ONEWEST is a commercial project in Nanakramguda, Serilingampally Mandal, Ranga Reddy District, developed by the registered promoter Terminus KG Ventures Pvt Ltd. The registered site area is 10,964.13 sq. m, and the project comprises one building with 3Cellar + Stilt + Ground + 21 floors. The RERA unit table records 82 OFFICE units, 207 HOTEL entries and 3 GYMNASIUM entries; filed saleable-area figures are 767.0 sq. m for OFFICE, 59.54 sq. m for HOTEL and 375.0 sq. m for GYMNASIUM. It is registered under TG-RERA number P02400000497, with a proposed completion date of 20/04/2021.

01What we found

Period endedTG-RERA registration ran to 20 Apr 2021 - check its extension on TG-RERA
17documents on file - each fact links to its page
0court cases on this project's land in the court records searched
9items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

9 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Photo from prophunt.ai

Project at a glance

Project identity

FieldRecord
Registered project nameONEWEST RERA record
Project typeThe registration record classifies it as commercial; project documents describe an office-and-hotel or mixed-use development. RERA record RERA filing
Phase / registered portionNo separate phase name is stated. Registration is for ONEWEST; the certificate identifies plot “88E/88AA.”
TG-RERA registrationP02400000497
Registration validity18/03/2019 to 20/04/2021, as recorded on the Form C certificate. Registration validity is distinct from the project completion date and OC status.
Registered promoterTerminus KG Ventures Pvt Ltd
RERA statusThe project record labels it “On-Going Project.” The supplied certificate records the registration period above; no extension is recorded in that certificate. RERA filing

Land and geographic identity

FieldRecord
LocalityNanakramguda / Nanakaramguda, as written in the RERA and filed project records RERA record RERA filing
Revenue villageNanakramguda Village; also recorded as Nanakaramguda in the registration record Land records
Mandal / districtSerilingampally / Ranga Reddy RERA record
PIN500008 in the project header and certificate RERA record
Survey numbers88/E and 88/AA in the GHMC permit, OC and environmental-clearance records; the registration certificate records 88E/ 88AA.
Registered site extent and areaTotal area: 10,964.13 sq. m; road-affected area: 1,502.34 sq. m; net area: 9,461.79 sq. m in the project land record. Land records
Boundaries in RERA land recordEast: ORR Service Raod; West: 100 Feet Road; North: Private property; South: 80 Feet Road. RERA filing
Additional survey number in OC documentThe supplied OC extraction also lists S.Y NO.133; its relationship to the RERA-recorded project parcel is not described in the extraction.

Development identity

FieldRecord
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC)
Principal building-permit approvalApproval No. 1/C11/06585/2018, dated 30 April, 2018 Approvals record
RERA-filed plan approval number1/C20/10586/2020 RERA record RERA filing
Approved built-up areaGHMC OC extraction records floor area of 85,626.6 m² as per sanctioned plan and 85,626.58 m² as per site building plan. The environmental-clearance order separately states total built-up area of 1,19,303.0 Sq.m.
Building countRERA land details record one total and proposed building unit. RERA filing
Building formGHMC building permit: 3Cellar + Stilt + Ground + 21 floors. The OC extraction records 3 Celler+3 Stilt Ground Floor+21 Upper Floor for both sanctioned plan and site building plan.
Parking provision recorded in documentsThe permit identifies cellar and stilt areas for parking; the OC extraction records 43,180.6 m² sanctioned parking area and 43,180.56 m² as per site building plan. The environmental-clearance order states parking for about 1070 four wheelers and 75 two wheelers.
Unit countsRERA unit table: 82 OFFICE units and 207 HOTEL units; it also lists 3 GYMNASIUM entries. The normalised filing summary treats the 207 HOTEL entries as unclassified and the gymnasium entries as common-area/non-sale rows. RERA unit details RERA unit table

