Sign in

Sai Teja Homes

GAUTAM CONSTRUCTIONS · Rangareddy · RERA P02400003845

SAI TEJA HOMES is a residential apartment project in KUNTLOOR, Abdullapurmet Mandal, Ranga Reddy District, developed by registered promoter GAUTAM CONSTRUCTIONS. The project occupies 641.57 sq. m. and comprises one residential building with 1 Stilt + 5 Upper floors and 20 2BHK homes. Its TG-RERA registration number is P02400003845, and the proposed completion date is 30/11/2026.

01What we found

Period endedTG-RERA registration ran to 17 Mar 2026 - check its extension on TG-RERA
12documents on file - each fact links to its page
0court cases on this project's land in the court records searched
11items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

11 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldProject record
Registered project nameSAI TEJA HOMES RERA record
Project typeResidential apartment project RERA record
Phase / registered portionNot separately identified as a named phase; registration is for the project on the stated site
TG-RERA registrationP02400003845
Registration validityStated as valid from 03/01/2022 to 17/03/2026. This is the registration period, not the project’s completion deadline.
Registered promoterGAUTAM CONSTRUCTIONS RERA record
RERA statusThe record calls this a “New Project.” No extension is recorded in the supplied registration certificate. Current registration status is not established by the supplied materials. RERA record

Land and geographic identity

FieldProject record
Locality / revenue villageKUNTLOOR; the approval document identifies Kuntloor village RERA record
Mandal / district / PINAbdullapurmet / Ranga Reddy / 501505 RERA record
Project survey numbers153, 159 and 160
SubdivisionsNot specified in the project’s stated survey identity. The supplied land-record material lists subdivision rows for these surveys, but does not establish which subdivision(s) comprise the project parcel. Land records
Plot identifiers225/A PART, 225PART AND 226 PART in the RERA certificate; the HMDA technical-approval extraction also refers to plot numbers including 225/A PART, 225PART and 226 PART.
Registered site extent641.57 sq. m. in the RERA land details and HMDA technical-approval extraction RERA filing
Total / net areaTotal area 641.57 sq. m.; net area 641.57 sq. m. RERA filing
BoundariesEast: 30 FT ROAD; west: 30FT RAOD; north: 30 FT ROAD; south: PLOT NO 224 AND 227 RERA filing

Development identity

FieldProject record
Sanctioning authority / principal approvalHyderabad Metropolitan Development Authority (HMDA), technical approval 022671/GHT/R1/U6/HMDA/16042019, dated 19 December, 2019; the letter delegates the building-plan sanctioning role to Pedda Amberpet Municipality, subject to the stated conditions. Approvals record
Approved built-up areaHMDA extraction lists Total Built up Area (In Sq.mts): 1789.03. It separately lists “Built up Area: 1458”; these are the labels and figures in the supplied approval extraction.
Building count and configurationOne residential building/block; 1 Stilt + 5 Upper floors. The supplied approval extraction gives building height as 15 without a unit in that field. RERA record
Basement / podiumNot identified in the supplied project records.
Parking levelStilt is approved for vehicle parking and is required by the approval conditions to remain exclusively for parking. No sanctioned parking-space count is supplied.
Units20 total units in the RERA unit record; the supplied HMDA approval extraction does not state an approved unit count, so a separate approved-versus-filed count cannot be confirmed here. RERA unit table RERA unit details

Offering and status

FieldProject record
RERA-filed configuration2BHK, 20 units RERA unit table RERA unit details
RERA-filed saleable area27.87 sq. m. per listed 2BHK configuration RERA unit table RERA unit details
Booked / available0 booked / 20 available, as last read from the TG-RERA portal; the portal record supplied has no as-of date, so these counts are indicative. RERA unit table RERA unit details
Construction stageNo independently verified site progress or construction-stage report is supplied. The RERA amenities record gives 0% for each listed item; that is a portal-recorded progress figure, not independent site verification. RERA amenities
Completion datesThe Form B declaration gives a promoter-undertaken completion date of 17/03/2026. The project header separately records a proposed completion date of 30/11/2026; the supplied material does not explain the relationship between these entries. RERA record
Occupancy / completion certificateNo occupancy or completion certificate is supplied. The HMDA letter requires completion and an occupancy certificate before occupation.

