Sign in

Laxmi Infobahn Tower 23

GAR T-11 PRIVATE LIMITED · Rangareddy

LAXMI INFOBAHN TOWER 23 is a commercial project at Plot No. 12, Kokapet, Gandipet Mandal, Ranga Reddy District, developed by GAR T-11 PRIVATE LIMITED. The site area is 16,308.84 sq. m, and the project comprises one building with 5 Cellar + 4 Stilt + 1 Ground + 29 Upper floors. The supplied record does not establish individual office or unit configurations. The project record gives proposed completion as 11/06/2027; a TG-RERA registration number is not available in the supplied project record.

01What we found

RegisteredTG-RERA
17documents on file - each fact links to its page
0court cases on this project's land in the court records searched
10items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

10 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

ItemRecord
Registered project nameLAXMI INFOBAHN TOWER 23 RERA record
Project typeCommercial RERA record
Phase / registered portionNew Project; one building is recorded. The registration record does not separately identify a phase name. RERA record RERA filing
TG-RERA registration numberNot available in the supplied project record; unverified. RERA record
Registration validityNot stated in the supplied record; unverified. RERA record
Registered promoterGAR T-11 PRIVATE LIMITED RERA record Corporate record
RERA statusListed as “New Project”; registration status and number are not supplied. RERA filing

Land and geographic identity

ItemRecord
Locality / plotKokapet; Plot No. 12 RERA filing
Revenue villageKokapet (also rendered in project records as “koKapet” and “Kokapet-ORRGC Village”) RERA record
MandalGandipet RERA record
District / PINRanga Reddy / 500075 RERA record
Project survey numbersSy. Nos. 109 and 114; no project subdivision is specified in the supplied project records. RERA filing
Site extent16,308.84 sq. m RERA filing
Total / net areaTotal area 16,308.84 sq. m; net area 16,308.84 sq. m; recorded affected area 0 sq. m. RERA filing
BoundariesEast: OTHERS LAND; West: OTHERS LAND; North: OTHERS LAND; South: ROAD. RERA filing

Development identity

ItemRecord
Sanctioning / technical approval authoritiesHMDA technical approval; building permit order issued by Narsingi Municipality.
Principal approvalHMDA technical approval 035756/SKP/C1/U6/HMDA/02052020, dated 10/06/2021; municipal building permit BA.NO: 17/2021-22, dated 12.07.2021.
Approved built-up areaHMDA approval extraction records Built up Area 175898.41 and Total Built up Area (In Sq.mts) 202129.13. Narsingi Municipality permit extraction records Built up area 175898.41 SqMts. The record does not explain the distinction between these area entries.
Building countOne building / one proposed building unit. RERA filing
Sanctioned configuration5 Cellar + 4 Stilt + 1 Ground + 29 Upper floors.
Building height135.35 (the approval extraction does not state a unit alongside this figure).
Parking levels / countFive cellar levels are in the sanctioned floor configuration. A parking-space count, allocation schedule and parking arrangement are not supplied.
Approved vs RERA-declared unitsApproved-plan record: 1 total building unit. The RERA unit table lists 29 floor-labelled rows, not a verified count of saleable units or individual offices. RERA filing RERA unit table

Offering and status

ItemRecord
Offering typeCommercial; the supplied record does not establish the individual office or unit configurations for sale. RERA filing RERA unit details
RERA-filed unit-table entries29 floor-labelled entries; the filing records 0 booked and 29 available, but these rows are not verified saleable units. The portal extract has no as-of date. RERA unit table RERA unit details
RERA-filed saleable areaFloor-labelled entries range from 4971.05 sq. m to 5931.71 sq. m; these figures should not be treated as verified individual-unit areas. RERA unit table RERA unit details
Construction stageNo construction-progress figure or independently verified site-progress evidence is supplied. RERA record RERA amenities
Completion deadlinePromoter’s Form-B declaration undertakes completion by 11th June 2027; the project record gives proposed completion as 11/06/2027. This is not the same as registration validity. RERA filing
Revised completion dateNo revised date disclosed. RERA record
Occupancy / completion certificateNo occupancy or completion certificate is supplied. The permit documents state that an occupancy certificate is compulsory before occupation.

