S Pride

FORTUNE DEVELOPERS · Khammam · RERA P00800006523

S PRIDE is a residential apartment project in Pakabanda Revenue, Khammam (Urban) Mandal, Khammam District. It is being developed by the registered promoter FORTUNE DEVELOPERS, recorded as a partnership. The project has a total site area of 696.75 m² and comprises one building, recorded as one block and one tower, with 1 stilt + 5 upper floors and 15 2BHK units. Its TG-RERA registration is P00800006523, issued 07/07/2023, and the promoter’s declared completion date is 24/09/2025.

01What we found

Period endedTG-RERA registration ran to 24 Sep 2025 - check its extension on TG-RERA
15documents on file - each fact links to its page
1court case on this project's land (survey 42, 105, Pakabanda)
8items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

8 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Pakabanda, Khammam, Khammam · geocoded — approximate.

1. Project at a glance

Project identity

FieldRecord
Registered project nameS PRIDE RERA record
Project type / statusResidential apartment project; recorded as “New Project” RERA record RERA filing
Registered portion / phaseNot disclosed as a separate phase in the supplied record RERA record
TG-RERA registrationP00800006523; Form C issued 07/07/2023; stated validity 07/07/2023–24/09/2025. No extension is recorded in the supplied certificate Approvals record
Registered promoterFORTUNE DEVELOPERS, recorded as a partnership RERA record RERA filing Corporate record
RERA statusThe certificate’s stated validity ended 24/09/2025; the supplied record does not establish a subsequent extension or current registration status

Land and geographic identity

FieldRecord
Locality / revenue villagePakabanda / Pakabanda Revenue RERA record RERA filing
Mandal / district / PINKhammam (Urban) Mandal / Khammam / 507002 RERA record RERA filing
Project survey numbers105/1 and 42/2 RERA filing
Plot numbers44, 45 & 46 RERA filing
Site areaTotal 696.75 m²; road-affected area 55.74 m². The RERA land record states net area 641.01 m², while the building-permit extraction records net area 635.15 m² RERA filing
Boundaries (RERA filing)East: “12 19 MT WIDE EXISTING 18 28 MT WIDE PROPOSED ROAD”; west: Plot No. 47; north: Plot Nos. 57, 58, 59; south: “12 19 MT WIDE EXIST ROAD” RERA filing

Development identity

FieldRecord
Sanctioning authorityKhammam Municipal Corporation Approvals record
Principal building approvalPermit 0314/BP/3018/2022, dated 24 September 2022; file no. 008794/BP/DTCP/3018/0365/2022 Approvals record
Approved building / floorsOne residential building; 1 stilt + 5 upper floors
Height / approved built-up areaHeight 14.25 m; approved built-up area 2,099.96 m² RERA filing
Site figures in building-permit extractionSite area 696.75 m²; road-affected area 55.74 m²; net area 635.15 m²
Units15 units recorded in the RERA unit data; the permit extraction does not provide an approved unit count RERA unit table

Offering and status

FieldRecord
RERA-filed configuration2BHK; 15 units RERA unit table
RERA-filed saleable area127.66 m² per unit RERA unit table
Booked / available0 booked / 15 available in the latest supplied portal read; no as-of date is provided, so counts are indicative RERA unit table
Completion deadlinePromoter’s Form-B declaration states 24/09/2025; the registration certificate also ends on that date
Construction stageRERA record indicates 80% completeness; this is a record-level progress figure, not independent site verification RERA record
Occupancy / completion certificateNot provided in the supplied evidence Document index Approvals record

2. The project story

S PRIDE is recorded with TG-RERA as a residential apartment project on plots 44, 45 and 46 at Pakabanda Revenue, Khammam, on survey numbers 105/1 and 42/2. The registered land record gives a total site area of 696.75 m² and identifies 55.74 m² as affected by road widening. The RERA filing describes a single building and 15 two-bedroom apartments. RERA record RERA filing RERA unit table RERA filing

The building approval on file is for one residential building with a stilt and five upper floors. The project record reports 80% completeness, but the supplied materials do not establish that this figure has been independently verified at the site or provide a dated construction update. No occupancy or completion certificate is included. RERA record Document index Approvals record

The promoter’s declared completion date was 24/09/2025. That date has passed; the supplied certificate records registration through the same date, but does not show an extension or establish current RERA status.

