Hillcrest Phase-2

Pacifica India Projects Pvt Ltd · Rangareddy · RERA P02400003989

Hillcrest Phase-2 is a residential apartment project in Gachibowli / Financial District, Gandipet Mandal, Ranga Reddy District, developed by registered promoter Pacifica India Projects Pvt Ltd. The filed site extent is 69,296.69 sq.m, including a net plot area of 60,929.53 sq.m, and the development comprises five residential blocks, A through E, and one amenities building; Block A has 2 Cellar + 1 Stilt + 22 upper floors, Blocks B, C, D and E have 1 Stilt + 22 upper floors, and the amenities building has 1 Ground + 4 upper floors. The RERA filing records 1,004 units in 2BHK, 3BHK and 4BHK configurations, with saleable areas of 110.65 sq.m, 165.03 sq.m and 244.67 sq.m respectively. Its TG-RERA registration is P02400003989, and the proposed completion date is 30/04/2028.

More from Pacifica India Projects Pvt Ltd · 3 projects →

01What we found

RegisteredTG-RERA - valid till 31 Dec 2027
14documents on file - each fact links to its page
0court cases on this project's land in the court records searched
9items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

9 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

ItemProject record
Registered project nameHillcrest Phase-2 RERA record
Project typeResidential apartment project RERA record
Registered phase / portionPhase-2; the certificate names “Hillcrest Phase-2.” The supplied record does not further define the phase boundary beyond its registered survey numbers and project documents. RERA record
TG-RERA registrationP02400003989, granted under section 5; certificate issued 22/01/2022.
Registration validity22/01/2022 to 31/12/2027, unless extended by the Authority. The evidence says no extension has been recorded. This is the registration period, not the completion deadline.
Registered promoterPacifica India Projects Pvt Ltd; company. RERA record Corporate record
RERA statusListed as an on-going project. RERA record

Land and geographic identity

ItemProject record
Locality / address descriptionGachibowli / Financial District; the RERA project address identifies Hillcrest By Pacifica, Financial District, Gachibowli. RERA record RERA filing
Revenue villagePuppalguda. The filed plans also label it “Puppalguda-ORRGC.” RERA record
MandalGandipet. RERA record
DistrictRanga Reddy. RERA record
PIN500048. RERA record
Project survey numbers310(P), 311, 318, 319(P). The plans render these as 310(p), 311, 318 and 319(p). RERA record
Filed site extentTotal plot area 69,296.69 sq.m; road-widening area 8,367.16 sq.m; net plot area 60,929.53 sq.m. RERA filing
BoundariesEast: Vacant Land; West: Road Width-24; North: Road Width-30; South: Vacant Land. RERA filing

Development identity

ItemProject record
Sanctioning / technical authorityHMDA technical approval, with construction permission proceedings by Manikonda Municipality. Approvals record
Principal approval referencesHMDA technical approval 042072/ZOA/R1/U6/HMDA/20012021, dated 22/09/2021; Manikonda Municipality proceedings MC MNK TP 25 2021-2022, dated 03-12-2021.
Approved / plan-recorded areaThe Manikonda proceedings state a site extent of 60,929.53 Sq.mtrs. The plan records 127,149.09 sq.m total proposed net built-up area; the technical approval lists total built-up area of 125,864.59 Sq.mts. These are the figures as stated in their respective records, not interchangeable area measures.
Building organizationFive residential blocks—A, B, C, D and E—and one amenities building.
Filed floor configurationBlock A: 2 Cellar + 1 Stilt + 22 upper floors; Blocks B, C, D and E: 1 Stilt + 22 upper floors; amenities building: 1 Ground + 4 upper floors.
Parking information in planThe plan records “Required Parking Area 27690.14” and “Total parking area 51584.80”; the supplied extracts do not establish a space count, resident/visitor allocation or unit-specific allocation.
Unit countRERA-filed configurations total 1,004 units. The HMDA plan records 1,008 dwelling units. RERA unit table

