Sri Sai Mansion Udaya Sris
UDAYASRI INFRA · Rangareddy · RERA P02400002396
SRI SAI MANSION UDAYA SRIS is a residential apartment project on Plot No. 52-B in Puppalaguda, Gandipet mandal, Ranga Reddy district. The registered promoter is UDAYASRI INFRA. The project covers 710.71 sq. m and comprises one residential building with 1 Stilt + 5 Upper Floors and 10 3BHK units. It is registered under TG-RERA number P02400002396, with a proposed completion date of 23/07/2025.
More from Udayasri Infra · 3 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
8 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered project name | SRI SAI MANSION UDAYA SRIS RERA record |
| Project type | Residential apartment project RERA record RERA filing |
| Phase / registered portion | No separate phase name is disclosed. The registration relates to the residential building on Plot No. 52-B in Survey Nos. 104(Part) and 105(Part), Puppalaguda. |
| TG-RERA registration | P02400002396 Approvals record |
| Registration validity | Certificate states 17/12/2020 to 23/07/2025; no extension is recorded in the supplied record. This is the registration period, distinct from the completion deadline. Approvals record |
| Registered promoter | UDAYASRI INFRA; the project record identifies it as a partnership. RERA filing Parties record |
| RERA status | Project status is recorded as “New Project”; the supplied registration certificate is not marked extended. The project record gives a proposed completion date of 23/07/2025. RERA filing Approvals record |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality / site | Plot No. 52-B, Puppalaguda RERA filing |
| Revenue village | Puppalaguda (also written “Puppalguda” in approval extracts) RERA record |
| Mandal | Gandipet appears in the HMDA intimation; the RERA project identity does not disclose a mandal. |
| District | Ranga Reddy RERA record |
| PIN | 500089 RERA record |
| Project survey numbers | 104 PART and 105 PART; the building-permission document writes these as 104(Part) and 105(Part). RERA record Land records |
| Registered site extent | 710.71 sq. m (the approval intimation records 710.71 Sq. Mt.) RERA filing |
| Total / net land area | 710.71 sq. m total and 710.71 sq. m net; recorded affected area is 0 sq. m. RERA filing Land records |
| Boundaries | North: ROAD WIDTH 12; South: PLOT NO 52A; East: PLOT NO 53B; West: PLOT NO 51B. RERA filing |
Development identity
| Item | Project record |
|---|---|
| Sanctioning authority | Manikonda Municipal Council; the proceedings release plans described as technically approved by HMDA. Approvals record |
| Principal building-permission reference | Roc. No. MC MNK/TP 12019-2020, dated 19-09-2019. The associated HMDA technical-approval reference is 020919/SKP/R1/U6/HMDA/27022019, dated 20-08-2019. Approvals record |
| Approved built-up area | 1834.03 sq. m RERA filing |
| Building count and floors | One residential building: 1 Stilt + 5 Upper Floors. RERA filing |
| Parking levels | A stilt level is part of the recorded building configuration; the supplied material does not state a parking-space count or establish which spaces are allocated to purchasers. RERA amenities |
| Unit count | 10 units in the RERA configuration record; the project’s land-details fields separately record 1 building unit. RERA unit table RERA filing |
| Approval-intimation qualification | The HMDA document dated 23/07/2019 is an intimation to pay charges and fulfil conditions for further processing; it expressly says it is not approval of the proposal or permission for development. |
Offering and status
| Item | Project record |
|---|---|
| RERA-filed configuration | 3BHK, 10 units; the portal-derived booking record shows 0 booked and 10 available, with no as-of date supplied. Treat booking counts as indicative. RERA unit table RERA unit details |
| RERA-filed saleable area | 197.66 sq. m per configuration record. RERA unit table RERA unit details |
| Construction stage | No independently verified site-progress report is supplied. The RERA infrastructure record reports water supply at 30% and the other listed infrastructure items at 0%; these are filed progress figures, not independent verification. RERA amenities |
| Completion deadline | 23/07/2025 is the proposed completion date in the project record and the promoter’s Form B undertaking. RERA filing |
| Occupancy / completion certificate | No occupancy or completion certificate is included in the supplied project documents. The building-permission proceedings say a “Fit for Occupancy” certificate is required before occupancy. Document index |
2. The project story
SRI SAI MANSION UDAYA SRIS is recorded as a residential apartment project on Plot No. 52-B in Puppalaguda village, Ranga Reddy district, covering the project portions of Survey Nos. 104 and 105. The RERA record describes one building, with a sanctioned configuration of one stilt level and five upper floors; the RERA unit schedule lists ten 3BHK apartments. RERA record Land records RERA unit table
The building-permission proceedings identify Udayasri Infra and the landowners as applicants and require construction to follow the technically approved building plans. The supplied documents do not establish how much construction has been completed on site, and no occupancy or completion certificate is supplied. The reported infrastructure percentages are portal-recorded figures rather than an independent site inspection. RERA amenities Document index
3. Master plan, architecture & building design
The filed building configuration is a single residential building with 1 Stilt + 5 Upper Floors on a recorded site extent of 710.71 sq. m. The approval extract records an approved built-up area of 1834.03 sq. m. No separate FSI-counted area, building footprint, floor-by-floor unit schedule, tower-height measurement, or detailed common-area schedule is available in the supplied material. RERA filing RERA filing
The building-permission proceedings require the construction to follow the technically approved plan, preserve the circulation pattern shown in that plan, and maintain the designated open space as open space with greenery; they also prohibit construction or parking in setback areas. The drawings needed to describe the detailed arrangement are not available in the extracted record.
