SIKHARA s NANDANAVANAM
SIKHARA BUILDERS · Rangareddy · RERA P02400010333
SIKHARA s NANDANAVANAM is a residential apartment project at Plot No. 106/F, Category-HIG of Nallagandla HUDA Residential Complex, Nallagandla, Serilingampally mandal, Ranga Reddy district. The registered promoter is SIKHARA BUILDERS. The project has a registered site extent of 432.0 sq. m and one residential building with 1 Stilt + 5 Floors, comprising 10 3BHK apartments with a RERA-filed saleable area of 146.78 sq.m. Its TG-RERA registration number is P02400010333, and the proposed completion date is 21/03/2029.
More from Sikhara Builders · 2 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
10 items to check before you pay, 2 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Project record |
|---|---|
| Registered project name | SIKHARA s NANDANAVANAM RERA record |
| Project type / status | Residential apartment project; TG-RERA filing classifies it as a New Project. RERA record |
| Phase / registered portion | No separate phase name or phase number is disclosed. The registration and building-permit records describe the Plot No. 106/F development. RERA record |
| TG-RERA registration | P02400010333. RERA record |
| Registration validity | 21/11/2025 to 21/11/2028; this is the registration-validity period, not the project’s completion date. RERA record |
| Registered promoter | SIKHARA BUILDERS. RERA record Corporate record |
| RERA status | The project is registered. TG-RERA registration was captured on 2026-09-10; no construction-progress percentage is supplied here. Approvals record |
Land and geographic identity
| Field | Project record |
|---|---|
| Locality / site description | Plot No. 106/F, Category-HIG of Nallagandla HUDA Residential Complex. RERA filing |
| Revenue village | Nallagandla (also rendered NALLAGANDLA in the building-permit and plan records). |
| Mandal / district / PIN | Serilingampally / Ranga Reddy / 500019. |
| Project survey numbers | 302 TO 310, 320 TO 322, 324 TO 361, 363 TO 365, 384, 385, 387 TO 391 AND 399. Land records |
| Subdivisions | No survey subdivisions are specified in the TG-RERA project identity or cited approval records. Land records |
| Registered site extent | 432.0 sq. m; the building-permit record also gives net plot area as 432.0 sq. m. RERA filing |
| Boundaries | Not stated in the supplied project record. Land records |
Development identity
| Field | Project record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC). |
| Principal building-permit number / date | Approval No. 1894/GHMC/SWBP/SLP2/2025, approved 21/11/2025; the permit also identifies File No. 005603/GHMC/02758/SWBP/SLP2/2025. Approvals record |
| Approved building / floors | One residential building: 1 Stilt + 5 Floors. |
| Height stated in permit | The permit’s sanctioned parameters state Height of the Building (m) 14.99; the plan extraction separately records Height from GL: 17.99 m, Total Height: 20.99 m, and Excluding Stilt: 14.99 m. |
| Approved built-up area | Plan records state Net BUA: 1187.50 sq.m and Gross BUA: 1449.36 sq.m. The plan extraction also reports proposed BUA excluding parking of 1187.5 sq.m and including parking of 1425.0 sq.m. These are separately labelled figures in the filed records. |
| Parking provision in plan | 237.50 sq.m parking area; the plan extraction records Car Parking Spaces 4.00. |
| Approved versus RERA-declared units | GHMC permit: 10 dwelling units. TG-RERA unit record: 10. RERA unit table |
Offering and status
| Field | Project record |
|---|---|
| Unit type | 3BHK apartments. RERA unit table |
| RERA-filed saleable area | 146.78 sq.m for the recorded 3BHK configuration. RERA unit table |
| Booked / available | 0 booked / 10 available, as last read from the TG-RERA portal; the portal record supplied here has no as-of date, so treat counts as indicative. RERA unit table |
| Construction stage | No independently verified site-progress information or construction-stage percentage is supplied. TG-RERA records the project as a New Project. RERA record RERA unit table |
| Completion dates | Promoter’s Form B undertaking gives 21-11-2028; the GHMC permit says construction is to be completed before 21/11/2028. TG-RERA’s proposed completion field states 21/03/2029. These are recorded separately here; the underlying date difference is not assessed in this Overview. RERA record |
| Occupancy / completion certificate | No occupancy or completion certificate is recorded in the supplied documents; the building permit records completion certification as false. |
2. The project story
SIKHARA s NANDANAVANAM is a registered residential apartment project on Plot No. 106/F in the Category-HIG section of the Nallagandla HUDA Residential Complex, Nallagandla village, Serilingampally mandal, Ranga Reddy district. The filed site extent is 432.0 sq. m. Its registered land description covers survey numbers 302 TO 310, 320 TO 322, 324 TO 361, 363 TO 365, 384, 385, 387 TO 391 and 399.