3. Master plan, architecture & building design

The building permit records one residential building, comprising 1 stilt + 5 upper floors, with a stated height of 14.25 m and approved built-up area of 2,099.96 m². The permit extraction gives the stilt area as 363.59 m² and the five residential upper floors’ combined area as 1,714.25 m². These are approval-document figures; the supplied material does not provide an independently measured building footprint or a separate FSI-counted-area figure. RERA filing

The RERA filing describes one block and one tower. No supplied drawing-derived record establishes the number of flats per floor, lift or stair arrangement, entrances, internal circulation, or residential-versus-common-area breakdown. The building-permit conditions call for a fenced tot-lot, perimeter greenery, a transformer space and rainwater-harvesting structures, but the supplied evidence does not establish their completion. RERA unit table

The building permit records nine rainwater-harvesting structures and a requirement for a transformer space. Its extracted site figures are 696.75 m² total and 635.15 m² net, with a 55.74 m² road-affected portion. The project filing separately reports 641.01 m² net area. RERA filing

4. Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK15015127.66 m²84.5–92.0 m²; median 85.9 m²33%

Unit counts, booking status and saleable area are RERA-filed figures; the booking snapshot has no stated as-of date. Carpet-area measurements were software-derived from approved floor-plan drawing geometry, across six measured flat designs, and are not RERA disclosures. The supplied drawing record says the measurement needs review. Saleable area and carpet area are different measures; the supplied record notes that saleable area includes the home’s share of common areas. RERA unit table RERA unit details Floor plans

One measured typical-plan example identifies a living room, dining/kitchen, two bedrooms, two toilets and an enclosed balcony. The drawing-based room schedule gives the enclosed balcony as 2.1 m² and marks it excluded from carpet area. These are software-measured drawing details, not RERA-filed room-area disclosures. RERA unit details

5. Parking & vehicle circulation

The building approval describes the stilt as parking and requires approved cellar/stilt parking, if present in the plan, to remain exclusively for vehicle parking without partitions or rolling shutters. The supplied extraction does not state a parking-space count, parking allocation by apartment, visitor or accessible spaces, or the presence of cellar parking.

No supplied evidence establishes parking ramps, vehicle entry/exit arrangements, pedestrian separation, mechanical parking, EV charging or exclusive parking rights for any unit. A parking area shown or required by the approval does not, by itself, establish a unit-specific allocation. Document index

6. Amenities, recreation & open spaces

Tot-lot / green area
Description / sizePermit condition requires a fenced tot-lot maintained as greenery; no size supplied
Evidence sourceBuilding approval
Declared progress / verified statusRequired before occupancy certificate; completion not established
Perimeter greenery
Description / sizeStrip of greenery along the site perimeter; no size supplied
Evidence sourceBuilding approval
Declared progress / verified statusRequired by permit; completion not established
Water supply
Description / sizeRERA amenity record says “YES”; capacity/source not supplied
Evidence sourceRERA amenity record
Declared progress / verified statusNo progress percentage beyond the record’s 0 entry; not independently verified RERA amenities
Sewerage
Description / sizeRERA amenity record says “YES” for sewerage (chamber, lines, septic tank, STP); specific system and capacity are not established
Evidence sourceRERA amenity record
Declared progress / verified statusNo progress percentage beyond the record’s 0 entry; not independently verified RERA amenities
Rainwater harvesting
Description / sizeRERA amenity record says “YES”; permit records nine rainwater-harvesting structures
Evidence sourceRERA amenity record; building approval
Declared progress / verified statusRequired/provided for in approval; completion not established RERA amenities

The RERA amenity register also lists internal roads and footpaths, storm-water drains, street lighting, community buildings, sewage/sullage treatment and disposal, solid-waste management, energy management, fire protection, an electrical meter room/sub-station/receiving station, and aggregate recreational open space. The supplied entries do not give sizes or establish completion for these items. RERA amenities