The registration filing lists 197.66 sq. m as saleable area for the 3BHK configuration. A separate software measurement from the drawing reports a median carpet area of 167.2 sq. m, ranging from 158.0 to 173.7 sq. m across four measured flat designs. That drawing-based measurement is not a RERA-filed carpet-area figure and is noted as requiring review; saleable area and carpet area are different measures. RERA unit table RERA unit details Floor plans
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 10 | 0 | 10 | 197.66 sq. m | Software-measured: median 167.2 sq. m; range 158.0–173.7 sq. m | 15% (drawing-based record) |
The unit counts, booking figures and saleable area are from the TG-RERA project record; booking figures have no supplied as-of date. Carpet area and loading are software-measured from the filed floor-plan drawing, not RERA disclosures, and the measurements are flagged for review. Saleable area may include a proportionate share of common areas; it should not be read as the same measurement as the usable interior carpet area. RERA unit table RERA unit details Floor plans
One measured first-floor plan describes a flat with three bedrooms, a living/dining room, a kitchen and three toilets. The drawing-derived room areas include a living/dining area of 56.92 m², kitchen of 11.2 m², and bedroom areas of 19.11 m², 17.64 m² and 17.64 m². These are software measurements from the drawing geometry, not independently surveyed dimensions. RERA unit details
5. Parking & vehicle circulation
The recorded building has a stilt level, but the supplied material does not establish the number of sanctioned parking spaces, visitor or accessible spaces, or any purchaser-specific parking allocation. A drawn or indicated parking area would not by itself establish exclusive ownership. RERA amenities
The building-permission proceedings require the circulation pattern shown on the plan to be used as driveways and not changed, and state that parking or construction is not permitted in setback areas. The detailed driveway layout, ramp arrangement and vehicle-entry/exit configuration are not available in the extracted material.
6. Amenities, recreation & open spaces
The TG-RERA infrastructure record lists the following facilities and progress. Percentages are portal-recorded figures; the supplied record does not independently verify completion.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Water supply | No source or capacity stated | RERA amenities | 30% filed progress; not independently verified |
| Sewerage, including chamber, lines, septic tank and STP | No capacities stated | RERA amenities | 0% filed progress; not independently verified |
| Storm-water drains | No size or extent stated | RERA amenities | 0% filed progress; not independently verified |
| Green strip / tot lot / park | No area stated | RERA amenities | 0% filed progress; not independently verified |
| Community buildings | No facility or size specified | RERA amenities | 0% filed progress; not independently verified |
| Recreational open space | Aggregate area not stated | RERA amenities | 0% filed progress; not independently verified |
7. Utilities, building services & safety
The building-permission proceedings specify water supply, drainage and sewerage disposal, a septic tank, rainwater-harvesting structures, a transformer, a garbage house, generator and emergency lighting. They also specify underground and terrace water-storage tanks of 25,000 litres each for the residential building. These are approval-document requirements; the supplied material does not independently establish that they have been installed or are operational.
For fire and life safety, the proceedings require fire-service clearance before applying for occupancy, fire-safety compliance with the National Building Code, emergency water storage and firefighting equipment, including extinguishers, house reel and down-comer; an automatic sprinkler system is specified where basement area exceeds 200 sq. m. The available record does not state whether a basement is part of this building. No lift count or capacity, accessibility provisions, CCTV or waste-segregation arrangements are established in the supplied project evidence.
