GARDEN OF EDEN - VII is a plotted development in GUNDLAPOTLAPALLY`, Rajapoor mandal, Mahabubnagar district, developed by GARDEN OF EDEN PROPERTY DEVELOPERS PRIVATE LIMITED. The RERA-filed land area is 63778.45 sqmts, and the draft-layout approval records 231 residential plots; building or tower count, floors, and plot configurations are not disclosed. The project is registered under TG-RERA number P01400001533, with a proposed completion date of 31/12/2022.

More from Garden Of Eden Property Developers Pvt Ltd · 5 projects →

01What we found

Period endedTG-RERA registration ran to 31 Dec 2022 - check its extension on TG-RERA
8documents on file - each fact links to its page
0court cases on this project's land in the court records searched
8items to check - 5 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

8 items to check before you pay, 5 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldProject record
Registered project nameGARDEN OF EDEN - VII RERA record
Project typePlotted development / plotted layout RERA record RERA filing
Phase / registered portionPhase VII is named in the registration; its extent across any larger development is not further described in the supplied record. RERA record
TG-RERA registrationP01400001533 RERA record
Registration validity27/12/2019 to 31/12/2022; certificate extract records no extension. This is registration validity, not an occupancy or completion certificate.
Registered promoterGARDEN OF EDEN PROPERTY DEVELOPERS PRIVATE LIMITED RERA record
RERA-record statusRegistration certificate issued under section 5. The recorded proposed completion date was 31/12/2022; current completion and occupancy-certificate status are not established by the supplied evidence. RERA filing

Land and geographic identity

FieldProject record
Locality / revenue villageGUNDLAPOTLAPALLY` is the RERA filing’s village/locality entry; the draft layout approval names Gundlapotlampally. RERA record RERA filing
MandalRajapoor in the RERA filing; Rajapur in the approval extract. RERA record RERA filing
District / PINMahabubnagar / 509001 RERA record
All project survey numbers and subdivisions141/P, 142, 182, 183, 184/P, 185, 186, 192, 193, 194 and 195 RERA record Land records
RERA-filed land areaTotal area 63778.45 sqmts; net area 63778.45 sqmts; area affected in road widening/FTL of tanks/nala widening 0. RERA filing
Draft-layout approval extentAc. 15.76 Cents; 76278.40Sq.Yds
RERA-filed boundariesEast: GP ROAD TO GALIGUDA; West: SY NO 182 AND 186; North: LAND OF GONELA NARSIMHULU AND OTHERS; South: GP ROAD AND HANUMAN TEMPLE RERA filing

Development identity

FieldProject record
Sanctioning authorityDirector of Town & Country Planning; approval extract says delegated to Gundlapotlampally Gram Panchayat.
Principal approvalDraft - TLP.No.48/2019/H; the approval extract’s date is rendered as “(1 -03-2019”, so the precise day is unclear in the supplied text. The RERA filing lists the plan approval number as TLP.No.48/2019/H. Approvals record
Approval characterThe available approval document describes a revised Draft Technical Layout Pattern for a 231-plot layout.
Approved built-up areaRERA filing records 37433.11 sqmts; the supplied material does not clarify how this field applies to the plotted layout. RERA filing
Building / tower count and floorsNot disclosed in the supplied project record.
Layout land-use split in approval extractPlotted area: Ac. 9.25 Cents; 44770.00 Sq. Yds. (58.69%); open space: Ac. 1.576 Cents; 7627.80 Sq. Yds. (10.00%); road area: Ac. 4.94 Cents; 23909.6Sq. Yds (31.34%); mortgage area: Ac: 1.41 Cents; 6824.40 Sq. Yds. (15.24 %). The document also has differing road-area figures in its conditions; see Approvals/Risk review.
ParkingNo sanctioned vehicle-parking count or parking arrangement is supplied.

Offering and status

FieldProject record
OfferingResidential plots; the approval extract records 231 plots.
RERA-filed plot size / availabilityUnit-level plot-size bands and booked/available counts are not supplied.
Promoter-marketed plot size1503 - 1935 sq.ft; the vendor record also renders this as 139.63 - 179.77 sq.m. This is marketing information, not a RERA-filed unit schedule. Promoter website
Construction stageNo independently verified site progress is supplied. The RERA amenities record gives reported percentages for certain layout infrastructure; those figures are not independent site verification. RERA amenities
Completion timelinePromoter’s Form B declares completion by 315T December 2022 (OCR rendering); the RERA project information and registration certificate give 31/12/2022. RERA filing
Occupancy / completion certificateNot supplied; no occupancy or completion certificate status is established by the available documents.

