O.R.R. Midcity

INDO INFRA DEVELOPERS PRIVATE LIMITED · Rangareddy · RERA P02400002841

O.R.R. MIDCITY is a plotted development in Bandaravirala, Abdullapurmet Mandal, Ranga Reddy District, developed by Indo Infra Developers Private Limited. The registered land extent is 43,549.14 sq.m, with a net area of 42,864.50 sq.m; the supplied records do not establish a complete plot count or individual plot sizes, and no tower or floor configuration is stated. The offering is open plots. Its TG-RERA registration is P02400002841, issued 30/04/2021, and the promoter’s declared completion date is 06* March, 2024.

More from Indo Infra Developers Pvt Ltd · 3 projects →

01What we found

Period endedTG-RERA registration ran to 6 Mar 2024 - check its extension on TG-RERA
12documents on file - each fact links to its page
3court cases on this project's land (survey 293, Bandaravirala)
12items to check - 5 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

12 items to check before you pay, 5 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

ItemRecord
Registered project nameO.R.R. MIDCITY RERA record
Project typePlotted development / open-plot layout RERA record
Phase / registered portionThe certificate identifies the registered project as a whole; no separate phase is stated. The registered survey description is 293/11/PART.
TG-RERA registrationP02400002841, issued 30/04/2021; certificate validity 30/04/2021–06/03/2024. No extension is recorded in the supplied certificate data. RERA record
Registered promoterIndo Infra Developers Private Limited RERA record
RERA statusThe certificate records registration under section 5 and the stated validity period. The supplied record does not establish a current extension or a current registration status beyond that period.

Land and geographic identity

ItemRecord
Locality / revenue villageBandaravirala; the HMDA draft-layout document also spells the village Bandaraviryal. RERA record
Mandal / district / PINAbdullapurmet, Ranga Reddy, 501505 RERA record
Project survey identificationSurvey No. 293/11/PART in the project header and RERA certificate; the HMDA draft-layout letter describes the land as Survey No. 293/11 PART. RERA record
Site areasTotal site area 43,549.14 sq.m; master-plan-road-affected area 684.64 sq.m; net site area 42,864.5 sq.m in the HMDA draft-layout letter.
Registered land extent43,549.14 sq.m total; 42,864.50 sq.m net area, as entered in the RERA land details. RERA filing
Boundaries in RERA filingEast: OTHERS LAND; west: 45 FT PROPOSED ROAD; north: EXISTING 40 FT ROAD AND PROPOSED 100 FT ROAD; south: OTHERS LAND. RERA filing

Development identity

ItemRecord
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA) Approvals record
Principal layout approvalHMDA draft layout letter 000140/LO/Plg/HMDA/2021, approved 06 March, 2021. The project filing also gives 000140/LO/Plg/HMDA/2 as the plan approval number. Approvals record
Approved / filed areaRERA filing states approved built-up area 42,864.50 sq.m; HMDA letter describes 42,864.5 sq.m as net site area. These labels are reproduced as recorded; they are not interchangeable area measures. RERA filing
Buildings, floors and parking levelsNot applicable as a disclosed building configuration for this plotted-layout registration; no building count, floor configuration or parking levels are supplied. RERA record
Plot countHMDA draft-layout document refers to plot numbers 112 to 133 in its mortgage condition; a complete total plot count is not established by the supplied records.
RERA-declared unit/plot count and sizesNot available in the supplied structured project data. The drawing-derived layout extraction is incomplete for plot counts and plot sizes. Layout record

Offering and status

ItemRecord
OfferingOpen plots in a plotted layout; individual plot types, sizes, prices and inventory are not established by the supplied records. RERA record
Completion datePromoter’s Form B declaration undertakes completion by 06* March, 2024; the RERA registration certificate also ends on 06/03/2024. These are separate records of the declared completion date and registration validity.
Construction / development stageThe supplied RERA amenity data reports percentage figures for selected infrastructure items, but does not establish an overall project-completion percentage or independently verified site progress. RERA amenities
Occupancy / completion certificateNo project completion certificate or occupancy certificate is identified in the supplied records. The registration certificate itself is not such a certificate. Document index

2. The project story

O.R.R. MIDCITY is registered as a plotted development at Bandaravirala, Abdullapurmet Mandal, Ranga Reddy District, on the portion identified as Survey No. 293/11/PART. The HMDA filing describes a draft open-plot layout, rather than a multi-storey residential building project. RERA record

The HMDA layout document records a total site area of 43,549.14 sq.m, a road-affected area of 684.64 sq.m, and a net site area of 42,864.5 sq.m. Its area statement allocates land to plots, roads, park/open space and social infrastructure. HMDA’s document also sets out development and handover conditions before release of a final layout plan. The supplied material does not establish that those later steps have been completed.

