SWASTHIKA is a plotted development in Ibrahimpatnam, Ibrahimpatnam Mandal, Ranga Reddy District, developed by the registered promoter CHEGURI BHARATH KUMAR AND OTHERS. The project has a total site area of 13,772.7 Sq.Mtrs and 57 plots, with drawing-derived plot sizes of 122.16–247.22 sq.m; no tower or floor configuration is stated. It is registered with TG-RERA as P02400009762, and the project header states a proposed completion date of 12/07/2028.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
7 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered project name | SWASTHIKA |
| Project type | Plotted development / open plotted layout RERA record |
| Phase or registered portion | No separate phase name or phase number is stated; the registration is for the project identified as SWASTHIKA RERA record |
| TG-RERA registration number | P02400009762 RERA record |
| Registration validity | Form C states validity from 13/03/2025 to 12/03/2028, unless extended by the Authority |
| Registered promoter | CHEGURI BHARATH KUMAR AND OTHERS RERA record |
| RERA status | New project; registration recorded as effective from 13 March 2025 RERA record Approvals record |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality | Ibrahimpatnam RERA record |
| Revenue village | Ramdaspalli (also written “Ramdaspalle” in the filed layout documents) RERA record |
| Mandal | Ibrahimpatnam RERA record |
| District | Ranga Reddy RERA record |
| PIN | 501510 in the project identity and registration record RERA record |
| Project survey number(s) and subdivision(s) | Sy. No. 69/PART; no further subdivision is identified in the filed project identity RERA record |
| Site extent | Total site area 13,772.7 Sq.Mtrs; net site area 13,537.37 Sq.Mtrs; master plan road-affected area 235.33 Sq.Mtrs |
| Boundaries | East: OPEN LAND; West: EXISTING HOUSES; North: 9 MT WIDE EXISTING ROAD; South: PROPOSED 100 WIDE MDP ROAD RERA filing |
Development identity
| Item | Project record |
|---|---|
| Sanctioning / approval authority | HMDA layout-permission record; the draft layout letter identifies Adibatla Municipality / Municipal Corporation in the approval authority fields Approvals record |
| Principal layout approval number and date | 013750/LO/HMDA/3740/SMD/2024, dated 13 March, 2025; the document is identified as a DRAFT LAYOUT LETTER |
| Approved built-up area | 0.00 proposed built-up area, both excluding and including parking, in the layout-plan details; this is a plotted layout, not a supplied building-plan schedule |
| Plot count | 57 plots in the draft layout and layout drawing |
| Building, floor and parking configuration | No building count, floor configuration, parking levels or building commencement certificate details are supplied for this plotted layout |
Offering and status
| Item | Project record |
|---|---|
| Offering | Plots; the filed layout documents state 57 plots |
| Plot sizes | Software-read from the approved layout drawing: 122.16–247.22 sq.m (smallest to largest); median 139.35 sq.m. Drawing-derived sizes should be checked against the drawing Layout record |
| Booked / available | Not disclosed in the supplied evidence RERA record |
| Construction stage | No independently verified site-progress measurement is supplied. The filed layout permission requires layout development works; progress percentages in the amenities record are 0 RERA amenities |
| Completion dates | The Form-B promoter declaration states 12/03/2028; the project header and Form C record 12/07/2028 as the proposed completion date / registration end date, respectively RERA record |
| Occupancy / completion certificate | No occupancy or completion certificate is recorded in the supplied evidence. The supplied approval is a draft layout permission, and a final layout release is described as conditional |
2. The project story
SWASTHIKA is registered with TG-RERA as a plotted-development project on Sy. No. 69/PART, in Ramdaspalli village, Ibrahimpatnam Mandal, Ranga Reddy District. Its filed layout drawing shows a 57-plot arrangement with internal roads, a park/open-space parcel, social-infrastructure land and a utilities area. The proposed use shown in the project record is plotted land rather than a supplied apartment or building scheme. RERA record
The approval record describes draft layout permission and sets out infrastructure and handover conditions that must be met before release of the final layout. It identifies nine mortgaged plots; the document states that these plots are not permitted for sale while mortgaged. The evidence pack does not establish that the required development works are complete or that the final layout has been released.
