Sunyuga Aranya is a residential apartment project in Dulapalle, Dundigal Gandimaisamma mandal, Medchal-Malkajgiri district, developed by SUNYUGA INFRA PRIVATE LIMITED. It is on 1,081.95 Sq. Mt. of land and comprises one residential building with 1 Stilt + 5 upper floors and 15 3BHK units. The project is registered under TG-RERA P02200004602, with a proposed completion date of 21/01/2025.

More from Sunyuga Infra Pvt Ltd · 12 projects →

01What we found

Period endedTG-RERA registration ran to 21 Jan 2025 - check its extension on TG-RERA
13documents on file - each fact links to its page
1court case on this project's land (survey 175, Dulapally)
8items to check - 5 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

8 items to check before you pay, 5 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Project photo
▦ View all 2 photos
Dulapally, Dundigal Gandimaisamma, Medchal-Malkajgiri · geocoded — approximate.

1. Project at a glance

Project identity

FieldRecord
Registered project nameSunyuga Aranya
Project typeResidential apartment project
Phase / registered portionPhase not separately identified in the supplied record; the registration is for the project on Survey No. 175/P.
TG-RERA registrationP02200004602
Registration validity13 June 2022 to 21 January 2025; the supplied certificate says validity was not extended. This is registration validity, not the project’s completion undertaking or an occupancy certificate.
Registered promoterSUNYUGA INFRA PRIVATE LIMITED
RERA status in supplied recordRegistered; certificate records validity through 21 January 2025. Current registration status beyond that date is not established here.

RERA record Approvals record

Land and geographic identity

FieldRecord
LocalityDulapalle
Revenue villageDulapally (also recorded as Dulapalle in approval documents)
MandalDundigal Gandimaisamma
DistrictMedchal-Malkajgiri
PIN500100
Project survey number / subdivisionSurvey No. 175/P; the HMDA approval also identifies Plot Nos. 5/Part and 6/Part.
Site extent1,081.95 Sq. Mt.
Total / net land areaRERA filing: total 1,081.95 sq. m and net 1,081.95 sq. m; affected area stated as 0.
BoundariesNorth: Road – 12Ft. Other boundaries are recorded as “NA” in the supplied filing.

RERA filing Land records

Development identity

FieldRecord
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA)
Principal building approval004020/BP/HMDA/0517/MED/2021, approved 31 December 2021; building-permit proceedings 000129/BP/HMDA/MED/2022, dated 21 January 2022.
Approved built-up area2,586.05 Sq.mts.
Building countOne residential building
Sanctioned configuration1 Stilt + 5 upper floors
Parking levels / provisionStilt is designated for vehicle parking; a parking count is not established in the supplied material.
Unit countApproved-plan unit count is not stated in the supplied approval extraction. TG-RERA filing records 15 units.

Approvals record RERA filing RERA unit table

Offering and status

FieldRecord
RERA-filed configuration3BHK
RERA-filed saleable area202.67 sq. m per unit
Booked / available0 booked / 15 available in the portal-derived record; booking figures are indicative because no as-of date is supplied.
Construction stageRERA filing reports 80% completeness; this is a reported figure, not an independent site inspection.
Completion datesRERA header proposed completion: 21/01/2025. The promoter’s Form B declaration states completion by 31/12/27.
Occupancy certificate (OC)No OC is evidenced in the supplied material. The HMDA permission requires an OC before occupation; its approval extraction marks completion certification “false.”

RERA record RERA unit table RERA unit table

2. The project story

Sunyuga Aranya is registered as a residential apartment project on Survey No. 175/P in Dulapally village, Dundigal Gandimaisamma mandal, Medchal-Malkajgiri district. The HMDA building permission is for one residential building comprising a stilt and five upper floors on a site of 1,081.95 Sq. Mt. RERA record Land records

The RERA filing lists 15 3BHK units, with 0 booked and 15 available in the portal-derived snapshot. The filing reports 80% completeness, but the supplied record does not establish this through an independent inspection. No occupancy certificate is supplied; the permission requires one before occupation. RERA unit table RERA unit table

3. Master plan, architecture & building design

The HMDA approval describes one residential building, 1 Stilt + 5 upper floors, with an approved built-up area of 2,586.05 Sq.mts. The supplied approval extraction does not provide a floor-by-floor dwelling schedule, footprint, flats per floor, building height, lift or staircase details, or a readable site layout. The stilt is required to be used exclusively for vehicle parking, without partition walls or rolling shutters; construction and parking are not permitted in setback areas.

