Highway Tranquil
BALAKISTI JAGDISH KUMAR · Mahabubnagar · RERA P01400008054
HIGHWAY TRANQUIL is a plotted development at Peddayapalle, Balanagar Mandal, Mahabubnagar District. The registered promoter is BALAKISTI JAGDISH KUMAR. The project covers 36874.47 sqmts and the tentative layout approval states 111 plots; buildings, floors and plot configurations are not disclosed. Its TG-RERA registration number is P01400008054, and the promoter’s declared completion date is 03-03-2026.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
11 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Project record |
|---|---|
| Registered project name | HIGHWAY TRANQUIL RERA record |
| Project type | Plotted development; the RERA record describes it as a “New Project.” RERA record RERA filing |
| Phase / registered portion | Phase not separately identified. Registration covers the project land in the survey numbers listed below; the certificate identifies the project as a whole, not a tower or building phase. RERA record |
| TG-RERA registration | P01400008054; registered from 22/04/2024 to 03/03/2026, unless extended by the Authority. RERA record Approvals record |
| Registered promoter | BALAKISTI JAGDISH KUMAR. RERA record RERA filing |
| RERA status | The supplied record identifies a new project and provides a registration certificate. Current post-expiry status or an extension is not supplied; the stated registration validity ended on 03/03/2026. RERA record Approvals record |
Land and geographic identity
| Field | Project record |
|---|---|
| Locality / revenue village | Peddayapalle (also rendered Peddaipally in the layout approval); revenue village stated as Peddayapalle. RERA record Land records |
| Mandal | Balanagar. RERA record Land records |
| District | Mahabubnagar (also rendered Mahaboobnagar in project and approval records). RERA record Land records |
| PIN | 509202. RERA record RERA filing |
| Project survey numbers / subdivisions | 2/P, 10/P, 11, 12/P, 13/P, 14, 129/P and 130/P. These are the complete survey identifiers stated in the RERA certificate and layout approval. RERA record Land records |
| Registered site extent | RERA land details state total area and net area of 36874.47 sqmts. RERA filing |
| Layout-plan area figures | The layout-plan extraction states 36873.80 as “Total net layout”; its sanctioned-parameters text also lists “Net Layout Area 36874.17.” |
| Boundaries in the RERA record | East: OTHERS LAND; West: OTHERS LAND; North: OTHERS LAND; South: ROAD. RERA filing |
Development identity
| Field | Project record |
|---|---|
| Sanctioning authority | MUDA Urban Development Authority; the approval is delegated to Peddaipally Grampanchayat. Approvals record |
| Principal layout approval | 358716/LP/GP/204903/0022/2023, approved 04-03-2024; an approval for a Tentative Layout Plan. Approvals record |
| Technical-person licence | TS/000131/2024, shown on the proposed layout plan. Approvals record |
| Approved built-up area | The RERA filing states approved built-up area 18168 sqmts. The proposed layout-plan extraction states total proposed built-up area 0.00, both excluding and including parking. These are separately reported plan-record fields, not a statement of constructed floor area. RERA filing |
| Buildings / floors | Not disclosed for this plotted layout; no building or floor configuration is supplied. The approval states that only a detached dwelling house for one family may be built on a site, subject to the stated approval conditions. |
| Plots | The tentative layout approval states 111 plots. |
| Parking | No common-parking area is recorded in the proposed layout-plan extraction (0.00). Individual plot parking provisions or buyer-specific allocations are not supplied. |
Offering and status
| Field | Project record |
|---|---|
| Offering | Plots in a plotted layout; plot-wise RERA unit counts, sizes, bookings and availability are not supplied in the provided data. RERA record RERA filing |
| Plot count | 111 plots stated in the tentative layout approval. |
| RERA completion undertaking / deadline | The promoter’s Form B declares completion by 03-03-2026. This is a promoter declaration, not independent verification of completion. |
| Revised completion date | Not supplied. RERA record |
| Construction / development stage | No current, independently verified site-progress report is supplied. Amenity entries show no progress percentage above 0%; this does not establish whether works are physically absent or simply unreported. RERA amenities |
| Occupancy / completion certificate | No occupancy or completion certificate is established by the supplied records. A file titled “Form–1A Architects certificate Overall completion of registered project” is illegible in the supplied extraction. |
2. The project story
- HIGHWAY TRANQUIL is registered as a plotted development at Peddayapalle in Balanagar Mandal, Mahabubnagar District. Its registered land covers survey numbers 2/P, 10/P, 11, 12/P, 13/P, 14, 129/P and 130/P. The RERA land details state a total and net area of 36874.47 sqmts. RERA record RERA filing
- The project record describes a layout rather than an apartment or multi-storey building development. The tentative layout approval states 111 plots and provides for roads, open space, social-infrastructure land and utility land. The proposed layout-plan extraction also identifies 111 individual subplots.