Offering and status

ItemProject record
Unit types2BHK, 3BHK and 4BHK apartments. RERA unit table
RERA-filed saleable areas2BHK: 110.65 sq.m; 3BHK: 165.03 sq.m; 4BHK: 244.67 sq.m. RERA unit table
Booked / available2BHK: 534 booked / 163 available; 3BHK: 223 / 40; 4BHK: 34 / 10. These portal figures have no supplied “as of” date and should be treated as indicative. RERA unit table RERA unit details
Construction stageNo independently verified site-stage report is supplied. RERA-portal amenity/infrastructure progress entries are reported in section 6; they are not independent site verification. RERA amenities
Completion timelineRERA project information gives proposed and revised proposed completion as 30/04/2028. The Form B affidavit separately states a completion undertaking of “31s December 2027.” RERA record RERA filing
Occupancy / completion certificateNo occupancy or completion certificate is supplied for this phase. The Manikonda proceedings extract states that completion was not certified in that record.

2. The project story

Hillcrest Phase-2 is a registered residential apartment development at Puppalguda, Gandipet Mandal, in Ranga Reddy District, addressed in the RERA filing to the Gachibowli / Financial District area. The registered land identifiers are Survey Nos. 310(P), 311, 318 and 319(P). The filed site figures show 69,296.69 sq.m total plot area, including 8,367.16 sq.m recorded for road widening, and a net plot area of 60,929.53 sq.m. RERA record RERA filing RERA filing

The plan and construction-permission records describe five residential blocks, A through E, alongside a separate amenities building. The residential blocks are recorded as high-rise buildings, generally with a stilt level and 22 upper floors; Block A additionally has two cellar levels. The amenities building is described as Ground + 4 upper floors. These are plan-record descriptions; the supplied evidence does not independently establish how much of each block has been built or occupied.

The RERA filing offers 2BHK, 3BHK and 4BHK apartments. Booked and available numbers are portal records without an “as of” date. The project is labelled on-going, but no independent construction-progress inspection or phase/tower-specific occupancy certification is supplied. RERA record RERA unit table RERA unit details

3. Master plan, architecture & building design

The filed plan describes a residential multistoried development with five residential blocks and a separate amenities building. It records total plot area of 69,296.69 sq.m, road-widening area of 8,367.16 sq.m, net plot area of 60,929.53 sq.m, proposed coverage area of 6,489.59 sq.m (10.65%), residential net BUA of 125,864.23 sq.m, and total proposed net BUA of 127,149.09 sq.m. The HMDA technical approval extract separately records total built-up area of 125,864.59 Sq.mts and proposed built-up area of 131,761.36. These figures are quoted as labelled in the respective records; the supplied extracts do not fully define their measurement bases.

BuildingPlan-record floor configurationOther recorded detail
Block A2 Cellar + 1 Stilt + 22 upper floorsTechnical approval lists built-up area 15,129.11 and height 66.
Block B1 Stilt + 22 upper floorsTechnical approval lists built-up area 24,955.04 and height 66.
Block C1 Stilt + 22 upper floorsTechnical approval lists built-up area 24,955.04 and height 66.
Block D1 Stilt + 22 upper floorsTechnical approval lists built-up area 31,208.76 and height 66.
Block E1 Stilt + 22 upper floorsTechnical approval lists built-up area 24,955.04 and height 66.
Amenities building1 Ground + 4 upper floorsTechnical approval lists built-up area 4,661.6 and height 15.

The plan labels the land use as residential and describes a vacant plot area of 54,371.94 sq.m, accessory-use area of 68.00 sq.m, and a mortgage area of 12,862.25 sq.m. It also records total parking area of 51,584.80 and required parking area of 27,690.14, without a supplied count of parking spaces. The approved drawing extracts supplied here do not provide a complete, readable account of typical-floor layouts, flats per floor, lifts, staircases, entrances, internal circulation or landscape areas.

The project drawings are not a basis for reporting a RERA-filed carpet area: the supplied floor-plan review says none of the seven drawings was software-measured, five are scans pending measurement, and two contain no flats. Floor plans

4. Homes, configurations & floor plans

The RERA filing records three apartment configurations. Unit counts and saleable areas below are filing figures; booked/available counts are portal figures with no stated as-of date. RERA unit details RERA unit table

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK697534163110.65 sq.mNot suppliedNot supplied
3BHK26322340165.03 sq.mNot suppliedNot supplied
4BHK443410244.67 sq.mNot suppliedNot supplied