3. Master plan, architecture & building design
This is a plotted layout, so the supplied design evidence concerns plot arrangement and land use rather than buildings, apartment plans or floor configurations. The filed layout record states a total site area of 13,772.7 Sq.Mtrs, a net site area of 13,537.37 Sq.Mtrs, and 57 individual plots. The layout drawing’s area schedule records 13,482.96 as “Vacant Plot Area”; the plotted-area schedule separately records 8,395.28 Sq.Mtrs.
| Layout component | Area / share shown in filed records |
|---|---|
| Total site area | 13,772.7 Sq.Mtrs |
| Master plan road-affected area | 235.33 Sq.Mtrs |
| Net site area | 13,537.37 Sq.Mtrs |
| Plotted area | 8,395.28 Sq.Mtrs |
| Layout roads | 3,561.74 Sq.mtrs (26.31%) |
| Open space / park | 1,015.74 Sq.mtrs (7.5%) |
| Social infrastructure | 338.53 Sq.mtrs (2.5%) |
| Utilities | 114.44 Sq.mtrs |
| Amenities area | 0 in the area schedule |
| Buffer-zone area | 111.62 sq.mt. in the layout-plan details |
The drawing identifies a 9.14 mt. wide internal road, a 9.00 MT WIDE EXISTING road and a 30.00 MT WIDE PROPOSED ROAD. The filed layout conditions call for road formation and surfacing, drainage, internal water supply, electrical infrastructure, street lighting, avenue planting and park development. These are listed as development requirements; the supplied records do not verify completion.
The submitted drawing lists TR SUMP, DUST BIN, SEPTIC TANK and Tot-lot. No building footprint, building height, floor or parking configuration is supplied for the plotted layout.
4. Homes, configurations & floor plans
No apartment or villa configuration schedule is supplied for this project. The offering is plotted land: see Project identity and Offering and status above.
| Plot information | Supplied figure |
|---|---|
| Plots in filed layout record | 57 |
| Plot size range | 122.16–247.22 sq.m; software-measured from the layout drawing Layout record |
| Median plot size | 139.35 sq.m; software-measured from the layout drawing Layout record |
| Booked / available plots | Not disclosed RERA record |
The layout drawing has two sheets and no flat plans were measured. The plot-size figures are software-read from drawing text and are not RERA-filed unit-size disclosures; verify them against the drawing before relying on an individual plot measurement. Floor plans Layout record
5. Parking & vehicle circulation
The supplied layout drawing records 0.00 Sq.Mtrs as common parking area. No sanctioned parking-space count, visitor or accessible parking provision, parking allocation arrangement, or parking levels are supplied.
The layout plan identifies internal roads and an existing and proposed connecting road. Approval conditions call for internal roads to remain accessible to neighbouring sites and prohibit obstructing roads; these are documented conditions, not confirmation that the works are complete.