- The promoter undertook to complete the project by 03-03-2026. The supplied evidence does not establish current construction progress or completion, and does not confirm an occupancy or completion certificate. The completion undertaking, the registration validity period and any later extension are separate matters; no extension record is supplied.
3. Master plan, architecture & building design
- The filed layout is organized around 111 plots with internal roads and separately identified open-space, social-infrastructure and utility areas. The proposed layout-plan extraction records 18168.67 for plotted area, 13960.76 for roads, 3355.13 for organized open space/park, 948.22 for social infrastructure and 441.02 for utility area; its stated total net layout is 36873.80. These are plan-extraction figures, not independently measured site areas.
- The tentative layout approval gives corresponding land-use figures as a layout area of Ac. 9.111 cents 44101.507 Sq.Yds, plotted area Ac4.489 cents 21729.729 Sq.Yds (49.2720785308523554564075612%), roads Ac3.45 cents 16697.069 Sq.Yds (37.860540318602425491882258%), open space/park Ac0.829 cents 4012.735 Sq.Yds (9.0988624286322919268420143%), social infrastructure Ac 0.234 cents 1134.071 Sq.Yds (2.5715019483828381764253948%) and utilities Ac 0.109cents 527.46 Sq.Yds (1.1960133611142976235126106%). The approval also lists Plot No 5 to 18, total 14 plots, as mortgaged to the Grampanchayat.
- The proposed layout-plan extraction identifies road widths of 9.14 mt., 10.06 mt. and 12.00 mt., and notes an existing 33'-0" road to be widened to 60'-0" wide road and an existing 18.00 mt wide proposed road. These are plan annotations. The approval requires roads to be opened for access to neighbouring sites and conditions final-layout approval on completion of development works and release of the mortgaged area.
- The approval states that only a detached dwelling house designed for occupation by one family may be built on a site. It does not provide building elevations, dwelling designs, building footprints, storey limits, plot-by-plot building areas or floor plans. No apartment-style floor configuration is applicable from the supplied project records.
4. Homes, configurations & floor plans
This is a plotted project, not a filed apartment configuration schedule. The RERA data supplied does not include plot-wise booked or available counts, plot-size bands, or RERA saleable areas. The tentative layout approval states a total of 111 plots.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Plots | 111 stated in the tentative layout approval | Not supplied | Not supplied | Not supplied | Not applicable | Not supplied |
- The vendor record lists plot sizes from 1,025 - 4,013 sq ft and separately lists residential-plot figures from 1025 sq.ft to 4013 sq.ft. These are vendor-supplied figures, not RERA-filed plot measurements. Promoter website
- No plot-dimension schedule or readable plot-by-plot area table is available in the supplied layout extraction. The two drawing sheets are layout sheets and contain no measured apartment floor plans. Layout record Floor plans
5. Parking & vehicle circulation
- The proposed layout-plan extraction lists Common Parking Area 0.00. The tentative approval’s reserved mortgage area consists of Plot No 5 to 18, total 14 plots; the documents describe this as security for layout-development conditions, not as buyer parking.
