Sign in

Sri Sai Homes

SARANYA CONSTRUCTIONS · Rangareddy · RERA P02400005996

SRI SAI HOMES is a residential apartment project located in Hayathnagar / Bagh Hayathnagar, Hayathnagar Mandal, Ranga Reddy District, developed by registered promoter SARANYA CONSTRUCTIONS. It is on 508.10 sq. m of land and comprises 1 building with 1 Stilt + 5 upper floors and 15 2BHK units, each with a filed saleable area of 82.09 sq. m. Its TG-RERA registration number is P02400005996, and the proposed completion date is 28-03-2025.

More from Saranya Constructions · 4 projects →

01What we found

Period endedTG-RERA registration ran to 28 Mar 2025 - check its extension on TG-RERA
12documents on file - each fact links to its page
1court case on this project's land (survey 185, Hayathnagar)
6items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

6 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldProject record
Registered project nameSRI SAI HOMES RERA record
Project typeResidential apartment project RERA record
Phase / registered portionNo phase name is disclosed. The RERA record identifies one building; the registration covers the project at Survey No. 185. RERA filing Land records
TG-RERA registrationP02400005996 RERA record
Registration validity01/04/2023 to 28/03/2025. This is the registration period shown on the certificate, not the project completion deadline. RERA record
Registered promoterSARANYA CONSTRUCTIONS, a partnership RERA record RERA filing Corporate record
RERA statusThe supplied record shows the registration validity ending 28/03/2025 and no extension recorded in the certificate. Current registration status is not otherwise supplied.

Land and geographic identity

FieldProject record
LocalityHayathnagar / Bagh Hayathnagar RERA record RERA filing
Revenue villageHayathnagar; the building permit describes the site as Bagh Hayathnagar. RERA record
MandalHayathnagar Mandal
DistrictRanga Reddy (the permit states Rangareddy District) RERA record
PIN500070 RERA record
Survey number(s)Survey No. 185; no subdivision is supplied. Land records
Plot numbers103 & 104 RERA filing
Registered site extentThe RERA land record gives 508.10 sq. m total and net area. The building permit gives 508.1 Sq. Mtrs plot and net plot area. Land records RERA filing
Road / nala affected area0 sq. m recorded in the permit for road-affected and nala-affected area.
BoundariesNorth: 30 FEET ROAD; south, east and west: NEIGHBOUR LAND. RERA filing Land records

Development identity

FieldProject record
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC) Approvals record
Principal building approval0735/GHMC/LBN/2022-BP, approved 28 March, 2022. File No. 001333/GHMC/0710/LBN2/2022-BP. Approvals record
Other layout / LRS identifier recorded on permitC/GHMC/040750/2020
Building count1 building; permit labels it Building A. RERA filing
Sanctioned configuration1 Stilt + 5 upper floors; the permit records building height as 15.
Approved built-up areaThe project filing records 1493.75 sq. m approved built-up area. The permit separately lists Residential 5 upper floors 1,231.45 Sq.Mt.; these are presented as separately labelled figures in the supplied records. RERA filing
ParkingThe permit records cellar and stilt parking, with Total Parking Area 231.3; it does not provide a parking-space count in the supplied extraction.
UnitsRERA filing: 15 2-bedroom units. The GHMC permit condition says sanctioned unit numbers must not be increased without prior GHMC approval. RERA unit table

Offering and status

FieldProject record
RERA-filed configuration2BHK, filed as “DOUBLE BEDROOM” / “DOUBLEBEDROOM” RERA unit table
RERA-filed saleable area82.09 sq. m per unit RERA unit table
Booked / available0 booked; 15 available, as last read from the TG-RERA portal; the record has no as-of date, so counts are indicative. RERA unit table
Completion deadlineThe GHMC permit and Form B declaration state 28-03-2025 as the completion date.
Construction stageNo independently verified construction-stage or site-progress evidence is supplied. Document index
Occupancy / completion certificateNo occupancy or completion certificate is included in the supplied project documents. The permit says an occupancy certificate is required before occupation. Document index

