HILL ROCK is a residential apartment project in Ameenapur, Ameenpur Mandal, Sangareddy District, developed by registered promoter EMMAREDDY DEVELOPERS. The project is on 362.32 sq. m of land and comprises one building with 1 Stilt + 5 upper floors and 10 apartments, all configured as 2BHK with 119.84 sq. m saleable area. It is registered with TG-RERA under P01100006600, and the promoter’s stated completion undertaking was 12/12/2025.

More from Emmareddy Developers · 7 projects →

01What we found

Period endedTG-RERA registration ran to 12 Dec 2025 - check its extension on TG-RERA
13documents on file - each fact links to its page
0court cases on this project's land in the court records searched
8items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

8 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

ItemProject record
Registered nameHILL ROCK RERA record
Project typeResidential apartment project RERA record RERA filing
Phase / registered portionPhase not separately identified in the supplied record; TG-RERA registration is for the project on Survey No. 332/PART
TG-RERA registrationP01100006600; Form ‘C’ registration certificate issued 07/07/2023, valid through 12/12/2025, unless extended by the Authority. The supplied record states no extension.
Registered promoterEMMAREDDY DEVELOPERS, a partnership Parties record Corporate record
RERA status in supplied recordRegistration validity ended 12/12/2025; the available record does not establish a later extension or current registration status.

Land and geographic identity

ItemProject record
LocalityAmeenpur / Ameenapur RERA record
Revenue villageAMEENAPUR (also written Ameenpur in the building-permit documents) RERA record Land records
MandalAMEENPUR (building-permit documents spell it Ameenpur) RERA record
DistrictSangareddy (building-permit documents spell it Sanga Reddy) RERA record
PIN502032 RERA record
Project survey number and subdivisionSurvey No. 332/PART RERA record Land records
Registered site extent362.32 sq. m in the project filing and building-permit extraction Land records
Total / net areaTotal area 362.32 sq. m; net area 362.32 sq. m; area shown as affected by road widening/FTL/nala widening: 0 sq. m RERA filing
Plot referencePlot No. 39 RERA filing
BoundariesNot disclosed in the supplied project land record Land records

Development identity

ItemProject record
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA) Approvals record
Principal building approvalBuilding Permit Order 007004/BP/HMDA/1409/SKP/2022, dated 12 December 2022; proceedings reference 001852/BP/HMDA/SKP/2022 Approvals record
Approved built-up area1,273.50 sq. m total built-up area in the permit extraction; the same extraction separately states 1,058.15 sq. m for the proposed building. These are the document’s labelled figures, not a carpet-area disclosure.
Building count and configurationOne proposed residential building, 1 Stilt + 5 upper floors
Parking levelsStilt is designated for vehicle parking in the approval conditions; a sanctioned parking-space count is not established by the supplied extract.
Unit countThe RERA filing records 10 apartments, all 2BHK; the approved plan extraction identifies one building. RERA unit table

Offering and status

ItemProject record
RERA-filed configuration and saleable area2BHK; 119.84 sq. m saleable area RERA unit table
Booked / available0 booked / 10 available, as last read from the TG-RERA portal; the portal record supplied has no as-of date, so these counts are indicative. RERA unit table
Construction stageNot established by the supplied evidence. The RERA filing’s stated completion undertaking was 12/12/2025; no independently verified current construction status is supplied. RERA record
Completion certificate / occupancy certificateAn architect’s certificate filed with RERA says the project is complete and identifies HMDA OC 006115/0C/HMDA/SKP/2024. The date is printed as /05/11/2024 in the extracted certificate; the exact day is not clear in the supplied extraction. The filing identifies the project overall, not a separate tower or phase.
Registration validity vs. completionRegistration validity ended 12/12/2025; this is separate from the promoter’s completion undertaking and the filed architect’s completion/OC certificate.