The promoter declared a completion undertaking of 06* March, 2024. The supplied evidence does not provide a current, independently verified construction-status report or a project completion/occupancy certificate; percentage entries in the RERA amenity data should therefore be read as reported records, not independent verification of delivery. RERA amenities Document index

3. Master plan, architecture & building design

This is a plotted layout, so the available design evidence concerns land allocation and layout infrastructure rather than apartment plans or building elevations. The HMDA draft-layout document gives a net site area of 42,864.5 sq.m and identifies 22,769.29 sq.m as plotted area, 13,715.49 sq.m as layout-road area, 5,305.81 sq.m as park area and 1,073.83 sq.m as social-infrastructure area. It records 0 amenities area.

A software extraction of the approved layout drawing reports the same general land-use categories and percentages of the drawing’s net-area base: plots 22,769.29 sq.m (53.1%), roads 13,715.49 sq.m (32.0%), parks/open space 5,305.81 sq.m (12.4%), and social infrastructure 1,073.83 sq.m (2.5%). These are drawing-derived measurements and percentages, not a complete plot schedule; the extraction states that plot count and plot sizes are not complete. Layout record

The supplied material does not establish building footprints, floors, heights, apartment layouts, or a building-wise phase arrangement. The HMDA letter directs the applicant to hand over internal roads, open space, utility and social-infrastructure areas to the local body by registered gift deed before release of the final layout plan.

4. Homes, configurations & floor plans

The registered offering is plotted development, not apartments. The supplied data does not provide a complete RERA-filed plot inventory, plot-size schedule, booked/available counts or prices; no unit configuration table can therefore be completed from this record. RERA record Layout record

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
PlotsNot establishedNot suppliedNot suppliedPlot areas not suppliedNot applicableNot supplied

The layout extraction reports a total plotted-area allocation of 22,769.29 sq.m, but it does not provide a complete count or size band for individual plots. The two drawing sheets listed in the floor-plan data contain no measured apartment plans; apartment carpet-area measurements are not applicable to this plotted offering. Layout record Floor plans

5. Parking & vehicle circulation

The available evidence does not establish a project-wide parking-space count, visitor or accessible parking provision, or an allocation of parking to individual plot purchasers. The HMDA letter identifies internal layout roads and includes a condition prohibiting construction on plots until final layout release; it does not specify parking arrangements.

The HMDA document states that Plot Nos. 112 to 133, to an extent of 3,485.28 sq.m, are mortgaged in favour of the Metropolitan Commissioner, HMDA, and says those plots/area are not to be sold or conveyed until HMDA’s necessary communication. This is a layout-document condition, not evidence of an individual buyer’s parking allocation.

6. Amenities, recreation & open spaces

The following infrastructure figures are reported in the supplied RERA amenity data. Percentages are presented as recorded and are not independent completion verification. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Internal roads & footpathsProject infrastructure; no separate size statedRERA amenity data100% recorded; independent verification not supplied
Water supplyNo source, capacity or storage details suppliedRERA amenity data50% recorded
Sewerage (chamber, lines, septic tank, STP)No capacity or treatment details suppliedRERA amenity data; HMDA draft-layout conditions list common septic tank / STP50% recorded in amenity data; delivery not independently verified
Green strip / tot lot / parkLayout park area 5,305.81 sq.m in HMDA area statementRERA amenity data;50% recorded in amenity data; completion not independently verified
Street lightingNo quantity or specification suppliedRERA amenity data50% recorded
Water conservation / rainwater harvestingHMDA conditions list rainwater-harvesting pits; no number or capacity suppliedRERA amenity data;50% recorded in amenity data
Electrical meter room / sub-station / receiving stationHMDA conditions list a transformer and transformer yard; no capacity suppliedRERA amenity data;50% recorded in amenity data
Social infrastructure1,073.83 sq.m in the HMDA area statementArea is recorded; facility type and delivery status are not established
Community buildingsNo size or facility description suppliedRERA amenity data0% recorded
Storm-water drainsNo size or design details suppliedRERA amenity data0% recorded
Sewage/sullage treatment and disposalNo further specification suppliedRERA amenity data0% recorded
Solid-waste management and disposalHMDA conditions list a bio-compost unit; no capacity or completion evidence suppliedRERA amenity data;0% recorded in amenity data
Energy managementNo details suppliedRERA amenity data0% recorded
Fire protection and fire-safety requirementsNo details suppliedRERA amenity data0% recorded
Aggregate recreational open-space areaNo separate figure in the RERA amenity entry; HMDA records park area 5,305.81 sq.mRERA amenity data;0% recorded in the amenity entry; completion not independently verified

The HMDA draft-layout letter also lists internal water-supply pipelines and an overhead tank. No storage capacity, water source or commissioning evidence is supplied.