Carpet area is not supplied as a measured value for these configurations. Saleable area is the RERA-filed figure; it should not be read as carpet area, since the supplied measurement note describes saleable area as including the home’s share of common areas. No room dimensions, balcony or utility measurements, or typical-floor arrangement are available in the supplied measured-drawing data. RERA unit details Floor plans

5. Parking & vehicle circulation

The HMDA plan extract records Required Parking Area 27690.14 and Total parking area 51584.80. The technical approval states that cellar space is to be used exclusively for vehicle parking, without partition walls or rolling shutters; Block A is shown with two cellar levels. The extracts do not establish the number of bays, two-wheeler provision, visitor or accessible spaces, mechanical parking, EV charging, parking allocation to individual homes, or the number and arrangement of vehicle ramps and entrances. A drawn or earmarked parking provision does not, on its own, establish exclusive ownership or allocation to a buyer.

6. Amenities, recreation & open spaces

The construction-permission and plan records identify an amenities building and project services including a tot-lot, STP, transformer/substation, electrical yard, waterbody, rainwater harvesting and garbage facilities. Separately, RERA portal progress fields report completion percentages for listed infrastructure items. Those percentages are portal-reported progress, not independently verified completion. RERA amenities

Clubhouse / indoor — Club / amenities building
Description / sizePlan labels “CLUB (G+4)” and “AMENITIES (G+4)”; building record gives 1 Ground + 4 upper floors. No facility schedule, area or capacity is supplied.
Evidence sourceFiled plan and technical approval
Declared progress / verified statusRERA portal “Community Buildings” progress: 0%; no independent completion verification. RERA amenities
Sports / recreation — Tot-lot / green strip
Description / sizeTot-lot identified in the approval record; RERA portal lists “Green Strip/TOT LOT/Park.” No size or capacity supplied. RERA amenities
Evidence sourceTechnical approval and RERA portal
Declared progress / verified statusPortal progress: 12%; not independently verified. RERA amenities
Landscape / open space — Open space / greenery
Description / sizeApproval requires the earmarked open space, tot-lot and buffer to be maintained as open space/greenery; no area is stated in the supplied extract.
Evidence sourceTechnical approval
Declared progress / verified statusRERA portal “Aggregate area of recreational Open Space” progress: 0%; not independently verified. RERA amenities
Convenience / community — Internal roads and footpaths
Description / sizeRERA portal item; dimensions or detailed road/footpath schedule not supplied here. RERA amenities
Evidence sourceRERA portal
Declared progress / verified statusProgress: 0%; not independently verified.
Convenience / community — Street lighting
Description / sizeRERA portal item; specifications not supplied. RERA amenities
Evidence sourceRERA portal
Declared progress / verified statusProgress: 0%; not independently verified.

7. Utilities, building services & safety

The filed approval records and RERA portal list services, but the supplied evidence does not establish that each service is complete or operational.

ServiceWhat the supplied record says
WaterManikonda permission specifies separate underground static water storage of 25,000 Its capacity and separate terrace tank of 25,000 lits capacity for residential buildings. The approval requires water disinfection and records rainwater-harvesting structures; no water-source or treatment capacity is supplied.
Sewerage and drainageSTP is listed in the technical approval and plan. RERA portal progress is 52% for “Sewerage (Chamber, Lines, Septic Tank, STP),” 35% for sewage/sullage treatment and disposal, and 25% for storm-water drains. These are portal progress entries, not independent verification. RERA amenities
Electrical and backupThe plan identifies a substation and electrical yard; the approval requires provision for a transformer. Solar water heating and solar lighting are listed as approval conditions. Generator provision appears among the technical approval’s utility conditions, but no capacity or operational status is supplied.
Vertical transportationLift count, type and capacity are not provided in the supplied extracts.
Fire and life safetyThe Manikonda proceedings require fire-safety requirements and fire-service clearance before applying for an occupancy certificate; the technical approval also refers to Fire Service NOCs and safety provisions. These approval conditions do not by themselves establish completed systems or current statutory compliance.
Waste and securityThe approval lists a garbage house and refuse chute / garbage-disposal systems. No security, CCTV or access-control detail is supplied.
AccessibilityNo accessible parking, ramp or accessible-circulation details are supplied.

