HIGHRISE LAKSHMI RESIDENCY is a residential apartment project in Haripuri Colony, Saroornagar Mandal, Ranga Reddy District. Registered promoter HIGHRISE CONSTRUCTIONS is developing it on a 635.16 sq. m site as one building with 1 Stilt + 5 upper floors and 10 3BHK units, each with a filed saleable area of 99.64 sq. m. The project is registered under TG-RERA number P02400005508, with a proposed completion date of 23/09/2025.

More from Highrise Constructions · 4 projects →

01What we found

Period endedTG-RERA registration ran to 23 Sep 2025 - check its extension on TG-RERA
12documents on file - each fact links to its page
8court cases on this project's land (survey 9, Saroornagar)
8items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

8 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldRecord
Registered nameHIGHRISE LAKSHMI RESIDENCY RERA record
Project typeResidential apartment project RERA record
Phase / registered portionPhase is not separately identified in the supplied record; the registration is for the project at Plot B-48, Survey No. 9/1
TG-RERA registrationP02400005508
Registration validity14/12/2022 to 23/09/2025; the supplied certificate records no extension
Registered promoterHIGHRISE CONSTRUCTIONS, identified as a partnership RERA filing Parties record
RERA statusNew Project in the supplied project record. Current registration status after the stated validity end date is not established by the supplied evidence RERA record

Land and geographic identity

FieldRecord
Locality / plotHaripuri Colony; Plot No. B-48
Revenue villageSaroornagar (also rendered “SAROOR NAGAR” in the building permit) RERA record
MandalSaroornagar RERA record
DistrictRanga Reddy (the permit renders it “Rangareddy District”) RERA record
PIN500074 RERA record
Project survey number(s)Survey No. 9/1; no project subdivision is specified in the registration or permit information provided RERA filing
Registered site extent635.16 sq. m
Total / net areaBuilding permit: plot area 635.16 sq. m; road-affected area 0.0 sq. m; nala-affected area 0.0 sq. m; net plot area 635.16 sq. m
BoundariesNorth: 30FT ROAD; South: PLOT NO B-33; East: PLOT NO B-49; West: 30FT ROAD RERA filing

Development identity

FieldRecord
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC), delegated to LB NAGAR ZONE
Principal building approvalBuilding Permit Order 3325/GHMC/LBN/2022-BP, dated 23 September, 2022; file no. 008677/GHMC/4283/LBN2/2022-BP Approvals record
Other approval identifier shownC/GHMC/062199/2020, recorded as “Approved Layout No. / LRS Proceeding No. / Sub division No” in the permit
Approved built-up areaResidential upper floors: 1,677.00 Sq.Mt.; the permit separately lists stilt area of 322.78 Sq.Mt.
Building countOne permitted building, named Building Name - A (HARIPURI COLONY LAKSHMANA)
Sanctioned floor configuration1 Stilt + 5 upper floors
Building height14.99 (unit not stated in the supplied extraction)
Parking provision in permitTotal Parking Area 335.35; cellar and stilt approved for parking are to be used exclusively for vehicle parking
Unit count10 units in the RERA filing; the building permit condition says the sanctioned unit count must not be increased without prior GHMC approval, but the extracted permit does not state a numeric count RERA unit table

Offering and status

FieldRecord
RERA-filed configuration3BHK; 10 units RERA unit table
RERA-filed saleable area99.64 sq. m per unit RERA unit table
Booked / available0 booked / 10 available in the TG-RERA data supplied; portal counts are indicative and have no recorded as-of date RERA unit table
Construction stageNo independently verified construction stage or physical progress is supplied. The amenities record lists 0% against its 14 listed infrastructure items; this is a portal status, not an independent site inspection RERA amenities
Completion deadlinePromoter’s Form B undertaking and the registration certificate state 23/09/2025 as the completion end date
Occupancy / completion certificateNo OC or completion certificate is included in the supplied documents. The permit requires an occupancy certificate before occupation

