Sri Venkateswara Realestate
JAKKULA VENKATESHWAR AND OTHERS · Nizamabad · RERA P03100010299
SRI VENKATESWARA REALESTATE is a residential plotted layout in KANTESHWAR, NIZAMABAD EAST (NEW), Nizamabad district, Telangana. The registered promoter is JAKKULA VENKATESHWAR AND OTHERS. The project covers 90,869.91 sq. m and comprises 283 plots; plot sizes are 97.46–463.16 sq. m. It is registered with TG-RERA as P03100010299, valid 26 April 2025 to 26 April 2027, with a proposed completion date of 26 August 2027.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
12 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered project name | SRI VENKATESWARA REALESTATE RERA record |
| Project type | Plotted development / residential plotted layout RERA record |
| Phase or registered portion | Not separately identified; the registration concerns the listed survey land |
| TG-RERA registration | P03100010299; valid 26 April 2025 to 26 April 2027 (two years, unless extended) RERA record |
| Registered promoter | JAKKULA VENKATESHWAR AND OTHERS RERA record |
| RERA status | Registered project; registration was captured on 10 September 2026 RERA record Approvals record |
| Legal-entity type | “Others” in the RERA filing; a more specific legal-entity form is not established by the supplied record RERA filing Corporate record |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality / revenue village | Registered location: KANTESHWAR, Nizamabad. The layout approval and filed land records describe the site as Kalur Revenue Village / Kalur Village Shivar. The records use both village labels; the precise revenue-village identity should be checked against the land records. RERA record |
| Mandal | RERA filing: NIZAMABAD EAST (NEW). Layout-plan document: NIZAMABAD RURAL MANDAL; tentative-layout approval: Nizamabad Mandal. RERA record |
| District / PIN | Nizamabad, Telangana; 503003 in the project identity and registration certificate RERA record |
| All project survey numbers and subdivisions | 202, 203, 204, 205/A, 205/AA/2, 205/E, 208, 209, 210, 211, 217, 218/AA/1/1/1, 218/AA/1/1/2, 218/AA/1/2, 218/AA/2 RERA record |
| Registered site extent | 90,869.91 sq. m in the RERA land details and layout-plan details RERA filing |
| Net layout area | 90,817.59 sq. m in the layout-plan details; the drawing’s land-use table separately totals 90,817.28 sq. m Layout record |
| Boundaries | East, west, north and south are each recorded as “OTHERS LAND”; adjoining land is not further identified in the supplied project record RERA filing |
| Road widening / FTL / nala area in RERA land details | 0 sq. m declared as affected area RERA filing |
Development identity
| Item | Project record |
|---|---|
| Sanctioning authority | Nizamabad Municipality / Municipal Corporation for tentative layout approval 0114/LO/3072/2025, dated 26 April 2025. The filed layout-plan details also name TS-DTCP, file G1/1001/2022-23, with delegation to Nizamabad Municipal Corporation. Approvals record |
| Principal approval | Tentative residential layout approval 0114/LO/3072/2025, dated 26 April 2025 Approvals record |
| Approved plot count | 283 plots in the tentative-layout approval and filed layout-plan details |
| Built-up area | 0.00 sq. m proposed, both excluding and including parking, in the filed layout-plan details; the RERA land record separately states approved built-up area 54,033.33 sq. m. These are distinct recorded fields; the supplied evidence does not explain their relationship. RERA filing |
| Buildings, floors and parking levels | No tower/building count, floor configuration or parking level is established in the supplied layout record. The project is a plotted layout, not an evidenced apartment-building scheme. Floor plans |
Offering and status
| Item | Project record |
|---|---|
| Unit type / count | Plots; 283 plots shown in the layout approval |
| Plot-size range | Software-read from the approved layout drawing: 97.46–463.16 sq. m (approximately 116.6–553.9 sq. yd as supplied); verify against the drawing Layout record |
| Booked / available plots | Not established in the supplied RERA inventory data RERA record Layout record |
| Construction / development stage | RERA record identifies a new project. The submitted materials do not establish independently verified on-site progress; amenity and infrastructure progress is recorded as 0% in the supplied amenity data. RERA record RERA amenities |
| Completion dates | Form B undertaking: 26 April 2027. Project header proposed completion: 26 August 2027. The tentative-layout approval requires infrastructure and amenities within two years of approval, 26 April 2027, subject to the stated possible extension. RERA record |
