SURYODAYA ABODE BLOCK C is a residential apartment project in Izzath Nagar, Serilingampally Mandal, Ranga Reddy District, developed by SIPIL INFRA PRIVATE LIMITED. The project is on a registered site extent of 664.91 sq. m and comprises one residential building with 1 Stilt + 5 upper floors. The TG-RERA filing records 10 3BHK apartments. Its TG-RERA registration number is P02400010401, and the project header records proposed completion as 30/11/2026.

More from Sipil Infra Pvt Ltd · 3 projects →

01What we found

Period endedTG-RERA registration ran to 3 Jun 2026 - check its extension on TG-RERA
17documents on file - each fact links to its page
217court cases on this project's land (survey 41, Izzath Nagar)
8items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

8 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Photo from housing.comPhoto from housing.com
▦ View all 2 photos
Izzath Nagar, Serilingampally, Ranga Reddy · geocoded — approximate.

1. Project at a glance

Project identity

FieldRecord
Registered project nameSURYODAYA ABODE BLOCK C RERA record
Project typeResidential apartment project RERA record
Registered portion / phaseBlock C; the RERA certificate identifies the project as “SURYODAYA ABODE BLOCK C.”
TG-RERA registration numberP02400010401 RERA record
Registration validity03/06/2023 to 03/06/2026; the certificate records a three-year validity and no extension. Validity is distinct from the completion deadline and does not establish an occupancy certificate. RERA record
Registered promoterSIPIL INFRA PRIVATE LIMITED, a private limited company RERA record Corporate record
RERA statusThe supplied registration certificate records the project as registered. The registration validity shown has ended; no extension is recorded in the supplied certificate. RERA record

Land and geographic identity

FieldRecord
LocalityIzzath Nagar; the building permit describes the locality as “KHANAMET AND IZZATH NAGAR.” RERA record
Revenue village(s)Izzath Nagar in the project identity record; Khanamet Village in the title, development-agreement and building-permit documents. Both names are retained because they appear in the supplied records. RERA record Land records
Mandal / district / PINSerilingampally / Ranga Reddy / 500084 RERA record
Survey numbers41/8 and 41/9 RERA record Land records
Plot identifiers21, 22 PART, 27 PART AND 28 RERA record
Registered site extentBuilding-permit record: plot area 664.91 sq. m, road-affected area 14.43 sq. m, and net plot area 650.48 sq. m.
Boundaries in RERA land recordEast: 60 feet wide road; west: 25 feet wide road; north: owners’ land, plot nos. 22 part and 27 part; south: neighbours’ land. Land records
Road-affected portion14.43 sq. m; the permit records this portion as to be surrendered to GHMC without compensation.

Development identity

FieldRecord
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC)
Principal building permit1735/GHMC/SLP/2023-BP, approved 03 June 2023; file no. 001584/GHMC/0793/SLP2/2023-BP. Approvals record
Approved built-up area1,547.45 sq. m for residential upper floors, as stated in the building-permit extraction.
Building arrangementOne residential building, identified as Building A in the permit; the RERA project is named Block C. RERA record
Sanctioned floor configuration1 Stilt + 5 upper floors; building height stated as 14.99 in the permit extraction (unit not supplied there).
Stilt area295.82 sq. m
Parking provision recorded in permitThe permit says the approved cellar and stilt areas are for vehicle parking; the extraction records total parking area 309.5 (unit not supplied in that field). It does not provide a count of parking spaces.
Unit countSanctioned dwelling-unit count is not separately stated in the supplied permit extraction. RERA filing records 10 apartments. RERA record RERA unit table
Other layout / LRS identifiersLRS/1590/CIR-12/WZ/GHMC/2008 and LRS/1591/CIR-12/WZ

Offering and status

FieldRecord
RERA-filed configuration3BHK, 10 units RERA unit table RERA unit details
RERA-filed saleable area204.84 sq. m per filed configuration RERA unit table RERA unit details
Portal booking count0 booked, 10 available; the portal count has no supplied as-of date and is indicative only. RERA unit table
Construction stageNo construction-progress percentage or independently verified site-stage information is supplied. RERA record RERA amenities
Completion datesThe RERA Form B declaration states completion by 03 June 2026; the project header records proposed completion as 30/11/2026. RERA record
Occupancy / completion certificateNo occupancy or completion certificate is included in the supplied project documents. The building permit requires an occupancy certificate before occupation. Document index