The GHMC building permit describes one residential building with a stilt and five floors, sanctioned for 10 dwelling units. TG-RERA records 10 3BHK units, with 0 booked and 10 available in the portal data supplied; the booking counts have no stated as-of date. RERA unit table
This is a proposed/registered development, not a project shown as completed or occupancy-certified in the documents reviewed. The supplied record does not establish the current construction progress through independent site verification. RERA record
3. Master plan, architecture & building design
The filed GHMC plan is for residential flats on a 432.0 sq. m plot. It records a proposed coverage area of 237.5 sq. m (55.00%), vacant plot area of 186.1 sq. m, and net plot area of 432.0 sq. m. The plan records proposed coverage and vacant area but does not provide a detailed, verified landscape or open-space design description in the supplied extraction.
The sanctioned arrangement is 1 Stilt + 5 Floors, with 1187.50 sq.m Net BUA and 1449.36 sq.m Gross BUA in the permit’s sanctioned parameters. The plan extraction separately reports 1187.5 as total proposed BUA excluding parking and 1425.0 as total proposed BUA including parking. These labels are retained as recorded; they are not treated as interchangeable area measures.
The plan identifies residential use and no commercial upper-floor area. It records required and proposed setbacks as: front 3.00 m, rear 2.50 m, side 1 2.50 m, and side 2 2.50 m. The plan lists a 9.0 m road width, while the building-permit extraction also records an 18 mt. road-width reference.
The supplied material does not establish detailed lift or stair counts, flats per floor, entrances and exits, internal circulation, or a full floor-by-floor unit arrangement. The permit requires the sanctioned plan to be followed and displayed at the construction site.
4. Homes, configurations & floor plans
The TG-RERA filing records 10 3BHK units, with a saleable area of 146.78 sq.m each as recorded in the configuration data. The unit count and booking availability are RERA-portal figures; the booking record has no as-of date. RERA unit table RERA unit details
The approved-plan drawing was software-measured for unit geometry. The measurement record covers four 3BHK flat designs and gives a median carpet area of 83.5 sq.m (898 sq.ft), with a range of 79.2–87.7 sq.m (853–944 sq.ft). These are software measurements from drawings, not RERA-filed carpet-area disclosures, and the drawing measurements are flagged as needing review. RERA unit details Floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 10 | 0 | 10 | 146.78 sq.m | Software-measured median 83.5 sq.m (898 sq.ft); range 79.2–87.7 sq.m (853–944 sq.ft) | 43% |
Carpet area is the software-measured internal floor-plan area reported above; the drawing-measurement record notes that it is smaller than saleable area, which also counts the home’s share of common areas. The available extraction identifies a balcony in one measured flat design but does not provide a complete, verified unit-by-unit balcony or room schedule for all 10 apartments. Floor plans RERA unit details
5. Parking & vehicle circulation
The building permit records 237.50 sq. m of parking area, and the sanctioned-parameters extraction lists Car Parking Spaces 4.00. The plan states that parking spaces in the stilt should be used exclusively for vehicle parking; the supplied material does not establish resident-versus-visitor allocation, accessible spaces, or a legally documented parking-space allocation to individual apartments.