2. The project story

Garden of Eden - VII is registered as a plotted residential development in the Mahabubnagar district, with the RERA filing identifying the location as GUNDLAPOTLAPALLY`, Rajapoor mandal. The recorded project parcel comprises survey numbers 141/P, 142, 182, 183, 184/P, 185, 186, 192, 193, 194 and 195. RERA record Land records

The project record describes a layout rather than apartment buildings: the filed approval extract is for a draft layout of 231 plots, with land allocated among plots, roads, open space and a mortgage area. The extract lists layout-development works including roads, drains, avenue planting, rainwater-harvesting pits, street lighting, electricity, sewerage disposal and protected water supply. These are approval-document requirements or specifications, not proof that the works have been completed.

The promoter’s declared completion date was 31/12/2022. The supplied materials do not establish present site completion, final layout release, or issuance of a completion/occupancy certificate. The amenities register reports 100% for some items and 0% for others, but does not provide independent inspection evidence or a dated site-verification record. RERA filing RERA amenities

3. Master plan, architecture & building design

This is a plotted layout, so the relevant design evidence concerns plot arrangement and site infrastructure rather than apartment towers or floor plans. The available document is a draft technical layout-pattern approval for 231 plots. It allocates 58.69% to plotted area, 10.00% to open space and 31.34% to roads in its land-use table; it separately records a mortgage area of 15.24 %.

The approval extract lists sub-surface roads, curbstones, metalling of the carriage-way, side drains, nala channelization, avenue plantation, rainwater-harvesting pits, fencing of open spaces, street lighting and electricity, a sewerage disposal system, and protected water supply. These are documented layout requirements/specifications, not verified completed works.

The RERA filing records an approved built-up area of 37433.11 sqmts, but the supplied documents do not explain the measurement basis or how it applies to this plotted layout. No plot-by-plot schedule, approved drawing sheet, building configuration, or measured plan geometry is available in the supplied material. RERA filing Document index Floor plans

4. Homes, configurations & floor plans

The registered offering is plotted development, not a configuration of flats. The approval extract records 231 plots, but the supplied material does not provide a RERA-filed plot schedule, plot-by-plot dimensions, or booked and available counts.

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
Residential plots231 in draft-layout approvalNot disclosedNot disclosedNot disclosedNot applicableNot supplied

The vendor record markets plots of 1503 - 1935 sq.ft (139.63 - 179.77 sq.m); these are promoter-marketed figures, not a RERA-filed unit schedule. The floor-plan review reports two drawings, with 0 measured and 2 scans pending; it therefore supplies no software-measured plot or room dimensions. Promoter website Floor plans

5. Parking & vehicle circulation

No sanctioned parking count, visitor or accessible parking provision, dedicated parking allocation, or vehicle-parking layout is supplied. The approval extract describes roads and requires roads to remain accessible to neighbouring sites, but does not establish parking facilities or exclusive parking rights for any plot.

The promoter’s marketing material mentions 40 feet main roads and 33 feet internal roads; these are marketing claims and are not confirmed as measured or sanctioned dimensions in the supplied approval extract. Promoter website

6. Amenities, recreation & open spaces

The approval extract allocates 10.00 % to open space and lists layout-development works. The RERA amenities register contains reported progress percentages but no independent verification date or site-inspection evidence. RERA amenities

Internal roads & footpaths
Description / sizeLayout infrastructure; no RERA-filed dimensions supplied.
Evidence sourceRERA amenities register; draft-layout approval RERA amenities
Declared progress / verified statusRERA register reports 100%; not independently verified.
Green strip / park
Description / sizeOpen space allocation: 10.00 %; the approval extract records Ac. 1.576 Cents; 7627.80 Sq. Yds.
Evidence sourceDraft-layout approval; RERA amenities register RERA amenities
Declared progress / verified statusRERA register reports 100% for Green Strip/TOT LOT/Park; not independently verified.
Water supply
Description / sizeApproval extract specifies protected water supply system.
Evidence sourceDraft-layout approval
Declared progress / verified statusRERA register reports Water Supply 100%; not independently verified.
Sewerage
Description / sizeApproval extract specifies a sewerage disposal system.
Evidence sourceDraft-layout approval; RERA amenities register RERA amenities
Declared progress / verified statusRERA register reports Sewerage 100%; not independently verified.
Storm-water drains
Description / sizeNo size or capacity supplied.
Evidence sourceRERA amenities register RERA amenities
Declared progress / verified statusRERA register reports 0%; not independently verified.
Street lighting
Description / sizeLayout street-lighting works specified.
Evidence sourceDraft-layout approval; RERA amenities register RERA amenities
Declared progress / verified statusRERA register reports 100%; not independently verified.
Community buildings
Description / sizeNo description or size supplied.
Evidence sourceRERA amenities register RERA amenities
Declared progress / verified statusRERA register reports 0%.
Sewage/sullage treatment and disposal
Description / sizeNo system capacity or treatment details supplied.
Evidence sourceRERA amenities register RERA amenities
Declared progress / verified statusRERA register reports 0% for Treatment and Disposal of Sewage and Sullage Water.
Solid-waste management
Description / sizeNo system details supplied.
Evidence sourceRERA amenities register RERA amenities
Declared progress / verified statusRERA register reports 0%.
Rainwater harvesting
Description / sizeApproval extract lists rainwater-harvesting pits.
Evidence sourceDraft-layout approval; RERA amenities register RERA amenities
Declared progress / verified statusRERA register reports Water Conservation/Rain water Harvesting 0%; not independently verified.
Electrical meter/substation/receiving station
Description / sizeRERA amenities entry; further equipment details not supplied.
Evidence sourceRERA amenities register RERA amenities
Declared progress / verified statusRERA register reports 100%; not independently verified.