2. The project story

SURYODAYA ABODE BLOCK C is registered as a residential apartment project on Survey Nos. 41/8 and 41/9, associated in the records with Izzath Nagar and Khanamet Village, Serilingampally Mandal, Ranga Reddy District. The GHMC permit authorizes one residential building with a stilt level and five upper floors. The RERA filing records ten 3BHK apartments; the supplied portal snapshot shows all ten as available, but carries no as-of date. RERA record Land records RERA unit table

The supplied records establish the sanctioned configuration and the promoter’s completion undertaking, but do not establish present construction progress or independently verify site completion. No occupancy or completion certificate is supplied, so the available evidence does not show an occupancy-certified portion. Document index

3. Master plan, architecture & building design

The GHMC building-permit extraction records a 664.91 sq. m plot, 14.43 sq. m road-affected portion and 650.48 sq. m net plot area. It sanctions residential construction of 1 Stilt + 5 upper floors, with 1,547.45 sq. m of residential upper-floor built-up area and a stilt area of 295.82 sq. m. These are permit figures; the supplied record does not provide a separate FSI-counted area.

The permit identifies one building as “A (RESIDENTIAL),” while the registered project name is “SURYODAYA ABODE BLOCK C.” No floor-by-floor apartment arrangement, footprint dimensions, lift or stair details, internal circulation plan, or approved landscaping/open-space plan is present in the supplied extraction. RERA record

4. Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
3BHK10010204.84 sq. m126.2 sq. m median (1,359 sq. ft)38%

Unit count, booking figures and saleable area are from the TG-RERA record; the booking snapshot has no supplied as-of date. Carpet area is software-measured from approved floor-plan drawing geometry, not a RERA-filed carpet-area disclosure, and is flagged for review. RERA unit details Floor plans RERA unit table

The measured plan sample includes a living/dining area, kitchen, bedrooms, toilets, balconies and a wash area. One balcony is labelled 1.50 m wide and has extracted dimensions of 1.45 m × 1.25 m; another is labelled 1.20 m wide. The available drawing extraction does not provide a complete, verified room schedule for every apartment. RERA unit details

5. Parking & vehicle circulation

The building permit states that the approved cellar and stilt areas are to be used exclusively for vehicle parking. It records total parking area as 309.5 (the supplied extraction does not specify the unit) and separately lists a stilt area of 295.82 sq. m. The supplied material does not establish a number of spaces, visitor or accessible parking provision, unit-wise allocation, or exclusive ownership of any bay.

The permit also identifies an 18 mt. road width and requires that vehicles do not ramp onto the road slope; it does not provide enough detail to describe a complete internal vehicle-circulation arrangement.

6. Amenities, recreation & open spaces

Rainwater harvesting
Description / sizePermit lists 5 rainwater-harvesting pits and requires a percolation pit with piped connections.
Evidence sourceGHMC building permit
Declared progress / verified statusRequired / specified; completion not verified.
Garbage house
Description / sizeRequired within the premises; no size stated.
Evidence sourceGHMC building permit
Declared progress / verified statusRequired / specified; completion not verified.
Tot-lot
Description / sizePermit states that the tot-lot is to be fenced; no area or equipment details supplied.
Evidence sourceGHMC building permit
Declared progress / verified statusRequired / specified; completion not verified.
Green strip / tot-lot / park
Description / sizeTG-RERA amenities record marks this item available “YES”; no size or completion evidence supplied.
Evidence sourceTG-RERA amenities record
Declared progress / verified statusDeclared in filing; progress field is 0%, not independent verification. RERA amenities
Kids’ play area / sand pit
Description / sizeListed in third-party vendor data; not established by the supplied GHMC permit extraction.
Evidence sourceVendor listing
Declared progress / verified statusMarketing/vendor claim; delivery not verified. Promoter website
Yoga area; indoor games
Description / sizeListed in third-party vendor data; no size or approved-plan detail supplied.
Evidence sourceVendor listing
Declared progress / verified statusMarketing/vendor claim; delivery not verified. Promoter website

7. Utilities, building services & safety

The TG-RERA amenities record marks water supply, sewerage, storm-water drains, sewage/sullage treatment and disposal, solid-waste management, rainwater harvesting, and an electrical meter room/substation/receiving station as available “YES.” Each listed progress field is 0%; the record does not provide capacities, technical specifications or independent completion verification. RERA amenities

The GHMC permit requires rainwater-harvesting works, space for a transformer, CCTV installation, a dust-mitigation/control plan during construction, and a fire NOC from the Director (EV&DM) before issue of the occupancy certificate. The permit also requires an occupancy certificate before the building is occupied. These are recorded permit conditions, not evidence that the facilities or approvals have been completed or obtained.