2. The project story

The RERA record describes a residential apartment development on Plot B-48 in Haripuri Colony, Saroornagar, on Survey No. 9/1. GHMC’s building permit authorizes one building comprising a stilt level and five upper floors on a 635.16 sq. m site. The intended use is residential; the registration lists ten 3BHK units RERA unit table

The promoter’s stated completion date was 23/09/2025. The supplied record does not establish current construction progress, physical completion, or issuance of an OC. The portal’s 0% entries for listed infrastructure and amenities are reported as filed status only and do not independently establish on-site condition RERA amenities

3. Master plan, architecture & building design

The GHMC permit identifies one residential building, “Building Name - A (HARIPURI COLONY LAKSHMANA),” with 1 Stilt + 5 upper floors. It records 1,677.00 Sq.Mt. for residential upper floors and 322.78 Sq.Mt. for the stilt area; these are separately stated permit figures, not unit carpet or saleable areas. The permit records a 635.16 sq. m plot and the same net plot area, with 0.0 sq. m road-affected area and 0.0 sq. m nala-affected area. It also specifies a building height of 14.99 (unit not stated in the supplied extraction), total parking area of 335.35, and two rainwater-harvesting pits

Detailed floor plans, floor-by-floor apartment arrangements, building footprint, lift and stair layout, circulation drawings, landscaping dimensions, and common-area distribution are not available in the supplied evidence. The floor-plan review reports two drawings measured but no measured flat designs for the 3BHK configuration; no drawing-based carpet measurement is therefore reported here Floor plans

4. Homes, configurations & floor plans

The TG-RERA filing lists 10 3BHK units, all shown as available in the supplied portal data, with a filed saleable area of 99.64 sq. m per unit. Booked and available counts have no as-of date in the record, so treat them as indicative RERA unit table

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
3BHK1001099.64 sq. m per unitNot measured / not availableNot supplied

Two floor-plan drawings were processed, but the supplied drawing analysis reports zero measured 3BHK flat designs and says two were held back as implausible. No software-measured carpet area or room dimensions can therefore be stated. The RERA-filed saleable area is not a carpet-area measurement; the supplied evidence does not provide a carpet-area figure or a loading figure Floor plans RERA unit details RERA unit table

5. Parking & vehicle circulation

The GHMC permit records a total parking area of 335.35 and states that the cellar and stilt approved for parking are to be used exclusively for vehicle parking, without partition walls or rolling shutters. The extracted permit does not establish the number of car or two-wheeler spaces, visitor or accessible parking, or parking allocation to individual units

A promoter-level specification in the vendor record mentions “covered car parking,” but the supplied material does not document unit-specific parking allotments or independently verify that parking has been completed Promoter website

6. Amenities, recreation & open spaces

The permit includes conditions relating to a fenced tot-lot maintained as greenery, a periphery strip of greenery, a garbage house, rainwater harvesting, and transformer space. Its extracted amenity schedule lists “Tot Lot NA” and two rainwater-harvesting pits; the permit also requires the tot-lot and greenery to be maintained in accordance with its conditions

Tot-lot / greenery
Description / sizePermit schedule states “Tot Lot NA”; permit condition requires a fenced tot-lot maintained as greenery
Declared progress / verified statusPermit condition; completion not independently verified
Perimeter greenery
Description / sizeStrip of greenery on the site periphery to be maintained as per rules
Declared progress / verified statusPermit condition; completion not independently verified
Rainwater harvesting
Description / sizeTwo pits listed
Declared progress / verified statusPermit-listed; amenity portal shows 0% for water conservation/rainwater harvesting RERA amenities
Park / garden / clubhouse / pool / gym / children’s play area
Description / sizeAppears in a third-party vendor amenity list, not in the supplied GHMC permit extraction
Evidence sourcePromoter website
Declared progress / verified statusMarketing/vendor listing; not established as sanctioned or delivered

The amenity portal lists 14 infrastructure and facility categories, each with 0% progress, including internal roads and footpaths, water supply, sewerage, storm-water drains, green strip/tot-lot/park, street lighting, community buildings, sewage treatment/disposal, solid-waste management, energy management, fire safety, electrical room/sub-station and recreational open space. These are recorded portal percentages, not independent verification of site condition RERA amenities