8. Location, access & connectivity

The registered location is Puppalguda Village, Gandipet Mandal, Ranga Reddy District, PIN 500048, with the project address described in the filing as Hillcrest By Pacifica, Financial District, Gachibowli. The filed boundaries identify Road Width-30 to the north and Road Width-24 to the west. The plan also records road widths of 30.00, 24, 30.0M (100'0"), 24.0M(80'0") and 9.0M. RERA record RERA filing RERA filing

The supplied location dataset lists these distances from the project location; no travel-time estimates are provided:

Nearby placeListed distance
Financial District (Nanakramguda)3.7 km
ICICI Bank0.4 km
Holy Mary College1.6 km
Rush Clinic0.2 km
Cyient Technologies pvt ltd1.7 km
Abdul Kalam Park0.2 km
Unnamed school0.6 km

These are supplied location-record distances; the evidence does not specify a route or measurement method. Location record

9. Developer & development status

The registered legal promoter is Pacifica India Projects Pvt Ltd, a company. The RERA record identifies Rakesh Israni as an authorized signatory. The promoter’s website is listed as pacificacompanies.com; the supplied evidence does not give a verified registered-office street address or direct project contact details. Corporate record RERA record Parties record

The project filing records the completion timeline as 30/04/2028. Its Form B affidavit, signed by the authorized signatory for the promoter, declares completion by “31s December 2027” and discloses an ICICI Bank Ltd loan sanction of INR 70 crores. The project’s registration certificate remains listed as valid through 31/12/2027 unless extended; registration validity and the stated project-completion date are distinct records. No independent construction-stage assessment or occupancy certificate is supplied. RERA record RERA filing

10. Approvals, official records & documents

TG-RERA registration certificate
Reference and scopeHillcrest Phase-2, P02400003989; issued 22/01/2022; valid to 31/12/2027 unless extended.
EvidenceForm C certificate.
HMDA technical approval
Reference and scope042072/ZOA/R1/U6/HMDA/20012021, dated 22/09/2021; residential project on the registered survey numbers; technical approval directs that plans be sanctioned by the Executive Authority.
EvidenceHMDA technical approval.
Manikonda Municipality construction permission
Reference and scopeMC MNK TP 25 2021-2022, dated 03-12-2021; permission for the residential apartment project on Survey Nos. 310 (P), 311, 318 and 319(P), extent 60,929.53 Sq.mtrs.
EvidenceMunicipality proceedings.
Filed layout / building plan
Reference and scopeFile No. 042072/ZOA/R1/U6/HMDA/20012021; includes five residential blocks and an amenities building, with site and built-up-area figures.
EvidencePlan showing proposed residential building/apartment.
Plan sheets
Reference and scopeHMDA-identified plan sheets 04/08, 05/08 and 02/08, dated 22-09-2021, are recorded in the supplied plan extract.
EvidenceFiled building-plan material.
Form B promoter declaration
Reference and scopeDeclaration by Rakesh Israni for Pacifica India Projects Private Limited; includes completion undertaking, land-title/development-agreement declaration and ICICI Bank Ltd loan disclosure.
EvidenceRERA-filed affidavit-cum-declaration.
Occupancy / completion certification
Reference and scopeNo completion or occupancy certificate is supplied for the project phase. The construction-permission record states occupancy requires completion in accordance with the technically approved plans and a Fit for Occupancy certificate.
EvidenceNot evidenced as issued.

The supplied floor-plan set has seven drawings recorded, with five scans pending measurement, two drawings with no flats, and none software-measured. Consequently, this Overview does not provide drawing-measured carpet areas or detailed room plans. Floor plans

Other registrations of Hillcrest

Frequently asked questions

Is Hillcrest Phase-2 registered with Telangana RERA?

Yes. Hillcrest Phase-2 is registered with the Telangana Real Estate Regulatory Authority as P02400003989; the registration status is On-Going Project.

Who is the developer of Hillcrest Phase-2?

The promoter named in the RERA registration is Pacifica India Projects Pvt Ltd.

Where is Hillcrest Phase-2 located?

Hillcrest Phase-2 is in Gachibowli, Puppalguda, Gandipet, Rangareddy, Telangana (500048).

When will Hillcrest Phase-2 be completed?

The promoter's proposed date of completion filed with RERA is 30/04/2028. This is the promoter's declaration, not a guarantee.