| Registration validity | 26 April 2025–26 April 2027; this is the registration period, not a statement that the project is complete |
| OC / completion certificate | No occupancy or completion certificate is recorded in the supplied evidence; for a plotted layout, the record does not establish an OC scope by plot or phase Document index Approvals record |
2. The project story
SRI VENKATESWARA REALESTATE is registered with TG-RERA as a plotted development in Nizamabad, comprising land listed under the 15 survey numbers and subdivisions above. The project’s primary physical plan is a 283-plot tentative residential layout, approved under LP No. 0114/LO/3072/2025 on 26 April 2025. The registration and approval details are set out above. RERA record
The filed layout drawing allocates land to plots, internal roads, open space/park, social infrastructure, utilities and a buffer zone. It shows no proposed built-up area in its layout-plan details, so the available evidence describes plots and site infrastructure rather than a defined programme of apartment buildings or homes. Layout record
The promoter’s Form B undertaking states completion by 26 April 2027; the project header separately lists 26 August 2027 as the proposed completion date. Neither the filed record nor the supplied amenity progress data independently verifies construction progress. The tentative-layout approval requires infrastructure and amenities within two years of its approval date and states that the municipality may extend that period by one year on specific request and payment of the stated fee. RERA record RERA amenities
3. Master plan, architecture & building design
This is a plotted layout rather than a building scheme in the supplied drawings. The filed layout-plan details state a total site area of 90,869.91 sq. m, a net layout area of 90,817.59 sq. m, and 52.32 sq. m of leftover owners’ land. Its land-use table reports 90,817.28 sq. m as total net layout area.
The drawing’s land-use table allocates the 90,817.28 sq. m base as follows:
| Layout use | Area | Share shown |
|---|---|---|
| Plotted area | 54,033.33 sq. m | 59.50% |
| Roads | 24,097.06 sq. m | 26.53% |
| Organized open space / park | 8,193.71 sq. m | 9.02% |
| Social infrastructure | 2,436.05 sq. m | 2.68% |
| Utility area | 911.96 sq. m | 1.00% |
| Buffer zone | 1,145.17 sq. m | 1.26% |
| Amenity area | 0.00 sq. m | 0.00% |
| Common parking area | 0.00 sq. m | 0.00% |
Layout record
The layout-plan details describe 283 individual subplots and identify internal roads of 9.14 m and 18.29 m; the tentative approval specifies roads 18 m and above. The layout details also record road labels for existing and proposed 30.48 m roads and a 12.19 m BT-road formation.
No tower arrangement, floor configuration, building footprint, FSI-counted area, apartment floor plan or building-height information is established by the supplied evidence. The drawings are layout records, not evidence of constructed buildings. Floor plans
4. Homes, configurations & floor plans
The RERA-filed offering is a plotted layout: 283 plots are stated in the tentative-layout approval and layout-plan details. A plot-by-plot schedule was read from the drawing by software; its plot sizes should be verified against the drawing. Layout record
| Plot-size band | Number of plots |
|---|---|
| 100–150 sq. yd | 4 |
| 150–200 sq. yd | 73 |
| 200–250 sq. yd | 151 |
| 250–300 sq. yd | 6 |
| 300–400 sq. yd | 35 |
| 400–500 sq. yd | 13 |
| 500–1000 sq. yd | 1 |
The software-read smallest plot is 97.46 sq. m (116.6 sq. yd), the median is 168.47 sq. m (201.5 sq. yd), and the largest is 463.16 sq. m (553.9 sq. yd). These are drawing-derived measurements, not RERA-filed saleable-area figures. Layout record
RERA booked/available inventory and plot-wise RERA saleable areas are not provided in the supplied data. The floor-plan record contains two layout sheets and no flat plans or measured carpet areas; apartment-style carpet-area and loading comparisons therefore do not apply on the evidence supplied. Floor plans RERA unit table
5. Parking & vehicle circulation
The filed layout-plan details show 0.00 sq. m of common parking area. The tentative-layout approval identifies 45 plots mortgaged to the Municipality; the approval’s mortgage-area figure is 0 Acer 86.06 Gts / 10,414 sq. yd, while the layout-plan details state 8,124.75 sq. m and 15% for land area to mortgage. These figures are reproduced as recorded, without treating them as a parking provision.