8. Location, access & connectivity
The registered project location is Plot No. 52-B, Puppalaguda village, Ranga Reddy district, PIN 500089. The parcel record gives road frontage on the north as ROAD WIDTH 12; the building-permission proceedings separately refer to road widths of 4.5 mtrs and 5 mtrs and require use of the circulation pattern shown in the approved plan. RERA record RERA filing
A supplied location record lists Financial District (Nanakramguda), 1.2 km away. No public-transport route or project-specific measured distances to other services are supplied. Location record
9. Developer & development status
The registered promoter is UDAYASRI INFRA, identified in the project record as a partnership. The listed members are EADA SRINIVASA RAO (authorized signatory) and EADA VIJAYA SRI (partner). The supplied evidence does not provide a verified corporate registration number or official project contact details. RERA filing Parties record Corporate record
The promoter’s Form B declaration, dated 26 January 2019, states that the project would be completed by 23 July 2025 and includes undertakings concerning the separate account, project-fund use, audit and pending approvals. These are promoter declarations. The supplied documents do not establish independent construction progress or an issued occupancy/completion certificate. Document index RERA amenities
10. Approvals, official records & documents
| Reference and scope | Form C; P02400002396, for SRI SAI MANSION UDAYA SRIS; validity stated as 17/12/2020–23/07/2025 |
|---|
| Reference and scope | Application 020919/SKP/R1/U6/HMDA/27022019, dated 23/07/2019; intimation to pay charges and fulfil conditions, expressly not development permission |
|---|
| Reference and scope | Manikonda Municipal Council, Roc. No. MC MNK/TP 12019-2020, dated 19-09-2019; residential building, 1 Stilt + 5 Upper Floors, Survey Nos. 104(Part) and 105(Part) |
|---|
| Reference and scope | 020919/SKP/R1/U6/HMDA/27022019, dated 20-08-2019, cited in the building-permission proceedings |
|---|
| Reference and scope | Registered mortgage deed 8689/2019, dated 01-08-2019; approval proceedings describe 10% of built-up area mortgaged in favour of MC, HMDA |
|---|
| Reference and scope | Promoter declaration dated 26 January 2019, including the stated completion undertaking of 23 July 2025 |
|---|
| Reference and scope | Floor-plan document 112059; drawing-based unit measurements are software-measured and flagged for review |
|---|
| Reference and scope | No extracted layout approval or occupancy/completion certificate is included in the supplied documents. |
|---|---|
| Evidence | Document index |
1. Project at a glance
Project identity
Registered project name: SRI SAI MANSION UDAYA SRIS
Project type: Residential apartment project
Phase / registered portion: No separate phase name is disclosed. The registration relates to the residential building on Plot No. 52-B in Survey Nos. 104(Part) and 105(Part), Puppalaguda.
TG-RERA registration: P02400002396
Registration validity: Certificate states 17/12/2020 to 23/07/2025; no extension is recorded in the supplied record. This is the registration period, distinct from the completion deadline.
Registered promoter: UDAYASRI INFRA; the project record identifies it as a partnership.
RERA status: Project status is recorded as “New Project”; the supplied registration certificate is not marked extended. The project record gives a proposed completion date of 23/07/2025.
Land and geographic identity
Locality / site: Plot No. 52-B, Puppalaguda
Revenue village: Puppalaguda (also written “Puppalguda” in approval extracts)
Mandal: Gandipet appears in the HMDA intimation; the RERA project identity does not disclose a mandal.
District: Ranga Reddy
PIN: 500089
Project survey numbers: 104 PART and 105 PART; the building-permission document writes these as 104(Part) and 105(Part).
Registered site extent: 710.71 sq. m (the approval intimation records 710.71 Sq. Mt.)
Total / net land area: 710.71 sq. m total and 710.71 sq. m net; recorded affected area is 0 sq. m.
Boundaries: North: ROAD WIDTH 12; South: PLOT NO 52A; East: PLOT NO 53B; West: PLOT NO 51B.
Development identity
Sanctioning authority: Manikonda Municipal Council; the proceedings release plans described as technically approved by HMDA.
Principal building-permission reference: Roc. No. MC MNK/TP 12019-2020, dated 19-09-2019. The associated HMDA technical-approval reference is 020919/SKP/R1/U6/HMDA/27022019, dated 20-08-2019.