The supplied records do not establish parking-ramp details, separate vehicle entry and exit arrangements, internal driveways, pedestrian separation, or two-wheeler parking counts. The permit requires electric-vehicle charging infrastructure in parking places, but the documents do not establish its installation or completion.
6. Amenities, recreation & open spaces
The GHMC plan and permit list certain site facilities and conditions. Separately, the TG-RERA amenity record identifies proposed project amenities and reports 0% progress for each listed item. “Available: YES” in that record is a filed availability field, not evidence that the facility has been completed. RERA amenities
| Description / size | Permit extraction records Tot Lot (Sq. Mtrs) 0; the plan also requires the tot-lot to be fenced and maintained as greenery. |
|---|---|
| Declared progress / verified status | Plan condition; no completion evidence supplied. |
| Description / size | Listed in the TG-RERA amenity record. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | 0% recorded; completion not independently verified. |
| Description / size | Listed as available in the TG-RERA amenity record. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | 0% recorded; no completed-facility evidence supplied. |
| Description / size | Listed in the TG-RERA amenity record. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | 0% recorded. |
| Description / size | Listed as available in the TG-RERA amenity record. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | 0% recorded. |
| Description / size | Permit records 1 rainwater-harvesting pit; the plan requires a rainwater-harvesting structure (percolation pit). |
|---|---|
| Declared progress / verified status | Required/provided for in the plan; completion not independently verified. |
| Description / size | These appear in third-party vendor listing data, not in the supplied TG-RERA amenity record. |
|---|---|
| Evidence source | Promoter website |
| Declared progress / verified status | Not treated as RERA-declared, sanctioned or delivered facilities in this Overview. |
7. Utilities, building services & safety
The plan lists a rainwater-harvesting percolation pit, transformer space, garbage house, septic tank, soak pit and sump. The GHMC permit extraction records 1 rainwater-harvesting pit and 15 trees. These are plan or permit provisions, not confirmation that they have been installed.
The TG-RERA amenity record lists water supply, sewerage (including chamber, lines, septic tank and STP), storm-water drains, sewage and sullage treatment/disposal, solid-waste management and disposal, energy management, fire protection and safety, and an electrical meter room/sub-station/receiving station. Each item in that record shows 0% progress; no capacities or independent completion verification are supplied. RERA amenities
The building permit requires fire-safety measures and an Occupancy FIRE NOC from the Director (EV&DM) before issue of the occupancy certificate. It also requires an occupancy certificate before occupation, requires parking places to have electric-vehicle charging infrastructure, and includes conditions concerning construction safety and services. These are permit conditions; the supplied records do not establish that the corresponding installations, clearances or certificates have been completed.
The provided evidence does not specify water-source capacity, storage capacity, STP capacity, generator/backup capacity, lift count or capacity, CCTV or access-control installation, accessible circulation, or the status of statutory fire clearances. RERA amenities
8. Location, access & connectivity
The registered location is Plot No. 106/F, Category-HIG of Nallagandla HUDA Residential Complex, Nallagandla village, Serilingampally mandal, Ranga Reddy district, PIN 500019. The project location record provides a cadastral parcel centroid at 17.469434085454374, 78.30876146862201. Location record
The location data records the nearest sampled Outer Ring Road interchange at approximately 6.4 km. This is a supplied mapped distance, not a travel-time estimate. The available project-specific location evidence does not provide an approach-road description, public-transport route, or verified distances to other landmarks. Location record
9. Developer & development status
The TG-RERA-registered promoter is SIKHARA BUILDERS, identified in the filing as a Partnership. Its GSTIN is 36AFBFS6239K1ZM. The promoter address in the project record is APARNA SAROVAR ZENITH, NALLAGANDLA, NALLAGANDLA, CATEGORY-HIG OF NALLAGANDLA HUDA RESIDENTIAL COMPLEX, Serilingampally, Ranga Reddy, 500019. No official website or project contact details are supplied in the reviewed record. Corporate record Parties record
The permit identifies SUMANTHA SAI CONSTRUCTIONS as developer/builder; the supplied record does not establish that entity as the registered RERA promoter.
