual extracted plan panels, not a guarantee that every unit has the same arrangement or dimensions. RERA unit details

The software record also measured one 4BHK design from the drawings, but 4BHK is not listed in the supplied RERA configuration schedule. It is therefore not included as a RERA-filed offering. Floor plans RERA unit details RERA unit table

5. Parking & vehicle circulation

The HMDA building-permit conditions designate the cellar and stilt for vehicle parking, without partition walls or rolling shutters, and identify a 4.5mts. road-width figure in the permit extraction. The supplied records do not give a sanctioned parking-space count, distinguish resident from visitor or accessible spaces, establish mechanical parking, or document parking allocations to individual apartments. A drawn or designated parking area should not be treated as proof of exclusive ownership or allotment.

6. Amenities, recreation & open spaces

RERA’s amenity schedule records the following facilities and declared completion percentages. These are filing entries, not independent confirmation that facilities have been delivered. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Water supplyNo source, capacity or storage volume specifiedRERA amenities scheduleYES; 100% declared; independent completion verification not supplied
Green Strip/TOT LOT/ParkNo area or dimensions specifiedRERA amenities scheduleYES; 100% declared; independent completion verification not supplied
Water conservation / rainwater harvestingNo capacity or design detail specifiedRERA amenities scheduleYES; 100% declared; independent completion verification not supplied
Electrical meter room / sub-station / receiving stationNo capacity or equipment detail specifiedRERA amenities scheduleYES; 100% declared; independent completion verification not supplied
GeneratorNo capacity or backup coverage specifiedRERA amenities scheduleYES; 100% declared; independent completion verification not supplied
CC camerasNo count or coverage specifiedRERA amenities scheduleYES; 100% declared; independent completion verification not supplied
Internal roads and footpathsNo area or specification suppliedRERA amenities schedule0% declared
Sewerage (chamber, lines, septic tank, STP)No capacity suppliedRERA amenities schedule0% declared
Storm-water drainsNo specification suppliedRERA amenities schedule0% declared
Street lightingNo specification suppliedRERA amenities schedule0% declared
Community buildingsNo size or capacity suppliedRERA amenities schedule0% declared
Treatment and disposal of sewage and sullage waterNo capacity or treatment detail suppliedRERA amenities schedule0% declared
Solid-waste management and disposalNo capacity or operating detail suppliedRERA amenities schedule0% declared
Energy managementNo system detail suppliedRERA amenities schedule0% declared
Fire protection and fire-safety requirementsNo systems or equipment details suppliedRERA amenities schedule0% declared
Aggregate recreational open spaceNo area suppliedRERA amenities schedule0% declared

7. Utilities, building services & safety

The HMDA building-permit extraction lists a transformer, garbage house, STP and rainwater-harvesting structures as amenities/utilities, and its conditions require the applicant to provide an STP and rainwater-harvesting structures. The RERA amenity schedule separately marks water supply, rainwater harvesting, electrical meter room/sub-station/receiving station, generator and CC cameras as 100% declared; it does not provide technical capacities or independent verification. RERA amenities

The permit conditions also refer to CCTV cameras, parking use of the cellar and stilt, and obtaining an occupancy certificate before occupation. The supplied evidence does not specify water sources or storage capacity, STP capacity or treated-water reuse, drainage design, electrical or generator capacity, lift number or capacity, fire-system details, accessible circulation, or security operating arrangements.

8. Location, access & connectivity

The official project location is Ameenapur Village, Ameenpur Mandal, Sangareddy District, PIN 502032; the project land is identified as Survey No. 333, plots 93–104. The RERA land record gives boundaries of 30-foot-wide roads to the north and south, neighbouring land to the east, and plots 92 and 105 to the west. RERA record Land records

The supplied geocode is the cadastral parcel centroid at 17.514068717133572, 78.34020142489469. The nearest sampled Outer Ring Road interchange is recorded at 8.7 km (approx); no route or travel time is supplied. Location record Cadastral map

9. Developer & development status

The registered legal promoter is GREATER INFRA PROJECTS PRIVATE LIMITED, a company. The supplied corporate record lists GSTIN 36AAHCG8193L1ZX. TG-RERA records the promoter address as 217/A, Opp Metro Station, Ameenpur, Ameenpur, Ameenpur, Sangareddy, 502032; the RERA certificate separately prints a promoter office at “Village: Mandal: District: Ranga Reddy, Pin: 500049.” Corporate record Parties record

The RERA record names NEKKANTI SRINIVAS as an authorised signatory and lists directors including NEKKANTI SRINIVAS, KONKA VENKATA PRASADA RAO, MANNE RAVI, JAWAHARLAL NEHRU KASUKURTHI, ADITY PRASAD CHADALAVADA and UPPALAPATI SREEKANTH. Parties record

10. Approvals, official records & documents

RecordSupplied evidence
TG-RERA registrationForm C registration certificate for GREATER INFRAS GARDENIA, No. P01100006696, issued 17/08/2023; stated validity through 20/05/2026 and no extension recorded in the supplied certificate.
HMDA building permit011529/BP/HMDA/2391/SKP/2022, approved 20 May, 2023; building permit order for the residential building on plots 93–104, Sy.No. 333.
HMDA occupancy certificate011393/HMDA/03333/SWOC/SKP2/2025; extraction identifies the building GREATER INFRA on plots 93–104, Survey No. 333, and records completion date 05/12/2025.
Duplicate supplied OC extractionDocument 707856 records the same approval and building-permit references and describes the same identified building and completion date.
Encumbrance statementDocument 337062, “Details of encumbrances”; parsed entries and period are addressed in the relevant land/title review. Document index
RERA Form B declarationDocument 331325, signed by N. Srinivas as authorised signatory; includes promoter declarations on title basis, encumbrances, completion and project-fund obligations.
Floor-plan / layout recordDocument 331338 is identified in the supplied data for floor-plan measurements; some drawing material remains unmeasured or pending scan. A publicly reachable HMDA approved-layout lookup is not available in the supplied evidence. Floor plans HMDA

Frequently asked questions

Is GREATER INFRAS GARDENIA registered with Telangana RERA?

Yes. GREATER INFRAS GARDENIA is registered with the Telangana Real Estate Regulatory Authority as P01100006696; the registration status is New Project.

Who is the developer of GREATER INFRAS GARDENIA?

The promoter named in the RERA registration is GREATER INFRA PROJECTS PRIVATE LIMITED.

Where is GREATER INFRAS GARDENIA located?

GREATER INFRAS GARDENIA is in AMEENPUR, AMEENAPUR, Sangareddy, Telangana (502032).

When will GREATER INFRAS GARDENIA be completed?

The promoter's proposed date of completion filed with RERA is 30/11/2026. This is the promoter's declaration, not a guarantee.

More projects in Ameenapur