- The supplied records do not state individual plot parking capacity, visitor or accessible parking, parking allotments, EV charging, vehicle-entry arrangements, or a spaces-per-plot ratio. The layout includes internal roads, but no detailed vehicle-circulation or pedestrian-separation plan is established in the extracted material.
6. Amenities, recreation & open spaces
- The tentative layout approval identifies open space/park, social-infrastructure land and utility land. It requires the developer to carry out infrastructure and amenity works, including road formation, drains and nala channelization, greenery, rainwater-harvesting pits, fencing of open spaces, street lighting, electricity facilities, sewerage disposal and protected water supply. The approval lists a water reservoir, septic tank / Sewerage Treatment Plant, electric transformer and solid-waste management among utility provisions. These are approval requirements or allocated provisions; the supplied records do not establish that the works are complete.
| Description / size | Ac0.829 cents 4012.735 Sq.Yds; 9.0988624286322919268420143% in the tentative approval. The proposed layout extraction states 3355.13. |
|---|---|
| Evidence source | Tentative layout approval; proposed layout-plan extraction |
| Declared progress / verified status | Approval provision; completion not independently verified. |
| Description / size | Ac 0.234 cents 1134.071 Sq.Yds; 2.5715019483828381764253948% in the tentative approval. The proposed layout extraction states 948.22. |
|---|---|
| Evidence source | Tentative layout approval; proposed layout-plan extraction |
| Declared progress / verified status | Land provision shown; use or facility completion not established. |
| Description / size | Ac 0.109cents 527.46 Sq.Yds; 1.1960133611142976235126106% in the tentative approval. The proposed layout extraction states 441.02. |
|---|---|
| Evidence source | Tentative layout approval; proposed layout-plan extraction |
| Declared progress / verified status | Land provision shown; utility works not independently verified. |
| Description / size | Ac3.45 cents 16697.069 Sq.Yds; 37.860540318602425491882258% in the tentative approval. |
|---|---|
| Evidence source | Tentative layout approval |
| Declared progress / verified status | Approval provision; road completion not independently verified. |
| Description / size | RERA amenity entries are present; no facility sizes or capacities are supplied. |
|---|---|
| Evidence source | RERA amenity record RERA amenities |
| Declared progress / verified status | Progress percentages recorded as 0; not independently verified. |
| Description / size | Vendor lists recreation facilities, fitness centres, swimming pools, indoor play areas, children’s activity zones and landscaped gardens, among other features; no corresponding sizes or project progress are supplied. |
|---|---|
| Evidence source | Vendor record Promoter website |
| Declared progress / verified status | Vendor-listed claims; not established as sanctioned or delivered facilities. |
The layout approval requires the open-space, social-infrastructure, utility and road areas to be handed over by registered gift deed before release of the final layout. It also states that land earmarked for open space or public purpose is not to be sold for another use.
7. Utilities, building services & safety
- The tentative layout approval requires the applicant to provide a water reservoir, septic tank / Sewerage Treatment Plant, electric transformer, solid-waste management, sewerage disposal and protected water supply. It also requires storm-water-related works, including drains and nala channelization, and rainwater-harvesting pits. These are approval requirements; the supplied evidence does not confirm installed capacity or completion.