7. Utilities, building services & safety

The building permit requires a rainwater-harvesting structure and space for a transformer, and requires a garbage house within the premises. It also states that an occupancy fire NOC from the Director (EV&DM) is to be obtained before issue of an occupancy certificate. These are permit requirements; the supplied evidence does not establish that the facilities or approvals have been completed

The RERA amenities record reports 0% progress for water supply, sewerage and sewage/sullage treatment and disposal, storm-water drains, solid-waste management, energy management, fire protection and fire safety, and electrical meter room/sub-station/receiving station. It lists water conservation and rainwater harvesting as available “YES,” while showing 0% progress. No water source or storage capacity, STP capacity, electrical or backup capacity, lift details, CCTV/access-control specification, accessibility provisions, or completed safety systems are established by the supplied project evidence RERA amenities

8. Location, access & connectivity

The registered project location is Plot B-48, Haripuri Colony, Saroornagar, Saroornagar Mandal, Ranga Reddy District, PIN 500074; the building permit also identifies Haripuri Colony and Saroornagar Mandal RERA record RERA filing

The supplied location data gives the cadastral parcel centroid as 17.35467, 78.54051 and records the nearest sampled Outer Ring Road interchange at approximately 9.3 km. The distance is a location-data measurement, not a promoter travel-time claim Location record

9. Developer & development status

The registered promoter is HIGHRISE CONSTRUCTIONS, identified in the project filing as a partnership, with GSTIN 36AAMFH9274K1ZN. The RERA record names ANNIREDDY NARSIMHA REDDY as authorized signatory. The promoter address recorded in the supplied data is SURYA MEADOWS, VASAVI COLONY, HARIPURI COLONY, KOTHAPET, Saroornagar, Ranga Reddy, 500074 Parties record Corporate record RERA filing

The promoter’s Form B declares a completion date of 23/09/2025 and includes statements about title, encumbrances and project-account obligations; these are promoter declarations, not independent verification of progress or completion. The supplied registration certificate states validity through 23/09/2025 and records no extension; the evidence provided does not establish the project’s current RERA registration status or an OC

10. Approvals, official records & documents

RecordDetailsEvidence
TG-RERA registration certificateForm C; P02400005508; project HIGHRISE LAKSHMI RESIDENCY; validity 14/12/2022–23/09/2025
GHMC building permitBuilding Permit Order 3325/GHMC/LBN/2022-BP, dated 23 September, 2022; file no. 008677/GHMC/4283/LBN2/2022-BP; one building, 1 Stilt + 5 upper floors
Additional identifier in permitC/GHMC/062199/2020, recorded as Approved Layout No. / LRS Proceeding No. / Sub division No
Form B declarationPromoter affidavit-cum-declaration; states completion date 23/09/2025
Occupancy / completion certificateNot included in the supplied evidence

The building permit makes occupancy certification compulsory before occupation and lists conditions including fire NOC before OC, rainwater harvesting, transformer space and a garbage house. The supplied documents do not establish fulfillment of these conditions or issuance of an occupancy certificate.

Frequently asked questions

Is HIGHRISE LAKSHMI RESIDENCY registered with Telangana RERA?

Yes. HIGHRISE LAKSHMI RESIDENCY is registered with the Telangana Real Estate Regulatory Authority as P02400005508; the registration status is New Project.

Who is the developer of HIGHRISE LAKSHMI RESIDENCY?

The promoter named in the RERA registration is HIGHRISE CONSTRUCTIONS.

Where is HIGHRISE LAKSHMI RESIDENCY located?

HIGHRISE LAKSHMI RESIDENCY is in KOTHAPET, Saroornagar, Rangareddy, Telangana (500074).

When will HIGHRISE LAKSHMI RESIDENCY be completed?

The promoter's proposed date of completion filed with RERA is 23/09/2025. This is the promoter's declaration, not a guarantee.