Offering and status

FieldRecord
Filed offeringOffice units and entries filed as HOTEL; the unit table also contains GYMNASIUM rows. RERA unit details RERA unit table
Filed office counts82 units; 59 booked and 23 available in the portal reading supplied. RERA unit details
Filed HOTEL counts207 units; 0 booked and 207 available in the portal reading supplied. The project filing labels them “HOTEL”; the supplied record does not establish their precise unit configuration. RERA unit details
Filed size figuresOFFICE: 767.0 sq. m; HOTEL: 59.54 sq. m; GYMNASIUM: 375.0 sq. m. These are RERA-filed saleable-area figures as provided in the unit data. RERA unit table RERA unit details
Booking-count contextBooked and available counts are a portal reading with no as-of date supplied; treat them as indicative. RERA unit table
Construction stageThe RERA record labels the project “On-Going Project.” No independently verified current construction-progress assessment is supplied. RERA filing
Completion datesOriginal and revised proposed completion dates are both 20/04/2021 in the RERA record. RERA record RERA filing
Occupancy-certificate status and scopeA GHMC Occupancy Certificate extraction is supplied for the commercial building named PROPOSED (ONE WEST), with survey numbers 88/E and 88/AA and the additional survey identifier S.Y NO.133; it records completion date 03 May, 2021 and approval date 12 June, 2021.

The project story

ONEWEST is a single-building commercial project in Nanakramguda, Serilingampally, registered under TG-RERA number P02400000497. The RERA project type is commercial, while the project-specific GHMC and environmental documents describe an office-and-hotel or mixed-use development. The building permit identifies 3Cellar + Stilt + Ground + 21 floors; the supplied OC extraction describes the building as 3 Celler+3 Stilt Ground Floor+21 Upper Floor. RERA record

The filed unit table records 82 OFFICE entries and 207 HOTEL entries, plus 3 GYMNASIUM entries. The RERA normalisation identifies the gymnasium rows as common-area/non-sale entries and leaves the HOTEL rows unclassified as a unit configuration; these labels should therefore be read as filing labels, not as independently confirmed descriptions of individual spaces. RERA unit table RERA unit details RERA unit table

The RERA record lists a proposed completion date of 20/04/2021. The supplied GHMC OC extraction records that the building was completed on 03 May 2021 and gives an OC approval date of 12 June 2021. These are documentary records for the building identified in that certificate; no independent inspection of its present physical condition is included here. RERA record

Master plan, architecture & building design

The RERA land record gives a total project area of 10,964.13 sq. m, an affected road area of 1,502.34 sq. m, and a net area of 9,461.79 sq. m. The GHMC permit describes a single office-and-hotel building and gives a height of 84.8 m; the OC extraction records a height of 101 m. Land records

The permit describes the building as 3Cellar + Stilt + Ground + 21 floors and lists 3,226.85 m² commercial ground-floor area, 80,253.56 m² commercial upper-floor area, 22,797.71 m² cellar parking, 1,143.72 m² ground/upper-floor parking, and 4,794.83 m² stilt parking. It also records a 982.59 m² tot-lot. The OC extraction records 85,626.6 m² floor area as sanctioned and 85,626.58 m² as per the site building plan. These are document-specific area descriptions and should not be treated as interchangeable area measures.

The environmental-clearance order describes the project as a mixed-use development for office space and hotel facility, with a stated configuration of 3B + G + 22 Floors. It also states 1,19,303.0 Sq.m. total built-up area and identifies a green area of 983.31 Sq.m.

The permit lists setbacks of Side I 11.69, Side II 17.5, Front 11, and Rear 20.31; the OC extraction records front 17.46 m, rear 20.31 m, side-1 11.00 m, and side-2 11.46 m.

Floor-plan review data reports two drawings, but no drawings are recorded as measured and both are marked as having no flats. Accordingly, no drawing-derived room dimensions, carpet areas, circulation details, or typical-floor arrangements are available in the supplied measurement data. Floor plans

Homes, configurations & floor plans

The project is recorded as commercial. Its unit table uses the labels OFFICE, HOTEL and GYMNASIUM. The supplied normalised RERA data identifies the OFFICE entries as commercial units, the HOTEL entries as an unclassified configuration, and the GYMNASIUM entries as non-sale/common-area rows. RERA unit details RERA unit table RERA unit table

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
OFFICE (commercial units)825923767.0 sq. mNot measured in supplied floor-plan dataNot supplied RERA unit details Floor plans
HOTEL (filed label; configuration unclassified)207020759.54 sq. mNot measured in supplied floor-plan dataNot supplied RERA unit details Floor plans

The filing also includes 3 GYMNASIUM entries, with 2 booked and 1 available, each with a filed saleable-area figure of 375.0 sq. m. The normalised record identifies this row as a common-area/non-sale entry, so it is not presented as an offering configuration above. RERA unit table RERA unit table

No carpet-area measurements were produced from the supplied floor-plan data. The supplied measurement note distinguishes software-measured carpet area from RERA-filed saleable area; no measured figures are available to report here. Floor plans

Parking & vehicle circulation

The GHMC permit states that cellar and stilt areas approved for parking are to be used exclusively for vehicle parking. It lists 22,797.71 m² of cellar parking, 4,794.83 m² of stilt parking and 1,143.72 m² of ground/upper-floor parking.