- The RERA amenity record lists water supply, sewerage (chambers, lines, septic tank, STP), storm-water drains, water conservation/rainwater harvesting, energy management, fire protection and fire-safety requirements, and an electrical meter room/sub-station/receiving station. It records 0 progress for these listed items. No water source or storage capacity, STP capacity, power-backup capacity, fire-system specifications, security systems, accessibility provisions or service capacities are supplied. RERA amenities
8. Location, access & connectivity
- The registered location is Peddayapalle, Balanagar Mandal, Mahabubnagar District, Telangana, PIN 509202. The RERA record describes the wider locality as “Mahaboobnagar Urban Development Authority, Peddaipally Grampanchayat, Balanagar Mandal, Mahaboobnagar District.” RERA record RERA filing
- The RERA land-boundary entries identify a road to the south and other land on the east, west and north. The proposed layout plan shows internal roads with stated widths of 9.14 mt., 10.06 mt. and 12.00 mt. and road-widening annotations. RERA filing
- A supplied location record places the cadastral parcel centroid at 16.93669, 78.18925 and gives the nearest sampled Outer Ring Road interchange as approximately 41.5 km away. Location record
9. Developer & development status
- The TG-RERA-registered promoter is BALAKISTI JAGDISH KUMAR. The RERA filing records the organization type as “Others” and describes it as “SREE NILAYA HOMES PRIVATE LIMITED.” A separate legal-entity type or corporate identifier for the registered promoter is not established in the supplied identity record. The registration certificate gives the promoter’s address as KHAIRTABAD, Hyderabad, PIN 500004. RERA record RERA filing
- The promoter’s Form B affidavit, dated 22 day of MARCH -2024 at Hyderabad, declares that the project will be completed by 03-03-2026 and states that 70 per cent of amounts realized from allottees will be deposited in a separate scheduled-bank account for construction and land costs. These are promoter declarations. The supplied records do not provide current construction progress, a revised completion date or confirmation of project completion.
10. Approvals, official records & documents
| Record | What the supplied evidence establishes |
|---|---|
| TG-RERA registration certificate | Form C registration for HIGHWAY TRANQUIL, registration P01400008054, identifying Balakisti Jagdish Kumar as promoter and stating the registration period and conditions. |
| Tentative layout approval | MUDA Urban Development Authority approval 358716/LP/GP/204903/0022/2023, dated 04-03-2024, for a tentative layout with 111 plots in the listed survey numbers. The approval says it is not proof of land title. |
| Proposed layout plan | Layout-plan record for the listed survey numbers, with licence number TS/000131/2024 and extracted land-use figures. The extraction labels the instrument “PROPOSED LAYOUT PLAN.” |
| Form B promoter declaration | Affidavit-cum-declaration by BALAKISTI JAGDISH KUMAR, dated 22 day of MARCH -2024, including the promoter’s completion undertaking and project-funds declaration. |
| Completion certificate / Form–1A | A document is listed as “Form–1A Architects certificate Overall completion of registered project,” but its OCR is marked illegible; no completion or occupancy status can be established from it. |
1. Project at a glance
Project identity
Registered project name: HIGHWAY TRANQUIL
Project type: Plotted development; the RERA record describes it as a “New Project.”
Phase / registered portion: Phase not separately identified. Registration covers the project land in the survey numbers listed below; the certificate identifies the project as a whole, not a tower or building phase.
TG-RERA registration: P01400008054; registered from 22/04/2024 to 03/03/2026, unless extended by the Authority.
Registered promoter: BALAKISTI JAGDISH KUMAR.
RERA status: The supplied record identifies a new project and provides a registration certificate. Current post-expiry status or an extension is not supplied; the stated registration validity ended on 03/03/2026.
Land and geographic identity
Locality / revenue village: Peddayapalle (also rendered Peddaipally in the layout approval); revenue village stated as Peddayapalle.
Mandal: Balanagar.
District: Mahabubnagar (also rendered Mahaboobnagar in project and approval records).
PIN: 509202.
Project survey numbers / subdivisions: 2/P, 10/P, 11, 12/P, 13/P, 14, 129/P and 130/P. These are the complete survey identifiers stated in the RERA certificate and layout approval.
Registered site extent: RERA land details state total area and net area of 36874.47 sqmts.
Layout-plan area figures: The layout-plan extraction states 36873.80 as “Total net layout”; its sanctioned-parameters text also lists “Net Layout Area 36874.17.”
Boundaries in the RERA record: East: OTHERS LAND; West: OTHERS LAND; North: OTHERS LAND; South: ROAD.
Development identity
Sanctioning authority: MUDA Urban Development Authority; the approval is delegated to Peddaipally Grampanchayat.
Principal layout approval: 358716/LP/GP/204903/0022/2023, approved 04-03-2024; an approval for a Tentative Layout Plan.