7. Utilities, building services & safety

The HMDA draft-layout conditions list a common septic tank/STP, internal water-supply pipelines and an overhead tank, a transformer and transformer yard, rainwater-harvesting pits, and a bio-compost unit. The supplied records do not state capacities, detailed specifications, commissioning dates or independent verification of operation.

The RERA amenity data records water supply, sewerage infrastructure, rainwater harvesting and electrical meter-room/sub-station/receiving-station items at 50%; it records storm-water drains, sewage/sullage treatment and disposal, solid-waste management, energy management and fire protection/safety at 0%. These are reported status fields, not a determination of statutory compliance or proof of current site condition. RERA amenities

No project-specific evidence is supplied for backup power, EV charging, lift services, fire-access design, security systems, accessibility features or waste-segregation arrangements. As a plotted layout, building-level systems are not established by the supplied evidence. Document index RERA amenities

8. Location, access & connectivity

The registered location is Bandaravirala, Abdullapurmet Mandal, Ranga Reddy District, Telangana, PIN 501505. The supplied map record places the project at coordinates 17.3896517, 78.7191314. RERA record Location record

The RERA filing describes the north boundary as an existing 40 FT ROAD and proposed 100 FT ROAD, and the west boundary as a 45 FT PROPOSED ROAD. The HMDA draft-layout letter also refers to a 100 ft wide Master plan road and requires layout roads to be opened for accessibility to neighbouring sites. RERA filing

The nearest sampled Outer Ring Road interchange is listed at approximately 7.9 km. No public-transport routes, travel times or additional landmark distances are supplied. Location record

9. Developer & development status

The registered promoter is INDO INFRA DEVELOPERS PRIVATE LIMITED, a company. The RERA filing provides GSTIN 36AACCI8151M1Z8; the project evidence also identifies the company as incorporated under the Companies Act, 1956, with CIN U45400AP2011PTC078164. RERA record Corporate record

The project record names MADHAVA RAO MALLEM as a director and SIVA GANESH BABU MALLEM as an authorized signatory. In Form B, Mr. M Shiva Ganesh Babu declares on behalf of the company that the project would be completed by 06* March, 2024. This is the promoter’s declaration; the supplied material does not provide an independently verified current completion status. Parties record

The RERA certificate records registration through 06/03/2024 and no extension in the supplied certificate data. No completion or occupancy certificate is identified in the supplied documents.

10. Approvals, official records & documents

TG-RERA registration certificate
What the supplied evidence establishesForm C records O.R.R. MIDCITY, promoter Indo Infra Developers Private Limited, registration P02400002841, issued 30/04/2021, with validity to 06/03/2024.
HMDA draft layout letter
What the supplied evidence establishesDraft open-plot layout for Survey No. 293/11 PART, approval number 000140/LO/Plg/HMDA/2021, dated 06 March, 2021; it records land areas and conditions for development and final layout release.
Form B declaration
What the supplied evidence establishesPromoter affidavit dated 24thday of March'2021, including the promoter’s title-basis and completion declarations.
Advocate’s title report
What the supplied evidence establishesReport dated 20.03.2021, concerning open plots numbered 112 to 133 in Survey No. 293/11, with a stated extent of Ac 10.30 gts equivalent to 42,864.5 sq.m.
Revenue land-conversion order
What the supplied evidence establishesRDO proceeding dated 20.06.2020 concerning conversion of land in Sy.No.293/11 Part at Bandaravirala; the extracted document states that conversion permission does not itself confer title or ownership.
Encumbrance statement
What the supplied evidence establishesProject-filed statement searches Book 1 and related indexes for 01-01-1983 to 07-09-2020 and reports nine transactions; the document itself cautions that a fresh current EC is needed to confirm current records.
Layout drawing
What the supplied evidence establishesDrawing-derived layout data is available, but plot counts and individual plot sizes are not complete in the supplied extraction.
SourceLayout record
Completion / occupancy record
What the supplied evidence establishesNo project completion certificate or occupancy certificate is identified in the supplied materials.
SourceDocument index

Frequently asked questions

Is O.R.R. MIDCITY registered with Telangana RERA?

Yes. O.R.R. MIDCITY is registered with the Telangana Real Estate Regulatory Authority as P02400002841; the registration status is New Project.

Who is the developer of O.R.R. MIDCITY?

The promoter named in the RERA registration is INDO INFRA DEVELOPERS PRIVATE LIMITED.

Where is O.R.R. MIDCITY located?

O.R.R. MIDCITY is in BANDARAVIRALA, Abdullapurmet, Rangareddy, Telangana (501505).

When will O.R.R. MIDCITY be completed?

The promoter's proposed date of completion filed with RERA is 06/03/2024. This is the promoter's declaration, not a guarantee.