Nlc Aadya

NEWLAND CONSTRUCTIONS · Sangareddy · RERA P01100003948

NLC AADYA is a residential apartment project in Ameenpur, Ameenpur mandal, Sangareddy district. The registered promoter is Newland Constructions, a partnership. The project is on 956.51 sq m of land and comprises one building with 1 Stilt + 5 upper floors and 25 2BHK units, each with a RERA-filed saleable area of 107.86 sq m. Its TG-RERA registration number is P01100003948, and the proposed completion date is 12 November 2024.

More from Newland Constructions · 9 projects →

01What we found

Period endedTG-RERA registration ran to 12 Nov 2024 - check its extension on TG-RERA
11documents on file - each fact links to its page
1court case on this project's land (survey 343, Ameenapur)
7items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

7 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldRecord
Registered projectNLC AADYA RERA record
Project typeResidential apartment project RERA record RERA filing
Phase / registered portionNot identified as a numbered phase. The RERA registration and building approval concern the project on Survey No. 343/16.
TG-RERA registrationP01100003948
Registration validity17/01/2022 to 12/11/2024; the supplied certificate records no extension. This is the registration period, not the construction deadline or OC status.
Registered promoterNewland Constructions, a partnership RERA record RERA filing
RERA statusThe supplied certificate records registration under section 5. It does not record an extension.

Land and geographic identity

FieldRecord
LocalityAmeenpur RERA record RERA filing
Revenue villageAmeenapur (also recorded in the project documents as Bandamkommu, Ameenpur Village) RERA filing
MandalAmeenpur RERA record RERA filing
DistrictSangareddy RERA record RERA filing
PIN502032 RERA record
Project survey number(s) / subdivision(s)343/16 RERA record
Registered site extentRERA project record: 956.51 sq m total area; 956.51 sq m net area. RERA filing
Building-permit site area956.51 m²; net area 954.58 m² in the building approval.
Boundaries in RERA recordEast: 30 FT ROAD; West: GOVT SCHOOL; North: VENDORS LAND; South: 40 FT ROAD. RERA filing

Development identity

FieldRecord
Sanctioning authorityAmeenpur Municipality/Municipal Corporation Approvals record
Principal building approval0006/BP/3121/2021, dated 12 November, 2021 Approvals record
Approved built-up area2,205.48 sq m in the project record. RERA filing
Building countOne building RERA filing
Sanctioned configuration1 Stilt + 5 upper floors; height 14.99 m
Floor areas stated in approvalResidential upper floors: 2,191.85 m²; stilt: 482.29 m²
Parking levels / sanctioned parking countStilt is approved for parking subject to the approval conditions; a total space count is not available in the supplied record.
Units25 RERA-filed 2BHK units; approved-plan unit count is recorded as 1 in the project fields, whose meaning is not further explained in the supplied data. RERA unit table RERA filing

Offering and status

FieldRecord
RERA-filed configuration and saleable area2BHK; 107.86 sq m saleable area RERA unit table
Booked / available25 booked; 0 available, as last read from the TG-RERA portal; the record supplies no as-of date, so counts are indicative. RERA unit table
Original completion deadline12 November 2024, stated in the building approval; the promoter’s Form B also undertakes completion by 12-11-2024.
Construction stageArchitect’s Form–1A, dated 15/10/2024, certifies completion in all aspects. This is a filed architect certificate, not an independent site inspection.
Occupancy certificateForm–1A identifies OC/application number 004114/OC/DTCP/3121/00 47/2023, dated 22/04/23, issued by Ameenpur Municipality. The supplied extract does not specify a separate tower or phase scope beyond the registered project.