2. The project story

LAXMI INFOBAHN TOWER 23 is recorded as a proposed commercial building at Plot No. 12, Kokapet, on Sy. Nos. 109 and 114, in the revenue village of Kokapet, Gandipet Mandal, Ranga Reddy District. The site is recorded as 16,308.84 sq. m. RERA record RERA filing

The approval documents describe a single commercial building with five cellar levels, four stilt levels, a ground floor and 29 upper floors. The permit record is conditional and requires construction to follow the sanctioned plan; the supplied evidence does not establish how much construction has been completed. The promoter’s Form-B declaration gives 11 June 2027 as its completion undertaking. No occupancy certificate is provided, so the record does not establish an occupancy-certified portion.

3. Master plan, architecture & building design

The supplied approval extracts describe one commercial building on a site of 16,308.84 sq. m, with a configuration of 5 Cellar + 4 Stilt + 1 Ground + 29 Upper floors. The HMDA extraction records Built up Area 175898.41 and Total Built up Area (In Sq.mts) 202129.13; the municipal permit records Built up area 175898.41 SqMts. These are approval-record figures, and no supplied document explains the distinction between the two HMDA area entries. RERA filing

The approvals refer to road widths of 18 mt. road widths, 4.5mts. and 5mts., and require maintenance of sanctioned-plan setbacks. The municipal permit also requires surrender of the road-affected portion without compensation and maintenance of a strip of greenery at the site periphery. No floor-plan drawing has been measured: three drawings are recorded as pending scan review, with no measured plans available. Details such as floorplate arrangement, offices per floor, building footprint, lifts, stairs, entrances, and internal circulation therefore cannot be confirmed from the supplied material. Floor plans

4. Homes, configurations & floor plans

This is a commercial project, but the supplied RERA unit table labels its 29 entries by floor rather than by an identified office configuration. They should not be interpreted as 29 independently verified saleable units. The portal extract shows 0 booked and 29 available, without an as-of date. RERA unit table RERA unit details

Commercial floors; unit configuration not filed
Units29 floor-labelled entries; not verified as saleable-unit count
Booked0 (portal extract; no as-of date)
Available29 (portal extract; no as-of date)
RERA saleable areaFiled floor-row figures range from 4971.05 sq. m to 5931.71 sq. m; not established as individual-unit areas
Measured carpet areaNot available: drawings are pending scan review and no software measurement is supplied
Loading (if supplied)Not supplied

The three floor-plan drawings have not been measured. Accordingly, no drawing-based carpet area, room layout or floor-by-floor commercial configuration is available here. RERA-filed saleable-area entries and any future drawing-measured carpet areas are different measures and should not be substituted for one another. Floor plans RERA unit details

5. Parking & vehicle circulation

The sanctioned configuration includes five cellar levels, but the supplied evidence does not state how many parking spaces are approved, their type, or whether they are allocated to particular units. It also does not establish visitor or accessible parking, parking-level layouts, ramps, vehicle entry and exit arrangements, EV charging, or any legally documented parking allocation. A cellar level in a floor schedule alone does not establish the number or allocation of parking spaces.

6. Amenities, recreation & open spaces

The RERA amenity table contains facility names and availability indications, but shows 0% progress for each listed item. These entries are not independent confirmation that facilities are complete. The approval documents also impose or record requirements for certain site facilities. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Clubhouse / indoor
Community BuildingsNo size or further description suppliedRERA amenitiesProgress shown as 0%; no independent completion verification
Sports / recreation
Tot-lot / open spaceHMDA condition requires tot-lot / open space / buffer to be maintained as greenery; no size suppliedRequired by approval condition; completion not verified
Green Strip/TOT LOT/ParkListed in RERA amenity table; no size suppliedRERA amenitiesAvailability indicated “YES”; progress shown as 0%; not independently verified
Aggregate area of recreational Open SpaceListed; area not suppliedRERA amenitiesProgress shown as 0%; no independent completion verification
Landscape / open space
Strip of greenery at site peripheryMunicipal permit condition; no area suppliedRequired by permit condition; completion not verified
Convenience / community
No further specific convenience or community facilities established in the supplied evidence———