The GHMC OC extraction records parking area of 43,180.6 m² as per sanctioned plan and 43,180.56 m² as per the site building plan. The environmental-clearance order states that the proposal provides for about 1070 four wheelers and 75 two wheelers. These are document-recorded provisions; no unit-wise parking allocation or exclusive parking entitlement is supplied.

The permit’s building-plan affidavit refers to a 3.0 MTS. WIDE DRIVEWAY and a 9.0 MTS. WIDE CRAVEWAY. The supplied record does not provide a parking-bay schedule, accessible or visitor space count, EV charging provision, or confirmed current parking status.

Amenities, recreation & open spaces

The permit and environmental-clearance order identify the following facilities or site provisions. The RERA amenities table also lists facilities, but its progress entries are 0; these entries do not establish completion. RERA amenities

Tot-lot
Description / sizePermit: 982.59 m²; OC extraction: 967.3 m²
Declared progress / verified statusRequired by permit to be fenced and maintained as greenery before OC; present condition not independently verified.
Green area
Description / size983.31 Sq.m. in environmental-clearance order
Declared progress / verified statusOrder requires green area of at least 10% of site area to be developed and maintained; delivered status not independently verified.
Green strip / tot-lot / park
Description / sizeListed as available in RERA amenities table; progress 0
Evidence sourceRERA amenities
Declared progress / verified statusRERA-listed; progress entry is 0, completion not established.
Internal roads and footpaths
Description / sizeListed as available in RERA amenities table; progress 0
Evidence sourceRERA amenities
Declared progress / verified statusRERA-listed; progress entry is 0, completion not established.
Community buildings
Description / sizeListed in RERA amenities table; no “available” value shown; progress 0
Evidence sourceRERA amenities
Declared progress / verified statusFiling entry only; no completion status supplied.

No separately evidenced clubhouse, indoor sports or recreation facility is described in the supplied project records. The GYMNASIUM rows in the unit table are treated as common-area/non-sale entries, but no further description or delivered-status evidence is supplied. RERA unit table RERA unit table

Utilities, building services & safety

ServiceSupplied evidence
WaterThe environmental-clearance order states occupational-stage water requirement of 608.15 KLD, comprising 383.07 KLD fresh water and 225.08 KLD treated recycled wastewater. The RERA amenities table lists water supply, but shows progress 0. RERA amenities
Sewerage and wastewaterThe environmental-clearance order specifies sewage generation of 264.80 KLD and an STP of 275.0 KLD capacity; it requires an independent expert’s certification of STP installation before commissioning. The permit requires an ETP and the RERA amenities table lists sewerage and sewage/sullage treatment, each with progress 0. The supplied record does not establish current installation or operating status. RERA amenities
Rainwater managementThe permit requires a rainwater-harvesting structure (percolation pit) and records 17 rainwater-harvesting points; the RERA amenities table lists rainwater harvesting with progress 0. RERA amenities
ElectricalThe permit requires space for a transformer; the RERA amenities table lists an electrical meter room, sub-station and receiving station, with progress 0. No capacity or completed-status evidence is supplied. RERA amenities
Emergency powerThe environmental-clearance order lists 4 x D.G. sets for emergency supply. No capacity or commissioning status is supplied.
Fire and life safetyFire protection and fire-safety requirements are listed in the RERA amenities table with progress 0. No fire-clearance certificate or project-specific fire-system details are supplied here. RERA amenities
WasteThe permit requires a garbage house. The environmental-clearance order estimates garbage at 865.13 kg/day and STP sludge at 20.0 kg/day, and lists an MSW segregation point. The RERA table lists solid-waste management and disposal but supplies no “available” value and shows progress 0. RERA amenities
Lifts, accessibility and securityLift details, accessibility arrangements, CCTV, access control and security-system specifications are not supplied.