2. The project story

  • SRI SAI HOMES is registered as a residential apartment project on Plots 103 and 104 in Survey No. 185, at Bagh Hayathnagar, Hayathnagar Mandal, Ranga Reddy District. The GHMC building permit describes one residential building, Building A, on a 508.1-square-metre site, with one stilt and five upper floors. RERA record Land records
  • The RERA filing lists fifteen 2BHK apartments, each with a filed saleable area of 82.09 sq. m. Portal inventory indicates all fifteen as available and none booked, but the record does not state the date of that inventory snapshot. RERA unit table
  • The permit and the promoter’s Form B declaration set 28-03-2025 as the completion deadline. The supplied materials do not establish the current construction stage or independently verify completion. No occupancy or completion certificate is supplied; the permit makes an occupancy certificate compulsory before occupation. Document index

3. Master plan, architecture & building design

  • The GHMC permit records a single residential building, Building A, configured as 1 Stilt + 5 upper floors, with a stated height of 15. The RERA filing records approved built-up area of 1493.75 sq. m; the permit separately lists Residential 5 upper floors 1,231.45 Sq.Mt. The supplied data does not identify either figure as carpet area or provide an FSI-counted area. RERA filing
  • The permit lists setbacks of Front 3.5, Rear 3.5, Side I 3.5, and Side II 3.5; the supplied extraction does not state their units. It also records 18 mt. road width.
  • The permit specifies cellar and stilt areas for parking and requires a tot-lot to be fenced and maintained as greenery before issuance of an occupancy certificate. It also lists a strip of greenery around the site. Detailed floor-plan and layout drawings are not available in the supplied materials: the layout-plan filing is an unextracted document, and no drawing-based building arrangement or floor-by-floor unit schedule is supplied. Document index

4. Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK1501582.09 sq. mNot supplied for the RERA-filed 2BHK configurationNot supplied
  • The 2BHK configuration is the one recorded in the RERA filing. The supplied software measurements from the filed floor-plan document concern 1BHK and 3BHK drawing configurations and are identified as not matched to the RERA configuration; no carpet-area measurement for the filed 2BHK is supplied. RERA unit table RERA unit details Floor plans
  • The RERA saleable-area figure is distinct from carpet area: the supplied measurement notes describe drawing-based carpet area as software-measured and smaller than saleable area, which also includes the home’s share of common areas. The available drawings and extracted room dimensions do not provide a supported description of the RERA-filed 2BHK plan. Floor plans RERA unit details

5. Parking & vehicle circulation

  • The GHMC permit records Total Parking Area 231.3 and says cellar and stilt areas shown for parking must be used exclusively for vehicle parking, without partition walls or rolling shutters. The permit extraction does not state a unit for the parking-area figure or give the number of parking spaces, parking allocation by apartment, visitor or accessible provision, or a parking layout.
  • A vendor listing mentions covered car parking and bike parking, but no sanctioned counts or legally documented apartment-wise allocations are supplied. A parking bay or area record alone does not establish exclusive ownership or allocation. Promoter website

6. Amenities, recreation & open spaces

The following are recorded in the GHMC permit or RERA-filed amenity information. Percentages are presented as recorded progress figures; they are not independent site verification. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Tot-lot / green stripPermit requires a fenced tot-lot maintained as greenery before occupancy certification; a peripheral greenery strip is also required. No size supplied.Permit condition; completion not independently verified. RERA amenity record lists Green Strip/TOT LOT/Park at 15%.
Aggregate recreational open spaceNo area or design detail supplied.RERA amenitiesRERA amenity record: 29%; not independently verified.
Community buildingsNo building, size or capacity detail supplied.RERA amenitiesRERA amenity record: 17%; not independently verified.
Common gardenNo size supplied.Promoter websiteVendor-listed; delivery status not verified.
Community hallNo size or capacity supplied.Promoter websiteVendor-listed; delivery status not verified.
Swimming poolNo size or capacity supplied.Promoter websiteVendor-listed; delivery status not verified.
GymNo size or equipment detail supplied.Promoter websiteVendor-listed; delivery status not verified.
Children’s play areaNo size supplied.Promoter websiteVendor-listed; delivery status not verified.
ClubhouseNo size or facility schedule supplied.Promoter websiteVendor-listed; delivery status not verified.