6. Amenities, recreation & open spaces
The filed layout approval and drawing describe open-space and site-development provisions. Their inclusion in the approval documents or RERA amenities record does not establish delivery: the supplied amenities record shows 0 progress percentages, and no independent completion evidence is supplied. RERA amenities
| Facility | Park / organized open space |
|---|---|
| Description / size | 1,015.74 Sq.mtrs (7.5%) |
| Evidence source | Draft layout letter and layout plan |
| Declared progress / verified status | Required / shown in layout records; completion not verified |
| Facility | Green Strip / TOT LOT / Park |
|---|---|
| Description / size | Listed as available “YES” in RERA amenities data |
| Evidence source | RERA amenities record RERA amenities |
| Declared progress / verified status | Progress 0; completion not verified |
| Facility | Social infrastructure area |
|---|---|
| Description / size | 338.53 Sq.mtrs (2.5%) |
| Evidence source | Draft layout letter |
| Declared progress / verified status | Area shown; no facility specification or completion evidence supplied |
| Facility | Utilities area |
|---|---|
| Description / size | 114.44 Sq.mtrs |
| Evidence source | Draft layout letter |
| Declared progress / verified status | Area shown; utility installations not verified |
| Facility | Tot-lot |
|---|---|
| Description / size | Named on layout drawing |
| Evidence source | Layout plan |
| Declared progress / verified status | Drawing label only; completion not verified |
| Facility | Dust bin |
|---|---|
| Description / size | Named on layout drawing |
| Evidence source | Layout plan |
| Declared progress / verified status | Drawing label only; completion not verified |
7. Utilities, building services & safety
The layout conditions specify proposed site infrastructure, including internal water-supply pipelines and an overhead tank, an assured water-supply source, underground drainage and a common septic tank / STP, storm-water drains, rainwater-harvesting pits, electrical supply lines, a transformer, street lighting and underground utility ducting. The drawing also labels a sump and septic tank. These are provisions or requirements in the filed material; the supplied record does not establish capacity, commissioning or completed operation.
The layout conditions also refer to source segregation of garbage, a solid-waste disposal area and a bio-compost unit, as well as footpaths and cycling tracks. No completed-facility verification, fire-system specification, emergency-access assessment, security system or accessibility audit is supplied for the layout.
8. Location, access & connectivity
The registered project location is Ramdaspalli, Ibrahimpatnam Mandal, Ranga Reddy District, PIN 501510, on Sy. No. 69/PART. The filed boundary details identify an existing road to the north and a proposed 100-wide MDP road to the south. The layout drawing also labels a 30.00 MT WIDE PROPOSED ROAD and a 9.14 mt. wide internal road. RERA record RERA filing
A supplied location record places the nearest sampled Outer Ring Road interchange at 11.8 km (approx). This is a location-data estimate, not a travel-time claim. Location record
9. Developer & development status
The registered promoter is CHEGURI BHARATH KUMAR AND OTHERS. The project filing gives the organization type as Others; a more specific legal-entity type, corporate identifier and official website/contact details are not established in the supplied evidence. RERA record RERA filing Corporate record
The project documents name Cheguri Bharath Kumar and Kyama Anjan Kumar as the applicants/owners for the layout permission. The RERA Form-B declaration is made by Cheguri Bharath Kumar and includes a promoter undertaking to complete by 12/03/2028. The RERA registration certificate records validity through 12/03/2028, unless extended; the project header gives 12/07/2028 as the proposed completion date. No independently verified construction-progress or final-layout-release status is supplied. RERA record
10. Approvals, official records & documents
| Identifier / date | P02400009762; validity 13/03/2025–12/03/2028, unless extended |
|---|---|
| What the supplied record establishes | Form C registration certificate for SWASTHIKA, identifying CHEGURI BHARATH KUMAR AND OTHERS as promoter |
| Identifier / date | 013750/LO/HMDA/3740/SMD/2024; 13 March, 2025 |
|---|---|
| What the supplied record establishes | Draft layout permission for the plotted development; records 57 plots and area schedule, with conditions including development works and final-layout release |
| Identifier / date | 013750/LO/HMDA/3740/SMD/2024 |
|---|---|
| What the supplied record establishes | HMDA layout-permission record describing a 57-plot layout on Sy. No. 69/PART |
| Identifier / date | Drawing record for Sy. No. 69/PART |
|---|---|
| What the supplied record establishes | Shows 57 plots and the layout land-use schedule; no building plan or building configuration is supplied |
| Identifier / date | 2184/2025; dated 17 February, 2025 |
|---|---|
| What the supplied record establishes | Nine plots—01, 02, 03, 50, 51, 52, 32, 31, 49—are identified as mortgaged to the Metropolitan Commissioner, HMDA, with extent 1288.54 Sq. Mtrs |
| Identifier / date | 2183/2025 |
|---|---|
| What the supplied record establishes | Municipality letter reports handing over road-affected land in Sy. No. 69/Part through a gift settlement deed |
| Identifier / date | Form B |
|---|---|
| What the supplied record establishes | Includes the promoter’s title, encumbrance and completion declarations |
The supplied records do not include a final layout release or an occupancy/completion certificate. The draft layout letter states that final release is subject to the specified development and handover requirements.