The project is registered for one residential building and 10 units. The promoter’s Form B declaration undertakes completion by 21-11-2028; the GHMC permit states construction is to be completed before 21/11/2028. No independently verified construction-progress percentage is supplied, and no occupancy or completion certificate is present in the documents reviewed.
10. Approvals, official records & documents
| Identifier / scope | P02400010333; SIKHARA s NANDANAVANAM; Nallagandla site and survey numbers. |
|---|---|
| What it establishes in the supplied record | Registration validity 21/11/2025–21/11/2028. |
| Identifier / scope | File No. 005603/GHMC/02758/SWBP/SLP2/2025; Plot No. 106/F. |
|---|---|
| What it establishes in the supplied record | Permit for one residential building, 1 Stilt + 5 Floors, and 10 dwelling units; approved 21/11/2025. |
| Identifier / scope | Approval No. 1894/GHMC/SWBP/SLP2/2025. |
|---|---|
| What it establishes in the supplied record | Plan for proposed residential flats on the stated 432.0 sq. m site; includes the plan’s area and parking figures and listed conditions. |
| Identifier / scope | 10186/2025, dated 31/10/2025. |
|---|---|
| What it establishes in the supplied record | Permit record identifies a mortgage of 119.17 sq. m on the fifth floor. |
| Identifier / scope | SIKHARA BUILDERS; signed by YAKANARAYANA MAKINENI as authorised signatory. |
|---|---|
| What it establishes in the supplied record | Contains the promoter’s title-basis and encumbrance declarations, fund-management statements, and completion undertaking. |
| Identifier / scope | Not supplied in the reviewed documents. |
|---|---|
| What it establishes in the supplied record | The permit extraction records completion certification as false; no OC or completion certificate is evidenced here. |
The permit states that the permission does not confer ownership rights and requires an occupancy certificate before occupation. This overview identifies the filed records; it does not independently verify construction progress, installed services or certificate issuance.
1. Project at a glance
Project identity
Registered project name: SIKHARA s NANDANAVANAM
Project type / status: Residential apartment project; TG-RERA filing classifies it as a New Project.
Phase / registered portion: No separate phase name or phase number is disclosed. The registration and building-permit records describe the Plot No. 106/F development.
TG-RERA registration: P02400010333.
Registration validity: 21/11/2025 to 21/11/2028; this is the registration-validity period, not the project’s completion date.
Registered promoter: SIKHARA BUILDERS.
RERA status: The project is registered. TG-RERA registration was captured on 2026-09-10; no construction-progress percentage is supplied here.
Land and geographic identity
Locality / site description: Plot No. 106/F, Category-HIG of Nallagandla HUDA Residential Complex.
Revenue village: Nallagandla (also rendered NALLAGANDLA in the building-permit and plan records).
Mandal / district / PIN: Serilingampally / Ranga Reddy / 500019.
Project survey numbers: 302 TO 310, 320 TO 322, 324 TO 361, 363 TO 365, 384, 385, 387 TO 391 AND 399.
Subdivisions: No survey subdivisions are specified in the TG-RERA project identity or cited approval records.
Registered site extent: 432.0 sq. m; the building-permit record also gives net plot area as 432.0 sq. m.
Boundaries: Not stated in the supplied project record.
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC).
Principal building-permit number / date: Approval No. 1894/GHMC/SWBP/SLP2/2025, approved 21/11/2025; the permit also identifies File No. 005603/GHMC/02758/SWBP/SLP2/2025.
Approved building / floors: One residential building: 1 Stilt + 5 Floors.