No supplied record establishes water source or storage capacity, STP capacity or reuse arrangements, backup-power capacity, lift count/capacity, fire-system details, accessible circulation, security-system installation, or waste-processing capacity. RERA amenities Document index

8. Location, access & connectivity

The project record places the site at Izzath Nagar, Serilingampally Mandal, Ranga Reddy District, PIN 500084; the building permit describes the locality as “KHANAMET AND IZZATH NAGAR” and identifies Khanamet as the village. The RERA land record gives road boundaries of a 60-foot-wide road to the east and a 25-foot-wide road to the west. RERA record Land records

The supplied location data records Financial District (Nanakramguda), 1.2 km as an anchor. A third-party vendor listing names Hitech City Railway Station at 0.6 km; this is vendor-provided connectivity information, not a RERA-filed measurement. Location record Promoter website

9. Developer & development status

The registered promoter is SIPIL INFRA PRIVATE LIMITED, a private limited company, GSTIN 36ABECS3048L1Z2. The promoter’s listed address is D No 7-1-644, Plot No 3, Sunder Nagar Colony, Khanamet, Izzath Nagar, Serilingampally, Ranga Reddy, 500084. The supplied records identify Vishnu Teja Doma as an authorized signatory. Corporate record RERA record

The project is recorded as a landowner–developer arrangement: the RERA-filed development agreement describes a 40% landowner share and 60% developer share in constructed apartments with proportionate undivided land shares. The promoter’s Form B affidavit declares a completion date of 03 June 2026; the project header separately records 30/11/2026 as proposed completion. No construction-progress certification or occupancy certificate is supplied. RERA record Document index

10. Approvals, official records & documents

RecordSupplied evidence
TG-RERA registrationForm C certificate for SURYODAYA ABODE BLOCK C, registration no. P02400010401, valid 03/06/2023–03/06/2026; certificate issue date shown as 23/12/2025.
GHMC building permitPermit no. 1735/GHMC/SLP/2023-BP, file no. 001584/GHMC/0793/SLP2/2023-BP, approved 03 June 2023.
Layout / LRS referencesLRS/1590/CIR-12/WZ/GHMC/2008 and LRS/1591/CIR-12/WZ appear in the building-permit record.
Development agreementRERA-filed development agreement-cum-GPA for the Khanamet Village property, recording the landowner/developer arrangement.
Title reportAdvocate’s title-search report concerning 795.40 sq. yards or 664.95 sq. m in Survey Nos. 41/8 and 41/9, Khanamet Village; the report also notes a GHMC mortgage.
Mortgage documentRegistered mortgage deed without possession in favour of GHMC, identifying 158.67 sq. m of proposed built-up area.
Occupancy / completion certificateNot included in the supplied document set. Document index
Approved-layout lookupHMDA DPMS approved-layout lookup is recorded as unavailable through the public channel; this is not evidence of refusal. HMDA

Other registrations of Suryodaya Abode

Frequently asked questions

Is SURYODAYA ABODE BLOCK C registered with Telangana RERA?

Yes. SURYODAYA ABODE BLOCK C is registered with the Telangana Real Estate Regulatory Authority as P02400010401; the registration status is New Project.

Who is the developer of SURYODAYA ABODE BLOCK C?

The promoter named in the RERA registration is SIPIL INFRA PRIVATE LIMITED.

Where is SURYODAYA ABODE BLOCK C located?

SURYODAYA ABODE BLOCK C is in Izzath Nagar, Serilingampally, Rangareddy, Telangana (500084).

When will SURYODAYA ABODE BLOCK C be completed?

The promoter's proposed date of completion filed with RERA is 30/11/2026. This is the promoter's declaration, not a guarantee.