1. Project at a glance
Project identity
Registered project name: SWASTHIKA
Project type: Plotted development / open plotted layout
Phase or registered portion: No separate phase name or phase number is stated; the registration is for the project identified as SWASTHIKA
TG-RERA registration number: P02400009762
Registration validity: Form C states validity from 13/03/2025 to 12/03/2028, unless extended by the Authority
Registered promoter: CHEGURI BHARATH KUMAR AND OTHERS
RERA status: New project; registration recorded as effective from 13 March 2025
Land and geographic identity
Locality: Ibrahimpatnam
Revenue village: Ramdaspalli (also written “Ramdaspalle” in the filed layout documents)
Mandal: Ibrahimpatnam
District: Ranga Reddy
PIN: 501510 in the project identity and registration record
Project survey number(s) and subdivision(s): Sy. No. 69/PART; no further subdivision is identified in the filed project identity
Site extent: Total site area 13,772.7 Sq.Mtrs; net site area 13,537.37 Sq.Mtrs; master plan road-affected area 235.33 Sq.Mtrs
Boundaries: East: OPEN LAND; West: EXISTING HOUSES; North: 9 MT WIDE EXISTING ROAD; South: PROPOSED 100 WIDE MDP ROAD
Development identity
Sanctioning / approval authority: HMDA layout-permission record; the draft layout letter identifies Adibatla Municipality / Municipal Corporation in the approval authority fields
Principal layout approval number and date: 013750/LO/HMDA/3740/SMD/2024, dated 13 March, 2025; the document is identified as a DRAFT LAYOUT LETTER
Approved built-up area: 0.00 proposed built-up area, both excluding and including parking, in the layout-plan details; this is a plotted layout, not a supplied building-plan schedule
Plot count: 57 plots in the draft layout and layout drawing
Building, floor and parking configuration: No building count, floor configuration, parking levels or building commencement certificate details are supplied for this plotted layout
Offering and status
Offering: Plots; the filed layout documents state 57 plots
Plot sizes: Software-read from the approved layout drawing: 122.16–247.22 sq.m (smallest to largest); median 139.35 sq.m. Drawing-derived sizes should be checked against the drawing
Booked / available: Not disclosed in the supplied evidence
Construction stage: No independently verified site-progress measurement is supplied. The filed layout permission requires layout development works; progress percentages in the amenities record are 0
Completion dates: The Form-B promoter declaration states 12/03/2028; the project header and Form C record 12/07/2028 as the proposed completion date / registration end date, respectively
Occupancy / completion certificate: No occupancy or completion certificate is recorded in the supplied evidence. The supplied approval is a draft layout permission, and a final layout release is described as conditional
2. The project story
SWASTHIKA is registered with TG-RERA as a plotted-development project on Sy. No. 69/PART, in Ramdaspalli village, Ibrahimpatnam Mandal, Ranga Reddy District. Its filed layout drawing shows a 57-plot arrangement with internal roads, a park/open-space parcel, social-infrastructure land and a utilities area. The proposed use shown in the project record is plotted land rather than a supplied apartment or building scheme.
The approval record describes draft layout permission and sets out infrastructure and handover conditions that must be met before release of the final layout. It identifies nine mortgaged plots; the document states that these plots are not permitted for sale while mortgaged. The evidence pack does not establish that the required development works are complete or that the final layout has been released.
3. Master plan, architecture & building design
This is a plotted layout, so the supplied design evidence concerns plot arrangement and land use rather than buildings, apartment plans or floor configurations. The filed layout record states a total site area of 13,772.7 Sq.Mtrs, a net site area of 13,537.37 Sq.Mtrs, and 57 individual plots. The layout drawing’s area schedule records 13,482.96 as “Vacant Plot Area”; the plotted-area schedule separately records 8,395.28 Sq.Mtrs.