2. The project story

  • HILL ROCK is filed with TG-RERA as a residential apartment project on Plot No. 39 in Survey No. 332/PART, in revenue village AMEENAPUR, Ameenpur Mandal, Sangareddy District. The RERA filing identifies a single building and ten 2BHK apartments. RERA record Land records RERA unit table
  • HMDA’s building-permit record describes a proposed building of 1 Stilt + 5 upper floors on a site of 362.32 sq. m. Its conditions designate the stilt/cellar for vehicle parking and require an occupancy certificate before occupation.
  • The promoter’s Form B declaration undertook completion by 12-12-2025. Separately, an architect’s certificate filed with TG-RERA certifies overall completion and identifies an HMDA occupancy certificate. That is a filed professional certification; the supplied materials do not independently verify the current physical condition or occupation status on site.

3. Master plan, architecture & building design

  • The HMDA permit extraction records one residential building on the 362.32 sq. m site, configured as 1 Stilt + 5 upper floors. It gives total built-up area as 1,273.50 sq. m and separately identifies 1,058.15 sq. m as the proposed building figure. The supplied material does not provide a verified breakdown of floor-by-floor areas, footprint, flats per floor, tower height beyond the approval extract’s 14.99 figure (unit not stated there), or circulation and open-space dimensions.
  • The approval conditions refer to parking in the stilt/cellar, setbacks, rainwater-harvesting structures, a transformer, a garbage house and an STP. Detailed drawings or extracted evidence establishing lifts, stairs, entrances, landscaping, internal circulation or common-area dimensions are not available in the supplied data.
  • The HMDA permit records a mortgage of built-up area in favour of HMDA under registered document 38265/2022. The approval materials contain differing descriptions of the mortgage area; the project overview does not resolve that documentary issue.

4. Homes, configurations & floor plans

The TG-RERA filing records ten 2BHK apartments, with 119.84 sq. m saleable area per unit. The available/b​​ooked counts below are portal counts without a supplied as-of date. RERA unit table

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK10010119.84 sq. m74.8–90.7 sq. m software-measured range; median 84.9 sq. m29%
  • Carpet-area measurements are software measurements from approved floor-plan drawing 301121, not RERA-filed area figures, and are identified in the supplied data as needing review. The drawing-derived sample covers four measured flat designs. Saleable area is the RERA-filed figure and is not interchangeable with carpet area; the supplied drawing-data caveat notes that saleable area also counts a home’s share of common areas. Floor plans
  • One measured plan lists a master bedroom, child bedroom, living/dining area, kitchen, foyer, wash area and two toilets. These room labels and measurements are drawing-derived, not separate RERA disclosures. RERA unit details

5. Parking & vehicle circulation

  • The HMDA approval conditions state that the stilt/cellar is to be used exclusively for vehicle parking and is not to be partitioned or converted; they also state that no parking or construction is to be placed in setback areas. The supplied record does not establish the sanctioned number of car or two-wheeler spaces, visitor or accessible spaces, a parking allocation for any particular apartment, or EV-charging provision.
  • The approval refers to an approach road of 4.5mts. and to the minimum approach-road width shown in the plan. The supplied data does not describe a ramp, internal driveway layout or pedestrian separation.

6. Amenities, recreation & open spaces

The following are amenities or infrastructure items recorded in the RERA-filed amenity data or HMDA approval conditions. The progress fields show 0 for the listed RERA amenity entries; that figure is a filed progress indicator, not independent verification of current site status. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Internal roads and footpathsSize not statedTG-RERA amenities RERA amenitiesFiled progress: 0; not independently verified
Green strip / tot lot / parkSize not statedTG-RERA amenities RERA amenitiesFiled progress: 0; not independently verified
Community buildingsSize or facility detail not statedTG-RERA amenities RERA amenitiesFiled progress: 0; not independently verified
Recreational open spaceAggregate area not statedTG-RERA amenities RERA amenitiesFiled progress: 0; not independently verified
Garbage houseRequired within the premises; size not statedHMDA approval conditionsApproval condition; completion not verified
  • The vendor listing mentions a community hall, swimming pool, gym, children’s play area and clubhouse, among other features. These are third-party/vendor descriptions and are not established in the supplied TG-RERA amenity schedule or approval extracts as delivered facilities. Promoter website