Approved built-up area: 1834.03 sq. m
Building count and floors: One residential building: 1 Stilt + 5 Upper Floors.
Parking levels: A stilt level is part of the recorded building configuration; the supplied material does not state a parking-space count or establish which spaces are allocated to purchasers.
Unit count: 10 units in the RERA configuration record; the project’s land-details fields separately record 1 building unit.
Approval-intimation qualification: The HMDA document dated 23/07/2019 is an intimation to pay charges and fulfil conditions for further processing; it expressly says it is not approval of the proposal or permission for development.
Offering and status
RERA-filed configuration: 3BHK, 10 units; the portal-derived booking record shows 0 booked and 10 available, with no as-of date supplied. Treat booking counts as indicative.
RERA-filed saleable area: 197.66 sq. m per configuration record.
Construction stage: No independently verified site-progress report is supplied. The RERA infrastructure record reports water supply at 30% and the other listed infrastructure items at 0%; these are filed progress figures, not independent verification.
Completion deadline: 23/07/2025 is the proposed completion date in the project record and the promoter’s Form B undertaking.
Occupancy / completion certificate: No occupancy or completion certificate is included in the supplied project documents. The building-permission proceedings say a “Fit for Occupancy” certificate is required before occupancy.
2. The project story
SRI SAI MANSION UDAYA SRIS is recorded as a residential apartment project on Plot No. 52-B in Puppalaguda village, Ranga Reddy district, covering the project portions of Survey Nos. 104 and 105. The RERA record describes one building, with a sanctioned configuration of one stilt level and five upper floors; the RERA unit schedule lists ten 3BHK apartments.
The building-permission proceedings identify Udayasri Infra and the landowners as applicants and require construction to follow the technically approved building plans. The supplied documents do not establish how much construction has been completed on site, and no occupancy or completion certificate is supplied. The reported infrastructure percentages are portal-recorded figures rather than an independent site inspection.
3. Master plan, architecture & building design
The filed building configuration is a single residential building with 1 Stilt + 5 Upper Floors on a recorded site extent of 710.71 sq. m. The approval extract records an approved built-up area of 1834.03 sq. m. No separate FSI-counted area, building footprint, floor-by-floor unit schedule, tower-height measurement, or detailed common-area schedule is available in the supplied material.
The building-permission proceedings require the construction to follow the technically approved plan, preserve the circulation pattern shown in that plan, and maintain the designated open space as open space with greenery; they also prohibit construction or parking in setback areas. The drawings needed to describe the detailed arrangement are not available in the extracted record.
The registration filing lists 197.66 sq. m as saleable area for the 3BHK configuration. A separate software measurement from the drawing reports a median carpet area of 167.2 sq. m, ranging from 158.0 to 173.7 sq. m across four measured flat designs. That drawing-based measurement is not a RERA-filed carpet-area figure and is noted as requiring review; saleable area and carpet area are different measures.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 10 | 0 | 10 | 197.66 sq. m | Software-measured: median 167.2 sq. m; range 158.0–173.7 sq. m | 15% (drawing-based record) |
The unit counts, booking figures and saleable area are from the TG-RERA project record; booking figures have no supplied as-of date. Carpet area and loading are software-measured from the filed floor-plan drawing, not RERA disclosures, and the measurements are flagged for review. Saleable area may include a proportionate share of common areas; it should not be read as the same measurement as the usable interior carpet area.
One measured first-floor plan describes a flat with three bedrooms, a living/dining room, a kitchen and three toilets. The drawing-derived room areas include a living/dining area of 56.92 m², kitchen of 11.2 m², and bedroom areas of 19.11 m², 17.64 m² and 17.64 m². These are software measurements from the drawing geometry, not independently surveyed dimensions.
5. Parking & vehicle circulation
The recorded building has a stilt level, but the supplied material does not establish the number of sanctioned parking spaces, visitor or accessible spaces, or any purchaser-specific parking allocation. A drawn or indicated parking area would not by itself establish exclusive ownership.
The building-permission proceedings require the circulation pattern shown on the plan to be used as driveways and not changed, and state that parking or construction is not permitted in setback areas. The detailed driveway layout, ramp arrangement and vehicle-entry/exit configuration are not available in the extracted material.