A vendor listing mentions “Open Parking,” but the supplied approval/layout evidence does not establish a sanctioned parking count, visitor or accessible parking, parking allocation by plot, or a dedicated parking facility. Promoter website
The drawing identifies internal roads, including 9.14 m and 18.29 m internal roads; the tentative approval states roads of 18 mts and above and requires roads to remain open for access to neighbouring sites. No separate vehicle-entry/exit design or pedestrian-separation detail is established in the supplied evidence. See Master plan, architecture & building design above for the other recorded road details.
6. Amenities, recreation & open spaces
The layout and approval records identify open space, social-infrastructure and utility land and list planned site works. The amenity data reports 0% progress for the listed facilities; no independent verification of completion is supplied. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Park / organized open space | 8,193.71 sq. m; 9.02% in the layout-plan land-use table | Listed as available in the amenity data, but progress is 0%; not independently verified complete RERA amenities | |
| Social infrastructure land | 2,436.05 sq. m; 2.68% | Land reservation shown; no delivered facility or progress verified | |
| Tot-lot | Named in layout-plan details; no size supplied | No completion evidence supplied | |
| Internal roads and footpaths | Layout roads include 9.14 m and 18.29 m internal roads; no footpath dimensions supplied | Amenity data lists internal roads/footpaths; progress 0%, not independently verified complete RERA amenities | |
| Street lighting | Listed as a layout facility; no quantity or specification supplied | Listed in amenity data; progress 0% RERA amenities | |
| Avenue plantation | Required/listed in the tentative-layout infrastructure provisions; no area or count supplied | Completion not established | |
| Community buildings / indoor facilities | No defined clubhouse or indoor facility is identified; the layout reserves social-infrastructure land | RERA amenities | Not established as built or delivered |
7. Utilities, building services & safety
The tentative-layout approval lists infrastructure and amenity works including a water reservoir, septic tank, sewerage treatment plant, electric transformer, solid-waste management, storm-water drains, underground drainage lines, internal water-supply pipelines, overhead tank, street lights, avenue plantation, park development and rainwater-harvesting pits. These are approval-recorded works, not evidence that they have been installed or commissioned.
The layout-plan details also name a septic tank and rainwater harvesting / percolation pits, and record a 1,145.17 sq. m buffer-zone area. The supplied records do not specify water source or storage capacity, STP capacity or reuse arrangements, electrical capacity or backup, waste-processing capacity, or completed-service status.
The amenity dataset lists sewerage, storm-water drainage, sewage treatment/disposal, solid-waste management, water conservation/rainwater harvesting, energy management, fire protection, and electrical meter room/substation/receiving station; progress is recorded as 0% for the listed entries. No fire clearance, commissioning evidence, accessibility design or independently verified service completion is supplied here. RERA amenities
8. Location, access & connectivity
The project’s TG-RERA identity places it at KANTESHWAR, Nizamabad, Telangana, PIN 503003. The tentative-layout approval and layout drawing describe the land as Kalur Revenue Village / Kalur Village Shivar, in Nizamabad district, while the mandal descriptions differ across the supplied records. The precise revenue-village and mandal mapping should be confirmed using the registered land records. See Land and geographic identity above for the recorded location and mandal descriptions. RERA record
The layout documents identify internal roads and refer to existing/proposed 30.48 m roads and a 12.19 m BT-road formation. The approval requires the roads to remain open for access to neighbouring sites. No project-specific public-transport information or verified nearby landmark distances are supplied.