7. Utilities, building services & safety

  • HMDA’s approval conditions call for rainwater-harvesting structures, an STP, a transformer and a garbage house within the premises. The RERA-filed amenity data marks water supply, sewerage, rainwater harvesting, energy management, fire protection and an electrical meter room/substation/receiving station as “YES,” but provides no capacities and records progress at 0 for those entries. These are filed declarations/indicators, not independent confirmation of installed or operating services. RERA amenities
  • The approval also requires an occupancy certificate before occupation and refers to fire-fighting installations in the approval extraction. The supplied materials do not establish details or capacities for water storage or treatment, sewerage reuse, electrical backup, lifts, fire equipment, waste segregation, CCTV, access control or accessibility features.

8. Location, access & connectivity

  • The registered location is AMEENAPUR, Ameenpur Mandal, Sangareddy District, PIN 502032; the building-permit document identifies Plot No. 39, Survey No. 332/PART, Ameenpur. RERA record Land records
  • The supplied location record gives the nearest sampled Outer Ring Road interchange at approximately 8.5 km. No other verified approach-road, public-transport or landmark distances are provided. The approval extract references an approach road of 4.5mts. and requires the indicated approach road to be developed and maintained as a black-topped road before release of the occupancy certificate. Location record

9. Developer & development status

  • The registered promoter is EMMAREDDY DEVELOPERS, identified in the RERA record as a partnership, with GSTIN 36AAJFE0360J1ZI. The supplied project record lists Madhusudhan Reddy Emmareddy as authorized signatory and Krishnaveni Emmareddy as partner. The registration certificate gives the promoter office as Village Miyapur, Serilingampally Mandal, Ranga Reddy District, PIN 500049. Parties record Corporate record
  • See project completion and registration status above.

10. Approvals, official records & documents

TG-RERA registration certificate, Form ‘C’
Identifier / dateP01100006600; issued 07/07/2023, valid through 12/12/2025 unless extended
Scope and sourceHILL ROCK; survey 332/PART.
HMDA building permit / approval for building construction
Identifier / date007004/BP/HMDA/1409/SKP/2022; 12 December 2022; proceedings 001852/BP/HMDA/SKP/2022
Scope and sourceOne residential building, 1 Stilt + 5 upper floors, Plot No. 39, Survey No. 332/PART.
HMDA occupancy certificate identified in architect’s certificate
Identifier / date006115/0C/HMDA/SKP/2024; date printed /05/11/2024 in the extraction
Scope and sourceArchitect’s certificate states overall completion; exact day in the extracted date is unclear.
Promoter Form B declaration
Identifier / dateCompletion undertaking 12-12-2025
Scope and sourcePromoter declaration concerning the project and RERA obligations.
RERA-filed floor-plan drawing
Identifier / dateDocument 301121
Scope and sourceDrawing-derived unit measurements; software measurements are not RERA area disclosures.

The supplied evidence index does not include a separately identified approved-layout document or a complete drawing set sufficient to describe all building services, circulation or common areas. The HMDA approval extracts include conditions concerning construction, parking, utilities and occupancy; this overview does not reproduce the full conditions. Document index

Frequently asked questions

Is HILL ROCK registered with Telangana RERA?

Yes. HILL ROCK is registered with the Telangana Real Estate Regulatory Authority as P01100006600; the registration status is New Project.

Who is the developer of HILL ROCK?

The promoter named in the RERA registration is EMMAREDDY DEVELOPERS.

Where is HILL ROCK located?

HILL ROCK is in AMEENPUR, AMEENAPUR, Sangareddy, Telangana (502032).

When will HILL ROCK be completed?

The promoter's proposed date of completion filed with RERA is 12/12/2025. This is the promoter's declaration, not a guarantee.