2. The project story

NLC AADYA is recorded with TG-RERA as a residential apartment project at Ameenpur, in Ameenapur revenue village, Sangareddy district. The project record identifies Survey No. 343/16 and one building. The building permit describes a residential building, “PROP (BUILDING),” with one stilt and five upper floors, at a sanctioned height of 14.99 m. RERA record RERA filing

The RERA unit schedule lists 25 two-bedroom apartments, all recorded as booked and none available; the portal extract has no as-of date. The architect’s Form–1A dated 15/10/2024 certifies overall completion and identifies the municipality’s occupancy-certificate number and date. These are filed records; no independent physical inspection or site-progress verification is supplied. RERA unit table

3. Master plan, architecture & building design

The building approval sanctions one residential building with 1 Stilt + 5 upper floors, a height of 14.99 m, and states residential upper-floor area of 2,191.85 m² and stilt area of 482.29 m². The project record separately reports approved built-up area of 2,205.48 sq m; these figures are retained as separately labelled records, not treated as interchangeable measures. RERA filing

The approval gives a site area of 956.51 m², net area of 954.58 m², and a 49.62 m² tot-lot. It lists setbacks of front 3 m, rear 4 m, and side I and side II 4 m each. The sanctioned drawing itself is not available in the supplied evidence for describing the floor-by-floor layout, footprint, apartment arrangement, lifts, stairs, entrances, or internal circulation.

4. Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK25250107.86 sq m66.8–78.5 sq m software-measured range; median 77.6 sq m (median 835 sq ft)28%

Unit count, booking count and saleable area are from the RERA filing; booking counts have no supplied as-of date and are indicative. Carpet measurements are software-measured from the approved floor-plan drawing, not RERA-filed area figures; the measurement record says it requires review. RERA unit table RERA unit details Floor plans

Saleable area and carpet area describe different measures: the supplied drawing-measurement record says saleable area includes the home’s share of common areas, whereas the measured carpet figure is drawing-derived. It provides measurements for 15 flat designs. A sample first-floor plan entry lists a living/kitchen, two bedrooms, two toilets and a wash area; room dimensions are in the drawing-measurement record and should be checked against the drawing. Floor plans RERA unit details

5. Parking & vehicle circulation

The approval states that the stilt approved for parking is to be used exclusively for vehicle parking, without partition walls or rolling shutters. It also requires one entry and one exit, each with a minimum width of 4.5 m and height clearance of 5 m. The supplied records do not establish the number of parking bays, visitor or accessible spaces, parking allocation to individual apartments, or any EV provision.

6. Amenities, recreation & open spaces

Tot-lot
Description / size49.62 m²
Evidence sourceSanctioned building approval
Declared progress / verified statusApproval requires fencing and maintenance as greenery before OC where applicable; delivery is not independently verified.
Rainwater-harvesting pits
Description / size3
Evidence sourceSanctioned building approval
Declared progress / verified statusRequired by approval; completion is not independently verified.
Tree planting
Description / sizeApproval calls for trees within the plot and planting along the periphery and front; the number is recorded as “NA.”
Declared progress / verified statusRequired by approval; completion is not independently verified.
Community buildings, green strip/tot-lot/park, street lighting, internal roads and footpaths
Description / sizeListed in the TG-RERA amenities record; no descriptions or sizes supplied.
Evidence sourceRERA amenities
Declared progress / verified statusRecorded progress: 0% for each listed item; no independent verification supplied.

The TG-RERA amenities record also lists water supply, sewerage, storm-water drains, sewage/sullage treatment and disposal, solid-waste management, water conservation/rainwater harvesting, energy management, fire protection, an electrical meter room/sub-station/receiving station, and aggregate recreational open space. Each is recorded at 0% in that amenities data. RERA amenities

7. Utilities, building services & safety

The building approval requires three rainwater-harvesting pits and space for a transformer. It also specifies a separate underground static water-storage tank of 25,000 litres and a separate terrace tank of 25,000 litres for residential buildings. These are approval requirements; the supplied evidence does not independently establish installation or completion.

