NEERA ENCLAVE is a residential apartment project in Dulapally, Dundigal Gandimaisamma, Medchal-Malkajgiri. The registered promoter is SHIVA SHAKTI CONSTRUCTIONS. The project is on a 448.39 sq. m site and comprises one residential apartment building with 1 stilt + 5 upper floors; the RERA filing lists 10 3BHK units, each with a saleable area of 126.71 sq. m. Its TG-RERA registration number is P02200005348, and its proposed completion date is 07/05/2028.

01What we found

RegisteredTG-RERA - valid till 7 Jan 2028
14documents on file - each fact links to its page
0court cases on this project's land in the court records searched
7items to check - 2 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

7 items to check before you pay, 2 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Photo from magicbricks.comPhoto from magicbricks.com
▦ View all 2 photos
Dulapally, Dundigal Gandimaisamma, Medchal-Malkajgiri · geocoded — approximate.

1. Project at a glance

Project identity

ItemProject record
Registered project nameNEERA ENCLAVE RERA record
Project type / statusResidential apartment project; recorded as a new project RERA record RERA filing
Phase / registered portionNo separate phase name is disclosed. The registered project is identified with Survey No. 142 PART
TG-RERA registrationP02200005348; issued 25/11/2022 and valid through 07/01/2028, subject to extension by the Authority under the Act and rules. This is the registration validity period, not the building completion deadline. RERA record
Registered promoterSHIVA SHAKTI CONSTRUCTIONS RERA record Corporate record
TG-RERA statusRegistration certificate records that the project is registered. The reviewed record does not state an occupancy or completion certificate for the building. Document index

Land and geographic identity

ItemProject record
LocalityDulapally RERA record
Revenue villageDulapally (also rendered “Dulapalle” in the approval documents) RERA record Land records
MandalDundigal Gandimaisamma RERA record
District / PINMedchal-Malkajgiri / 500014 RERA record
Project survey number(s)142 PART; the building-permit document renders this as Sy.No.142part. Land records
Plot / site extentPlot No. 65; 448.39 sq. m site area, recorded as both total and net area in the municipality permit. RERA filing
Boundaries recorded in RERA filingEast: Plot – Neighbours Land; West: 40 Feet Wide Road; North: 40 Feet Wide Road; South: Plot No 64. RERA filing

Development identity

ItemProject record
Sanctioning authoritiesHMDA technical approval, followed by a Kompally Municipality building permit. Approvals record
Principal approvalHMDA technical approval 047003/MED/R1/U6/HMDA/08072021, dated 07 January, 2022. Approvals record
Local building permitKompally Municipality Permit.No.0002/2022, dated 11.05.2022; file Lr.No.1108/TP/KM/2022. Approvals record
Approved built-up area1267.3 sq. m is recorded as built-up area in the municipal permit. The HMDA approval also records Total Built up Area (In Sq.mts) 1520.76 and Proposed Built-up Area 1520.76; these are distinct figures as stated in the filed approval records.
Building count and floorsOne residential apartment building; 1 stilt + 5 upper floors in both approval records.
Parking provision in approval recordThe municipal permit records Parking Area Built up Area (Sqm.) 253.46. A sanctioned space count and unit-wise parking allocations are not disclosed in the reviewed material.
Unit counts10 units listed in the RERA filing; the approved-plan summary records 1 total building unit. The supplied records do not explain that difference. RERA unit table RERA filing

Offering and status

ItemProject record
RERA-filed configuration3BHK; 10 units. RERA unit table
RERA-filed saleable area126.71 sq. m per listed 3BHK configuration. RERA unit table
Booked / available0 booked / 10 available, as last read from the TG-RERA portal; the portal record supplied here has no as-of date, so counts are indicative. RERA unit table
Proposed completion07/05/2028 in the project filing. RERA record RERA filing
Completion dates in filed recordsThe Form B declaration states 07 January 2028; the municipal permit states construction to be completed before 10.05.2028.
Occupancy / completion certificateNo issued occupancy or completion certificate is identified in the reviewed project records. The municipal permit says an occupancy certificate is compulsory before occupation and requires a completion notice to obtain it.