Total site area: 13,772.7 Sq.Mtrs
Master plan road-affected area: 235.33 Sq.Mtrs
Net site area: 13,537.37 Sq.Mtrs
Plotted area: 8,395.28 Sq.Mtrs
Layout roads: 3,561.74 Sq.mtrs (26.31%)
Open space / park: 1,015.74 Sq.mtrs (7.5%)
Social infrastructure: 338.53 Sq.mtrs (2.5%)
Utilities: 114.44 Sq.mtrs
Amenities area: 0 in the area schedule
Buffer-zone area: 111.62 sq.mt. in the layout-plan details
The drawing identifies a 9.14 mt. wide internal road, a 9.00 MT WIDE EXISTING road and a 30.00 MT WIDE PROPOSED ROAD. The filed layout conditions call for road formation and surfacing, drainage, internal water supply, electrical infrastructure, street lighting, avenue planting and park development. These are listed as development requirements; the supplied records do not verify completion.
The submitted drawing lists TR SUMP, DUST BIN, SEPTIC TANK and Tot-lot. No building footprint, building height, floor or parking configuration is supplied for the plotted layout.
4. Homes, configurations & floor plans
No apartment or villa configuration schedule is supplied for this project. The offering is plotted land: see Project identity and Offering and status above.
Plots in filed layout record: 57
Plot size range: 122.16–247.22 sq.m; software-measured from the layout drawing
Median plot size: 139.35 sq.m; software-measured from the layout drawing
Booked / available plots: Not disclosed
The layout drawing has two sheets and no flat plans were measured. The plot-size figures are software-read from drawing text and are not RERA-filed unit-size disclosures; verify them against the drawing before relying on an individual plot measurement.
5. Parking & vehicle circulation
The supplied layout drawing records 0.00 Sq.Mtrs as common parking area. No sanctioned parking-space count, visitor or accessible parking provision, parking allocation arrangement, or parking levels are supplied.
The layout plan identifies internal roads and an existing and proposed connecting road. Approval conditions call for internal roads to remain accessible to neighbouring sites and prohibit obstructing roads; these are documented conditions, not confirmation that the works are complete.
6. Amenities, recreation & open spaces
The filed layout approval and drawing describe open-space and site-development provisions. Their inclusion in the approval documents or RERA amenities record does not establish delivery: the supplied amenities record shows 0 progress percentages, and no independent completion evidence is supplied.
| Facility | Park / organized open space |
|---|---|
| Description / size | 1,015.74 Sq.mtrs (7.5%) |
| Evidence source | Draft layout letter and layout plan |
| Declared progress / verified status | Required / shown in layout records; completion not verified |
| Facility | Green Strip / TOT LOT / Park |
|---|---|
| Description / size | Listed as available “YES” in RERA amenities data |
| Evidence source | RERA amenities record |
| Declared progress / verified status | Progress 0; completion not verified |
| Facility | Social infrastructure area |
|---|---|
| Description / size | 338.53 Sq.mtrs (2.5%) |
| Evidence source | Draft layout letter |
| Declared progress / verified status | Area shown; no facility specification or completion evidence supplied |
| Facility | Utilities area |
|---|---|
| Description / size | 114.44 Sq.mtrs |
| Evidence source | Draft layout letter |
| Declared progress / verified status | Area shown; utility installations not verified |
| Facility | Tot-lot |
|---|---|
| Description / size | Named on layout drawing |
| Evidence source | Layout plan |
| Declared progress / verified status | Drawing label only; completion not verified |
| Facility | Dust bin |
|---|---|
| Description / size | Named on layout drawing |
| Evidence source | Layout plan |
| Declared progress / verified status | Drawing label only; completion not verified |
7. Utilities, building services & safety
The layout conditions specify proposed site infrastructure, including internal water-supply pipelines and an overhead tank, an assured water-supply source, underground drainage and a common septic tank / STP, storm-water drains, rainwater-harvesting pits, electrical supply lines, a transformer, street lighting and underground utility ducting. The drawing also labels a sump and septic tank. These are provisions or requirements in the filed material; the supplied record does not establish capacity, commissioning or completed operation.