For safety and building services, the approval requires a generator as an alternate electricity source, emergency lighting in corridors/common passages and staircases, fire-resistant swing doors for collapsible lifts on all floors, and two water-type fire extinguishers for every 600 Sq.mts. of floor area, with at least four per floor. It requires an automatic sprinkler system if basement area exceeds 200 Sq.mts.; the supplied record does not establish that this threshold applies or that a system is installed. It also places responsibility for structural and fire safety on the listed project professionals and requires services including sanitation, plumbing, fire safety, lifts and electrical installations to be carried out under qualified technical supervision.

The approval requires a garbage house within the premises with dry and wet waste segregation. The RERA amenities record lists water supply, sewerage, storm-water drains, sewage treatment/disposal, solid-waste management, energy management and fire protection, but records 0% progress for each. No capacities or completed-service verification are supplied for those items. RERA amenities

8. Location, access & connectivity

The registered location is Ameenpur, Ameenapur village, Ameenpur mandal, Sangareddy district, PIN 502032, on Survey No. 343/16. The project record gives the site boundaries as 30 FT ROAD to the east, GOVT SCHOOL to the west, VENDORS LAND to the north and 40 FT ROAD to the south. RERA record RERA filing RERA filing

The supplied location data gives the nearest sampled Outer Ring Road interchange at approximately 8.4 km. No other measured distances, public-transport details or verified landmark connections are provided. Location record

9. Developer & development status

The registered promoter is NEWLAND CONSTRUCTIONS, identified in the RERA record as a partnership. Its supplied GSTIN is 36AASFN3244K1ZT. The promoter address recorded in the project data is SURAKSHA ENCLAVE, ROAD NO 10, BANDMKOMMU, AMEENPUR, AMEENPUR, Sangareddy, 502032. The registration certificate separately records a promoter-office address in Hyderabad, PIN 500050; no contact details or official website are supplied. RERA record RERA filing Corporate record Parties record

The promoter’s Form B, signed by authorized signatory Venkata Narayana Kethireddy on 14 December 2021, states a completion undertaking of 12-11-2024. The architect’s Form–1A dated 15/10/2024 certifies completion in all aspects and identifies the occupancy-certificate record. No independent construction-progress assessment is supplied.

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP01100003948; issued 17/01/2022; valid to 12/11/2024
What the supplied record establishesForm ‘C’ registration for NLC AADYA; the supplied certificate records no extension.
Building-construction approval
Identifier / date0006/BP/3121/2021; 12 November, 2021
What the supplied record establishesAmeenpur Municipality/Municipal Corporation approval for a residential building on Survey No. 343/16, with listed sanctioned configuration and conditions.
Building file number
Identifier / date002393/BP/DTCP/3121/0027/2021
What the supplied record establishesListed in the building approval.
Architect’s completion certificate (Form–1A)
Identifier / dateDated 15/10/2024
What the supplied record establishesCertifies completion in all aspects and identifies the occupancy-certificate number/date.
Occupancy-certificate record identified in Form–1A
Identifier / date004114/OC/DTCP/3121/00 47/2023; 22/04/23
What the supplied record establishesIdentified as issued by Ameenpur Municipality.
Form B promoter declaration
Identifier / date14 December 2021
What the supplied record establishesPromoter declaration concerning title, encumbrances, funds, approvals and completion undertaking.

A separate approved-layout document is not available in the supplied evidence. The building approval states that the sanctioned plan is to be followed and displayed at the site; the supplied material does not include drawing details sufficient to describe all architectural or site-layout features.

Frequently asked questions

Is NLC AADYA registered with Telangana RERA?

Yes. NLC AADYA is registered with the Telangana Real Estate Regulatory Authority as P01100003948; the registration status is New Project.

Who is the developer of NLC AADYA?

The promoter named in the RERA registration is NEWLAND CONSTRUCTIONS.

Where is NLC AADYA located?

NLC AADYA is in AMEENPUR, AMEENAPUR, Sangareddy, Telangana (502032).

When will NLC AADYA be completed?

The promoter's proposed date of completion filed with RERA is 12/11/2024. This is the promoter's declaration, not a guarantee.