2. The project story

  • NEERA ENCLAVE is a registered residential apartment project on Plot No. 65 in Dulapally, on land identified in the project record as Survey No. 142 PART. The approvals describe one residential building with a stilt level and five upper floors. The RERA filing lists ten 3BHK units, and the supplied portal snapshot indicates that all ten were available and none booked when its inventory was read; that snapshot is undated. RERA record Land records RERA unit table
  • The project is recorded as a new project, but the material supplied does not provide an independently verified construction-stage assessment or site inspection. The completion date, registration validity and occupancy status are separate matters: the project filing gives a proposed completion date, the registration certificate remains valid through 07/01/2028, and no issued occupancy certificate is present in the reviewed documents. RERA record Document index

3. Master plan, architecture & building design

  • The HMDA technical approval describes a residential building, PRO BLG (1), on an approved extent of 448.39 Sq. Mt., with 1 stilt + 5 upper floors. The local building permit likewise identifies one residential apartment building and records a site area of 448.39.
  • The approval records contain more than one built-up-area figure: HMDA lists Built up Area 1267.3, Total Built up Area (In Sq.mts) 1520.76 and Proposed Built-up Area 1520.76; the municipal permit lists Built up Area (Sqm.) 1267.3. These labels and figures are reproduced as recorded, without treating them as interchangeable area measures.
  • The approved floor-plan drawing is identified as a typical floor plan. It supports a software measurement of one 3BHK design, but the supplied material does not establish the number of flats on each floor, building footprint, tower orientation, lift and stair count, or a full circulation arrangement. The RERA-filed amenities schedule lists internal roads and footpaths, green strip/tot lot/park and aggregate recreational open space, but gives no progress percentage above 0 for those entries. RERA amenities

4. Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
3BHK10010126.71 sq. m84.1 sq. m (software-measured from drawing; needs review)34%
  • The RERA filing records the 3BHK count, booking status and saleable area; its inventory read has no stated as-of date. The carpet-area figure is measured by software from the typical-floor-plan drawing, is not a RERA-filed measurement, and should be checked against the drawing. Saleable area and carpet area are different measures; the supplied drawing analysis also identifies balcony and utility areas separately from the measured carpet area. RERA unit table Floor plans RERA unit details
  • The drawing measurement covers one flat design, labelled flat 02. The listed rooms include a hall, kitchen, three bedrooms and three toilets; it also shows a sit-out, a 1.81M UTILITY and a 1.73M BALCONY. The supplied room dimensions are drawing-derived measurements, not RERA disclosures. RERA unit details

5. Parking & vehicle circulation

  • The municipal building-permit record lists 253.46 sq. m as parking-area built-up area and the HMDA approval states that the stilt/cellar is to be used exclusively for vehicle parking, without partition walls or rolling shutters and not to be converted. The HMDA approval also says no parking or construction is to be made in setback areas. These are approval-record provisions, not evidence of completed parking.
  • A number of parking spaces, visitor or accessible bays, two-wheeler provision, EV charging, ramp details and unit-specific parking allocations are not established in the supplied records. A drawn or designated parking area does not by itself establish exclusive ownership or allocation to a particular apartment.

6. Amenities, recreation & open spaces

The RERA-filed amenities schedule lists the following items. It records availability as “YES” for water supply and sewerage, while the other listed entries show 0 progress in the supplied schedule; no independent completion verification is provided. RERA amenities

Clubhouse / indoor
Description / sizeNo clubhouse or indoor facility is identified in the RERA-filed amenities schedule.
Evidence sourceRERA amenities
Declared progress / verified statusNot established in the RERA schedule
Sports / recreation
Description / sizeGreen Strip/TOT LOT/Park; aggregate area of recreational open space. No sizes supplied.
Evidence sourceRERA amenities
Declared progress / verified statusEach listed at 0; completion not independently verified
Landscape / open space
Description / sizeGreen strip/tot lot/park; internal roads and footpaths; street lighting. No sizes supplied.
Evidence sourceRERA amenities
Declared progress / verified statusEach listed at 0; completion not independently verified
Convenience / community
Description / sizeCommunity buildings; solid waste management and disposal. No sizes or capacities supplied.
Evidence sourceRERA amenities
Declared progress / verified statusEach listed at 0; completion not independently verified