Promoter marketing additionally lists a landscaped garden, security, entrance arch and other features; these are marketing claims and are not treated here as approved or delivered facilities. Promoter website

7. Utilities, building services & safety

The draft layout approval specifies protected water supply, sewerage disposal, side drains and nala channelization, rainwater-harvesting pits, street lighting and electricity. It does not supply source or storage capacity for water, treatment or reuse capacity, storm-water design details, electrical load or backup arrangements, or waste-management specifications.

The RERA amenities register reports Water Supply, Sewerage, Street Lighting, and Electrical Meter Room/Sub-Station/Receiving Station at 100%, while Storm Water Drains, Treatment and Disposal of Sewage and Sullage Water, Solid Waste Management and Disposal, Water Conservation/Rain water Harvesting, and Fire Protection and Fire Safety Requirements are reported at 0%. These are register figures, not independently verified completion findings. The supplied documents do not establish fire-system design, emergency access, accessibility provisions, CCTV or security arrangements. RERA amenities

8. Location, access & connectivity

The RERA-filed location is GUNDLAPOTLAPALLY`, Rajapoor mandal, Mahabubnagar district, PIN 509001. The cadastral parcel centroid supplied is 17.41528, 78.35459. The filed boundary descriptions identify a GP road to Galiguda on the east and GP road and Hanuman Temple on the south. RERA record RERA filing Location record

The promoter’s marketing material claims proximity to the Hyderabad–Bangalore National Highway, TSIIC Pharma SEZ, Shadnagar transport facilities and other local services, and references proposed infrastructure. Those travel-time and connectivity statements are marketing claims; the supplied evidence does not independently establish distances or travel times. Promoter website

9. Developer & development status

The registered legal promoter is GARDEN OF EDEN PROPERTY DEVELOPERS PRIVATE LIMITED, a company. The RERA record identifies MATHEW SHAJI as authorized signatory and director and MAYA SHAJI as director. A board resolution authorizes Shaji Mathew and Maya Shaji to act for the company in project-registration and related compliance matters. RERA record Corporate record Parties record

The promoter’s project completion undertaking is recorded as 31/12/2022 in the registration record; the Form B extraction renders the date as “315T December 2022.” The registration certificate extract records no extension. The supplied evidence does not establish current construction progress, final layout release, or a completion/occupancy certificate for the layout. RERA filing

10. Approvals, official records & documents

RecordSupplied evidence and scope
TG-RERA registrationForm C for GARDEN OF EDEN - VII, registration P01400001533, issued 27/12/2019; validity recorded through 31/12/2022.
Layout approvalDirector of Town & Country Planning approval extract for Draft - TLP.No.48/2019/H, a revised draft technical layout pattern for 231 plots; extract date is OCR-rendered as “(1 -03-2019.”
Filed survey identityRegistration certificate lists 141/P, 142, 182, 183, 184/P, 185, 186, 192, 193, 194 and 195.
Promoter declarationForm B affidavit by Shaji Mathew, director, dated March 2019; includes promoter declarations concerning title, encumbrances, completion and project funds.
Encumbrance filingRERA-filed encumbrance statement is available as document 69802; it is not a current independent search result.
Detailed title reportRERA-filed title report is available as document 69801.
Layout-plan documentA layout-plan item is listed in the RERA documents, but the supplied record says it was not extracted. Document index
Completion / occupancy recordsNo completion certificate, occupancy certificate, or final layout-release record is supplied.

The approval extract describes a draft layout and states that development works and specified conveyances are required before final layout release. The supplied record does not establish whether those steps were completed.

Frequently asked questions

Is GARDEN OF EDEN - VII registered with Telangana RERA?

Yes. GARDEN OF EDEN - VII is registered with the Telangana Real Estate Regulatory Authority as P01400001533; the registration status is New Project.

Who is the developer of GARDEN OF EDEN - VII?

The promoter named in the RERA registration is GARDEN OF EDEN PROPERTY DEVELOPERS PRIVATE LIMITED.

Where is GARDEN OF EDEN - VII located?

GARDEN OF EDEN - VII is in GUNDLAPOTLAPALLY`, Rajapoor, Mahabubnagar, Telangana (509001).

When will GARDEN OF EDEN - VII be completed?

The promoter's proposed date of completion filed with RERA is 31/12/2022. This is the promoter's declaration, not a guarantee.