2. The project story

SAI TEJA HOMES is registered with TG-RERA as a residential apartment project on a 641.57 sq. m. site in Kuntloor, Abdullapurmet Mandal, Ranga Reddy District. Its registered land identity includes Survey Nos. 153, 159 and 160, with plot identifiers 225/A PART, 225PART AND 226 PART. RERA record RERA filing

The HMDA technical approval describes one residential building with 1 Stilt + 5 Upper floors. The RERA unit record lists 20 2BHK homes, all shown as available in the supplied portal extract. No site inspection evidence or verified construction-progress report is provided, so the project’s actual construction stage cannot be established from this material. RERA unit table RERA amenities

The promoter’s Form B affidavit states a completion undertaking of 17/03/2026; the project header records a proposed completion date of 30/11/2026. The supplied records do not establish whether either date has since been revised or achieved. No occupancy or completion certificate is included. RERA record

3. Master plan, architecture & building design

The supplied HMDA technical approval concerns a residential apartment building on the stated 641.57 sq. m. site and specifies 1 Stilt + 5 Upper floors. It also lists a total built-up area of 1789.03 sq. m. and, separately, a “Built up Area” figure of 1458. No FSI-counted area, footprint, flat-per-floor layout, floor-by-floor arrangement, lift or stair count, or detailed internal circulation plan is supplied.

The RERA record identifies one building and one block; the approved drawing set’s detailed organization and dimensions cannot be described from the supplied extracts. The HMDA conditions require the stilt/cellar area, if provided as approved, to be used exclusively for parking and not subdivided or converted to other use. RERA record

The stated area figures should be kept distinct: the approval extraction’s Total Built up Area (In Sq.mts): 1789.03, its separately labelled Built up Area: 1458, the RERA-filed saleable area of 27.87 sq. m. for the listed 2BHK, and any carpet area. No carpet-area measurement was completed from the supplied drawings: both drawing scans are pending measurement. RERA unit details Floor plans

4. Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK2002027.87 sq. m.Not measured; two drawing scans are pending measurementNot supplied

RERA unit table RERA unit details Floor plans

The 2BHK configuration, count, booking status and saleable area are from the TG-RERA unit record. “Saleable area” is the filed figure; it is not a measured carpet area. Carpet area, balcony or utility area, and any common-area loading should not be inferred from it. The supplied floor-plan record reports two drawings, 0 measured, and 2 scans pending, so room dimensions and drawing-based carpet measurements cannot be reported. RERA unit table RERA unit details Floor plans

5. Parking & vehicle circulation

The HMDA approval specifies a stilt level and requires it to be used exclusively for vehicle parking, without partition walls or rolling shutters. The approval extraction does not provide a number of parking spaces, a resident/visitor allocation, accessible spaces, or a unit-wise parking allotment.

A stilt parking requirement in the approval does not establish that a particular bay is allocated to a particular apartment. No evidence is supplied on ramps, mechanical parking, EV charging, visitor parking, or pedestrian separation.

6. Amenities, recreation & open spaces

The TG-RERA amenities record lists the following items and records 0% progress for each. These are portal entries, not independent confirmation of construction or delivery. The HMDA approval separately includes certain site requirements and provisions noted below. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Internal Roads & FootpathsSize not suppliedTG-RERA amenities record RERA amenities0%; not independently verified
Green Strip/TOT LOT/ParkSize not suppliedTG-RERA amenities record RERA amenities; HMDA approval requires a tot-lot and peripheral greenery0% in RERA record; delivery not independently verified
Community BuildingsSize or description not suppliedTG-RERA amenities record RERA amenities0%; not independently verified
Water Conservation, Rain water HarvestingSize or system details not suppliedTG-RERA amenities record RERA amenities; HMDA approval requires rainwater-harvesting structuresMarked “YES” in the amenities record; 0% progress; completion not independently verified
Street LightingDetails not suppliedTG-RERA amenities record RERA amenities0%; not independently verified

The vendor record also lists security, CCTV camera, power backup, sewage treatment plant, fire safety and waste management. These are vendor-attributed descriptions, not established as sanctioned or delivered facilities by the supplied project approval or RERA progress record. Promoter website

7. Utilities, building services & safety

The HMDA technical approval sets conditions for water supply, sewerage disposal, rainwater harvesting, electrical provision, fire safety and waste arrangements. These are approval requirements; the supplied materials do not independently establish that the works have been completed or commissioned.