Location, access & connectivity

The RERA location is Nanakramguda / Nanakaramguda, Serilingampally Mandal, Ranga Reddy District, PIN 500008. The RERA land record gives the site boundaries as ORR Service Raod to the east, a 100 Feet Road to the west, private property to the north and an 80 Feet Road to the south. RERA record RERA filing

The project-specific permit records road widths of 18 mt.; the building-plan affidavit also refers to an 80-foot-wide road (24M) and a 100-foot-wide road (30M), together with driveway and “CRAVEWAY” entries.

The supplied location dataset lists these distances: Financial District (Nanakramguda), 1.1 km; ICICI Bank, 0.1 km; an unnamed bus station, 1.7 km; Maulana Azaad National Urdu University, 1.5 km; Continental Hospitals, 1.4 km; Accenture Services Private Limited, 0.5 km; South india shopping mall, 2.4 km; an unnamed park, 1.4 km; and Nanakramguda Govt primary school, 0.0 km. These are location-dataset distances; no travel times are supplied. Location record

Developer & development status

The registered promoter is Terminus KG Ventures Pvt Ltd, identified in the project record as a company. The corporate record gives CIN U93030MH2012PTC228435. RERA record Corporate record

The RERA filing gives the promoter address as SLN TERMINUS, KODAPUR GACHIBOWLI ROAD, Sri Ram Universal school Road, Nanakramguda, Serilingampally, Ranga Reddy, 500008. The registration certificate separately records the promoter office as Village: Gachi Bowli, Mandal: Serilingampally, District: Ranga Reddy, PIN 500032. Parties record

The promoter’s website is listed as https://www.terminus-group.com; no individual official project contact details are supplied in the evidence. Parties record

The RERA record states original and revised completion dates of 20/04/2021 and labels the project on-going. The supplied GHMC OC extraction records a completion date of 03 May, 2021 and an OC dated 12 June, 2021 for the building identified as PROPOSED (ONE WEST). No current, independently verified construction-progress figure is supplied. RERA record RERA filing

Approvals, official records & documents

RecordSupplied evidence
TG-RERA registrationForm C certificate for ONEWEST, registration P02400000497, issued 18/03/2019, valid to 20/04/2021.
GHMC building permitApproval No. 1/C11/06585/2018, dated 30 April, 2018, for ONE WEST (OFFICE AND HOTEL), Survey Nos. 88/E and 88/AA.
RERA-filed plan reference1/C20/10586/2020, recorded in the project information. RERA filing
GHMC occupancy certificateApproval No. 1/C20/07446/2021, application No. 1/C20/08126/2021-OC; the extraction records completion on 03 May, 2021 and approval on 12 June, 2021 for PROPOSED (ONE WEST).
Environmental clearanceSEIAA Telangana order SEIAA/TS/OL/RRD-177/2017-3 93, dated 22.12.2017, for the One West mixed-use development at Survey Nos. 88/E and 88/AA.
GHMC mortgage affidavitAnnexure-II affidavit concerning the project and a stated 15.01% mortgage of 11,963.00 square meters of built area in favour of the Commissioner, GHMC.
Promoter RERA declarationForm B affidavit by S. Prabhaker Reddy on behalf of the promoter, dated 05.10.2018; it declares the project land free from encumbrances and describes a title report and development-agreement materials as the title basis. This is a promoter declaration.
Title reports and agreement templateProject-filed title-investigation reports include KVCMS Sarma’s report dated 5-5-2018 and an Annexure-B report by Lakshmi Koduri; a partially completed Telangana RERA-form Agreement for Sale is also on file.

Frequently asked questions

Is ONEWEST registered with Telangana RERA?

Yes. ONEWEST is registered with the Telangana Real Estate Regulatory Authority as P02400000497; the registration status is On-Going Project.

Who is the developer of ONEWEST?

The promoter named in the RERA registration is Terminus KG Ventures PVT LTD.

Where is ONEWEST located?

ONEWEST is in Nanakramguda, Nanakaramguda, Serilingampally, Rangareddy, Telangana (500008).

When will ONEWEST be completed?

The promoter's proposed date of completion filed with RERA is 20/04/2021. This is the promoter's declaration, not a guarantee.

More projects in Nanakaramguda