6. Amenities, recreation & open spaces
The TG-RERA infrastructure record lists the following facilities and progress. Percentages are portal-recorded figures; the supplied record does not independently verify completion.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Water supply | No source or capacity stated | 30% filed progress; not independently verified | |
| Sewerage, including chamber, lines, septic tank and STP | No capacities stated | 0% filed progress; not independently verified | |
| Storm-water drains | No size or extent stated | 0% filed progress; not independently verified | |
| Green strip / tot lot / park | No area stated | 0% filed progress; not independently verified | |
| Community buildings | No facility or size specified | 0% filed progress; not independently verified | |
| Recreational open space | Aggregate area not stated | 0% filed progress; not independently verified |
7. Utilities, building services & safety
The building-permission proceedings specify water supply, drainage and sewerage disposal, a septic tank, rainwater-harvesting structures, a transformer, a garbage house, generator and emergency lighting. They also specify underground and terrace water-storage tanks of 25,000 litres each for the residential building. These are approval-document requirements; the supplied material does not independently establish that they have been installed or are operational.
For fire and life safety, the proceedings require fire-service clearance before applying for occupancy, fire-safety compliance with the National Building Code, emergency water storage and firefighting equipment, including extinguishers, house reel and down-comer; an automatic sprinkler system is specified where basement area exceeds 200 sq. m. The available record does not state whether a basement is part of this building. No lift count or capacity, accessibility provisions, CCTV or waste-segregation arrangements are established in the supplied project evidence.
8. Location, access & connectivity
The registered project location is Plot No. 52-B, Puppalaguda village, Ranga Reddy district, PIN 500089. The parcel record gives road frontage on the north as ROAD WIDTH 12; the building-permission proceedings separately refer to road widths of 4.5 mtrs and 5 mtrs and require use of the circulation pattern shown in the approved plan.
A supplied location record lists Financial District (Nanakramguda), 1.2 km away. No public-transport route or project-specific measured distances to other services are supplied.
9. Developer & development status
The registered promoter is UDAYASRI INFRA, identified in the project record as a partnership. The listed members are EADA SRINIVASA RAO (authorized signatory) and EADA VIJAYA SRI (partner). The supplied evidence does not provide a verified corporate registration number or official project contact details.
The promoter’s Form B declaration, dated 26 January 2019, states that the project would be completed by 23 July 2025 and includes undertakings concerning the separate account, project-fund use, audit and pending approvals. These are promoter declarations. The supplied documents do not establish independent construction progress or an issued occupancy/completion certificate.
10. Approvals, official records & documents
| Reference and scope | Form C; P02400002396, for SRI SAI MANSION UDAYA SRIS; validity stated as 17/12/2020–23/07/2025 |
|---|
| Reference and scope | Application 020919/SKP/R1/U6/HMDA/27022019, dated 23/07/2019; intimation to pay charges and fulfil conditions, expressly not development permission |
|---|
| Reference and scope | Manikonda Municipal Council, Roc. No. MC MNK/TP 12019-2020, dated 19-09-2019; residential building, 1 Stilt + 5 Upper Floors, Survey Nos. 104(Part) and 105(Part) |
|---|
| Reference and scope | 020919/SKP/R1/U6/HMDA/27022019, dated 20-08-2019, cited in the building-permission proceedings |
|---|
| Reference and scope | Registered mortgage deed 8689/2019, dated 01-08-2019; approval proceedings describe 10% of built-up area mortgaged in favour of MC, HMDA |
|---|
| Reference and scope | Promoter declaration dated 26 January 2019, including the stated completion undertaking of 23 July 2025 |
|---|
| Reference and scope | Floor-plan document 112059; drawing-based unit measurements are software-measured and flagged for review |
|---|
| Reference and scope | No extracted layout approval or occupancy/completion certificate is included in the supplied documents. |
|---|
Frequently asked questions
Is SRI SAI MANSION UDAYA SRIS registered with Telangana RERA?
Yes. SRI SAI MANSION UDAYA SRIS is registered with the Telangana Real Estate Regulatory Authority as P02400002396; the registration status is New Project.
Who is the developer of SRI SAI MANSION UDAYA SRIS?
The promoter named in the RERA registration is UDAYASRI INFRA.
Where is SRI SAI MANSION UDAYA SRIS located?
SRI SAI MANSION UDAYA SRIS is in PUPPALAGUDA, Rangareddy, Telangana (500089).
When will SRI SAI MANSION UDAYA SRIS be completed?
The promoter's proposed date of completion filed with RERA is 23/07/2025. This is the promoter's declaration, not a guarantee.