The supplied location record contains a geocode resolving to a Jeedimetla/Greater Hyderabad address, which is not a verified project-location description and is not used here. It also reports an approximate Outer Ring Road interchange distance of 8.5 km; the available data does not establish that this measurement is for the registered project site. Location record
9. Developer & development status
The registered promoter is JAKKULA VENKATESHWAR AND OTHERS, with the RERA filing describing the organization type as “Others.” The project record names Jakkula Venkateshwar as an authorized signatory and identifies 26 others in the tentative-layout applicant description. A specific incorporated-entity type, corporate registration number, registered office or official project contact details are not established in the supplied material. RERA record RERA filing
The Form B affidavit dated 25 June 2025 declares project completion by 26 April 2027. The project header records a proposed completion date of 26 August 2027. The supplied records do not provide independently verified construction progress; the amenity data records 0% progress for listed facilities. See Offering and status above for the registration validity and related completion-date information. RERA record RERA amenities
10. Approvals, official records & documents
| Record | What the supplied evidence establishes |
|---|---|
| TG-RERA registration certificate | Form C certificate for SRI VENKATESWARA REALESTATE, registration P03100010299, valid 26 April 2025–26 April 2027; includes registration conditions concerning sale agreements, conveyance, separate-account deposits and quarterly updates |
| Tentative layout approval | Nizamabad Municipality / Municipal Corporation approval 0114/LO/3072/2025, dated 26 April 2025, for a tentative residential plotted layout stating 283 plots; it expressly says tentative approval is not proof of title |
| Filed layout-plan details | TS-DTCP file G1/1001/2022-23; layout-plan details list the site, survey numbers, 283 plots, land-use allocation, roads and buffer-zone details |
| Form B affidavit | Promoter declaration dated 25 June 2025, including a completion undertaking of 26 April 2027 |
| Sale-agreement extract | Standard agreement extract containing plot/apartment conveyance and common-area provisions; it does not identify a specific plot or allottee |
| Completion / occupancy records | No completion certificate or occupancy certificate is evidenced in the supplied documents Document index Approvals record |
1. Project at a glance
Project identity
Registered project name: SRI VENKATESWARA REALESTATE
Project type: Plotted development / residential plotted layout
Phase or registered portion: Not separately identified; the registration concerns the listed survey land
TG-RERA registration: P03100010299; valid 26 April 2025 to 26 April 2027 (two years, unless extended)
Registered promoter: JAKKULA VENKATESHWAR AND OTHERS
RERA status: Registered project; registration was captured on 10 September 2026
Legal-entity type: “Others” in the RERA filing; a more specific legal-entity form is not established by the supplied record
Land and geographic identity
Locality / revenue village: Registered location: KANTESHWAR, Nizamabad. The layout approval and filed land records describe the site as Kalur Revenue Village / Kalur Village Shivar. The records use both village labels; the precise revenue-village identity should be checked against the land records.
Mandal: RERA filing: NIZAMABAD EAST (NEW). Layout-plan document: NIZAMABAD RURAL MANDAL; tentative-layout approval: Nizamabad Mandal.
District / PIN: Nizamabad, Telangana; 503003 in the project identity and registration certificate
All project survey numbers and subdivisions: 202, 203, 204, 205/A, 205/AA/2, 205/E, 208, 209, 210, 211, 217, 218/AA/1/1/1, 218/AA/1/1/2, 218/AA/1/2, 218/AA/2
Registered site extent: 90,869.91 sq. m in the RERA land details and layout-plan details
Net layout area: 90,817.59 sq. m in the layout-plan details; the drawing’s land-use table separately totals 90,817.28 sq. m
Boundaries: East, west, north and south are each recorded as “OTHERS LAND”; adjoining land is not further identified in the supplied project record
Road widening / FTL / nala area in RERA land details: 0 sq. m declared as affected area
Development identity
Sanctioning authority: Nizamabad Municipality / Municipal Corporation for tentative layout approval 0114/LO/3072/2025, dated 26 April 2025. The filed layout-plan details also name TS-DTCP, file G1/1001/2022-23, with delegation to Nizamabad Municipal Corporation.