7. Utilities, building services & safety

  • The GHMC permit requires a rainwater-harvesting structure and records No. of Rain Water Harvesting Pits 2. The permit also requires space for a transformer and a garbage house within the premises. It does not provide transformer capacity, water-storage or treatment capacity, sewerage-treatment capacity, or backup-power specifications.
  • The RERA amenity record lists water supply (24%), sewerage (23%), storm-water drains (18%), treatment and disposal of sewage and sullage water (16%), solid-waste management (28%), water conservation/rainwater harvesting (26%), energy management (21%), fire protection and fire-safety requirements (31%), electrical meter room/sub-station/receiving station (23%), and street lighting (21%). These are declared progress figures, not independently verified completion or statutory-compliance findings. RERA amenities
  • The vendor listing additionally mentions borewell water, battery backup, CCTV, security, fire safety, waste management and a lift. No capacities, equipment schedules, lift specifications, fire-system details, accessible-circulation information or independent completion verification are supplied. Promoter website

8. Location, access & connectivity

  • The registered project location is Hayathnagar / Bagh Hayathnagar, Ranga Reddy District, Telangana, PIN 500070, on Survey No. 185 and Plots 103 and 104. The GHMC permit records an 18 mt. road width and the project boundary to the north as 30 FEET ROAD. RERA record Land records
  • The supplied location data identifies Financial District (Nanakramguda), 1.2 km as a connectivity point. A vendor listing names Hayathnagar as the nearest landmark and makes general claims about nearby schools, airports, restaurants, bus stops and railway stations; no distances or travel times for those claims are supplied. Location record Promoter website

9. Developer & development status

  • The registered promoter is SARANYA CONSTRUCTIONS, recorded as a partnership. The supplied promoter identifiers include GSTIN 36ADVFS3211P1ZE; a PAN-like identifier is masked as xxxxxx211P. The listed address is Sanavi Nivas, Road No. 1, Bagh Hayathnagar, Hayathnagar, Ranga Reddy, PIN 500070. RERA record RERA filing Corporate record
  • The RERA record identifies VENKAIAH MADHAVARAPU as partner and authorized signatory, and SUBBULAMMA MADHAVARAPU as partner. Form B is a promoter declaration that the project would be completed by 28-03-2025. The supplied evidence does not establish current construction progress or an independently verified completion date. Parties record

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP02400005996, issued 01/04/2023; stated validity through 28/03/2025
What the supplied document establishesRegistration certificate for SRI SAI HOMES; includes conditions including the separate-account requirement.
GHMC building permit order
Identifier / date0735/GHMC/LBN/2022-BP; 28 March, 2022; file 001333/GHMC/0710/LBN2/2022-BP
What the supplied document establishesConditionally sanctions Building A, 1 Stilt + 5 upper floors, on a 508.1 Sq. Mtrs site; includes construction and occupancy conditions.
Layout / LRS identifier recorded on permit
Identifier / dateC/GHMC/040750/2020
What the supplied document establishesIdentifier shown in the permit; the separate RERA layout-plan filing is not extracted in the supplied record. Document index
Form B declaration
Identifier / dateDated 16" day of December, 2022
What the supplied document establishesPromoter declaration covering the stated land-title basis, encumbrance statement, separate-account undertaking and completion date.
Advocate’s title investigation report
Identifier / date23-11-2022
What the supplied document establishesTitle report for Plots 103 and 104 in Survey No. 185; see the Land & Title section for its source documents and qualifications.
Occupancy / completion certificate
Identifier / dateNot supplied
What the supplied document establishesThe permit requires an occupancy certificate before occupation; the supplied document set does not include one. Document index

Frequently asked questions

Is SRI SAI HOMES registered with Telangana RERA?

Yes. SRI SAI HOMES is registered with the Telangana Real Estate Regulatory Authority as P02400005996; the registration status is New Project.

Who is the developer of SRI SAI HOMES?

The promoter named in the RERA registration is SARANYA CONSTRUCTIONS.

Where is SRI SAI HOMES located?

SRI SAI HOMES is in HAYATHNAGAR, Rangareddy, Telangana (500070).

When will SRI SAI HOMES be completed?

The promoter's proposed date of completion filed with RERA is 28/03/2025. This is the promoter's declaration, not a guarantee.

More projects in Rangareddy