Height stated in permit: The permit’s sanctioned parameters state Height of the Building (m) 14.99; the plan extraction separately records Height from GL: 17.99 m, Total Height: 20.99 m, and Excluding Stilt: 14.99 m.
Approved built-up area: Plan records state Net BUA: 1187.50 sq.m and Gross BUA: 1449.36 sq.m. The plan extraction also reports proposed BUA excluding parking of 1187.5 sq.m and including parking of 1425.0 sq.m. These are separately labelled figures in the filed records.
Parking provision in plan: 237.50 sq.m parking area; the plan extraction records Car Parking Spaces 4.00.
Approved versus RERA-declared units: GHMC permit: 10 dwelling units. TG-RERA unit record: 10.
Offering and status
Unit type: 3BHK apartments.
RERA-filed saleable area: 146.78 sq.m for the recorded 3BHK configuration.
Booked / available: 0 booked / 10 available, as last read from the TG-RERA portal; the portal record supplied here has no as-of date, so treat counts as indicative.
Construction stage: No independently verified site-progress information or construction-stage percentage is supplied. TG-RERA records the project as a New Project.
Completion dates: Promoter’s Form B undertaking gives 21-11-2028; the GHMC permit says construction is to be completed before 21/11/2028. TG-RERA’s proposed completion field states 21/03/2029. These are recorded separately here; the underlying date difference is not assessed in this Overview.
Occupancy / completion certificate: No occupancy or completion certificate is recorded in the supplied documents; the building permit records completion certification as false.
2. The project story
SIKHARA s NANDANAVANAM is a registered residential apartment project on Plot No. 106/F in the Category-HIG section of the Nallagandla HUDA Residential Complex, Nallagandla village, Serilingampally mandal, Ranga Reddy district. The filed site extent is 432.0 sq. m. Its registered land description covers survey numbers 302 TO 310, 320 TO 322, 324 TO 361, 363 TO 365, 384, 385, 387 TO 391 and 399.
The GHMC building permit describes one residential building with a stilt and five floors, sanctioned for 10 dwelling units. TG-RERA records 10 3BHK units, with 0 booked and 10 available in the portal data supplied; the booking counts have no stated as-of date.
This is a proposed/registered development, not a project shown as completed or occupancy-certified in the documents reviewed. The supplied record does not establish the current construction progress through independent site verification.
3. Master plan, architecture & building design
The filed GHMC plan is for residential flats on a 432.0 sq. m plot. It records a proposed coverage area of 237.5 sq. m (55.00%), vacant plot area of 186.1 sq. m, and net plot area of 432.0 sq. m. The plan records proposed coverage and vacant area but does not provide a detailed, verified landscape or open-space design description in the supplied extraction.
The sanctioned arrangement is 1 Stilt + 5 Floors, with 1187.50 sq.m Net BUA and 1449.36 sq.m Gross BUA in the permit’s sanctioned parameters. The plan extraction separately reports 1187.5 as total proposed BUA excluding parking and 1425.0 as total proposed BUA including parking. These labels are retained as recorded; they are not treated as interchangeable area measures.
The plan identifies residential use and no commercial upper-floor area. It records required and proposed setbacks as: front 3.00 m, rear 2.50 m, side 1 2.50 m, and side 2 2.50 m. The plan lists a 9.0 m road width, while the building-permit extraction also records an 18 mt. road-width reference.
The supplied material does not establish detailed lift or stair counts, flats per floor, entrances and exits, internal circulation, or a full floor-by-floor unit arrangement. The permit requires the sanctioned plan to be followed and displayed at the construction site.
4. Homes, configurations & floor plans
The TG-RERA filing records 10 3BHK units, with a saleable area of 146.78 sq.m each as recorded in the configuration data. The unit count and booking availability are RERA-portal figures; the booking record has no as-of date.