Principal approval: Tentative residential layout approval 0114/LO/3072/2025, dated 26 April 2025
Approved plot count: 283 plots in the tentative-layout approval and filed layout-plan details
Built-up area: 0.00 sq. m proposed, both excluding and including parking, in the filed layout-plan details; the RERA land record separately states approved built-up area 54,033.33 sq. m. These are distinct recorded fields; the supplied evidence does not explain their relationship.
Buildings, floors and parking levels: No tower/building count, floor configuration or parking level is established in the supplied layout record. The project is a plotted layout, not an evidenced apartment-building scheme.
Offering and status
Unit type / count: Plots; 283 plots shown in the layout approval
Plot-size range: Software-read from the approved layout drawing: 97.46–463.16 sq. m (approximately 116.6–553.9 sq. yd as supplied); verify against the drawing
Booked / available plots: Not established in the supplied RERA inventory data
Construction / development stage: RERA record identifies a new project. The submitted materials do not establish independently verified on-site progress; amenity and infrastructure progress is recorded as 0% in the supplied amenity data.
Completion dates: Form B undertaking: 26 April 2027. Project header proposed completion: 26 August 2027. The tentative-layout approval requires infrastructure and amenities within two years of approval, 26 April 2027, subject to the stated possible extension.
Registration validity: 26 April 2025–26 April 2027; this is the registration period, not a statement that the project is complete
OC / completion certificate: No occupancy or completion certificate is recorded in the supplied evidence; for a plotted layout, the record does not establish an OC scope by plot or phase
2. The project story
SRI VENKATESWARA REALESTATE is registered with TG-RERA as a plotted development in Nizamabad, comprising land listed under the 15 survey numbers and subdivisions above. The project’s primary physical plan is a 283-plot tentative residential layout, approved under LP No. 0114/LO/3072/2025 on 26 April 2025. The registration and approval details are set out above.
The filed layout drawing allocates land to plots, internal roads, open space/park, social infrastructure, utilities and a buffer zone. It shows no proposed built-up area in its layout-plan details, so the available evidence describes plots and site infrastructure rather than a defined programme of apartment buildings or homes.
The promoter’s Form B undertaking states completion by 26 April 2027; the project header separately lists 26 August 2027 as the proposed completion date. Neither the filed record nor the supplied amenity progress data independently verifies construction progress. The tentative-layout approval requires infrastructure and amenities within two years of its approval date and states that the municipality may extend that period by one year on specific request and payment of the stated fee.
3. Master plan, architecture & building design
This is a plotted layout rather than a building scheme in the supplied drawings. The filed layout-plan details state a total site area of 90,869.91 sq. m, a net layout area of 90,817.59 sq. m, and 52.32 sq. m of leftover owners’ land. Its land-use table reports 90,817.28 sq. m as total net layout area.
The drawing’s land-use table allocates the 90,817.28 sq. m base as follows:
| Layout use | Area | Share shown |
|---|---|---|
| Plotted area | 54,033.33 sq. m | 59.50% |
| Roads | 24,097.06 sq. m | 26.53% |
| Organized open space / park | 8,193.71 sq. m | 9.02% |
| Social infrastructure | 2,436.05 sq. m | 2.68% |
| Utility area | 911.96 sq. m | 1.00% |
| Buffer zone | 1,145.17 sq. m | 1.26% |
| Amenity area | 0.00 sq. m | 0.00% |
| Common parking area | 0.00 sq. m | 0.00% |
The layout-plan details describe 283 individual subplots and identify internal roads of 9.14 m and 18.29 m; the tentative approval specifies roads 18 m and above. The layout details also record road labels for existing and proposed 30.48 m roads and a 12.19 m BT-road formation.