7. Utilities, building services & safety

The RERA amenity record marks water supply, sewerage, rainwater harvesting and an electrical meter room/sub-station/receiving station as available, but does not provide capacities, detailed system specifications or evidence of completed installation. The building approval requires rainwater harvesting, space for a transformer and a garbage house within the premises; it also requires public water and electricity connections to be provided only on production of an occupancy certificate. RERA amenities

The approval conditions require sanitation, plumbing, fire-safety requirements, lifts and electrical installations to be carried out under qualified technical supervision, and make structural and fire-safety provision the responsibility of the owner, builder/developer and technical professionals. These are approval conditions, not evidence that the systems have been installed, inspected or certified. No lift count or capacity, backup-power arrangement, water-treatment system, STP capacity, accessibility design, CCTV or security-system details are supplied. RERA amenities

8. Location, access & connectivity

The official project identity places S PRIDE in Pakabanda revenue village, Khammam (Urban) Mandal, Khammam District, PIN 507002. The building approval identifies the site as Pakabanda and records neighbouring plots and road boundaries, including an existing and a proposed road on the east and an existing road on the south. No verified public-transport details or measured distances to local services are supplied. RERA record RERA filing RERA filing

The supplied location record gives a distance of 1.2 km to Financial District (Nanakramguda), but identifies the coordinate as a cadastral parcel centroid and does not provide a route or measurement methodology. Location record

9. Developer & development status

The registered promoter is FORTUNE DEVELOPERS, recorded as a partnership, with GSTIN 36AAGFF7533D1ZK. The supplied promoter address is B, Ramachandra Nagar, Pakabanda Bazar, near SBIT College, Pakabanda, Khammam (Urban) Mandal, Khammam, PIN 507002. The project’s RERA record names Sujatha Mandapati and Ramanarasamma Venkata Perala as partners and Sabitha Perala as authorized signatory. Corporate record Parties record RERA filing RERA record RERA filing

The promoter’s Form-B affidavit, signed by authorized signatory Perala Sabitha, declares a completion date of 24/09/2025 and includes undertakings concerning approvals, project funds and accounts. These are promoter declarations. The supplied RERA progress record states 80% completeness, without an as-of date or independent site verification. No completion or occupancy certificate is included in the supplied project documents. RERA record Document index Approvals record

10. Approvals, official records & documents

RecordSupplied evidence
TG-RERA registrationForm C for S PRIDE, registration P00800006523, issued 07/07/2023; stated validity through 24/09/2025
Building permitKhammam Municipal Corporation permit 0314/BP/3018/2022, dated 24 September 2022; file no. 008794/BP/DTCP/3018/0365/2022
Layout referencePermit extraction cites LP NO 19/2002, dated 15/03/2005
RERA Form-B declarationPromoter affidavit/declaration by Perala Sabitha; completion undertaking states 24/09/2025
Occupancy/completion certificateNot present in the supplied documents Document index
Other identified approval-document referencesContractor’s All Risk Policy No. 552401442210000022 (12 September 2022); transaction reference TS/24380/2022; the permit extraction also records 11481/2022 alongside “Floor handed over”

The supplied material identifies the principal building permit and the RERA registration certificate, but does not include a completed occupancy/completion certificate. The registration’s stated validity and the promoter’s completion deadline are separate record items; neither, on its own, establishes that the building is complete or certified for occupation. Document index

Frequently asked questions

Is S PRIDE registered with Telangana RERA?

Yes. S PRIDE is registered with the Telangana Real Estate Regulatory Authority as P00800006523; the registration status is New Project.

Who is the developer of S PRIDE?

The promoter named in the RERA registration is FORTUNE DEVELOPERS.

Where is S PRIDE located?

S PRIDE is in PAKABANDA, Khammam (Urban) Mandal, Khammam, Telangana (507002).

When will S PRIDE be completed?

The promoter's proposed date of completion filed with RERA is 24/09/2025. This is the promoter's declaration, not a guarantee.