The layout conditions also refer to source segregation of garbage, a solid-waste disposal area and a bio-compost unit, as well as footpaths and cycling tracks. No completed-facility verification, fire-system specification, emergency-access assessment, security system or accessibility audit is supplied for the layout.
8. Location, access & connectivity
The registered project location is Ramdaspalli, Ibrahimpatnam Mandal, Ranga Reddy District, PIN 501510, on Sy. No. 69/PART. The filed boundary details identify an existing road to the north and a proposed 100-wide MDP road to the south. The layout drawing also labels a 30.00 MT WIDE PROPOSED ROAD and a 9.14 mt. wide internal road.
A supplied location record places the nearest sampled Outer Ring Road interchange at 11.8 km (approx). This is a location-data estimate, not a travel-time claim.
9. Developer & development status
The registered promoter is CHEGURI BHARATH KUMAR AND OTHERS. The project filing gives the organization type as Others; a more specific legal-entity type, corporate identifier and official website/contact details are not established in the supplied evidence.
The project documents name Cheguri Bharath Kumar and Kyama Anjan Kumar as the applicants/owners for the layout permission. The RERA Form-B declaration is made by Cheguri Bharath Kumar and includes a promoter undertaking to complete by 12/03/2028. The RERA registration certificate records validity through 12/03/2028, unless extended; the project header gives 12/07/2028 as the proposed completion date. No independently verified construction-progress or final-layout-release status is supplied.
10. Approvals, official records & documents
| Identifier / date | P02400009762; validity 13/03/2025–12/03/2028, unless extended |
|---|---|
| What the supplied record establishes | Form C registration certificate for SWASTHIKA, identifying CHEGURI BHARATH KUMAR AND OTHERS as promoter |
| Identifier / date | 013750/LO/HMDA/3740/SMD/2024; 13 March, 2025 |
|---|---|
| What the supplied record establishes | Draft layout permission for the plotted development; records 57 plots and area schedule, with conditions including development works and final-layout release |
| Identifier / date | 013750/LO/HMDA/3740/SMD/2024 |
|---|---|
| What the supplied record establishes | HMDA layout-permission record describing a 57-plot layout on Sy. No. 69/PART |
| Identifier / date | Drawing record for Sy. No. 69/PART |
|---|---|
| What the supplied record establishes | Shows 57 plots and the layout land-use schedule; no building plan or building configuration is supplied |
| Identifier / date | 2184/2025; dated 17 February, 2025 |
|---|---|
| What the supplied record establishes | Nine plots—01, 02, 03, 50, 51, 52, 32, 31, 49—are identified as mortgaged to the Metropolitan Commissioner, HMDA, with extent 1288.54 Sq. Mtrs |
| Identifier / date | 2183/2025 |
|---|---|
| What the supplied record establishes | Municipality letter reports handing over road-affected land in Sy. No. 69/Part through a gift settlement deed |
| Identifier / date | Form B |
|---|---|
| What the supplied record establishes | Includes the promoter’s title, encumbrance and completion declarations |
The supplied records do not include a final layout release or an occupancy/completion certificate. The draft layout letter states that final release is subject to the specified development and handover requirements.
Frequently asked questions
Is SWASTHIKA registered with Telangana RERA?
Yes. SWASTHIKA is registered with the Telangana Real Estate Regulatory Authority as P02400009762; the registration status is New Project.
Who is the developer of SWASTHIKA?
The promoter named in the RERA registration is CHEGURI BHARATH KUMAR AND OTHERS.
Where is SWASTHIKA located?
SWASTHIKA is in IBRAHIMPATNAM, Ramdaspalli, Rangareddy, Telangana (501510).
When will SWASTHIKA be completed?