No tower arrangement, floor configuration, building footprint, FSI-counted area, apartment floor plan or building-height information is established by the supplied evidence. The drawings are layout records, not evidence of constructed buildings.
4. Homes, configurations & floor plans
The RERA-filed offering is a plotted layout: 283 plots are stated in the tentative-layout approval and layout-plan details. A plot-by-plot schedule was read from the drawing by software; its plot sizes should be verified against the drawing.
100–150 sq. yd: 4
150–200 sq. yd: 73
200–250 sq. yd: 151
250–300 sq. yd: 6
300–400 sq. yd: 35
400–500 sq. yd: 13
500–1000 sq. yd: 1
The software-read smallest plot is 97.46 sq. m (116.6 sq. yd), the median is 168.47 sq. m (201.5 sq. yd), and the largest is 463.16 sq. m (553.9 sq. yd). These are drawing-derived measurements, not RERA-filed saleable-area figures.
RERA booked/available inventory and plot-wise RERA saleable areas are not provided in the supplied data. The floor-plan record contains two layout sheets and no flat plans or measured carpet areas; apartment-style carpet-area and loading comparisons therefore do not apply on the evidence supplied.
5. Parking & vehicle circulation
The filed layout-plan details show 0.00 sq. m of common parking area. The tentative-layout approval identifies 45 plots mortgaged to the Municipality; the approval’s mortgage-area figure is 0 Acer 86.06 Gts / 10,414 sq. yd, while the layout-plan details state 8,124.75 sq. m and 15% for land area to mortgage. These figures are reproduced as recorded, without treating them as a parking provision.
A vendor listing mentions “Open Parking,” but the supplied approval/layout evidence does not establish a sanctioned parking count, visitor or accessible parking, parking allocation by plot, or a dedicated parking facility.
The drawing identifies internal roads, including 9.14 m and 18.29 m internal roads; the tentative approval states roads of 18 mts and above and requires roads to remain open for access to neighbouring sites. No separate vehicle-entry/exit design or pedestrian-separation detail is established in the supplied evidence. See Master plan, architecture & building design above for the other recorded road details.
6. Amenities, recreation & open spaces
The layout and approval records identify open space, social-infrastructure and utility land and list planned site works. The amenity data reports 0% progress for the listed facilities; no independent verification of completion is supplied.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Park / organized open space | 8,193.71 sq. m; 9.02% in the layout-plan land-use table | Listed as available in the amenity data, but progress is 0%; not independently verified complete | |
| Social infrastructure land | 2,436.05 sq. m; 2.68% | Land reservation shown; no delivered facility or progress verified | |
| Tot-lot | Named in layout-plan details; no size supplied | No completion evidence supplied | |
| Internal roads and footpaths | Layout roads include 9.14 m and 18.29 m internal roads; no footpath dimensions supplied | Amenity data lists internal roads/footpaths; progress 0%, not independently verified complete | |
| Street lighting | Listed as a layout facility; no quantity or specification supplied | Listed in amenity data; progress 0% | |
| Avenue plantation | Required/listed in the tentative-layout infrastructure provisions; no area or count supplied | Completion not established | |
| Community buildings / indoor facilities | No defined clubhouse or indoor facility is identified; the layout reserves social-infrastructure land | Not established as built or delivered |
7. Utilities, building services & safety
The tentative-layout approval lists infrastructure and amenity works including a water reservoir, septic tank, sewerage treatment plant, electric transformer, solid-waste management, storm-water drains, underground drainage lines, internal water-supply pipelines, overhead tank, street lights, avenue plantation, park development and rainwater-harvesting pits. These are approval-recorded works, not evidence that they have been installed or commissioned.