Water
What the supplied record saysApproval conditions address the water source, bore depth and size, and disinfection to maintain residual chlorine of 0.3 to 0.4 p.m. in sump/overhead tanks. It specifies a separate underground static water tank of 25,000 Its. and a separate residential terrace tank of 25,000 Its.
Status supported by evidenceApproval conditions; implementation not independently verified
Sewerage and drainage
What the supplied record saysApproval conditions address connecting treated sewerage to an existing Gram Panchayat drain where available, or treated overflow to a natural drain/nala where applicable; drainage is not to overflow onto roads or public places. Periodic septic-tank cleaning and sludge removal are also specified.
Status supported by evidenceApproval conditions; actual system and connections not independently verified
Rainwater harvesting
What the supplied record saysRainwater-harvesting structures and a percolation pit are required by the approval.
Status supported by evidenceApproval condition; completion not independently verified
Electrical supply and backup
What the supplied record saysApproval requires transformer space and a generator as an alternate supply, and requires electrical wiring and installation certification for electrical fire safety.
Status supported by evidenceApproval conditions; no commissioning evidence supplied
Fire and life safety
What the supplied record saysApproval conditions specify fire-fighting installations, emergency lighting in corridors/common passages and staircases, a manual alarm system, hose reel and down comer, fire extinguishers, and sprinkler provision if basement area exceeds 200 Sq.mts.
Status supported by evidenceApproval conditions; no fire-clearance or completion evidence supplied
Access and circulation
What the supplied record saysApproval requires one entry and one exit with minimum width 4.5mts. and height clearance 5mts.
Status supported by evidenceApproval condition; as-built provision not independently verified
Waste
What the supplied record saysThe HMDA approval requires a garbage house within the premises.
Status supported by evidenceApproval condition; completion not independently verified
Lifts
What the supplied record saysApproval conditions refer to fire-resistant swing doors for collapsible lifts, but no lift count, capacity or installation status is supplied.
Status supported by evidenceNo lift schedule or completion evidence supplied
Accessibility
What the supplied record saysThe supplied approval condition concerning facilities for physically handicapped persons is expressly for public and semi-public buildings above 300Sa.mts; the evidence does not establish a project-specific accessibility schedule.
Status supported by evidenceProject-specific accessible facilities not established

8. Location, access & connectivity

The registered project location is KUNTLOOR, Abdullapurmet Mandal, Ranga Reddy District, PIN 501505. The cadastral parcel centroid is recorded at 17.34723, 78.62731. RERA record Location record

The supplied connectivity record lists the nearest sampled Outer Ring Road interchange at approximately 3.1 km. No approach-road route, public-transport information, other measured landmark distances, or travel-time evidence is supplied. The site boundaries identify 30-foot roads on the east, west and north, and Plot Nos. 224 and 227 on the south. Location record RERA filing

9. Developer & development status

The registered promoter is GAUTAM CONSTRUCTIONS, identified in the RERA data as a partnership. The supplied corporate identifier is GSTIN 36AAJFG2090B1ZQ. The listed partners are LOKAVARAPU VENKATA RAMANA and LOKAVARAPU RAMADEVI; the RERA records identify Lokavarapu Venkata Ramana as authorized signatory. Corporate record Parties record

The Form B declaration, signed by Lokavarapu Venkata Ramana and verified at Hyderabad on 04-12-2021, declares a completion undertaking of 17/03/2026. The project header separately records 30/11/2026 as the proposed completion date; the supplied records do not explain the relationship between those entries. No verified construction-progress evidence, completion certificate or occupancy certificate is supplied. RERA record RERA amenities

The registration certificate lists a promoter-office location as Village: Mandal: District: Medchal-Malkajgiri, Pin: 500011. The village and mandal fields are blank in that extracted text. No official contact details or official website are supplied.

10. Approvals, official records & documents

RecordSupplied evidence
TG-RERA registrationForm C certificate for SAI TEJA HOMES, registration P02400003845, issued 03/01/2022, with validity stated through 17/03/2026
Principal technical approvalHMDA technical approval 022671/GHT/R1/U6/HMDA/16042019, dated 19 December, 2019, for a residential building in Survey Nos. 153, 159 and 160, Kuntloor; approval extraction identifies 1 Stilt + 5 Upper floors
Approval conditionsThe technical-approval record includes construction, parking, water, sewerage, rainwater harvesting, transformer, waste, fire-safety, inspection and occupancy conditions
Promoter declarationForm B affidavit-cum-declaration by Lokavarapu Venkata Ramana, verified at Hyderabad on 04-12-2021
Occupancy / completion recordNo occupancy or completion certificate is included in the supplied documents. The HMDA approval states that occupation is conditional on completion in accordance with approved plans, compliance with conditions and issue of a “Fit for Occupancy” certificate by the Executive Authority.
Detailed approved plans / floor drawingsThe supplied record identifies two floor-plan drawings, but both scans are pending measurement; detailed drawing-derived room and carpet-area information is not available here. Floor plans

Frequently asked questions

Is SAI TEJA HOMES registered with Telangana RERA?

Yes. SAI TEJA HOMES is registered with the Telangana Real Estate Regulatory Authority as P02400003845; the registration status is New Project.

Who is the developer of SAI TEJA HOMES?

The promoter named in the RERA registration is GAUTAM CONSTRUCTIONS.

Where is SAI TEJA HOMES located?

SAI TEJA HOMES is in KUNTLOOR, Abdullapurmet, Rangareddy, Telangana (501505).

When will SAI TEJA HOMES be completed?

The promoter's proposed date of completion filed with RERA is 30/11/2026. This is the promoter's declaration, not a guarantee.

More projects in Kuntloor