7. Utilities, building services & safety

  • The RERA-filed amenities schedule marks Water Supply and Sewerage (Chamber, Lines, Septic Tank, STP) as “YES,” but records 0 progress for both; it does not identify the water source, storage capacity, treatment plant capacity or present operating status. It also lists storm-water drains, treatment and disposal of sewage and sullage water, solid-waste management and disposal, rainwater harvesting, energy management, fire protection, and an electrical meter room/sub-station/receiving station, each with 0 progress in the supplied schedule. RERA amenities
  • The filed approvals specify rainwater-harvesting structures, a garbage house and ETP; the HMDA approval additionally requires a transformer. Its conditions include separate underground and terrace tanks of 25,000 lts. each, a generator, emergency lighting in common passages and staircases, fire extinguishers, a manual alarm system, hose reel and down corner. These are approval conditions, not confirmation that systems have been installed or tested.
  • The municipal permit requires an occupancy certificate before occupation and states that public water-supply and electricity connections will be provided only on production of that certificate. The reviewed documents do not establish lift count or capacity, CCTV or security systems, accessibility provisions, or completion and commissioning of the listed services. RERA amenities

8. Location, access & connectivity

  • The registered location is Dulapally, Dundigal Gandimaisamma, Medchal-Malkajgiri, Telangana 500014. The RERA filing records 40 Feet Wide Roads on the site’s north and west boundaries. A supplied location record lists the nearest sampled Outer Ring Road interchange at approximately 9.4 km; no travel time is supplied. RERA record RERA filing Location record
  • The reviewed material does not provide a verified public-transport route, neighbourhood landmark distances, or road-access travel times. Location record

9. Developer & development status

  • The registered promoter is SHIVA SHAKTI CONSTRUCTIONS, identified in the project filing as a partnership. Its supplied corporate identifier is GSTIN 36ACCFS5751L3ZO. The RERA record gives the promoter address as SRI SIVA SAI NIVAS, RAJEEV NAGAR, Dulapally, Dulapally, Dundigal Gandimaisamma, Medchal-Malkajgiri, 500014. No official website, contact telephone or email is provided in the reviewed project data. Corporate record Parties record RERA filing RERA filing
  • The RERA filing records one landowner, RAMESH DAMISETTY, and an area-share arrangement. The Form B declaration identifies him as landowner and refers to a development agreement-cum-GPA as the basis for the development arrangement. Parties record
  • The project’s supplied status is “New Project”; the record does not include independently verified construction progress. The promoter’s Form B declaration gives 07 January 2028 as its completion undertaking; the registration certificate is valid to 07/01/2028, and the municipality permit gives a completion-before date of 10.05.2028. No occupancy certificate is identified in the reviewed documents. RERA record Document index

10. Approvals, official records & documents

RecordSupplied evidence
TG-RERA registrationForm C certificate for NEERA ENCLAVE, registration P02200005348, issued 25/11/2022, valid through 07/01/2028.
HMDA technical approval047003/MED/R1/U6/HMDA/08072021, dated 07 January, 2022, for a residential building on Plot No. 65, Survey No. 142 PART, Dulapally.
Kompally Municipality building permitPermit.No.0002/2022, dated 11.05.2022; file Lr.No.1108/TP/KM/2022. It refers to the HMDA technical approval and states conditions including an occupancy certificate before occupation.
RERA Form B declarationPromoter affidavit for NEERA ENCLAVE identifying Ramesh Damisetty as landowner and stating a completion undertaking of 07 January 2028.
Typical floor-plan drawingRERA-filed layout-plan document 261847, used for software-measured 3BHK drawing analysis; the drawing measurement is not a RERA area disclosure.
Occupancy / completion certificateNo issued certificate is identified in the supplied project records. The municipality permit describes the process and requirement to obtain an occupancy certificate. Document index

The supplied approval records describe one approved building and the project’s principal HMDA and municipal permissions. A publicly reachable HMDA approved-layout lookup was unavailable in the supplied records; this does not establish an approval outcome either way. HMDA

Frequently asked questions

Is NEERA ENCLAVE registered with Telangana RERA?

Yes. NEERA ENCLAVE is registered with the Telangana Real Estate Regulatory Authority as P02200005348; the registration status is New Project.

Who is the developer of NEERA ENCLAVE?

The promoter named in the RERA registration is SHIVA SHAKTI CONSTRUCTIONS.

Where is NEERA ENCLAVE located?

NEERA ENCLAVE is in Dulapally, Dundigal Gandimaisamma, Medchal-Malkajgiri, Telangana (500014).

When will NEERA ENCLAVE be completed?

The promoter's proposed date of completion filed with RERA is 07/05/2028. This is the promoter's declaration, not a guarantee.