7. Utilities, building services & safety

RERA’s amenity table lists water supply, sewerage/STP, storm-water drains, rainwater harvesting, energy management, fire protection and fire-safety requirements, and an electrical meter room/sub-station/receiving station. These entries show “YES” where availability is recorded, but each has 0% progress in the supplied table; capacities and independent completion evidence are not supplied. RERA amenities

The approval extracts include requirements for rainwater-harvesting structures, a transformer, a garbage house and an STP; the municipal permit specifically mentions a rainwater-harvesting percolation pit. HMDA also requires a tot-lot/open-space/buffer area to be maintained as greenery. The documents require completion notice and an occupancy certificate before occupation. No detailed fire-system design, water source or storage capacity, STP capacity, reuse arrangements, backup-power capacity, lift specification, waste-segregation plan, CCTV or accessibility details are established by the supplied records.

8. Location, access & connectivity

The registered project location is Plot No. 12, Kokapet, revenue village Kokapet, Gandipet Mandal, Ranga Reddy District, PIN 500075; project records identify Sy. Nos. 109 and 114. The site boundary schedule identifies a road on the south and other land on the east, west and north. RERA record RERA filing

A supplied location record lists Financial District (Nanakramguda) — 2.1 km. The approval documents refer to road widths of 18 mt. road widths, 4.5mts. and 5mts. No public-transport stops, additional measured distances, travel times or specific approach-road names are supplied. Location record

9. Developer & development status

The registered promoter is GAR T-11 PRIVATE LIMITED, a private limited company. The supplied project identity lists the promoter’s tax identifier only in masked form as xxxxxx435A. Its RERA filing address is recorded as LAXMI CYBER TOWER, BANJARA HILLS, KOKAPET, KOKAPET, Gandipet, Ranga Reddy, 500075. Corporate record Parties record

The RERA filing identifies NARASAPURAM SRINIVAS as authorised signatory, GAVVA AMARENDER REDDY as Managing Director, and GAVVA ABHINAV RAM REDDY as Director. The building approval records Kailash Ganga Constructions Pvt Ltd and others as applicants/owners and GAR T-11 Pvt Ltd as developer or GPA representative. The supplied evidence does not establish a construction-progress percentage or a completed/occupied phase. The promoter’s Form-B affidavit, dated 20/07/2021, declares a completion undertaking of 11 June 2027. Parties record

10. Approvals, official records & documents

RecordSupplied evidence
TG-RERA registrationProject is identified as “New Project”; registration number, registration validity and captured registration certificate are not supplied. RERA record RERA filing
HMDA technical approval035756/SKP/C1/U6/HMDA/02052020, dated 10/06/2021; technical approval for the proposed commercial building.
Narsingi Municipality building permitBA.NO: 17/2021-22, dated 12.07.2021; file G1/1314/2021.
Legal-title-related filingForm-B declaration, dated 20/07/2021; the title materials filed include a development agreement-cum-GPA.
Commencement / occupancyThe supplied approval documents include a commencement-certificate document category and building-permit records. No occupancy or completion certificate is supplied. Document index
Approved layoutNo publicly accessible approved-layout lookup result is supplied; the HMDA DPMS lookup is recorded as unavailable from the public internet. This does not establish a refusal. HMDA
Further project documentsRERA filing records a partially filled allotment letter and a partially completed draft agreement for sale; neither is a completed conveyance.

The approval documents state that the building must follow the sanctioned plan, that commencement and completion notices are required, and that an occupancy certificate is compulsory before occupation. Further approval conditions are set out in the source documents; this overview reports the principal records and does not reproduce every condition.

Frequently asked questions

Who is the developer of LAXMI INFOBAHN TOWER 23?

The promoter named in the RERA registration is GAR T-11 PRIVATE LIMITED.

Where is LAXMI INFOBAHN TOWER 23 located?

LAXMI INFOBAHN TOWER 23 is in KOKAPET, Gandipet, Rangareddy, Telangana (500075).

When will LAXMI INFOBAHN TOWER 23 be completed?

The promoter's proposed date of completion filed with RERA is 11/06/2027. This is the promoter's declaration, not a guarantee.