The layout-plan details also name a septic tank and rainwater harvesting / percolation pits, and record a 1,145.17 sq. m buffer-zone area. The supplied records do not specify water source or storage capacity, STP capacity or reuse arrangements, electrical capacity or backup, waste-processing capacity, or completed-service status.
The amenity dataset lists sewerage, storm-water drainage, sewage treatment/disposal, solid-waste management, water conservation/rainwater harvesting, energy management, fire protection, and electrical meter room/substation/receiving station; progress is recorded as 0% for the listed entries. No fire clearance, commissioning evidence, accessibility design or independently verified service completion is supplied here.
8. Location, access & connectivity
The project’s TG-RERA identity places it at KANTESHWAR, Nizamabad, Telangana, PIN 503003. The tentative-layout approval and layout drawing describe the land as Kalur Revenue Village / Kalur Village Shivar, in Nizamabad district, while the mandal descriptions differ across the supplied records. The precise revenue-village and mandal mapping should be confirmed using the registered land records. See Land and geographic identity above for the recorded location and mandal descriptions.
The layout documents identify internal roads and refer to existing/proposed 30.48 m roads and a 12.19 m BT-road formation. The approval requires the roads to remain open for access to neighbouring sites. No project-specific public-transport information or verified nearby landmark distances are supplied.
The supplied location record contains a geocode resolving to a Jeedimetla/Greater Hyderabad address, which is not a verified project-location description and is not used here. It also reports an approximate Outer Ring Road interchange distance of 8.5 km; the available data does not establish that this measurement is for the registered project site.
9. Developer & development status
The registered promoter is JAKKULA VENKATESHWAR AND OTHERS, with the RERA filing describing the organization type as “Others.” The project record names Jakkula Venkateshwar as an authorized signatory and identifies 26 others in the tentative-layout applicant description. A specific incorporated-entity type, corporate registration number, registered office or official project contact details are not established in the supplied material.
The Form B affidavit dated 25 June 2025 declares project completion by 26 April 2027. The project header records a proposed completion date of 26 August 2027. The supplied records do not provide independently verified construction progress; the amenity data records 0% progress for listed facilities. See Offering and status above for the registration validity and related completion-date information.
10. Approvals, official records & documents
TG-RERA registration certificate: Form C certificate for SRI VENKATESWARA REALESTATE, registration P03100010299, valid 26 April 2025–26 April 2027; includes registration conditions concerning sale agreements, conveyance, separate-account deposits and quarterly updates
Tentative layout approval: Nizamabad Municipality / Municipal Corporation approval 0114/LO/3072/2025, dated 26 April 2025, for a tentative residential plotted layout stating 283 plots; it expressly says tentative approval is not proof of title
Filed layout-plan details: TS-DTCP file G1/1001/2022-23; layout-plan details list the site, survey numbers, 283 plots, land-use allocation, roads and buffer-zone details
Form B affidavit: Promoter declaration dated 25 June 2025, including a completion undertaking of 26 April 2027
Sale-agreement extract: Standard agreement extract containing plot/apartment conveyance and common-area provisions; it does not identify a specific plot or allottee
Completion / occupancy records: No completion certificate or occupancy certificate is evidenced in the supplied documents
Frequently asked questions
Is SRI VENKATESWARA REALESTATE registered with Telangana RERA?
Yes. SRI VENKATESWARA REALESTATE is registered with the Telangana Real Estate Regulatory Authority as P03100010299; the registration status is New Project.
Who is the developer of SRI VENKATESWARA REALESTATE?
The promoter named in the RERA registration is JAKKULA VENKATESHWAR AND OTHERS.
Where is SRI VENKATESWARA REALESTATE located?
SRI VENKATESWARA REALESTATE is in NIZAMABAD, KANTESHWAR, NIZAMABAD EAST (NEW), Telangana (503003).
When will SRI VENKATESWARA REALESTATE be completed?
The promoter's proposed date of completion filed with RERA is 26/08/2027. This is the promoter's declaration, not a guarantee.