The RERA filing records site area of 1,081.95 sq. m, with the same total and net area and no affected area reported. The supplied material does not establish a separate FSI-counted area, gross built-up area, or common-area distribution; these should not be inferred from the approved built-up-area figure. RERA filing

4. Homes, configurations & floor plans

The RERA filing lists 15 3BHK units. The supplied filing-derived unit record gives a saleable area of 202.67 sq. m per unit. The floor-plan drawing measurement is software-derived and is not a RERA disclosure; it reports a 3BHK carpet-area measurement of 149.7 sq. m (1,612 sq. ft.) from one measured design. The measurement record also reports 26% loading. These drawing-based figures require review against the drawing and are not a substitute for the registered agreement or area definition. RERA unit table RERA unit table Floor plans RERA unit details

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
3BHK15015202.67 sq. m149.7 sq. m (software-measured; 1,612 sq. ft.)26%

The measured drawing lists three bedrooms, living/dining, drawing-room areas, kitchen, toilets and a balcony for the measured 3BHK design. The supplied drawing data does not establish a complete room schedule for all units. Carpet area, balcony area and a unit’s share of common areas are distinct; saleable area should not be treated as carpet area. RERA unit details

5. Parking & vehicle circulation

The HMDA permission designates the stilt exclusively for vehicle parking and prohibits parking or construction in setback areas. The supplied documents do not establish the number of parking spaces, visitor or accessible parking, a parking allocation for individual units, or the arrangement of ramps, internal driveways and pedestrian routes. A parking space shown or designated in a plan does not by itself establish exclusive ownership or an allotment to a particular unit.

6. Amenities, recreation & open spaces

The RERA amenity record reports progress percentages for listed facilities; these figures are filing data, not independent verification of completion. No specific clubhouse, sports or recreation facility is established in the supplied project-specific records.

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Green Strip/TOT LOT/ParkSize not statedRERA amenity record0%; not independently verified
Community BuildingsSize or description not statedRERA amenity record0%; not independently verified
Aggregate recreational open spaceArea not statedRERA amenity record0%; not independently verified

RERA amenities

7. Utilities, building services & safety

The RERA amenity record marks water supply, sewerage and rainwater harvesting as available, each at 50% progress; it marks the electrical meter room/sub-station/receiving station as available at 50%. These are declared progress entries, not confirmation of operational service. It records storm-water drains, street lighting, treatment and disposal of sewage and sullage, energy management and fire protection at 0%; solid-waste management is marked available at 0%. RERA amenities

The HMDA approval requires rainwater-harvesting structures and an ETP, and lists a transformer and garbage house among project utilities. Its conditions also require CCTV cameras, a minimum of four fire extinguishers per floor, and an occupancy certificate before occupation. The supplied material does not establish the installed capacity, commissioning or independent inspection of these systems.

8. Location, access & connectivity

The registered location is Dulapalle, Dundigal Gandimaisamma mandal, Medchal-Malkajgiri district, PIN 500100. The supplied location record gives a geocode of 17.5467126, 78.4668466 and reports the nearest sampled Outer Ring Road interchange at approximately 9.4 km. The HMDA approval identifies road widths of 4.5mts., 3.0mts. and 1.5mts. in its extracted parameters; it separately requires the indicated minimum-width approach road to be developed and maintained as a black-topped road before occupancy-certificate release. RERA record Location record

9. Developer & development status

The registered promoter is SUNYUGA INFRA PRIVATE LIMITED, a private limited company. Its supplied corporate identifier is GSTIN 36AAZCS9049M1Z4. The RERA record lists DADIMI SUNITHA as authorized signatory and DADIMI VISHWANATH REDDY as director. Corporate record Parties record

The promoter’s Form B declaration states a completion undertaking of 31/12/27. The project header separately gives 21/01/2025 as the proposed completion date. The RERA registration certificate records validity ending 21/01/2025 and no extension in the supplied certificate. These dates describe different recorded items—completion undertaking, proposed completion and registration validity—and should not be read as evidence of an OC or project completion. RERA record

10. Approvals, official records & documents

RecordSupplied evidence
TG-RERA registrationForm C records P02200004602 for Sunyuga Aranya, under section 5; validity stated as 13/06/2022 to 21/01/2025.
HMDA technical approvalBuilding approval 004020/BP/HMDA/0517/MED/2021, dated 31 December 2021, for a residential building of 1 Stilt + 5 upper floors.
HMDA building-permit orderProceedings 000129/BP/HMDA/MED/2022, dated 21 January 2022, concerning Survey No. 175/P and site extent 1,081.95 Sq. Mt.
Promoter declarationForm B filed for SUNYUGA INFRA PVT. LTD.; includes the promoter’s completion undertaking and declarations concerning title, encumbrances and the separate account.
Approved plan drawing recordFloor-plan drawing document 218323 is cited for software-measured unit geometry; the supplied record does not include a complete extracted plan schedule.
Occupancy / completion certificateNo OC or completion certificate is supplied. The HMDA approval requires an OC before occupation.

Frequently asked questions

Is Sunyuga Aranya registered with Telangana RERA?

Yes. Sunyuga Aranya is registered with the Telangana Real Estate Regulatory Authority as P02200004602; the registration status is New Project.

Who is the developer of Sunyuga Aranya?

The promoter named in the RERA registration is SUNYUGA INFRA PRIVATE LIMITED.

Where is Sunyuga Aranya located?

Sunyuga Aranya is in Dulapalle, Dulapally, Dundigal Gandimaisamma, Medchal-Malkajgiri, Telangana (500100).

When will Sunyuga Aranya be completed?

The promoter's proposed date of completion filed with RERA is 21/01/2025. This is the promoter's declaration, not a guarantee.