The approved-plan drawing was software-measured for unit geometry. The measurement record covers four 3BHK flat designs and gives a median carpet area of 83.5 sq.m (898 sq.ft), with a range of 79.2–87.7 sq.m (853–944 sq.ft). These are software measurements from drawings, not RERA-filed carpet-area disclosures, and the drawing measurements are flagged as needing review.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 10 | 0 | 10 | 146.78 sq.m | Software-measured median 83.5 sq.m (898 sq.ft); range 79.2–87.7 sq.m (853–944 sq.ft) | 43% |
Carpet area is the software-measured internal floor-plan area reported above; the drawing-measurement record notes that it is smaller than saleable area, which also counts the home’s share of common areas. The available extraction identifies a balcony in one measured flat design but does not provide a complete, verified unit-by-unit balcony or room schedule for all 10 apartments.
5. Parking & vehicle circulation
The building permit records 237.50 sq. m of parking area, and the sanctioned-parameters extraction lists Car Parking Spaces 4.00. The plan states that parking spaces in the stilt should be used exclusively for vehicle parking; the supplied material does not establish resident-versus-visitor allocation, accessible spaces, or a legally documented parking-space allocation to individual apartments.
The supplied records do not establish parking-ramp details, separate vehicle entry and exit arrangements, internal driveways, pedestrian separation, or two-wheeler parking counts. The permit requires electric-vehicle charging infrastructure in parking places, but the documents do not establish its installation or completion.
6. Amenities, recreation & open spaces
The GHMC plan and permit list certain site facilities and conditions. Separately, the TG-RERA amenity record identifies proposed project amenities and reports 0% progress for each listed item. “Available: YES” in that record is a filed availability field, not evidence that the facility has been completed.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Tot-lot / recreational open space | Permit extraction records Tot Lot (Sq. Mtrs) 0; the plan also requires the tot-lot to be fenced and maintained as greenery. | Plan condition; no completion evidence supplied. | |
| Green strip / tot-lot / park | Listed in the TG-RERA amenity record. | 0% recorded; completion not independently verified. | |
| Community buildings | Listed as available in the TG-RERA amenity record. | 0% recorded; no completed-facility evidence supplied. | |
| Internal roads and footpaths | Listed in the TG-RERA amenity record. | 0% recorded. | |
| Street lighting | Listed as available in the TG-RERA amenity record. | 0% recorded. | |
| Water conservation / rainwater harvesting | Permit records 1 rainwater-harvesting pit; the plan requires a rainwater-harvesting structure (percolation pit). | Required/provided for in the plan; completion not independently verified. | |
| Clubhouse, swimming pool, gym and children’s play area | These appear in third-party vendor listing data, not in the supplied TG-RERA amenity record. | Not treated as RERA-declared, sanctioned or delivered facilities in this Overview. |
7. Utilities, building services & safety
The plan lists a rainwater-harvesting percolation pit, transformer space, garbage house, septic tank, soak pit and sump. The GHMC permit extraction records 1 rainwater-harvesting pit and 15 trees. These are plan or permit provisions, not confirmation that they have been installed.
The TG-RERA amenity record lists water supply, sewerage (including chamber, lines, septic tank and STP), storm-water drains, sewage and sullage treatment/disposal, solid-waste management and disposal, energy management, fire protection and safety, and an electrical meter room/sub-station/receiving station. Each item in that record shows 0% progress; no capacities or independent completion verification are supplied.
The building permit requires fire-safety measures and an Occupancy FIRE NOC from the Director (EV&DM) before issue of the occupancy certificate. It also requires an occupancy certificate before occupation, requires parking places to have electric-vehicle charging infrastructure, and includes conditions concerning construction safety and services. These are permit conditions; the supplied records do not establish that the corresponding installations, clearances or certificates have been completed.
The provided evidence does not specify water-source capacity, storage capacity, STP capacity, generator/backup capacity, lift count or capacity, CCTV or access-control installation, accessible circulation, or the status of statutory fire clearances.