Technical-person licence: TS/000131/2024, shown on the proposed layout plan.
Approved built-up area: The RERA filing states approved built-up area 18168 sqmts. The proposed layout-plan extraction states total proposed built-up area 0.00, both excluding and including parking. These are separately reported plan-record fields, not a statement of constructed floor area.
Buildings / floors: Not disclosed for this plotted layout; no building or floor configuration is supplied. The approval states that only a detached dwelling house for one family may be built on a site, subject to the stated approval conditions.
Plots: The tentative layout approval states 111 plots.
Parking: No common-parking area is recorded in the proposed layout-plan extraction (0.00). Individual plot parking provisions or buyer-specific allocations are not supplied.
Offering and status
Offering: Plots in a plotted layout; plot-wise RERA unit counts, sizes, bookings and availability are not supplied in the provided data.
Plot count: 111 plots stated in the tentative layout approval.
RERA completion undertaking / deadline: The promoter’s Form B declares completion by 03-03-2026. This is a promoter declaration, not independent verification of completion.
Revised completion date: Not supplied.
Construction / development stage: No current, independently verified site-progress report is supplied. Amenity entries show no progress percentage above 0%; this does not establish whether works are physically absent or simply unreported.
Occupancy / completion certificate: No occupancy or completion certificate is established by the supplied records. A file titled “Form–1A Architects certificate Overall completion of registered project” is illegible in the supplied extraction.
2. The project story
- HIGHWAY TRANQUIL is registered as a plotted development at Peddayapalle in Balanagar Mandal, Mahabubnagar District. Its registered land covers survey numbers 2/P, 10/P, 11, 12/P, 13/P, 14, 129/P and 130/P. The RERA land details state a total and net area of 36874.47 sqmts.
- The project record describes a layout rather than an apartment or multi-storey building development. The tentative layout approval states 111 plots and provides for roads, open space, social-infrastructure land and utility land. The proposed layout-plan extraction also identifies 111 individual subplots.
- The promoter undertook to complete the project by 03-03-2026. The supplied evidence does not establish current construction progress or completion, and does not confirm an occupancy or completion certificate. The completion undertaking, the registration validity period and any later extension are separate matters; no extension record is supplied.
3. Master plan, architecture & building design
- The filed layout is organized around 111 plots with internal roads and separately identified open-space, social-infrastructure and utility areas. The proposed layout-plan extraction records 18168.67 for plotted area, 13960.76 for roads, 3355.13 for organized open space/park, 948.22 for social infrastructure and 441.02 for utility area; its stated total net layout is 36873.80. These are plan-extraction figures, not independently measured site areas.
- The tentative layout approval gives corresponding land-use figures as a layout area of Ac. 9.111 cents 44101.507 Sq.Yds, plotted area Ac4.489 cents 21729.729 Sq.Yds (49.2720785308523554564075612%), roads Ac3.45 cents 16697.069 Sq.Yds (37.860540318602425491882258%), open space/park Ac0.829 cents 4012.735 Sq.Yds (9.0988624286322919268420143%), social infrastructure Ac 0.234 cents 1134.071 Sq.Yds (2.5715019483828381764253948%) and utilities Ac 0.109cents 527.46 Sq.Yds (1.1960133611142976235126106%). The approval also lists Plot No 5 to 18, total 14 plots, as mortgaged to the Grampanchayat.
- The proposed layout-plan extraction identifies road widths of 9.14 mt., 10.06 mt. and 12.00 mt., and notes an existing 33'-0" road to be widened to 60'-0" wide road and an existing 18.00 mt wide proposed road. These are plan annotations. The approval requires roads to be opened for access to neighbouring sites and conditions final-layout approval on completion of development works and release of the mortgaged area.
- The approval states that only a detached dwelling house designed for occupation by one family may be built on a site. It does not provide building elevations, dwelling designs, building footprints, storey limits, plot-by-plot building areas or floor plans. No apartment-style floor configuration is applicable from the supplied project records.