8. Location, access & connectivity
The registered location is Plot No. 106/F, Category-HIG of Nallagandla HUDA Residential Complex, Nallagandla village, Serilingampally mandal, Ranga Reddy district, PIN 500019. The project location record provides a cadastral parcel centroid at 17.469434085454374, 78.30876146862201.
The location data records the nearest sampled Outer Ring Road interchange at approximately 6.4 km. This is a supplied mapped distance, not a travel-time estimate. The available project-specific location evidence does not provide an approach-road description, public-transport route, or verified distances to other landmarks.
9. Developer & development status
The TG-RERA-registered promoter is SIKHARA BUILDERS, identified in the filing as a Partnership. Its GSTIN is 36AFBFS6239K1ZM. The promoter address in the project record is APARNA SAROVAR ZENITH, NALLAGANDLA, NALLAGANDLA, CATEGORY-HIG OF NALLAGANDLA HUDA RESIDENTIAL COMPLEX, Serilingampally, Ranga Reddy, 500019. No official website or project contact details are supplied in the reviewed record.
The permit identifies SUMANTHA SAI CONSTRUCTIONS as developer/builder; the supplied record does not establish that entity as the registered RERA promoter.
The project is registered for one residential building and 10 units. The promoter’s Form B declaration undertakes completion by 21-11-2028; the GHMC permit states construction is to be completed before 21/11/2028. No independently verified construction-progress percentage is supplied, and no occupancy or completion certificate is present in the documents reviewed.
10. Approvals, official records & documents
| Identifier / scope | P02400010333; SIKHARA s NANDANAVANAM; Nallagandla site and survey numbers. |
|---|---|
| What it establishes in the supplied record | Registration validity 21/11/2025–21/11/2028. |
| Identifier / scope | File No. 005603/GHMC/02758/SWBP/SLP2/2025; Plot No. 106/F. |
|---|---|
| What it establishes in the supplied record | Permit for one residential building, 1 Stilt + 5 Floors, and 10 dwelling units; approved 21/11/2025. |
| Identifier / scope | Approval No. 1894/GHMC/SWBP/SLP2/2025. |
|---|---|
| What it establishes in the supplied record | Plan for proposed residential flats on the stated 432.0 sq. m site; includes the plan’s area and parking figures and listed conditions. |
| Identifier / scope | 10186/2025, dated 31/10/2025. |
|---|---|
| What it establishes in the supplied record | Permit record identifies a mortgage of 119.17 sq. m on the fifth floor. |
| Identifier / scope | SIKHARA BUILDERS; signed by YAKANARAYANA MAKINENI as authorised signatory. |
|---|---|
| What it establishes in the supplied record | Contains the promoter’s title-basis and encumbrance declarations, fund-management statements, and completion undertaking. |
| Identifier / scope | Not supplied in the reviewed documents. |
|---|---|
| What it establishes in the supplied record | The permit extraction records completion certification as false; no OC or completion certificate is evidenced here. |
The permit states that the permission does not confer ownership rights and requires an occupancy certificate before occupation. This overview identifies the filed records; it does not independently verify construction progress, installed services or certificate issuance.
Frequently asked questions
Is SIKHARA s NANDANAVANAM registered with Telangana RERA?
Yes. SIKHARA s NANDANAVANAM is registered with the Telangana Real Estate Regulatory Authority as P02400010333; the registration status is New Project.
Who is the developer of SIKHARA s NANDANAVANAM?
The promoter named in the RERA registration is SIKHARA BUILDERS.
Where is SIKHARA s NANDANAVANAM located?
SIKHARA s NANDANAVANAM is in CATEGORY-HIG OF NALLAGANDLA HUDA RESIDENTIAL COMPLEX, Nallagandla, Serilingampally, Rangareddy, Telangana (500019).
When will SIKHARA s NANDANAVANAM be completed?
The promoter's proposed date of completion filed with RERA is 21/03/2029. This is the promoter's declaration, not a guarantee.
More projects in Nallagandla