4. Homes, configurations & floor plans
This is a plotted project, not a filed apartment configuration schedule. The RERA data supplied does not include plot-wise booked or available counts, plot-size bands, or RERA saleable areas. The tentative layout approval states a total of 111 plots.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Plots | 111 stated in the tentative layout approval | Not supplied | Not supplied | Not supplied | Not applicable | Not supplied |
- The vendor record lists plot sizes from 1,025 - 4,013 sq ft and separately lists residential-plot figures from 1025 sq.ft to 4013 sq.ft. These are vendor-supplied figures, not RERA-filed plot measurements.
- No plot-dimension schedule or readable plot-by-plot area table is available in the supplied layout extraction. The two drawing sheets are layout sheets and contain no measured apartment floor plans.
5. Parking & vehicle circulation
- The proposed layout-plan extraction lists Common Parking Area 0.00. The tentative approval’s reserved mortgage area consists of Plot No 5 to 18, total 14 plots; the documents describe this as security for layout-development conditions, not as buyer parking.
- The supplied records do not state individual plot parking capacity, visitor or accessible parking, parking allotments, EV charging, vehicle-entry arrangements, or a spaces-per-plot ratio. The layout includes internal roads, but no detailed vehicle-circulation or pedestrian-separation plan is established in the extracted material.
6. Amenities, recreation & open spaces
- The tentative layout approval identifies open space/park, social-infrastructure land and utility land. It requires the developer to carry out infrastructure and amenity works, including road formation, drains and nala channelization, greenery, rainwater-harvesting pits, fencing of open spaces, street lighting, electricity facilities, sewerage disposal and protected water supply. The approval lists a water reservoir, septic tank / Sewerage Treatment Plant, electric transformer and solid-waste management among utility provisions. These are approval requirements or allocated provisions; the supplied records do not establish that the works are complete.
| Description / size | Ac0.829 cents 4012.735 Sq.Yds; 9.0988624286322919268420143% in the tentative approval. The proposed layout extraction states 3355.13. |
|---|---|
| Evidence source | Tentative layout approval; proposed layout-plan extraction |
| Declared progress / verified status | Approval provision; completion not independently verified. |
| Description / size | Ac 0.234 cents 1134.071 Sq.Yds; 2.5715019483828381764253948% in the tentative approval. The proposed layout extraction states 948.22. |
|---|---|
| Evidence source | Tentative layout approval; proposed layout-plan extraction |
| Declared progress / verified status | Land provision shown; use or facility completion not established. |
| Description / size | Ac 0.109cents 527.46 Sq.Yds; 1.1960133611142976235126106% in the tentative approval. The proposed layout extraction states 441.02. |
|---|---|
| Evidence source | Tentative layout approval; proposed layout-plan extraction |
| Declared progress / verified status | Land provision shown; utility works not independently verified. |
| Description / size | Ac3.45 cents 16697.069 Sq.Yds; 37.860540318602425491882258% in the tentative approval. |
|---|---|
| Evidence source | Tentative layout approval |
| Declared progress / verified status | Approval provision; road completion not independently verified. |
| Description / size | RERA amenity entries are present; no facility sizes or capacities are supplied. |
|---|---|
| Evidence source | RERA amenity record |
| Declared progress / verified status | Progress percentages recorded as 0; not independently verified. |
| Description / size | Vendor lists recreation facilities, fitness centres, swimming pools, indoor play areas, children’s activity zones and landscaped gardens, among other features; no corresponding sizes or project progress are supplied. |
|---|---|
| Evidence source | Vendor record |
| Declared progress / verified status | Vendor-listed claims; not established as sanctioned or delivered facilities. |
The layout approval requires the open-space, social-infrastructure, utility and road areas to be handed over by registered gift deed before release of the final layout. It also states that land earmarked for open space or public purpose is not to be sold for another use.
7. Utilities, building services & safety
- The tentative layout approval requires the applicant to provide a water reservoir, septic tank / Sewerage Treatment Plant, electric transformer, solid-waste management, sewerage disposal and protected water supply. It also requires storm-water-related works, including drains and nala channelization, and rainwater-harvesting pits. These are approval requirements; the supplied evidence does not confirm installed capacity or completion.
- The RERA amenity record lists water supply, sewerage (chambers, lines, septic tank, STP), storm-water drains, water conservation/rainwater harvesting, energy management, fire protection and fire-safety requirements, and an electrical meter room/sub-station/receiving station. It records 0 progress for these listed items. No water source or storage capacity, STP capacity, power-backup capacity, fire-system specifications, security systems, accessibility provisions or service capacities are supplied.
8. Location, access & connectivity
- The registered location is Peddayapalle, Balanagar Mandal, Mahabubnagar District, Telangana, PIN 509202. The RERA record describes the wider locality as “Mahaboobnagar Urban Development Authority, Peddaipally Grampanchayat, Balanagar Mandal, Mahaboobnagar District.”
- The RERA land-boundary entries identify a road to the south and other land on the east, west and north. The proposed layout plan shows internal roads with stated widths of 9.14 mt., 10.06 mt. and 12.00 mt. and road-widening annotations.
- A supplied location record places the cadastral parcel centroid at 16.93669, 78.18925 and gives the nearest sampled Outer Ring Road interchange as approximately 41.5 km away.
9. Developer & development status
- The TG-RERA-registered promoter is BALAKISTI JAGDISH KUMAR. The RERA filing records the organization type as “Others” and describes it as “SREE NILAYA HOMES PRIVATE LIMITED.” A separate legal-entity type or corporate identifier for the registered promoter is not established in the supplied identity record. The registration certificate gives the promoter’s address as KHAIRTABAD, Hyderabad, PIN 500004.
- The promoter’s Form B affidavit, dated 22 day of MARCH -2024 at Hyderabad, declares that the project will be completed by 03-03-2026 and states that 70 per cent of amounts realized from allottees will be deposited in a separate scheduled-bank account for construction and land costs. These are promoter declarations. The supplied records do not provide current construction progress, a revised completion date or confirmation of project completion.
10. Approvals, official records & documents
TG-RERA registration certificate: Form C registration for HIGHWAY TRANQUIL, registration P01400008054, identifying Balakisti Jagdish Kumar as promoter and stating the registration period and conditions.
Tentative layout approval: MUDA Urban Development Authority approval 358716/LP/GP/204903/0022/2023, dated 04-03-2024, for a tentative layout with 111 plots in the listed survey numbers. The approval says it is not proof of land title.
Proposed layout plan: Layout-plan record for the listed survey numbers, with licence number TS/000131/2024 and extracted land-use figures. The extraction labels the instrument “PROPOSED LAYOUT PLAN.”
Form B promoter declaration: Affidavit-cum-declaration by BALAKISTI JAGDISH KUMAR, dated 22 day of MARCH -2024, including the promoter’s completion undertaking and project-funds declaration.
Completion certificate / Form–1A: A document is listed as “Form–1A Architects certificate Overall completion of registered project,” but its OCR is marked illegible; no completion or occupancy status can be established from it.
Frequently asked questions
Is HIGHWAY TRANQUIL registered with Telangana RERA?
Yes. HIGHWAY TRANQUIL is registered with the Telangana Real Estate Regulatory Authority as P01400008054; the registration status is New Project.
Who is the developer of HIGHWAY TRANQUIL?
The promoter named in the RERA registration is BALAKISTI JAGDISH KUMAR.
Where is HIGHWAY TRANQUIL located?
HIGHWAY TRANQUIL is in Mahaboobnagar Urban Development Authority , Peddaipally Grampanchayat, Balanagar Mandal, Mahaboobnagar District, Peddayapalle, Balanagar, Mahabubnagar, Telangana (509202).
When will HIGHWAY TRANQUIL be completed?
The promoter's proposed date of completion filed with RERA is 03/03/2026. This is the promoter's declaration, not a guarantee.